International Project Management Association (IPMA) Award Winning Research
|
|
|
- Russell Benson
- 9 years ago
- Views:
Transcription
1 Contingent Governance Framework for Projects (CGFP) Contingent Governance Framework for Projects (CGFP) Research Summary International Project Management Association (IPMA) Award Winning Research Dated: 4 th September 2013 By: Dr. Muhammad Ehsan Khan, PgMP, PMP, CEPM [email protected] Mobile: Summary for the IPMA award winning research conducted by Dr. Muhammad Ehsan Khan for PhD in Strategy, Programme and Project Management from SKEMA Business School, France. This study is focused toward project governance domain, and concentrates on Contingency of Governance Frameworks.
2 Contents ABOUT THE AUTHOR... 3 ABSTRACT... 4 INTRODUCTION... 5 PROJECT AND PROJECT ATTRIBUTES... 5 Defining a Project... 5 Project Attributes... 6 PROJECT PERFORMANCE... 6 PROJECT GOVERNANCE... 8 Defining Project Governance... 8 Project Governance Dimensions... 9 METHODOLOGY AND ANALYSIS... 9 RESULTS OF THE RESEARCH Influence of Project Attributes Project Complexity Project Uncertainty Project Strategic Value Conclusion Influence of Project Performance Meeting constraints and stakeholder expectations Meeting design goals and expectations Adherence to process Overall Performance Conclusion Contingent Governance Framework for Projects (CGFP)
3 IMPLICATIONS Theoretical Implications Identification of Constructs Development of Framework Quantitative Research Practical Implications Efficient Governance of Projects Project Categorization Project Performance Metrics Understanding the Role of Governance
4 About the Author Dr. Muhammad Ehsan Khan PgMP, PMP is a pracademic and consultant who has been associated with the growing profession of project governance and management for more than a decade. Ehsan holds a PhD in Strategy, Programme and Project Management from SKEMA Business School, France. He was awarded with Young Researcher of the Year 2013 by International Project Management Association (IPMA) and James R. Snyder Student Paper of the Year Award 2012 by Project Management Institute (PMI). With special inclination towards strategic planning and governance of projects and programs, Ehsan has provided management, consulting and mentoring services in the Middle East Region. He has been involved in establishment of PMO, implementation of governance frameworks, and related practices and tools, in order to create an environment of project management excellence. He has also been managing medium-large scale ICT programmes and projects for various customers, especially in the government sector. As an academic, his research interests are in the field of Contingent Governance Frameworks for Temporary Organizations. He has written research papers in the project governance domain and has also featured as an author in various publications. He is currently authoring a book on Program Governance and has been part of major conferences where he has presented papers related to his area of interest. Ehsan has also been involved in establishing successful technology startups in his career. He is currently providing consulting services to different customers and is also engaged as a partner, and founding member, of a Business Intelligence Startup in Abu Dhabi, UAE. You can contact him on: [email protected] Linked In: Mob:
5 By Muhammad Ehsan Khan, PhD, PgMP, PMP, CEPM PM Strategist and Confidential Customer, UAE SKEMA Business School, France Abstract The research summary proposes a new model for project governance termed as Contingent Governance Framework for Projects (CGFP). The framework is based on the idea that a successful model for project governance can be put into practice by considering the project context. Some of the factors remain stable during the project lifecycle whereas others change as the project progresses. Based on the changing project context the project governance framework should evolve. This paper examines the impact of project attributes and project performance, using quantitative methods, on the manner in which project governance is carried out in organizations. This impact is analyzed by measuring the preference of project governors for different dimensions of project governance during the project life cycle. The results showed that certain project attributes, and project performance dimensions, influence the preference of project governors for governance dimensions. It was evident that the overall project performance also impacts the preference of project governors for project governance dimensions, as well as overall governance. Along with that, through extensive literature review, various other factors have been identified that influence project governance framework. These factors include corporate governance, the experience of project team, organizational governance paradigm, social and other cultural influences. The proposed model is the first step toward development of this novel framework which organizations can utilize to govern their projects and improve the probability of project success. 4
6 Introduction The basic nature of humans, to learn and do new things, has created a sense of competition and uncertainty. Because of this uncertain nature of our environment, organizations have to constantly change the way they are doing work, in order to keep them competitive, and perform different functions in a more productive manner. That might be the reason that Turner and Keegan state that our current environment is a more project-based economy (Turner and Keegan, 2001, p. 254). Such organizational changes and resulting initiatives cannot be handled through the routine operations that organizations perform; thus organizations have to create projects within them, or amongst themselves, which can keep them more viable and competitive in the market. These projects are formed to meet the desired objectives, using the provided resources, within the defined constraints. Although similar in terms of the certain attributes these projects may differ in complexity, size, organizational setup and other attributes. Because of these differences all project cannot be managed in a similar manner and will require different management models (Shenhar, 2001). Along with management, these projects need surveillance, support and guidance from executives in order to achieve the desired objectives. This is part of the governance mechanism that needs to be put in place. However, the governance mechanism for projects cannot be applied in a similar manner for all types of projects (Miller and Hobbs, 2005). This paper focuses on the relationship between project attributes, project performance and project governance dimensions or roles. The following section summarizes certain aspects of the literature review that was conducted as part of this research. Project and Project Attributes Defining a Project Office of Government Commerce (OGC) defines project as "a temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case" (OGC, 2009, p. 3.). Project Management Institute (PMI) states that a project is a temporary endeavor undertaken to create unique product, service or result (PMI, 2008, p. 5).Association for Project Management (APM) on the other hand defines project as "a unique, transient endeavor undertaken to achieve a desired outcome" (APM, 2009a, p. XV).These definitions focus on three project characteristics: 1. Temporary organization which represents a beginning and an end 2. Endeavour or production function which represents some actions 3. Objective or outcome which represents something to achieve 5
7 Project Attributes Projects differ from each other based on different attributes. Some projects might have high complexity and uncertainty, whereas, for others these factors would be at a lower level (Shenhar, 2001). There might be projects which have a longer conceptualization phase as compared to others (Miller and Hobbs, 2005). Organizations tend to group project projects together based on these attributes in order to manage them more effectively. Project attributes that were analyzed as part of this research were: 1. Project Complexity: This factor determines the complexity of the project from the following perspectives: a. Project Duration b. Technical Complexity c. Scope Complexity d. Stakeholder Complexity e. Impact Complexity f. Project Ownership Structure Complexity 2. Project Uncertainty: This factor determines the uncertainty of the project from the following perspectives: a. Requirement Certainty b. Requirement Stability c. Process Certainty 3. Project Strategic Value: This factor determines the strategic value of the project under consideration. The strategic value of the project is being determined from the following perspectives: a. The strategic importance of the project b. The investment the organization is making in the project. Project Performance There seems to be general agreement amongst researchers (Shenhar, Levy and Dvir, 1997; Atkinson 1999; Cookie-Davies 2002; Hartman and Ashrafi 2002), that project performance measures, in terms of project progress, and project success criteria, though interlinked, can be differentiated from a perspective of ex ante and ex post project closure metrics. In terms of software projects Jiang et al. define project performance as "the extent to which the software development process has been undertaken as well as performance of the delivered system from the view point of the users" (Jiang et al., 2004, p. 282). They relate to the idea proposed by Nidumolu (1996), and mention that the project performance should be studied from the perspective of 6
