Strategic project portfolio management in multinational companies: a case study



Similar documents
Project management as a tool for implementing strategy

ALINING PROJECT SCOPE AND DELIVERABLES WITH BUSINESS STRATEGY

Evaluating project manager performance: a case study

Investigating the roles, responsibilities and practices of portfolio managers in Australia: A literature review and research outline

The Standard for Portfolio Management. Paul E. Shaltry, PMP Deputy PM PPMS ( ) BNS02

Successful management in multi-project environment

project portfolio management

Challenges of Intercultural Management: Change implementation in the context of national culture

Aligning Business Strategies and Project Management

Nydia González 1, Franck Marle 1 and Jean-Claude Bocquet 1. Ecole Centrale Paris, FRANCE

The OneMBA significantly accelerated my development as a global leader with an inspiring and challenging experience.

The Effects of the Project Management Office on Companies Performance - A Case Study on a Project-Oriented Company

Interview studies. 1 Introduction Applications of interview study designs Outline of the design... 3

The Business Balanced Scorecard and Key Performance Indicators. The principles and approach to build

Project Portfolio Management for a Support Function - Neglected challenges inhibiting effective PPM

USING ALIGNMENT WITH CORPORATE STRATEGY FOR THE SELECTION OF A PROJECT PORTFOLIO BASED ON ANP

Market Research Methodology

Principles of Execution. Tips and Techniques for Effective Project Portfolio Management

CORPORATE INFORMATION AND TECHNOLOGY STRATEGY

EFFECTIVE STRATEGIC PLANNING IN MODERN INFORMATION AGE ORGANIZATIONS

Types of Project Management Offices (PMO)

Project Portfolio Management: A Pilot Survey on the Importance of Project Building Stones in Corporate Life

4.1 Identify what is working well and what needs adjustment Outline broad strategies that will help to effect these adjustments.

Leading and Managing Innovation

COVER PAGE. Paper title: Inquiry into the Conceptual Dimensions of the Performance of Project Portfolio Management

IPMA Presents Research Awards at the 25 th IPMA World Congress

Basic Risk Identification Techniques

Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition

Case study research design

The Balanced Scorecard (BSC)

Strategic solutions to drive results in matrix organizations

Strategic Planning. Credit value: 15 Guided learning hours: 45. Unit aim. Unit introduction

Author: Carlos Eduardo Martins Serra, MSc, PMP Supervisor: Martin Kunc, PhD

Designing multidiscipline cases Asplund, Carl-Johan; Jordan, Paula F.

structures stack up Tom McMullen

A Guide to the. Incorporating the Essential Elements of Strategy Within Your Organization. Empower

THE CONTRIBUTION OF THE BALANCED SCORECARD AS A STRATEGIC MANAGEMENT TOOL IN MANAGEMENT SUPPORT

Cascading KPIs using the 9 Steps to Success

Topic 1 Introduction. to the Fundamentals of Project Management INTRODUCTION LEARNING OUTCOMES

Designing a Metrics Dashboard for the Sales Organization By Mike Rose, Management Consultant.

The Change Enablement Center

Project Management Office Charter

The real success factors on projects

Introduction to project management and concepts

FIVE STEPS. Sales Force

The Impact of Leadership in. Agile Information System Development Projects: A Pitch

Sales Checkpoint Performance Feedback System

Western Carolina University Master s Degree in Project Management (MPM) Program Department of Management & International Business College of Business

Assessing the Appropriate Level of Project, Program, and PMO Structure

HRQM AND COLLIDING GYROSCOPES AN ALTERNATIVE WAY OF LOOKING AT VALUE CREATION IN ORGANIZATIONS

Practical-Theoretical Approach in the Application of Theory Models of Organizational Behavior Dr. Robert DeYoung - Saint Thomas University

Most CPA firms understand the importance of strategic

BALANCE SCORE CARD - A STRATEGIC PROJECT MANAGEMENT TOOL FOR INFRASTRUCTURE DEVELOPMENT PROJECTS

Performance Management for Inter-organization Information Systems Performance: Using the Balanced Scorecard and the Fuzzy Analytic Hierarchy Process

The Balanced Scorecard. Background Discussion

Why Your Strategy Isn t Working

Field Guide to Consulting and Organizational Development. Table of Contents

THE RELATIONSHIP BETWEEN PROJECT MANAGER LEADERSHIP STYLE AND PROJECT SUCCESS. Approved: Date:9 May Paper Advisor

