PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples



Similar documents
Facility Maintenance Management Competency 4.9

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Project Risk Assessment Examples

Basic Concepts of Earned Value Management (EVM)

Baseline Change Control Procedure

PROJECT MANGEMENT PLAN EXAMPLES Prepare Baselines - Performance Baseline Examples

Cost Estimating Procedure. Table of Contents

IT Baseline Management Policy. Table of Contents

Appendix D Glossary Of Terms

Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

Project Management Guidelines

PROJECT MANAGEMENT PLAN CHECKLIST

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

300 Scheduling and Budgeting

A Gentle Introduction to Earned Value Management Systems

A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

The PNC Financial Services Group, Inc. Business Continuity Program

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Central Agency for Information Technology

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services

11.0 WORK SCHEDULE, WORK PLANS, AND ASSOCIATED REPORTS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

Information Technology Project Management (ITPM)

Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP

Why are PMO s are Needed on Large Projects?

Head, Office of Project Management Oversight

IT Project Management Methodology. Project Scope Management Support Guide

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision

Organization. Project Name. Project Overview Plan Version # Date

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Orange County Convention Center Orlando, Florida June 3-5, Using SAP PS Earned Value to Manage IT Projects Michael Kim

Proposed Scope of Consulting Services for Business Plan Development and Performance Based Budgeting

VA ICJIS. Program Management Plan

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

Project Management Guidelines

Status Report. Status Report Guide. Strategic Capital, Infrastructure and Projects. A guide to completing the Status Report

ORACLE PROJECT PLANNING AND CONTROL

7 Characteristics of High Performing Firms. Smartsoftware Seminar

Gartner, Inc. DIR-SDD-2042

Minnesota Health Insurance Exchange (MNHIX)

TECHNICAL BASELINE MANAGEMENT SYSTEM- A LIFE CYCLE PROJECT PLANNING AND TRACKING SYSTEM

PROJECT MANAGEMENT in Research and Development

700 Analysis and Reporting

Project Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Computing Services Network Project Methodology

Frequently Asked Questions in Project Management

AACE International Recommended Practice No. 86R 14

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

Project Management Framework

1200 Project Control System Procedures

DoD Business Process Reengineering CONSTRUCTION IN PROGRESS REQUIREMENTS DOCUMENT

Concept of Operations for Line of Business Initiatives

SCHEDULE 8 Generalist Project Services Framework 2015

technical tips and tricks

Project Management Plan for

Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision

SCHEDULE AND BUDGETING

Project Management Office Charter

Project Execution - PM Elements

Release: 1. BSBPMG510A Manage projects

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

Brainstorm. What is Cost and Project Cost Management?

Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites

The Standard for Portfolio Management. Paul E. Shaltry, PMP Deputy PM PPMS ( ) BNS02

<PROJECT NAME> PROJECT MANAGEMENT PLAN

Project Management Using Microsoft Project Plan - Basic

Sound Transit Internal Audit Report - No

Earned Value Management Best Practices

Audit of the Management of Projects within Employment and Social Development Canada

Earned Value Management System Description

SECTION I PROJECT SUMMARY (TRW)

The Fast Track Project Glossary is organized into four sections for ease of use:

Financial Management and Program Management: Integration and Intersections

Project success depends on

Estimating Cost at Completion - Judgment & EV Information

FOREWORD. Page 2 of 88

PMO Metrics Recommendations

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

Project Charter and Scope Statement

The Gateway Review Process

Digital Advisory Services Professional Service Description Network Assessment

VIII. Project Management Glossary

How To Plan A University Budget

Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)

Project Management Using Earned Value

COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

Project Management Professional (PMP)

Transcription:

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples Example 40 5.0 PROJECT MANAGEMENT AND CONTROL The Project Management and Control section provides an overview of the project management and control systems that will be used to manage the 324/327 Buildings Stabilization/Deactivation Project, addressing the following key elements of project management and control: Project Management Control System (PMCS) - Work breakdown structure - Baseline development/update - Scheduling - Performance measurement and reporting - Change control Information and reporting - Project status report - Project manager s monthly report - FDH/RL project status review - DOE-HQ project management reviews - Special reviews 5.1 Project Management Control System The Project Management and Control System (PMCS) for the 324/327 Buildings Stabilization/Deactivation Project is consistent with the current WHC-CM-2-5, Management Control System (as adopted through FDH-MD-001, Rev. 1). The PMCS provides a consistent approach to be used throughout the project. The primary goal of this management system is to ensure planning and implementation of this project is conducted in a manner that is technically sound, timely, and cost effective. In addition, the system is designed to have an upward flow of integrated, summarized information from BWHC to FDH, to RL, to DOE-HQ, ensuring that the project team can make timely management decisions, accomplished by the following process: Develop an integrated plan and accomplish the project objectives in a cost effective manner using demonstrated and innovative technology where appropriate. Provide a WBS that defines the project in a disciplined manner from the top project level to the detailed, manageable work packages. A technical scope of effort and associated schedule and budget are established and responsibility for performance is assigned for each work package.

Ensure that the PMCS is capable of organizing, planning, scheduling, budgeting, accounting, and reporting work in a timely, consistent manner. Obtain technical, schedule, cost, and funding information in the format and to the level of detail necessary to meet management and reporting needs. Integrate the submitted data to compare the project status and progress to planned accomplishments. Evaluate and analyze the resulting information; identify key problems that require management decision and corrective actions be taken. Correlate the project funding profile with planned commitments, expenditures, and work accomplished to date. Prepare and control changes that affect established work scope, budgets, and schedules. 5.1.1 Work Breakdown Structure The WBS will be developed in accordance with HNF-MD-013, Rev. 0, Work Breakdown Structure. The management directive provides responsibilities, requirements, and the process for development, review, and approval of the Project Hanford WBS and contractor WBS, index, and dictionary, during implementation of the Project Hanford Management Contract (PHMC). The 324/327 Buildings Stabilization/Deactivation Project WBS has been developed to provide a basis for scope definition, resource planning, and project implementation and control. The WBS is based on the combination of two methodologies. The Minimum Safe Subproject (Chapter 3.0, Section 3.2.1), was developed using a requirements-based approach (i.e., Surveillance, Maintenance, Project Management, Utilities and Assessments). The Stabilization/Waste and Risk Reduction Subprojects (Chapter 3.0, Section 3.2.2) and the Deactivation Preparation Subprojects (Chapter 3.0, Section 3.2.3), are based on a logical flow of activities required to meet desired endpoints. In March 1998, the endpoint criteria document was updated for both the 324 and 327 Buildings (Chapter 7.0). When complete, deactivation endpoint criteria and activities will meet the deactivation mission objectives. The current areas and systems defined in the draft endpoint criteria documents are the major subprojects included in the WBS. Discreet project activities are identifiable within the lower level WBS, and linked together (schedule logic) or sequenced-based on the planned order in which the actual work will be completed. Completing endpoint objectives within these subprojects will be defined and traceable through the WBS. WBS dictionaries will be prepared at the subproject level for inclusion in the MYWP. The dictionaries will include a summary-level statement of the technical scope, key milestones, key interfaces, and subproject assumptions. Lower-level WBS dictionaries can be developed at the discretion of the subproject manager. 5.1.2 Baseline Development/Update Subproject baselines will use the Project Hanford ABC Preparation Template as guidance for developing and documenting baseline activities. The following steps will be used as a guide in developing or updating the Project and subproject baselines: Develop a subproject baseline or subproject baseline modification by identifying and defining the desired outcomes (endpoint). Define the endpoint in sufficient detail to describe the following: - Subproject goal and objectives - Major project elements and activities - Technical, functional, and regulatory requirements - Enabling assumptions - Key interfaces and dependencies (intra-, inter-project) - Key deliverables and milestones.