8 product performance as well as process performance (Jiang et al., 2004). This is because, a project that delivers a high-quality product, while exceeding time and cost expectation, cannot be considered as a high-performing project. Jiang et al. relate to the idea of standardization and mention that the software development maturity level of the organization has an influence on project performance (Jiang et al., 2004). This study focuses on the monitoring and measurement of project performance and progress, during its life cycle or right after closure and does not directly relate to measurement of project success in terms of business benefits or product success over its lifetime. This is in alignment with the Cookie-Davies proposal that "For the project management community, it is also important to make the distinction between project success (which cannot be measured until after the project is completed) and project performance (which can be measured during the life of the project)"(cookie-davies, 2002, p. 188). Three performance dimensions, along with overall performance, were analyzed as part of this research. These are: 1. Meeting Constraints and Stakeholder Expectations: This factor combines variables that determine the project performance as perceived by the stakeholder and certain aspects which seem to create that perception. This alignment seems to be logical as meeting project milestones generally creates a perception of improved project performance and increases the stakeholder satisfaction level. The following are the underlying variables: a. Meeting budget goals b. Meeting schedule goals c. Meeting milestones d. Client satisfaction project progress. e. Client satisfaction project results f. End-user satisfaction g. Project team s satisfaction h. Other stakeholder satisfaction 2. Meeting Design Goals and Expectations: This factor determines whether the project is meeting the user requirements, and delivering a high quality solution that is aligned with the technical design specifications. The underlying variables for this factor are: a. Meeting user requirements b. Meeting technical specification c. High quality solution 3. Adherence to Process: 7
9 This factor determines whether the project is performing well in terms of the application of a defined process. The following variables determine this: a. Adherence to project process b. Successful audits Adherence to project process is an internal perspective which ensures that the team is following the defined process. Successfully passing audits means that the audit results confirm that the project is compliant with the process, and the audit report depicts none-to-few non-compliance issues. Project Governance Defining Project Governance Researchers have focused on project governance from different perspectives and scope. Some researchers focused on the governance using behavioral control (Müller, 2010b) through governance of project management, whereas, others have paid attention to governing the project environment through different mechanisms, roles and institutions (Turner and Keegan, 2001; Müller, 2011). Yet there are others who have paid attention to governance functions required for specific projects based on project attributes (Miller and Hobbs, 2005; Müller and Blomquist, 2006; Klakegg et al., 2008). All of these perspectives are important to design an effective project governance environment within an organization. Klakegg et al. mention that alignment of the portfolio with organizational objectives and sustainability of results can be termed as governance through projects whereas efficient delivery of project is related to governance of projects (Klakegg, et al. 2008). Klakegg et al. defined project governance as Governance of projects concerns those areas of governance (Public and Corporate) that are specifically related to project activities. Good project governance ensures relevant, sustainable alternatives are chosen and delivered efficiently. (Klakegg et al., 2008, p. 29). Turner and Keegan focus on the objectives of governance mechanisms, for project-based organizations, and mention that these mechanisms are "adopted to support the operation control processes, and to manage the interface between project teams and their clients." (Turner and Keegan, 2001, p. 256). Turner states that Project governance provides a structure through which objectives of the project are set and the means of attaining those objectives are determined and the means of monitoring the performance are determined (Turner, 2006b, p. 93). Taking an internal perspective, in order to elaborate on the relational structure of project governance, he further explains that "Project governance involves a set of relationships between a project's management, its sponsor, its owner and other stakeholders." (Turner, 2006b, p. 93). Müller takes an objective achievement and value addition perspective about project governance, when he states that It comprises the value system, responsibilities, processes and policies that allow projects 8
10 to achieve organizational objectives and foster implementation that is in the best interests of all the stakeholders, internal and external, and the corporation itself"(müller, 2010a, p. 3; Müller, 2011, p. 306). Müller identified three important aspects of project governance which are (Müller, 2010a; Müller, 2010b): 1. Defining the objectives of the project. 2. Providing the means and resources. 3. Monitoring and controlling the project progress and utilization of resources through governance oversight. PMI defines project governance as a mechanism that "provides a comprehensive, consistent method of controlling the project and ensuring its success" (PMI, 2008, p. 20). The project governance framework must be aligned with the larger context of the organization, which owns, or sponsors, the project. Project Governance Dimensions It is important to discuss the term dimension, which is considered as a synonym for attribute, or aspect. American Heritage Dictionary (2004) defines dimension as aspect or element. The concept of governance dimension is at a higher level, of abstraction, and is, in some terms, different from the functions of governance. Crawford et al. (2008), when they discuss the role of sponsor, and Müller (2009), when he discusses the role of steering group; refer to governance roles, which is in alignment with the concept of governance dimensions. There are three main roles or dimensions of project governance identified in this research: 1. Project Surveillance, which relates to overseeing the project progress in order to ensure that the project is moving as per the committed plan and within the defined threshold (Müller, 2010a; Müller, 2010b). 2. Project Control, which relates to controlling the progress of the project and the action of the management team. 3. Project Support and Guidance, which relates to the need of support and guidance from the project governance team during project life cycle. Methodology and Analysis This study can be considered as quantitative in nature, with data being gathered using online survey. The survey request was sent to 343 IT project governors, out of which 183 responded to the survey. This gives us a response rate of 53.35%, however, 168 were considered as complete and relevant responses. So the overall response rate of completed responses is 48.98%. Some of the salient findings from the demographics data above show that: 1. The majority of the respondents of the survey are male. 9
11 2. All of the respondents are above 30 years in terms of age, with 25.6% being at or above the age of 45 years. 3. The majority of the respondents have more than 10 years of work experience. 4. From a qualification and experience perspective, the majority of the respondents mentioned that they have relevant qualifications to oversee and govern projects, and have up to 10 years of project governance experience. 5. Seventy-nine% of the survey respondents mentioned that hold senior positions in their respective organizations. 6. The respondents were from all over the world, however most of the survey respondent s organizations belonged to Gulf Cooperation Countries (GCC) or North America; the cumulative percentage being 68%. 7. From an organizational type perspective, the respondents were equally divided between private and non-private (public and state owned enterprise) organizations. 8. From an organizational domain perspective, the respondents belonged to all domains mentioned in the survey. However IT, consulting, banking and finance represent 56% of the respondents. The above analysis of demographic information enhanced the confidence of the researcher about the data collection source, as it shows that appropriate respondents answered the survey. The data was reviewed and cleansed for analysis, while treating the outliers and missing values. Factor analysis was conducted to identify the underlying factors within the variables, and Cronbach's alpha technique was applied to test the reliability of the constructs. Lastly regression analysis was used to test the hypotheses. Results of the Research Influence of Project Attributes From a project attributes perspective, it is clear that certain project attributes have an influence on the project governors for preference of project governance dimensions and the overall governance. This is aligned with the earlier studies of researchers (Miller and Hobbs 2005; APM 2007b; Klakegg et al. 2008; Müller 2009). The following sections discussion this in further detail. Project Complexity If we further analyze the results in depth, project complexity did not have any impact on any of the project governance dimensions. This may be because the aspect of project complexity is generally handled at the level of project manager and the project team, without excessive intervention from the project governors. Project governors have an inclination of not getting too much involved in the technical details related to the project. Even though they may have a general impression about the complexity involved in the projects that they are governing, however their preference for governance dimensions typically is not influenced by this high-level understanding. 10