Effect of the learning support and the use of project management tools on project success: The case of Pakistan

Characteristics of Effective and Sustainable Teaching Development Programs for Quality Teaching in Higher Education

Strategic Executive Coaching: An Integrated Approach to Executive Development

International Project Management Association (IPMA) Award Winning Research

Portfolio Management Professional (PfMP)SM. Examination Content Outline

Building Web based Communities: Factors Supporting Collaborative Knowledge-Building

Charting our outcomes

Gartner's Business Intelligence and Performance Management Framework

Managing new product development process: a proposal of a theoretical model about their dimensions and the dynamics of the process

Project Categorization Systems and Their Role for Project Portfolio Management

Effects of Project Management on the Performance of a Construction Firm in Nigeria

Issues in Information Systems

Enterprise Release Management

EDUCATIONAL LEADERSHIP PROGRAM Recognition. Standards:

Leading Self. Leading Others. Leading Performance and Change. Leading the Coast Guard

The Impact of Market Orientation and IT Management Orientation on Customer Relationship Management (CRM) Technology Adoption

Developing Greater Professionalism in GIS Project Management

Manager, Corporate Planning & Reporting BC Oil & Gas Commission, Victoria Applied Leadership. Office of the Commissioner - Corporate Affairs

Values, ethics and ideology in modern organizations- Alignment to company values

Name Chapter 1: Introduction to Project Management Description Instructions

The Need for Strategic Planning for Project Management

Understanding the links between employer branding and total reward

Grounded Theory. 1 Introduction Applications of grounded theory Outline of the design... 2

ICT in pre-service teacher education in Portugal: trends and needs emerging from a survey

Bridging Micro and Macro Domains: Workforce Differentiation and Strategic Human Resource Management

Agile project portfolio manageme nt

UTILIZING PROJECT MANAGEMENT TO STARTUP A COMPANY IN THE IT INDUSTRY

Application of the Prado - Project Management Maturity Model at a R&D Institution of the Brazilian Federal Government

Building Online Learning Communities: Factors Supporting Collaborative Knowledge-Building. Joe Wheaton, Associate Professor The Ohio State University

Role of Project Portfolio Control Techniques in Achieving Efficiency in Project Based Firms

Performance Measures for Internal Auditing

ARCHITECTURE IN TOURISM

Transcription:

Strategic project portfolio management in multinational companies: a case study Orlando Cattini Junior, PhD (orlando.cattini@fgv.br) Professor, Escola de Administração de Empresas de São Paulo da Fundação Getulio Vargas Wilson Roberto L. Zatti, PMP (wilson.zatti@gmail.com), Master in Business Administration, Escola de Administração de Empresas de São Paulo da Fundação Getulio Vargas Abstract The study examines how projects are identified, assessed and prioritized in order to contribute to the strategies chosen by companies. A case study in the Brazilian branch of a multinational automaker compares what is proposed by the literature with what actually takes place in practice. Keywords: project management, portfolio management, strategy planning, strategy execution Introduction The Strategic Plan implementation in a company is made possible by the implementation of integrated and coordinated activities in order to achieve a particular goal. It must comply the constraints of time, human resources, available capital, technology, etc., similar to what is done in project execution. According to Nieto-Rodriguez (2012, p.59) the company needs to be focused and use project management practices to have an effective and successful strategy implementation. The projects, which are part of management, compose the group of activities that focus on the implementation of improvements and business development ("change-the-business"). There is also a group of repetitive and continuous activities in the operations ("run-the-business") (Nieto-Rodriguez 2012; Shenhar and Dvir 2010). Some companies treat projects with utmost importance applying modern and complex methods recommended in the literature. Others develop their own methodologies beside others that simply run their projects based on empirical experience of its employees and not recognizing project management as a core activity of the company. The temporary nature of projects indicates that a project has a beginning and an end (PMBOK 2013, p.3) becoming in some cases the strategy itself. According to Artto et al. (2008) project strategy depends on two dimensions in the environment in which the project is developed: independence of the project and number of interested strong stakeholders in the organization. But, it was only in recent years that companies began organizing work around projects and when the tools, techniques and methods used have become standard in the industry, a new discipline came up: Project Management (Shenhar and Dvir 2010). These tools contributed to start grouping the projects into programs and portfolios in accordance with the strategies and goals of the company. In this research we interviewed 24 professionals for whom language and work culture related to projects are not unknown (22 executives, 1 specialist and 1 consultant) in an automaker installed in Brazil since the sixties. As the interviewed persons were 1

