Time Planning and Control



Similar documents
Project Scheduling. Introduction

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Microsoft Project 2010

Lecture 26 CPM / PERT Network Diagram

Guidance on Critical Path Analysis

Use project management tools

Scheduling Glossary Activity. A component of work performed during the course of a project.

SECTION CONSTRUCTION SCHEDULE B. Part 1 - General Work Included Related Requirements Reference Standards...

Large Scale Systems Design G52LSS

EdExcel Decision Mathematics 1

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Cambridge International AS and A Level Computer Science

Resources Management

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

A Short Introduction to Project Management

Chapter 2: Project Time Management

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

ME 407 Mechanical Engineering Design Spring 2016

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Network Planning and Analysis

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

8. Project Time Management

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

Collaborative Scheduling using the CPM Method

Review on Using Packages to Enhance the Teaching of Critical Path Networks

5. Creating a Gantt Chart

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

The work breakdown structure can be illustrated in a block diagram:

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Project Management Glossary

Introduction to Project Management

Earned Value Analysis Exercise

Project Planning and Scheduling

Project Time Management

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Unit 1: Project Planning and Scheduling

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Leaving Certificate Technology. Project Management. Student Workbook

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Priori ty

technical tips and tricks

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

technical tips and tricks

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

Operational Research. Project Menagement Method by CPM/ PERT

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS

A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN

Leaving Certificate Technology. Project Management. Teacher Notes

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Project Control. 1. Schedule Updating

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

Chapter-6. Developing a Project Plan

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

Project Time Management

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Spec. Standard: 11/27/ Revision: 11/27/06

Chapter 6: Project Time Management

Chapter 4: Project Time Management

Notes on the Critical Path Method for project planning and management.

The management of the projects with MS Project

OVERVIEW. Microsoft Project terms and definitions

Critical Path Analysis

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Critical Path Analysis & PERT Charts (taken from

Tracking Project Progress

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Time Management II. June 5, Copyright 2008, Jason Paul Kazarian. All rights reserved.

Dashboards and Reporting for Program Management

Construction Project Scheduling

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

Project management using Excel spreadsheets: The case of Jules Event Planning Company

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.

MODEL SCHEDULING SPECIFICATION

Module 3: The Project Planning Stage

Project Time Management

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

Work Breakdown Structure & Schedules

SESSION 4 PLANNING THE PROJECT PROJECT PLANNING DEFINITIONS

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

Basic Project Management & Planning

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

CPM and GANTT: The Next Step in Multi-Project Management

The Project In the beginning was The Project, and then arose the Assumptions.! And The Project was without form and the Assumptions were void.

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Project Management Dr. James A. Bednar

Transcription:

TOBIC 4 TIM SCLD NTWORK 1 June 3013 Time Planning and Control Time-Scaled Network G404 NGINRING MNGMNT 1

TOBIC 4 TIM SCLD NTWORK 1 June 3013 Processes of Time Planning and Control 1. Visualize and define the activities..sequence the activities (Job Logic). 3.stimate the activity duration. 4.Schedule of the project or phase. 5.llocate and balance resources. 6. Compare target, planned and actual dates and update as necessary. 7.Control the time schedule with respect to changes. G404 NGINRING MNGMNT

TOBIC 4 TIM SCLD NTWORK 1 June 3013 TIM-SCLD DIGRM The original project network is not plotted to a time scale. When drawing a time-scaled diagram, two time scales can be used: one in terms of working days and the other as calendar dates. ach activity is shown as a one dimensional line rather than as a two dimensional box. The horizontal length is equal to its estimated time duration (beginning at its S and ending with its values). G404 NGINRING MNGMNT 3

TOBIC 4 TIM SCLD NTWORK 1 June 3013 xample 1 The following activity list represents the job logic and the durations of activities for a small engineering project. Draw a time- scaled network for the project, determine project time and calculate the activities float times. ctivity Depends on Duration (day) B C G H D I J B, C C, D None, G, H, I 3 4 3 5 5 4 G404 NGINRING MNGMNT 4