12 Project governors tend to trust their managers, and the project team, to handle and reduce project complexity and deliver the project within the defined constraints. Thus, while designing the governance framework, project complexity is not considered as a major influencer, whereas during project execution and delivery the complexity of the project does not influence the governors to alter their preference for governance dimensions. There are factors, other than project complexity, influencing this phenomenon. Project Uncertainty Based on the results, project uncertainty has an influence on the project support and control dimensions as well as overall governance. This influence, however, is in the negative direction, which means that higher the uncertainty, the lesser will be the preference for support, control and overall governance. Projects in our sample are IT projects, which generally have high level of uncertainty (Na et al. 2004), and this uncertainty gets resolved as the project progresses (Turner and Cochrane 1993). To resolve this uncertainty aspect highly evident in IT projects, special practices related to managing IT projects are developed by organizations. Researchers have also emphasized that specific project management techniques are being developed for standardization, in order to manage requirement uncertainty (Na et al. 2004). This means that project uncertainty is handled at the level of project management, and project governors allow the project team to handle the uncertainty aspect of the project. This may be because that project governors might consider themselves to be in a position where they are unable to take project related decisions because of a lack of clear information and a detailed roadmap. Project governors tend to withdraw themselves from the project at this stage, and the project team owns the project during this uncertainty period and tries to reduce this by clarifying the requirements and putting a clearer roadmap with minimal governance. As the project progresses and more details are available, the project governors tend to get more involved in the project and provide the required support to the project team. Along with that, because of the clearer understanding of the project, project governors start controlling different aspects of the project when things tend to move in the wrong direction. Thus, project clarity allows project governors to take informed decisions and the level of support and control increases with increased level of certainty. Based on this discussion, we can state that project uncertainty is an important attribute that needs to be considered when designing project governance frameworks. Also the level of uncertainty has to be reduced, as early as possible, by the project team in order to ensure that the project governors can understand different aspects of the project, which are relevant to them, so that they can play their true role of overseeing and steering the project. Project Strategic Value The results show that project strategic value is the most influential attribute impacting all governance dimensions, as well as overall governance. This impact is in a positive direction, which means that higher 11
13 strategic value will result in increased support, control, and surveillance as well as an increased preference for overall governance. The result is aligned with what we observe as practitioners as well as researchers. Strategic decisions are taken by senior managers, where projects act as strategy execution vehicles. Because of the investments made by the organization in highly strategic projects, the project governors focus on these projects in order to ensure that the projects meet their desired objectives. Unlike project uncertainty and complexity, the information flow in case of strategic value is from the senior managers to the project manager and the project team. Project governors have to ensure that the project stays aligned with the organizational goals, and the investment made in these projects delivers the required value to the organization. As the strategic value of the project decreases, i.e. if the project is of low strategic importance or the cost of the project is low, the focus on different dimensions of governance also decreases. This may be because the investment required governing such projects may be much higher than the project s value to the organization. This is in alignment with the classical transaction cost economics perspective, which advocates economization of governance structure based on the transaction attributes (Williamson 1979). This means that it does not make economic sense to create governance frameworks with complex structure, multi-facet measurement parameters and tools for projects of low strategic value. Rather a simpler model can be created that can still ensure project delivery without creating cumbersome bureaucracy. Based on the discussion, above, we can conclude that high strategic value projects require a higher level of governance from the project governors in order to ensure that the project can deliver its strategic value. Even though the project governors still allow the project manager to manage and execute the project activities, they work very closely with the project manager and the project team. They advocate for the project in front of other stakeholders and support the project team whenever needed. They also create monitoring mechanisms in such a way that any deviation, above the threshold, is observed, and decisions are made to bring the project back on track. All this is done to ensure that the project delivers its objectives, which are critical for organizational success. Conclusion We can conclude from the discussion, that project attributes have an influence on project governance dimensions. These attributes should be considered while designing the governance frameworks. As the project attributes change during the course of the project, the project governance framework should be reevaluated and revised if it is not aligned with the project attributes. This will ensure that an economical, effective and efficient governance framework is in place during the course of the project, which will result in improved project results. One thing that is worth discussing at this stage is the reflexivity of the circumstances. In our current study we are hypothising that project attributes influence project governance dimension. However the causality may be the other way around, that is, because governors do not engage in the project it 12
14 remains uncertain for a prolonged period because of lack of support from the governors. This can be a good topic to research in future. One should however be careful in deciding which attributes have a real impact on the governance framework. Based on this study, project complexity does not have an impact of governance dimensions, whereas project uncertainty and strategic value influenced the preference for governance dimensions. Thus governance frameworks that are considerate of these results may have a more positive impact on the project. The following conceptual diagram (Figure 1) displays an initial version of Contingent Governance Framework for Projects (CGFP): Pre-Initiation and Project Setup Governance Framework Design Influencing Factors Project Attributes Governance Framework Elements Governance Structure and Roles Governance Mechanism Governance Functions Assets to Govern Preference for Governance Dimensions Project Life Cycle (Review Based on Governance Mechanism) Governance Framework Redesign Influencing Factors Project Attributes Review Objective Project Reporting and Status Project related Decisions Review of Governance Framework Elements Figure 1: Contingent Governance Framework based on influence of Project Attributes Influence of Project Performance From a project performance perspective, it is clear that certain project performance dimensions have an influence on the preference of project governors for support and control governance dimensions and the overall governance. However, there was no impact on project surveillance dimension, which means that the monitoring aspect of governance remains uninfluenced by the project performance dimensions. Along with that, overall project performance (as a combined concept) has an impact on preferences of all governance dimensions, as well as overall governance. This is aligned with the earlier studies of researchers, which mention that project performance has an influence on project governance dimensions (Cable et al. 2004; Crawford et al. 2008). The following sections discuss this in further detail. Meeting constraints and stakeholder expectations The results show that meeting constraints and stakeholder expectations had an impact on the support and control dimension, whereas the surveillance aspect of governance remained uninfluenced by this performance dimension. Meeting constraints and stakeholder expectations also has an influence on the overall governance. All of these impacts are in a positive direction, which means that if the project is 13
15 performing well from this perspective, it will receive more support, however, the project governors will also be controlling the project, and the overall level of governance will also be high. The focus of this dimension is on measuring the project performance by assessing the adherence to defined constraints of budget, schedule and milestones. It also looks at the perspective of different stakeholders in terms of project performance. This aspect ensures that the impact of project performance on different beneficiaries or impacted groups is taken into consideration. If a project is doing well from this perspective, the project governors tend to get more involved in the project by providing the required support and controlling the project so that the project keeps on performing well and stakeholders remain satisfied with the progress. However, a project, which is a non-performer from this dimension, seems to progressively lose attention of the project governors, as it does not get the required support, and project governors do not take control of such projects. This is in contradiction with what was reviewed in the literature (Crawford et al. 2008), which mentions that non-performing projects are controlled by the project governors. However it does make sense from one perspective, because the project governors, instead of supporting or controlling the project, may want to terminate projects, which are consistently not meeting the defined deadlines and milestones, and the stakeholders are not happy with the performance for a prolonged period. Such decisions are made by projects governors during the status review sessions (Müller 2010a). This phenomenon can also be explained by discussing the reflexivity