Flood Damage Mitigation And Insurance Costs Friday, September 25, 2015 at 7:00 PM Saturday, September 26, 2015 at 10:00 AM This presentation was prepared by the Town of South Bethany using Federal Funds under award NA14 NOS 419 0123 from the Delaware Coastal Programs and the Office for Coastal Management (OCM), National Oceanic and Atmospheric Administration (NOAA), U.S. Department of Commerce. The statements, findings, conclusions, and recommendations are those of the authors and do not necessarily reflect the views of the OCM, NOAA or the U.S. Department of Commerce. 1
Introductions This presentation was prepared by The South Bethany Sea Level Rise & Storm Surge (SLR & SS) Committee With inputs from our SLR Adaptation Grant Partner, Anchor QEA 2
Topics to be Discussed Flood Insurance Rate Maps (FIRMs) Mitigating Flood Hazard Risks Building Higher Flood Insurance Information Working to Improve Resiliency Elevations in South Bethany Building Higher in Flood Zones Freeboard Sea Level Rise Adaptation Grant 3
Flood Insurance Rate Map (FIRM) The FIRM documents the flood hazard risks in South Bethany as determined by FEMA (Federal Emergency Management Agency) 4
Definition of Base Flood Elevation (BFE) Is the height of the water for the 100 year storm Is based on historic data Is shown on Flood Insurance Rate Maps (FIRMs) Is not based on projected SLR 5
The Flood Hazard Zones in South Bethany Zone AE AO VE X BFE The number following AE is the BFE BFE is the number following AO plus the highest grade adjacent to the house The number following the VE is the BFE This zone is not in the floodplain. There is no BFE 6
VE-12 AE-6 AO-2 X Ocean Drive AE-5 DE Rt. 1 Current FIRM 7
The Proposed 2016 FIRM Raises BFE By One Foot in Most Areas of South Bethany 8
VE-13 AE-7 AO-3 VE-10 AO-2 AE-5 Ocean Drive AE-6 DE Rt. 1 Proposed FIRM, 2016 9
Flood Information Portal Provides Current and Proposed BFE for South Bethany Home Owners http://maps.riskmap3.com/de/southbethany/ 10
Mitigating Flood Hazard Risks Building Higher In Flood Zones Freeboard Having Flood Insurance 11
Historically Speaking What is Freeboard? Freeboard is a nautical term. It refers to the height of a ship s deck above the waterline. If you think of the lowest floor of your house as the deck of your ship, and the BFE as the height of the sea, freeboard is the extra height that keeps the larger waves off your deck. 12
Benefits of Freeboard The greatest benefit of freeboard is that it reduces the risk of property damage due to high water 13
Freeboard Reduces Flood Insurance Premiums Source: FEMA Fact Sheet, Building Higher in Flood Zones : Freeboard Reduce You Risk, Reduce Your Premium 14
South Bethany code allows for building height * to increase at least 2 feet if there is at least 2 feet of freeboard * Building height is measured from the centerline of the road to the peak of the roof 15
The News About Insurance From FEMA FEMA will add a surcharge to all insurance bills 2nd homes: $250 per year. Permanent residence: $25 per year. 16
The News About Insurance Cont d Congress determined that this year premiums must increase by at least 5% but by no more than 18%. There are exceptions. See your insurance agent 17
The News About Insurance Cont d To reduce your flood insurance premium you may select a $10,000 deductible; your insurance premium could go down by as much as 40%. 18
The News About Insurance Cont d Grandfathering In general, if you have carried flood insurance continuously since your house was built, it will be rated according to the FIRM that was in place when it was built. There are exceptions. See your insurance agent 19
Resiliency Is the ability of the Town to recover from coastal hazard events. Is dependent on planning and preparing before the event occurs. 20
Working To Improve Our Resiliency Formed the SLR & SS Committee in June 2013 Passed an ordinance in 2014 to encourage building with freeboard by allowing an increase in house height if there is freeboard. Surveyed the elevation of all streets, bulkheads, ground mounted transformers and storm drains to be used to assess the vulnerability of critical infrastructure. Obtained a DNREC grant in 2015 that will facilitate the development of a Comprehensive SLR Adaptation Plan to span 50 to 100 years. 21
Vulnerability of Critical Infrastructure Infrastructure Lowest (ft. above Sea Level) Highest (ft. above Sea Level) Streets 1.4 12.0 Bulkheads 0.5 4.0 Ground Mounted Transformers 1.6 9.7 Storm Drain Grates 0.9 6.1 22
Grant Specific Tasks Establish Elevation Database Complete Select SLR Scenarios Complete Identify Criteria of Interest Target Date 11/1/15 Complete SLR risk identification and inundation mapping Target Date 02/01/16 Hold Public Outreach Meetings This meeting 23
SLR Scenarios Elevation data together with SLR projections, tidal variations and storm surge are used to assess the vulnerability of critical infrastructure. The Town contracted with Anchor QEA to develop SLR scenarios using data from numerous authoritative sources. 24
SLR Scenarios Developed by Anchor QEA Recommended a 50 year time horizon for South Bethany SLR analysis Recommended SLR Scenario for the next 50 years (2015 to 2065) Lower bound: 0.7 feet Upper bound: 1.7 feet Recommended that the scenarios be re-evaluated every 5 to 10 years 26
Local Water Levels Have Been Rising Over The Past 100 Years Gage Location Years of Recorded Data SLR Extrapolated (ft. per 50 yrs.) Lewes, DE 96 0.56 Ocean City Inlet, MD 37 0.94 Indian River Inlet, DE 25 0.93 Little Assawoman Bay, Fenwick Is. 14 1.45 Jefferson Creek, South Bethany 14 1.50 27
Recent History at Local Tide Gages Consistent With Scenario Lower (0.7 ft.) and Upper (1.7 ft.) Bounds Gage Location Years of Recent Recorded Data SLR Extrapolated (ft. per 50 yrs.) Lewes, DE 11 1.30 Ocean City Inlet, MD 11 1.50 Indian River Inlet, DE 14 1.02 Little Assawoman Bay, Fenwick Is. 14 1.45 Jefferson Creek, South Bethany 14 1.50 28
SLR Long Term Adaptation Goals Assess SB s vulnerability to SLR (current grant) Develop a Comprehensive SLR Adaptation Plan for a timeframe of 50 years Identify metrics/triggers for action Adapt to the challenges of SLR through prioritizing resources and funding 29
Questions? 30