Determine whether the baseline change/addition requires updating the Project baseline or multiple subproject baselines, or whether it is a scope change requiring the addition of one or more subprojects. - Communicate change/update requirements to Baseline Control - If a baseline change request (Section 5.1.5) is required, assist in developing the appropriate change control documentation. Draft the new or modified WBS. Use right-to-left planning (i.e., completion of subtask Z, the project endpoint, requires completion of subtasks X and Y). Develop lower level WBS descriptions, assumptions, and alternative approaches to task completion (if appropriate). Complete the subproject plan, including technical scope and resource- and timed-phased schedules, using the Project Hanford ABC Estimating Preparation Template. Document project scope, cost, and schedule risks. Rank project risks based on an evaluation of potential impact to completing the subproject scope within the regulatory, schedule, and cost baseline (low, medium, and high) (Chapter 12.0). As appropriate, develop a risk management plan including risk mitigation strategies. On completion of this baseline development and update process, provide a draft to the facility manger, project director, and project baseline control manager for review and approval. The project baseline control manager will determine the appropriate change control level for updating the Subproject Baseline, 300 Area Project Baseline (Project Baseline Summary or MYPP), and/or potential impacts to the Hanford Site Strategic Plan. If required, the change will be presented to the BWHC Change Control Board. 5.1.3 Scheduling Developing and maintaining the project schedule will be in accordance with HNF-MD-014, Rev. 1, Scheduling. The subproject management team will develop subproject schedules at a level that allows for performance measurement and making decisions (i.e., inter- or intra-subproject prioritization). Developing and maintaining the schedules includes assessing the impact of factors, such as delays, equipment failures, procurement lead time, productivity, resource availability constraints, and facility outages. In addition, the project critical path will be identified and maintained on a real-time basis. The subproject scheduler, along with the subproject manager, will update schedules daily, weekly, or monthly, to effectively manage and integrate inter- and intra-subproject activities. The Subproject management team will define issues and concerns that may affect key milestones, performance agreements, and higher level deliverables (i.e., DOE requests, Tri-Party Agreement milestones, DNFSB actions, etc.), or affect the critical path of the Project or Level I Subproject. The scheduler also will develop subproject corrective action plans as required. 5.1.4 Performance Measurement and Reporting The subproject manager will communicate subproject technical issues and accomplishments, schedule performance, cost and schedule issues, and corrective action plans, as appropriate, in the Project Directors weekly Path Forward meeting. However, the primary performance measurement for reporting subproject performance is provided by the performance measurement system. Within the new common database containing core information on Project Hanford, called HANDI 2000, the performance measurement system compares the resource-loaded schedules (budgeted cost of work scheduled [BCWS]), the actual cost of work performed (ACWP), and the actual work completed (budgeted cost of work performed [BCWP]), monthly. The subproject scheduler will meet with the subproject manager and/or cost account manager near the end of the reporting period or the fiscal month, to determine the status of work in progress or scheduled to start during the month, based on the earned value assigned to each activity. This effort results in the monthly BCWP. Following the final month-end processing of actual cost within the Financial Data System (FDS), the Subproject Planner, Scheduler, and Analyst, will generate performance reports that will compare BCWP to BCWS and ACWP, to determine the cost and schedule variances based on current month and fiscal year-to-date data. (One of the functional applications in HANDI 2000 is the FDS.) The data will be