of situation here as well. The performance of the project from this aspect can be low because the project governance might not be engaged in the project. This aspect has been discussed by Turner and Müller (2004) when discussing the communication model between principle and agent and its impact on project results. Based on this discussion we can state that, during the project progress, performance from a perspective of meeting constraints and stakeholder expectations should be considered when re-defining the project governance framework at the time of the review. The monitoring mechanism may remain consistent, however, the project governors should consistently reevaluate their preference for support and control throughout the project life cycle based on the project performance from this aspect. However, when projects do not perform well for a prolonged period, they should be considered for termination or realignment. Meeting design goals and expectations The results show that meeting design goals and expectations had an impact on the support dimension, whereas the control and surveillance aspect of governance remained uninfluenced by this performance dimension. Meeting design goals and expectations also has an influence on the overall governance. All of these impacts are in a positive direction, which means that if the project is performing well from this perspective, it will receive more support, and the overall level of governance will also be high. The concept of reflexivity, as discussed above, can also be applied for this observation. 14
16 The focus of this dimension is on measuring project performance by meeting the user requirements and ensuring that the end deliverable is a high-quality solution. If a project is doing well from this perspective, the project governors tend to get more involved in the project by providing the required support. This support is to ensure that the project keeps on meeting the user requirements and design goals expected from the end product or solution. It should be clear that fulfilling the customer requirements in terms of solutions development is an internal looking perspective, and is the responsibility of the project manager and the team without much intervention from the project governors. Project governors are expected to provide an oversight function and support the project team when required. That might be the reason that the control and surveillance aspect of project governance are uninfluenced because of this performance aspect. This is in partial alignment with the literature (Crawford et al. 2008), which mentions that if a project is performing well it gets the required support; however, a non-performing project loses this support. Based on this discussion we can state that, during the project progress, performance from a perspective of meeting design goals and expectations should be considered when re-defining the project governance framework at the time of a project review. The monitoring and controlling mechanism may remain consistent; however, the project governors should consistently reevaluate their preference for support throughout the project life cycle based on the project performance from this aspect. Adherence to process The results show that adherence to process had an impact on the support dimension, whereas the control and surveillance aspect of governance remained uninfluenced by this dimension. Adherence to process also has an influence on the overall governance. All of these impacts are in a positive direction, which means that if the project is performing well from this perspective, it will receive more support, and the overall level of governance will also be high. The concept of reflexivity, as discussed above, can also be applied for this observation. Process alignment is considered as a major aspect of project performance, especially in IT projects (Nidumolu 1996). The focus of this dimension is on ensuring that the project is following the defined process, and it is passing through the internal and external compliance audits with minimal issues. Similar to the above perspective of meeting design goal and expectations, if a project is doing well from a process adherence perspective, the project governors tend to get more involved in the project by providing the required support. They may provide additional resources in order to ensure that the project remains aligned with the process. This is important, as standardized process reduces dependency from individuals. It should be clear that fulfilling following the process and adhering to standards is also an internal looking perspective, and is the responsibility of the project manager and the project team without much intervention from the project governors. Project governors are expected to provide an oversight function and support the project team when required. That might be the reason that control and surveillance aspect of project governance are uninfluenced because of this performance aspect. Similar 15
17 to the previous section this phenomenon is also in partial alignment with the literature (Crawford et al. 2008), which mentions if a project is performing well it gets the required support; however a nonperforming project loses this support. Based on this discussion we can state that, during the project s progress, project s adherence to process should be considered when re-defining the project governance framework at the time of the project review especially from a perspective of providing support to the project. The monitoring and controlling mechanism may remain consistent; however, the project governors should consistently reevaluate their preference for support throughout the project life cycle based on the project performance from this aspect. Overall Performance Project performance from an overall perspective had an impact on all project governance dimensions as well as overall governance. All of these impacts are in a positive direction, which means that if the project is performing fine, it will receive more support, however the project governors will also be monitoring controlling the project, and the overall level of governance will also be high. Along with that the bi-directional relationship between project performance and governance can also be applied for this observation. This means that lack of governance might be acting as a cause of low performance of projects. This perspective of performance is based on an overall perception of project performance in the organization. Organizations value high-performing projects and governors provide support to such projects by advocating the projects in front of different stakeholders and granting the required resources for successful execution and project delivery. Because of the high probability of success for such projects, project governors consider them as opportunities for successful delivery of business value, and tend to closely monitor and control such projects so that such project continue to perform well. As discussed earlier, consistently non-performing project lose the support from the governors. The governors also tend to become less interested in such projects and may eventually suggest terminating such projects. Thus we see that the level of monitoring and control reducing as the performance of the project is no longer in alignment with strategic objectives. Based on this discussion we can state that, during the project progress, the overall performance should be considered when re-defining the project governance framework at the time of the review. The project governors should consistently reevaluate their preference for support, monitoring and control throughout the project life cycle based on the project performance. However, when projects do not perform well for a prolonged period they should be considered for termination and the organization s project portfolio should be rebalanced. 16
18 Conclusion We can conclude from the discussion that overall project performance and its underlying dimensions have an influence on project governance dimensions. As the project performance changes during the course of the project, the project governance framework should be reevaluated and revised. This will ensure that an economical, effective and efficient governance framework is in place during the course of the project, which will result in improved project results. There are some interesting findings in this area. One of them is the contradiction with the existing literature that low-performing projects will require more control from the project governors. This was not the case in this study. We have seen from the results that as the project performance misaligns with the performance expectations and strategic objectives, the level of control from the project governors also is lessened. We have justified this by mentioning that project governors tend to disassociate from consistent low-performing projects and such projects eventually qualify for termination. The project governors may lose interest in governing such projects and may escalate the project for cancellation. This can also be explained from a perspective, that projects that are performing exceptionally well receive more support and control from project governors because the probability of eventual success of such projects is high. Thus project governors focus on such initiatives to ensure that they deliver the expected value to the organization. However, there are two more interesting aspects related to this phenomenon which have been briefly discussed in the sections above: 1. Project performance is one of the factors that explain the variance in project governance dimensions. There would be other factors, such as project attributes, that may also explain this reduction in project monitoring and control, as well as overall governance when measured in conjunction. This can be researched in future studies. 2. It is also evident in the literature (Crawford and Cooke-Davies 2005; Simonsen 2007) that project governance and top management support has an influence on the project performance. This means that there may be a bidirectional relationship between the two concepts which can be explained by reflexivity of circumstances. There is a possibility that because governors do not engage in the project the project performance turns out to be below the expectation level. This has more support through existing literature (Turner and Müller, 2004) and can be an interesting topic for future research. Having said this, it is important for the governance frameworks to be adaptive to the project performance context. It is also important to identify, in a particular context, the performance dimensions that are relevant and imperative for the organization to monitor. Based on the performance variance, from the perspective of identified performance dimensions, the organization may redefine its governance mechanism in order to improve the performance of the project resulting in eventual success. 17