not statistically selected, the sample could be biased. In spite of this, they indicate a significant difference between the theoretical models and what is done in practice, suggesting that new models and standards should eventually be developed and/or adapted. Finally, we propose an answer to the research question: "How strategic project portfolio management is used in order to contribute to the strategies chosen by companies?" Theoretical Background Although projects often take quite tactical roles (Artto et al. 2004) they have been considered important tools to implement strategies and promote changes (Johnson and Parente 2013; Patanakul and Shenhar 2012; Nieto-Rodriguez 2012; MacLennan 2011; Guedes et al. 2011; Turner 2009; Srivannaboon 2009; Morgan et al. 2007; Morris and Jamieson 2004; 2005; Artto et al. 2004; Longman and Mullins 2004; Pellegrinelli and Bowman 1994; Lord 1993). When organizations conduct their projects linked to strategy, they are more able to achieve their organizational goals (Milosevic and Srivannaboon 2006). When a project is created or approved for execution, it has a special purpose, a strategy. Project strategy is a guideline that contributes to success of the project in its environment (Artto et al. 2008). According to the authors the project strategy depends on two dimensions in the environment in which the project is located: independence of the project and number of strong stakeholders interested in the project (Figure 1). Figure 1 Project strategy according two dimensions (Artto et al. 2008) The project with obedient servant strategy considers its parent organization as the most important stakeholders in their environment. In this case the project supports the business strategy. The project as independent innovator strategy sets its direction, encouraging innovative and independent behavior to find or keep business content and purpose of the project itself. It can originate from an independent action. Project as flexible mediator strategy finds its meaning by defining its operational environment, such between the group of strong stakeholders, sharing goals. Finally, the project as a strong leader strategy selects its direction, creating a strong independent culture and sense of importance of becoming a success. The project is able to establish a single and focused vision of the various stakeholders. A project can be created to meet the need of a strategy (deliberate or emergent), then they are being chosen by selection tools to integrate the portfolio that fits the business strategy. According to Mintzberg (1978) deliberate strategies are those desired and performed while 2

emergent strategies are strategies that, normally, never had an intention or those that were obtained along the way. Emergent strategies exist simultaneously to deliberate strategies (Mintzberg and Waters 1985; Mariotto 2003) in an interdependent process. Morris and Jamieson (2004; 2005) consider the project strategy as the project objectives and explore the process of transforming corporate strategy into project strategy. The authors define corporate strategy as a way of thinking and articulating how corporate goals and objectives of the organization are achieved. This strategy is then, typically, operationalized at the level of a "strategic" business unit. Strategic initiatives are then often grouped into portfolios of programs and projects for implementation (Morris and Jamieson 2004; 2005). From this definition the authors explore the basic model presented by Turner (2009) (originally published in the second edition in 1999) to connect, in a cascade, the corporate strategy to project strategy (Figure 2). Figure 2 Connecting the corporate strategy with project strategy (Morris and Jamieson 2004; 2005) In this process, portfolio management is connected directly with the corporate business strategy. To be neatly implemented and in order to rationalize the use of scarce resources in the company, there are guidelines and tools for project portfolio management, which has become an important topic in recent years (Urli and Terrien 2010). An improved definition of portfolio management is presented by Cooper et al. (1999), where the "portfolio management is a dynamic decision process, in which a list of active projects is constantly updated and revised, where new projects are evaluated, selected and prioritized, others are put on hold and resources are allocated in the active projects". The portfolio management is from the strategic point of view the same as the project management from tactical point of view (Urli and Terrien 2010). Although, the portfolio management does not ensure success in achieving strategic objectives, an effective portfolio management process can increase the chances of selecting and completing the projects that best meet the organizational objectives and that are aligned with the organization's vision (Bible and Bivins 2012). The annual report PMI's Pulse of the Profession (2012) reinforces the importance of portfolio management and point out that matter as one of the main trends for the coming years. Project, program and portfolio management (PPPM) has been neglected over the years. It is not common for the most recognized authors in Business Management refer to project management as an important business methodology or a critical component for implementing 3