presented in monthly report at the subproject or sub-subproject level, based on complexity and resource levels of the project activities (cost variance BCWP ACWP and schedule variance = BCWP BCWS). In addition, the subproject planner/analyst will develop an estimate at completion (EAC), beginning no later than March, for the current fiscal year activities and out-year life-cycle activities, if required. The EAC will be based on detailed analysis of performance data and subproject managers assessment of variances, performance, and any relevant changes to baseline scope. The EAC will be evaluated at the two-digit cost element level. (The one-digit cost element includes labor, materials, and contracts. The twodigit cost element detail includes type of labor, type of material, etc.) Development of the EAC should be an ongoing process, with updated information provided from daily, weekly, or monthly reviews with the Subproject management team. Performance reporting will be in accordance with HNF-MD-018, Rev. 0, Performance Reporting. The management directive provides information for continuing a performance reporting process during implementation of the PHMC. 5.1.5 Change Control Baseline change control will be developed and administered in accordance with HNF-MD-008, Rev. 0, Baseline Change Control. The management directive provides guidance for baseline change control during implementation of the PHMC. Responsibilities and requirements for management, administration, and use of the technical, schedule, and cost baseline control system are defined, including the process for preparing and implementing the baseline change request (BCR). 5.2 Information and Reporting Management reporting provides timely and accurate data to apprise BWHC, FDH, and DOE management of current and projected project conditions. Information contained in these reports is obtained from the same database that supports day-to-day management by BWHC. 5.2.1 Project Status Report Reporting for the 324/327 Buildings Stabilization/Deactivation Project is incorporated in the monthly PSR, prepared by BWHC for FDH and RL. The PSR summarizes performance and compares it with the technical, schedule, and cost baselines contained in the MYWP. The report provides the data required by the DOE-HQ process. 5.2.2 Project Manager s Monthly Report The project manager s monthly report (PMMR) is a progress report, and includes the cost performance, the milestone schedule status, variance analysis, and issues. The report will be presented monthly to the Project director. 5.2.3 FDH/RL Project Status Review FDH, RL, and BWHC will conduct a monthly project status review. The review will focus on significant accomplishments since the last meeting; expected accomplishments for the next month; major problems and issues facing the project; and current cost, schedule, and technical status. This review may be in conjunction with the PMMR, presented monthly to the Project director. 5.2.4 DOE-HQ Project Management Reviews Throughout the project, RL will schedule regular (typically quarterly) DOE-HQ project management review meetings. The appropriate personnel from DOE-HQ, RL, FDH and BWHC will attend the meetings. BWHC will be responsible for preparing and issuing the agenda and recording action items, agreements, and commitments that result from the meeting. Quarterly reviews focus on significant accomplishments since the previous meeting; expected accomplishment for the next quarter; major problems and issues facing the project; and current cost, schedule, and technical status.

5.2.5 Special Reviews As required, RL, FDH, and BWHC will conduct special-topic project meetings to review progress, review issues and action items requiring management decisions, change actions, and other items as necessary. Special reviews include status to the stakeholders (i.e., IAMIT, Project Management Meeting with Ecology, etc.). Example 41 5.3 BASELINE CHANGE CONTROL The technical, schedule, and financial planning documents that comprise the official PFP Project baseline are contained as supplements in Section 11. These documents are subject to change control as specified in FDH Procedure HNF-PRO-533, Change Control. Implementation of these procedural requirements may be further specified in PFP specific procedures. Project changes are processed in accordance with FDH Procedure HNF-PRO-533, Change Control, which establishes minimum change control requirements for the PHMC. The Hanford Integrated Site Baseline, made up of technical, schedule, and cost baselines that together define what is necessary to accomplish the Hanford Site clean up mission, is a management tool that defines and communicates site clean up activities, progress, and performance. The baseline management process presented in this procedure provides the methodology that FDH uses to control changes to the Integrated Site Baseline. The baseline management process ensures changes are made only in accordance with approved and documented requirements with appropriate authorization. While the emphasis of this procedure is control of changes to technical, schedule and, cost baselines, a comprehensive approach is used to integrate those processes that affect change control. To that end, this procedure defines the integrated, comprehensive, change control process to include the following: Baseline Changes (Technical, Schedule, and Cost Baselines) Multi-Year Work Plans Project Plans Construction Activities Line Item Construction Projects Hanford Site Technical Baseline Annual Work Plans Indirect Funded Work Scope Tri-Party Agreement Milestones Defense Nuclear Facility Safety Board (DNFSB) Commitments Funding Transfers (Contract Control Points and Mission Areas) Advance Work Authorization. Detailed change control procedures developed by the PHMC Team for managing PHMC scope must align and comply with the requirements of this procedure.