19 The following conceptual diagram (Figure 2) shows the influence of project attributes and project performance on project governance framework, and displays a more refined version of CGFP: Pre-Initiation and Project Setup Governance Framework Design Influencing Factors Project Attributes Governance Framework Elements Governance Structure and Roles Governance Mechanism Governance Functions Assets to Govern Preference for Governance Dimensions Project Life Cycle (Review Based on Governance Mechanism) Governance Framework Redesign Influencing Factors Project Attributes Project Performance Review Objective Project Reporting and Status Project related Decisions Review of Governance Framework Elements Figure 2: Contingent Governance Framework based on influence of Project Attributes and Project Performance Contingent Governance Framework for Projects (CGFP) In the end, based on the literature review and the subsequent hypotheses testing, we have attempted to build an initial version for Contingent Governance Framework for Projects (CGFP). CGFP has Transaction Cost Economics as its underlying theory, as it is based on the concept that in order to economize on transaction costs, projects of different attributes should be governed through frameworks that are aligned with the project attributes and context. The objective of creating such a framework is based on the understanding that the governance frameworks should adapt to the changing project contexts. This may result in provisioning of effective oversight organization that will assist the project in delivering its objectives, instead of creating additional layers of reporting and delayed decisions. The following figure (Figure 3) provides the first draft for CGFP. This model will be further analyzed, refined and elaborated in future studies: 18
20 Figure 3: Contingent Governance Framework for Projects (CGFP) Various factors influence the design of the project governance frameworks, and we call them Influential Factors (IFs). Some of the factors, such as project attributes and project performance, have been 19
21 quantitatively analyzed in this research, whereas others have been identified during the literature review, and it would be interesting to analyze them further in other studies. The following table (Table 1) shows different IFs and their related references: Table 1: Influential Factors and References - CGFP Influential Factor Project Attributes Project Performance Organizational Governance Paradigm References Analyzed quantitatively in current study Analyzed quantitatively in current study Weil 2004; Weil and Ross 2004; Müller 2010a; Müller 2010b; Müller 2011 Project Manage and Team Experience Crawford et al Social and Cultural Impact Klakegg et al Corporate Governance APM 2007a; Klakegg et al. 2008; Müller 2010a Theses IFs impact the different Governance Framework Elements (GFE) which are: 1. Governance Structure and Roles, which identifies the people and groups that should be involved in governance e.g. Sponsor, PMO, and Project Governance Board. The bodies and entities for governance may differ from organization to organization and type of projects that have to be governed. 2. Governance Mechanism, which defines how the governance will take place such as Stage Gates and Project Audits. Similar to the management model, the governance mechanism for projects cannot be applied in a similar manner for all projects (Miller and Hobbs, 2005). Thus, organizations adopt different mechanisms to govern their initiatives depending on the influential factors identified in this research. 3. Governance Functions, which define different functions performed by the governance entities. These functions include activities such as governing the benefits delivered by the project, strategic alignment of projects with organizational strategy, reviewing the project progress and providing governance oversight throughout project life cycle. 4. Assets to Govern, which identifies the different areas of projects that will be governed. Project governance functions are applied to provide an oversight function over assets that have to be overseen in order to meet the project objectives. These assets include but are not limited to project processes, project decisions and project resources. 5. Preference for Governance Dimensions, which will define the level of preference for each dimension of project governance. These dimensions include support, control and surveillance 20
22 dimensions as identified in this research. An effective governance framework will have a balanced level of support, control and surveillance applied by the governance entities. These elements should be carefully designed based on the IFs so that an economically viable and efficient governance framework can be designed, which should influence improved project performance. Figure 3 shows that project governors provide governance oversight on project assets by implementing a right balance of support, control and surveillance dimension through governance functions. These functions are utilized based on the governance mechanism adopted by the organization. It is however important to note that once the governance model is operational, it should not become something which cannot be redesigned or altered for improvement. Because of the project execution the overall project context will change, and additional IFs such as project performance will come into play. These IFs will play a role in redesigning the governance framework so that the objective of economic viability and efficient governance is consistently achieved. The redesigning of governance framework may take place at predefined milestones or at the time of a gate review or project audits. This review could also occur during an overall review for greater process effectiveness or during a maturity assessment. Relating to the current research it is clear that project attributes and project performance (IFs) influence the preference of project governors (GFE) for different project governance dimensions (GFE). Thus these IFs should be considered when designing and redesigning the governance frameworks. The role of governance is to oversee the project and ensure that the project either delivers its objectives, or its existence is reassessed. The redesigning of governance framework based on IFs ensures that governance consistently plays its role effectively and efficiently. Implications Theoretical Implications The following sections discuss the theoretical implications of this study in different areas of research. Identification of Constructs This research focuses on identifying different factors that have an influence on project governance and its dimensions. While the main focus of this research is project attributes and project performance, other factors, such as corporate governance, organizational governance paradigm and others, have also been identified during the literature review that can be verified in other studies. This research helped in identification of some underlying dimensions of project governance through the literature review, which were later confirmed using data analysis. The project governance dimensions, i.e. support, control and surveillance, can be used in future studies related to project governance, e.g. to test the influence of different dimensions of governance on project manager motivation or project success. 21
23 Along with that the research also helped in identification of some underlying dimensions of project performance. The performance dimensions identified in this study, i.e. meeting constraints and stakeholder expectations, meeting design goals and expectations and adherence to process, are aligned with project performance and success measures of earlier studies. These performance measures can be used in future studies e.g. measure project performance from different aspects or influence of different factors on different performance dimensions. Development of Framework This research is a step toward development of a contingent framework for governance of projects. The author would like to title it as Contingent Governance Framework for Projects (CGFP). This framework considers the importance of context when designing, implementing and redesigning project governance frameworks. Even though the framework is in its initial stages, i.e. certain aspects of the framework will require significant research; it provides an initial direction for subsequent researches. Having said that, the existing framework is based on current literature and certain phenomenon were tested as part of this study. Quantitative Research Most of the studies in the field of project governance have been qualitative in nature (Turner and Keegan 2001; Miller and Hobbs 2005; Crawford et al. 2008; Klakegg et al. 2008). Even though Müller and Blomquist did conduct mixed-methods research related to this concept (Müller and Blomquist 2006); however, such studies can be considered as limited at this moment. This study, which provides insights about the level of influence that certain factors exert on project governors, can be considered as a significant addition to the area of quantitative studies in project governance. Practical Implications Efficient Governance of Projects This research will help practitioners to recognize different factors that influence the manner in which projects are governed. These insights will help them in adjusting their governance style based on the influencing factors. Along with that the results of this study may help practitioners to deploy more effective governance frameworks for different types of projects, which can adjust based on changing project contexts, especially its performance. Using the initial version of CGFP, practitioners can develop governance frameworks, which are not rigid and have a redesigning mechanism during the project life cycle. This will improve the likelihood of having a framework that is effective, efficient and aligned with the project attributes, project performance and other influencing factors. 22