strategy (Nieto-Rodriguez 2012), but no longer simply a middle management tool for planning, organizing and controlling human and other resources, project management can now be regarded as an essential means of turning strategic objectives into operational ventures (Lord 1993). Although many executives believe that the alignment of project management with business strategy improve significantly the scope of organizational success in terms of strategy and performance, the literature on this subject is still in its beginning (Srivannaboon 2009). When organizations have their projects related to strategy, they better achieve their organizational goals (Milosevic and Srivannaboon 2006). Longman and Mullins (2004) consider the project management an essential tool for implementing strategies and say that project management must be practical and relevant for the organization. People, at various levels, must realize the benefits of project management day-by-day in strategy implementation. Methodology This research is a qualitative descriptive one and seeks to identify, in an automotive car maker installed in Brazil for many years, how projects are identified, assessed and prioritized in order to contribute to the strategies chosen by companies. The philosophical conception is pragmatist focusing on the consequence of actions, problem-centered, pluralistic and oriented to the practice in real world (Creswell 2010), with constant comparison of these practices with those described in the literature. It was used as a methodological approach combination of qualitative methods as shown in Figure 3. Figure 3 Methodological approach: combination of qualitative methods (from the authors) Case Study Data collection Interviews Participant observation Use of documents Data analysis Template Analysis Discussion Discussion of results, conclusion and proposal for future studies Data collection Interviews: we applied the individual interviews method with open-end structure (Vergara 2009), where interviewees has the role of respondents (the most common model of interviews, in which participants are asked and share their own experiences about the subject) (Alvesson and Ashcraft 2012), and describes internal processes that help to understand how this phenomenon occurs. Our position as interviewers was neo-positivist, focused on the facts and practices existent on the environment and context, but a novelist position (Alvesson and Ashcraft 2012) was not abandoned, with appreciation of human interaction and build of a confidence process. We interviewed 24 people in the automaker, for whom language and work culture for projects are not 4

unknown: 22 executives, 1 specialist and e 1 internal consultant. The last two, although not being executives, are responsible for implementing projects in the company. We attempted to obtain a multidisciplinary overview of processes focusing on those departments dealing with projects and strategy formation. The most represented areas are extremely active in projects of product development, capacity and structure of factories, the core categories of projects for the business development (Table 1). Table 1 Areas participant in the interviews (from the authors) Área Qt Qt Product Management 2 Finance 1 Manufacturing Engineering 3 Information Technology 1 Process Engineering 3 Sustainability Management 1 Product Engineering 1 Logistics 1 Corporate Strategy 3 Governance, Risks and Compliance 1 Quality Assurance 3 Marketing 1 Human Resources 2 Purchasing 1 TOTAL = 24 The applied questionnaire had 17 questions elaborated from the studies of Mintzberg (1978), Mintzberg and Waters (1982; 1985) and Mintzberg and McHugh (1985), Mariotto (2003), Bower (1970), Burgelman (1983), Weick (1979), March (1976), Waldrop (1992), Anderson (1999), Weaver (2007), Artto et al. (2008) and Archibald (2004). The total amount of interviews is enough to reveal the main codes (Guest et al. 2006; Griffin and Hauser 1993). Participant observation: it is based on direct contact between the researcher and the phenomenon of interest (Brannan and Oultram 2012). We followed the complete participation mode, where the role of observer and observational goals are reserved for other participants. Use of documents (Lee 2012): in this research we used only primary documents provided by the interviewees and others from various departments, excerpts of meetings where the method of participant observation were used, internal newspapers and intranet data. These documents, beyond reveal important phenomena for research, validate the information given by the interviewees. Data Analysis Template analysis: according to King (2012), Template Analysis is a style of thematic analysis that balances a high degree of structure in textual data analysis with flexibility to fit the needs of a particular study process. This model has been widely used to analyze data from individual interviews. It is a more flexible technique with few specific procedures, allowing researchers to adapt these techniques to their needs. According to the author, three aspects influence the choice of this technique by the researcher: 1. flexibility of the structure data encoding 2. the use of a priori theme 3. use of an initial template. The method follows some specific steps: 1. Defining themes and codes 2. Hierarchical coding 3. Parallel coding 4. Integrative themes 5. Displaying the template into list and/or mind maps 6. Quality checks 5

Results The interviews were coded in Figure 4 shown in a Mind Map. The first layer shows the f. The second one shows the main points found to each category. The third one show the points emerged into each point found in the second layer and finally, the forth layer shows the main points that emerged in each point described in the third layer. Figure 4: Main codes found using the Template Analysis (from the authors) 6

Figure 4: Main codes found using the Template analysis (continuation) (from the authors) Discussion and Conclusion The content of the Template Analysis, from the surveyed people s point of view, shows some similarities between the results and the theoretical models, but also brings some significant differences between what is actually used and experienced by them. The main points refer to: 7