TOBIC 4 TIM SCLD NTWORK 1 June 3013 xample 1 B C Time-scaled Diagram G ctivity Depends on Duration (day) B C G H D I J B, C C, D None, G, H, I 3 4 3 5 5 4 H D I J 1 3 4 5 6 7 8 9 10 11 1 13 14 15 16 17 18 Project completion time = 18 working days Critical Path:, D,, I, J. ctivity B C D G H I J Total float 0 6 1 0 5 0 5 0 0 ree float 0 1 1 0 0 0 5 0 0 G404 NGINRING MNGMNT 5

TOBIC 4 TIM SCLD NTWORK 1 June 3013 xample 1 Time-scaled Diagram ctivity Depends on Duration (day) B C G H D I J B, C C, D None, G, H, I 3 4 3 5 5 4 B G H C D I J 1 3 4 5 6 7 8 9 10 11 1 13 14 15 16 17 18 Project completion time = 18 working days Critical Path:, D,, I, J. ctivity B C D G H I J Total float 0 6 1 0 5 0 5 0 0 ree float 0 1 1 0 0 0 5 0 0 G404 NGINRING MNGMNT 6

TOBIC 4 TIM SCLD NTWORK 1 June 3013 TIM-SCLD DIGRM: xplained Vertical solid (dashed) lines indicate sequential dependence of one activity on another. In effect, time-scaled networks are merely extensions of bar charts. When an activity has an early finish time that precedes the earliest start of activities following, the time interval between the two is the free float of the activity. loat times are shown as horizontal dashed lines. G404 NGINRING MNGMNT 7

TOBIC 4 TIM SCLD NTWORK 1 June 3013 TIM-SCLD DIGRM: xplained ree float or activity float is the amount of time that an activity s completion time may be delayed without affecting the earliest start of succeeding activity. Total float or path float is the amount of time that an activity s completion may be delayed without extending project completion time. Total float or path float is the amount of time that an activity s completion may be delayed without affecting the earliest start of any activity on the network critical path. G404 NGINRING MNGMNT 8

TOBIC 4 TIM SCLD NTWORK 1 June 3013 TIM-SCLD DIGRM: xplained ctivity float is owned by an individual activity, whereas path or total float is shared by all activities along a slack path. Total path float time for activity (i-j) is the total float associated with a path. G404 NGINRING MNGMNT 9

TOBIC 4 TIM SCLD NTWORK 1 June 3013 TIM-SCLD DIGRM: xplained dvantages of Time-scaled Diagram Very suitable device for checking daily project needs of different resources, and for the advance detection of conflicting demands among activities for the same resource. Useful for project financial management applications. Disadvantages of Time-scaled Diagram Because it is drawn by manual drafting methods, the level of effort needed to modify and update them is very large. Dependencies among activities are not always so obvious as they are on the activity on node network. G404 NGINRING MNGMNT 10

TOBIC 4 TIM SCLD NTWORK 1 June 3013 xample: TSN market survey The following activity list represents the job logic and the durations of activities for a market survey project. Draw a time- scaled network for the project, determine project time and calculate the activities float times. ctivity Description predecessors Duration, week Plan survey 1 B Hire personnel 1 C Design questionnaire 3 D Train personnel B, C Select samples of customers C 1 Print questionnaire C 1 G Conduct survey D,, 3 H nalyze results G G404 NGINRING MNGMNT 11

TOBIC 4 TIM SCLD NTWORK 1 June 3013 xample Time-scaled Diagram ctivity Description predecessors Duration, week Plan survey 1 B Hire personnel 1 C Design questionnaire 3 D Train personnel B, C Select samples of customers C 1 Print questionnaire C 1 G Conduct survey D,, 3 H nalyze results G C D G H B 1 3 4 5 6 7 8 9 10 11 Project completion time = 11 working days Critical Path:, C, D, G, H. ctivity B C D G H Total float 0 0 0 1 1 0 0 ree float 0 0 0 1 1 0 0 G404 NGINRING MNGMNT 1