24 Project Categorization The research identified certain project attributes that can be used by people in organizations in developing their project categorization systems. This categorization system can be used by the executives in organization to manage and govern projects by using appropriate methodologies and frameworks. Organizations tend to customize their project management methodology based on the type of project; for example project of high complexity and uncertainty might require a different management mechanism than a project which has relative low complexity. Along with that certain project attributes such as the strategic value of the project might influence different portfolio level decisions. Organizations might create different portfolios for different types of project in order to manage and govern them more effectively. Project Performance Metrics The research identified certain project performance dimensions that can be used by organizational leaders in measuring project performance from different aspects. Different organizational groups can focus on different aspects of performance, which will result in ensuring that the overall performance of the project stays aligned with the performance metrics. In order to explain this further, an organizational entity such as enterprise process group, that focus on the process aspect of the project, might closely monitor the project from adherence to process aspects, whereas, the quality control and design authority teams might be more interested in monitoring the meeting design goals and expectations metric. This model will help organizations to measure different aspects of project progress by entities that are considered experts in the specific domain. Understanding the Role of Governance This study can also help project managers, project teams and other stakeholders in understanding the role that governance should play during the project life cycle. It will also help them understand different factors that influence different aspects of governance, including the method in which the governance is carried out by the governing entities. This knowledge can help in better alignment between different project roles resulting in improved chances of project success. 23
25 References American Heritage Dictionary. (2004). The American Heritage Dictionary of the English Language (4 th ed.). Boston, USA: Houghton Mifflin Harcourt. Association for Project Management (APM). (2007a). Directing Change: A Guide to Governance of Project Management: Buckinghamshire, UK. Association for Project Management (APM). (2007b). Co-Directing Projects: A Guide to the Governance of Multi-Owned Projects: Buckinghamshire, UK. Atkinson, R. (1999). Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), Cable, J. H., Ordonez, J. F., Chintalapani, G., & Plaisant, C. (2004). Project portfolio earned value management using treemaps. Paper presented at the Project Management Institute (PMI) Research Conference, London, UK. Cooke-Davies, T. (2002). The "real" success factors on projects. International Journal of Project Management, 20 (3), Crawford, L., & Cooke-Davies, T. (2005). Project Governance: The pivotal role of the executive sponsor. Paper presented at the PMI Global Congress 2005, Toronto, Canada. Crawford, L., Cooke-Davies, T., Hobbs, B., Labuschagne, L., Remington, K. & Chen, P. (2008). Governance and support in the sponsoring of projects and programs. Project Management Journal, 39(1), doi: /pmj Hartman, F., & Ashrafi, R. A. (2002). Project management in the information systems and information technologies industries. Project Management Journal, 33(3), Jiang, J. J., Klein, G., Hwang, H., Huang, J., & Hung, S. (2004). An exploration of the relationship between software development process maturity and project performance. Information and Management, 41(3), Klakegg, O. J., Williams, T., Magnussen, O. M., & Glasspool, H. (2008). Governance frameworks for public project development and estimation. Project Management Journal, 39 (1), doi: /pmj Miller, R., & Hobbs, B. (2005). Governance regimes for large complex projects. Project Management Journal, 36(3), Müller, R. (2009). Project Governance. Surrey, England: Gower Publishing Limited. 24
26 Müller, R. (2010a). Project governance: Procedural straight jacket or freedom of arts. [Presentation at the CONCEPT Symposium, Oscarsborg, Norway]. Müller, R. (2010b). Project governance. [Monthly Column - Series on Advances in Project Management]. PM World Today, XII(III), 1-6. Müller, R. (2011). Project governance. In Pinto, J., Morris, P., & Söderlund, J. (Ed.), Oxford Handbook of Project Management. Oxford, UK: Oxford University Press. Müller, R., & Blomquist, T. (2006). Practices, roles, and responsibilities of middle managers in program and portfolio management. Project Management Journal, 37(1), Na, K., Li, X., Simpson, J. T., & Kim, K. (2004). Uncertainty profile and software project performance: A cross-national comparison. The Journal of Systems and Software, 70(1-2), Nidumolu, S. (1996). Standardization, requirements uncertainity and software project performance. Information and Management, 31 (3), Office of Government Commerce (OGC). (2009). Managing Successful Projects with PRINCE2. London, United Kingdom: The Stationery Office (TSO). Project Management Institute (PMI). (2008). A Guide to the Project Management Body of Knowledge (Fourth Edition). PA, USA: Project Management Institute, Inc. Shenhar, A. J. (2001). One Size does not fit all projects: Exploring classical contingency domains. Management Science, 47(3), doi: /mnsc Shenhar, A. J., Levy, O., & Dvir, D. (1997). Mapping the dimensions of project success. Project Management Journal, 28(2), Simonsen, J. (2007). Involving top management in IT projects: Aligning business needs and IT solutions with the problem-mapping technique. Communication of the ACM, 50(8), Turner, J. R. (2006a). Towards a theory of project management: The nature of the project. International Journal of Project Management, 24(1), 1-3. Turner, J. R. (2006b). Towards a theory of project management: The nature of project governance and project management. International Journal of Project Management, 24(2), Turner, J. R., & Cochrane, R. A. (1993). Goals-and-methods matrix: coping with projects with ill defined goals and/or methods of achieving them. International Journal of Project Management, 11(2), Turner, J. R., & Keegan, A. (2001). Mechanisms of governance in the project-based organization: Roles of the broker and steward. European Management Journal, 19(3),
27 Turner, J. R., & Müller, R. (2004). Communication and cooperation on projects between the project owner as principal and the project manager as agent. European Journal of Management, 22(3), Weil, P. (2004). Don't just lead, govern: How top-performing firms govern IT. MIS Quarterly Executive, 3(1), Weil, P., & Ross, J. W. (2004). IT Governance: How top performers manage IT decision rights for superior results. Boston, MA, USA: Harvard Business School Press. Williamson, O. E. (1979). Transaction cost economics: The governance of contractual relationships. Journal of Law and Economics, 22(2),
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
Author: Carlos Eduardo Martins Serra, MSc, PMP [email protected] Supervisor: Martin Kunc, PhD [email protected]
Benefits Realization Management and its influence on project success, project governance, and execution of business strategy - Analysis of Brazil, the United Kingdom, and the United States of America This
The Agile PMO. Contents. Kevin Thompson, Ph.D., PMP, CSP Agile Practice Lead cprime, Inc. 4100 E. Third Avenue, Suite 205 Foster City, CA 94404
The Agile PMO Kevin Thompson, Ph.D., PMP, CSP Agile Practice Lead cprime, Inc. 4100 E. Third Avenue, Suite 205 Foster City, CA 94404 [email protected] Abstract The development of Agile processes
Project Management Office Charter
Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management
Sound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
Program Management Professional (PgMP) Examination Content Outline
Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management
EVOLVING THE PROJECT MANAGEMENT OFFICE: A COMPETENCY CONTINUUM
EVOLVING THE PROJECT MANAGEMENT OFFICE: A COMPETENCY CONTINUUM Gerard M. Hill Many organizations today have recognized the need for a project management office (PMO) to achieve project management oversight,
Portfolio Management Professional (PfMP)SM. Examination Content Outline
Portfolio Management Professional (PfMP)SM Examination Content Outline Project Management Institute Portfolio Management Professional (PfMP) SM Examination Content Outline Published by: Project Management
Project Management and Scrum A Side by Side Comparison by Anne Loeser, October 2006
Project Management and Scrum A Side by Side Comparison by Anne Loeser, October 2006 For decades, software development projects have followed the classic waterfall method in which software development initiatives
PRINCE2:2009 Glossary of Terms (English)
accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain
Assessing Your Information Technology Organization
Assessing Your Information Technology Organization Are you running it like a business? By: James Murray, Partner Trey Robinson, Director Copyright 2009 by ScottMadden, Inc. All rights reserved. Assessing
Partnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
Introduction to OpenPPM
0 Introduction to OpenPPM Content Table Introduction to OpenPPM... 1 0.1. OpenPPM: A tool thought by and for Project Managers... 2 0.2. Project, Program and Portfolio Management... 3 0.3. What is not OpenPPM?...