1. Strategy: the process shown in Figure 2 is noticeable in the company, mainly with the portfolio of projects related to products and new launchings. The corporate processes followed (like those used in the Headquarter) helps the company in Brazil to achieve the milestones and results according to the targets. The same process is not identified to projects related to structure, capacity and non-product (diverse projects with no relation to the products of the company, e.g., projects like improvement of performance, training, sustainability, etc.). The Strategic Map illustrates the objectives managed through the Balanced Scorecard (Kaplan and Norton 2007). These objectives are deployed to the managerial level until the operational one, than controlled through indicators. Strategy formation/creation is a complex process with many inputs, mainly from the Headquarter and Marketing area according to the results of some indicators, like customer satisfaction, movements from the competitors, and so on. It was also identified a lot of internal and external sources of strategy changes were the process of planned strategy exists together the emergent strategy in a complex interrelated process. 2. Operational: often, during the execution of strategies, new projects emerge, influenced by the sources of changes. They can be big or small ones to correct the course of the ongoing strategy. But these projects can be aborted before they achieve the appreciation from the Board of the company that approves or not a new project. There are lots of factor that inhibits new ideas/projects, like bureaucracy, conflicts of interest and limitation of resources. 3. PPPM: a project born from official and structured processes followed in the company or from emergent processes. Each project has a strategy and the four types of project strategy described for Artto et al. (2008) were identified. The projects as obedient servant strategy were cited 30 times during the interviews. Projects related to structure and capacity of the factories are the main representatives. Projects as flexible mediator strategy were cited 29 times and the product projects are the main representatives. Projects as independent innovator strategy were cited less, 15 times followed by the projects as strong leader strategy, just 5 times. Both are represented by projects classified as non-product. Depends on the strategy and purpose of the project it is approved or not by the Board of the company and can integrate the strategic portfolio of projects, but a systematic to classify the project was not identified in this research. The projects are mainly approved according to their financial return and pay-back period. Some good and important projects, but with not so good results, can be approved over some that are not technically so important, if the business case promises good financial results. Quality issues are also important, but not over the financial ones. In general, the authority of the Project Manager is lower than the Functional Manager. This leads to low motivation and commitment to project results, as well as conflicts between the operation and the needs of strategic goals accomplishment. The same occurs in allocation and prioritization of resources. 8

We concluded that the alignment between the portfolio of projects and corporate strategy occurs, but just considering the projects of products development. A structured systematic according to the Headquarter procedures were identified and it is essential for this alignment occurs. This methodology can be explored in order to identify some new process not described in the literature, but used by the company with good acceptance and results. For the other category of projects there are many gaps in process from the role of the Project Manager until the selection process for projects. Given this the misalignment our study indicates that many of the basic practices of portfolio management are ignored or misused by the responsible people, opening a huge opportunity for improvement of operational performance, better allocation and use of resources and improvement of management practices. The findings also encourage the development and adaptation of new models and standards to approach the practices proposed in the literature with that actually used daily by executives. References Alvesson, M., Ashcraft, K. L. 2012. Interviews. In: Symon, G., Cassell, C. Qualitative organizational research: core methods and current challenges. Sage Publications, 239-257. Anderson, P. 1999. Complexity theory and organization science. Organization Science 10(3): 216-32. Archibald, R. D. 2004. A global system for categorizing projects: the need for, recommended approach to, practical uses of, and description of a current project to develop the system. In: Latin American PMIGOVSIG Forum on Project Management In Government, Brasilia, Brazil, 1-16. Artto, K. et al. 2008. What is project strategy? International Journal of Project Management 26: 4-12. Artto, K. et al. 2004. Strategy implementation by projects. In: Proceedings of the PMI Research Conference, London. Bible, M. J., Bivins, S. S. 2012. Evaluating strategic project and portfolio performance. Journal of Project, Program & Portfolio Management 3(1):10-30. Bower, J. L. 1970. Managing the resource allocation process: a study of corporate planning and investment. Boston: division of research, Harvard Business School. Brannan, M. J., Oultram, T. 2012. Participant observation. In: SYMON, G.; CASSELL, C. (Orgs). Qualitative organizational research: core methods and current challenges. Sage, 296-313. Burgelman, R. A. 1983. A model of the interaction of strategic behavior, corporate context, and the concept of strategy. Academy of Management Review 8(1): 61-70. Cooper, R. et al. 1999. New product portfolio management: practices e performance. Journal of Innovation Management 16(4): 333-361. Creswell, J. W. 2010. Projeto de pesquisa: métodos qualitativo, quantitativo e misto. Bookman. Griffin, A., Hauser, J. R. 1993. The voice of the customer. Marketing Science 12(1): 1-27. Guedes, R. M. et al. 2011. Alinhamento do portfólio de projetos à estratégia das organizações: um estudo exploratório quantitativo. E&G Revista de Economia e Gestão 11(27): 67-93. Guest, G. et al. 2006. How many interviews are enough? An experiment with data saturation and variability. Field Methods 18(1): 59-82. Johnson, W. H. A., Parente, D. H. 2013. Project strategy and strategic portfolio analysis: A Primer. Business Expert Press, LLC (Kindle version). Kaplan, R. S., Norton, D. P. 2007. Using the Balanced Scorecard as a strategic management system. Harvard Business Review July-August. King, N. 2012. Doing template analysis. In: SYMON, G.; CASSELL, C. (Orgs). Qualitative organizational research: core methods and current challenges. Sage, 2012, 427-450. Lee, B. Using documents in Organizational research. In: SYMON, G.; CASSELL, C. (Orgs). Qualitative organizational research: core methods and current challenges. Sage, 2012, 389-407. Lord, A. M. 1993. Implementing strategy through project management. Long Range Planning 26(1):76-85. Longman, A., Mullins, J. 2004. Project management key tool for implementing strategy. Journal of Business Strategy 25(5): 54-60. MacLennan, A. 2011. Strategy execution: translating strategy into action in complex organizations. Routledge. 9