General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
DNV GL Assessment Checklist ISO 9001:2015
DNV GL Assessment Checklist ISO 9001:2015 Rev 0 - December 2015 4 Context of the Organization No. Question Proc. Ref. Comments 4.1 Understanding the Organization and its context 1 Has the organization
Project Management Office (PMO) Charter
Project Management Office (PMO) Charter Information & Communication Technologies 10 January 2008 Information & Communication Technologies Enterprise Application DISCLAIMER Services Project Management Office
Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion
Measuring ROI of Agile Transformation
Measuring ROI of Agile Transformation Title of the Paper: Measuring Return on Investment (ROI) of Agile Transformation Theme: Strategic & Innovative Practices Portfolio, Programs & Project (PPP) Management
Project organisation and establishing a programme management office
PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC Abstract PMBOK is the recognized (de facto) standard of project management knowledge. In the UK and Europe, PRINCE2
Why are PMO s are Needed on Large Projects?
Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects
Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R.
August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R. Max Wideman This series of papers has been developed from our work
ITIL Service Lifecycles and the Project Manager
1 ITIL Service Lifecycles and the Project Manager The intersection of IT Service and Project Delivery Presented to: Kansas City Mid-America PMI Chapter Mark Thomas January 17, 2011 1 Agenda 2 Introduction
ISO 9001:2015 Internal Audit Checklist
Page 1 of 14 Client: Date: Client ID: Auditor Audit Report Key - SAT: Satisfactory; OBS: Observation; NC: Nonconformance; N/A: Not Applicable at this time Clause Requirement Comply Auditor Notes / Evidence
Assessing the Appropriate Level of Project, Program, and PMO Structure
PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects
IRNOP VIII. Brighton, United Kingdom, 2007. Title: A study of project categorisation based on project management complexity
IRNOP VIII Brighton, United Kingdom, 2007 Title: A study of project categorisation based on project management complexity Authors: Alicia Aitken, Dr Lynn Crawford ESC Lille, France and Bond University,
Project Charter and Scope Statement
Prepared by: Mike Schmidt Version: 1.0 Last Revision Date: April 14, 2010 Create Date: May 6, 2010 EXECUTIVE SUMMARY... 3 1 INTRODUCTION... 4 2 PROJECT OBJECTIVES... 4 2.1 MISSION... 4 2.2 OBJECTIVES...
Reaching CMM Levels 2 and 3 with the Rational Unified Process
Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP174 Table of Contents INTRODUCTION... 1 LEVEL-2, REPEATABLE... 3 Requirements Management... 3 Software Project
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
Government Communication Professional Competency Framework
Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their
Name Chapter 1: Introduction to Project Management Description Instructions
Name Chapter 1: Introduction to Project Management Description Instructions Modify Question 1 / 0 points Modify Remove Question Until the 1980s, project management primarily focused on providing schedule
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
PRINCE2 and governance
PRINCE2 and governance Andy Murray, lead author of PRINCE2 (2009) and Director of Outperform UK Ltd White Paper November 2011 2 PRINCE2 and governance Contents 1 Purpose of this white paper 3 2 What is
Project Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP ) Examination Content Outline Revised August 2011 Published by: Project
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Internal Quality Management System Audit Checklist (ISO9001:2015) Q# ISO 9001:2015 Clause Audit Question Audit Evidence 4 Context of the Organization
Internal Quality Management System Audit Checklist (ISO9001:2015) Q# ISO 9001:2015 Clause Audit Question Audit Evidence 4 Context of the Organization 4.1 Understanding the organization and its context
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
http://www.io4pm.org IO4PM - International Organization for Project Management
THE ONLY BOOK CAN SIMPLY LEARN PROJECT MANAGEMENT! Page 1 Contents ABOUT THE AUTHOR... 3 WHAT IS PROJECT MANAGEMENT?... 5 ORGANIZATIONAL INFLUENCES AND PROJECT LIFECYCLE... 11 PROJECT MANAGEMENT PROCESSES...
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
Project Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management
Introduction to project management and concepts
37E01500 Project Management and Consulting Practice Introduction to project management and concepts Matti Rossi, Professor Dept. of Information and Service Economy Lecture 1, Mon 26.10.2015 Learning objectives
Project Governance & Controls
Project Governance & Controls The PMI Perspective, Challenges, Initiatives and Opportunities Sean Whitaker, BA, MSc, MBA, PMP Overview This presentation provides an overview of project management governance
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
System Development Life Cycle Guide
TEXAS DEPARTMENT OF INFORMATION RESOURCES System Development Life Cycle Guide Version 1.1 30 MAY 2008 Version History This and other Framework Extension tools are available on Framework Web site. Release
National IT Project Management Methodology
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version
Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
Topic 1 Introduction. to the Fundamentals of Project Management INTRODUCTION LEARNING OUTCOMES
Topic 1 Introduction to the Fundamentals of Project Management LEARNING OUTCOMES By the end of this topic, you should be able to: 1. Describe the nature of projects; 2. Identify the project life cycle;
Benefits of conducting a Project Management Maturity Assessment with PM Academy:
PROJECT MANAGEMENT MATURITY ASSESSMENT At PM Academy we believe that assessing the maturity of your project is the first step in improving the infrastructure surrounding project management in your organisation.
10 Reasons Why Project Managers Need Project Portfolio Management (PPM)
10 Reasons Why Project Managers Need Project Portfolio Management (PPM) Introduction Many project managers might think they are doing just fine with spreadsheets or basic project management software and
Project Management Methodologies By Jason Charvat, published by Wiley, NJ, 2003 (A book review by R. Max Wideman)
Project Management Methodologies By Jason Charvat, published by Wiley, NJ, 2003 (A book review by R. Max Wideman) 7/8/05 Introduction Jason Charvat published this book in 2003 and in it he discusses "Selecting,
44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
AN INNOVATIVE SQA SERVICE MATURITY MODEL USING CMMI AND ITIL
AN INNOVATIVE SQA SERVICE MATURITY MODEL USING CMMI AND ITIL Shankar Gurumoorthy Senior Quality Leader, Bangalore, India [email protected] ABSTRACT This paper details a maturity model for SQA services
State of California. Contents. California Project Management Office Project Management Framework. Project Management. Framework.
Contents State of California Project Management Framework Page i Contents Overview 1 Introduction 3 8 15 Overview of the CA-PMF Document Structure and Convention Guide Discussion of Lifecycles Templates
Project Management: Back to Basics
About this research note: Technology Insight notes describe emerging technologies, tools, or processes as well as analyze the tactical and strategic impact they will have on the enterprise. Project Management:
HKITPC Competency Definition
HKITPC Competency Definition for the Certification copyright 2011 HKITPC HKITPC Competency Definition Document Number: HKCS-CD-L1L2 Version: 1.0 Date: June 2011 Prepared by Hong Kong IT Professional Certification
Project Management Best Practice Benchmarks
A PM SOLUTIONS RESEARCH COMPENDIUM Project Management COST SCOPE Quality SCHEDULE 2 Project Management Senior executives want to know one thing about project management: What s the value? Today more than
MoP Glossary of Terms - English
English Term aggregated risk English Definition The overall level of risk to the portfolio when all the risks are viewed as a totality rather than individually. This could include the outputs of particular
APPENDIX X1 - FIFTH EDITION CHANGES
APPENDIX X1 FIFTH EDITION CHANGES The purpose of this appendix is to give a detailed explanation of the changes made to A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
The ITIL v.3 Foundation Examination
The ITIL v.3 Foundation Examination Sample Paper A, version 3.1 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. There are no trick questions. 3. All answers are to be marked on
Appendix B Data Quality Dimensions
Appendix B Data Quality Dimensions Purpose Dimensions of data quality are fundamental to understanding how to improve data. This appendix summarizes, in chronological order of publication, three foundational
Governance, Risk and Best Value Committee
Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary
WVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office
WVU Robert C. Byrd Health Sciences Center Chancellor s Office PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members Fostering a culture of high purpose, accountability & accomplishment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
METRICS DRIVEN CONTINUAL SERVICE IMPROVEMENT USING AGILE CONCEPTS
METRICS DRIVEN CONTINUAL SERVICE IMPROVEMENT USING AGILE CONCEPTS John Osteen B Cognizant Business Consulting Process Quality Consulting Cognizant Technology Solutions, Chennai, India [email protected]
Agile project portfolio manageme nt
Agile project portfolio manageme nt Agile project & portfolio summit at Harrisburg University May 9, 2016 Agile project portfolio management Agenda Portfolio management challenges Traditional portfolio
Project Management Framework
Project Management Framework Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Business Intelligence and Strategic Choices
Business Intelligence and Strategic Choices Walter Cunningham Paul McNamara BenchMark Consulting International Introduction In the preceding article in this series, strategy was defined as a series of
Frank P.Saladis PMP, PMI Fellow
Frank P.Saladis PMP, PMI Fellow Success factors for Project Portfolio Management The Purpose of Portfolio Management Organizational Assessment Planning a Portfolio Management Strategy The Portfolio Management
Chapter 4. The IM/IT Portfolio Management Office
Chapter 4 The IM/IT Portfolio Management Office Learning Objectives Identify some of the primary causes of IM/IT project failures. Describe the main differences between IM/IT project management, IM/IT
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Five Core Principles of Successful Business Architecture
Five Core Principles of Successful Business Architecture Authors: Greg Suddreth and Whynde Melaragno Strategic Technology Architects (STA Group, LLC) Sponsored by MEGA Presents a White Paper on: Five Core
A Comparison of Project, Program & Portfolio Management Responsibilities and who should be responsible for what. By R. Max Wideman
A Comparison of, & Management Responsibilities and who should be responsible for what. By R. Max Wideman This analysis was inspired by Darren Radford, coauthor of Going Beyond The Waterfall, published
The Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
IT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected].
The Job of the Project Manager Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected] For any organization and for any project manager it is vitally important
Job Description. Applications Analyst (BI) (BISRID_033)
Job Description Job Title: Reports to: Team: Location: Applications Analyst (BI) (BISRID_033) SAP Applications Leader BIS Nelson Job Purpose Responsible for the provision of the overall management of BI
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Key Leadership Behaviors Necessary to Advance in Project Management
Key Leadership Behaviors Necessary to Advance in Project Management Project / Program Management Research Lynda Carter, Kristin Tull and Donna VanRooy Specific behaviors need to be developed in order to
The integrated leadership system. ILS support tools. Leadership pathway: Individual profile EL1
The integrated leadership system ILS support tools Leadership pathway: Individual profile Executive Level 1 profile Shapes strategic thinking Achieves results Cultivates productive working relationships
Information Technology Project Management, Sixth Edition
Management, Sixth Edition Note: See the text itself for full citations. Visit www.cie-wc.edu for more courses. Understand the growing need for better project management, especially for information technology
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
MGMT 4135 Project Management. Chapter-16. Project Oversight
MGMT 4135 Project Management Chapter-16 Project Oversight Project Oversight: defined as a set of principles and processes to guide and improve the management of projects. Ensures projects meet the needs
PM Competency Mapping Dhananjay Gokhale, PMP Vice-President, Project Excellence Learning & Consulting Center Compulink Systems Limited.
PM Competency Mapping Dhananjay Gokhale, PMP Vice-President, Project Excellence Learning & Consulting Center Compulink Systems Limited Abstract A number of organisations try to define and document project
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
The Effects of the Project Management Office on Companies Performance - A Case Study on a Project-Oriented Company
Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 9, 2014 The Effects of the Project Management Office on Companies Performance
Position Title: Management Info Chief. Working Title: Technical Project Management Section Chief
Position Title: Management Info Chief Working Title: Technical Project Management Section Chief This management position directs the operational activities of the Project Management Office whose mission
Project Risk Management
Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
SEBA Solutions Inc. 2802 Bellwind Circle Rockledge, Florida 32955 321.269.1222 voice, 321.577.0210 fax www.sebasolutions.com.
Solutions Inc. Project Status Dr. James T. Brown PMP A project status process is one of the greatest opportunities to establish a positive, disciplined project management culture. The status monitoring
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Project Execution Guidelines for SESAR 2020 Exploratory Research
Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project
PMOs. White Paper. 1 www.mosaicprojects.com.au. 1 For more papers on PMOs see: http://www.mosaicprojects.com.au/resources_papers.
s A 1 will have various roles and responsibilities according to whether the service (or support) is focused at the project, program or portfolio level. Project management offices (PjMO) provide centralised