March, J. G. 1976. The technology of foolishness. In MARCH, J. G., OLSEN, J. P. Ambiguity and Choice in Organizations. Bergen: Universitetsforlaget. Mariotto, F. L. 2003. Mobilizando estratégias emergentes. RAE Revista de Administração de empresas 43(2): 78-93. Milosevic, D. Z., Srivannaboon, S. 2006. A theoretical framework for aligning project management with business strategy. Project Management Journal 37(3):98-110. Mintzberg, H. 1978. Patterns in strategy formation. Management Science 24(9): 934-948. Mintzberg, H., McHugh, A. 1985. Strategy formation in an adhocracy. Administrative Science Quarterly 30(2): 160-197. Mintzberg, H., Waters, J. A. 1982. Tracking information in an entrepreneurial firm. Academy of Management Journal 25(3): 465-499. Mintzberg, H., Waters, J. A. 1985. Of strategies, deliberate and emergent. Strategic Management Journal 6(3): 257-272. Morgan, M. et al. 2007. Executing your strategy: how to break it down and get it done. Boston: Harvard Business School. Morris, P., Jamieson, A. 2004. Translating corporate strategy into project strategy. PMI, Project Management Institute. Morris, P., Jamieson, A. 2005. Moving from corporate strategy to project strategy. Project Management Journal 36(4): 5-18. Nieto-Rodriguez, A. 2012. The focused organization How concentrating on a few key initiatives can dramatically improve strategy execution. Grower. Patanakul, P., Shenhar, A. J. 2012. What project strategy really is: the fundamental building block in strategic project management. Project Management Journal 43(1):4-20. Pellegrinelli, S., Bowman, C. 1994. Implementing strategy through projects. Long Range Planning 27(4): 125-132. PMI, Project Management Institute. 2013. Project Management Body of Knowledge. Edition 5. PMI, Project Management Institute. 2012.PMI s Pulse of the Profession. Shenhar, A. J., Dvir D. 2010. Reinventing project management. Harvard Business School Press. Srivannaboon, S. 2009. Achieving competitive advantage through the use of project management under the plan-docheck-act concept. Journal of General Management 34(3):1-19. Turner, J. R. 2009. The handbook of project-based management. The McGraw-Hill Companies, Inc. (ebook version). Urli, B., Terrien, F. 2010. Project portfolio selection model, a realistic approach. International Transactions in Operational Research 17: 809-826. Vergara, S. C. 2009. Métodos de coleta de dados de campo. Atlas. Waldrop, M. M. 1992. Complexity. New York, Simon & Schuster. Weaver, P. 2007. Effective project governance linking PMI s standards to project governance. In: PMI Global Congress Hong Kong. Weick, K. E. 1995. Sensemaking in organizations. Thousand Oaks, Sage. 10