Energy Efficiency Experience with a Successful Performance Contract Island Place Shopping Centre



Similar documents
ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM

CONTRACTING (EPC) GUIDEBOOK

HVAC Costs. Reducing Building. Building owners are caught between two powerful forces the need to lower energy costs. By Stephen J.

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY

Dear Customers, Striving for Innovation and Looking to the Future

Application of Building Energy Simulation to Air-conditioning Design

Optimization of Water - Cooled Chiller Cooling Tower Combinations

Code of Practice for Building Energy Audit

Data Centres A complete solution to noise control and acoustic packages

Cooling Efficiency Summary of 60-Day Notice - First Steps

Seven Steps to Maximizing Central Plant Efficiency

Alternatives to regular inspection of heating and air-conditioning systems for the EPBD: evaluation and comparison. Bruce Young.

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS

CFD Beyond the Whitespace. Datacentres Central & Eastern Europe

AN APPLICATION MANUAL FOR BUILDING ENERGY AND ENVIRONMENTAL MODELLING

Introduction Building project management

American Society of Heating Refrigeration and Air Conditioning Engineers (ASHRAE) Procedures for Commercial Building Energy Audits (2004)

Infrastructure & Cities Sector

Fläkt Woods Building Future

MODELLING AND OPTIMIZATION OF DIRECT EXPANSION AIR CONDITIONING SYSTEM FOR COMMERCIAL BUILDING ENERGY SAVING

Challenges of District Cooling System (DCS) Implementation in Hong Kong

HK Electric Smart Power Fund. Application Guideline

COOKING THE ROOF CFD BEYOND THE WHITE SPACE

A Guide to Small Works. A brief explanation

BUILDING PERFORMANCE METRICS

Hertsmere Borough Council. Data Quality Strategy. December

GREEN FACTS. Marina Bay Sands

Building Energy Efficiency Opportunity Report

How To Benchmark Power Production

HEATING, VENTILATION & AIR CONDITIONING

Can old buildings be just as energy-efficient as new ones?

Improving Data Center Energy Efficiency Through Environmental Optimization

Building HVAC Load Profiling Using EnergyPlus

Making the Most of Property

Post-accreditation monitoring report: The Chartered Institute of Personnel and Development. June 2007 QCA/07/3407

Modeling Guide for Daikin VRV in EnergyPro 6

Air-Conditioning Buying Guide

Drives and motors. A guide to using variable-speed drives and motors in car parks

Financial Planning Practice Standards

The University of Adelaide Business School

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Shared service centres

Large Energy Savings Per Installation VFDs for Large Chillers

Year project completed or estimated year of completion: October 2014

HOT & COLD. Basic Thermodynamics and Large Building Heating and Cooling

FIRST RADIANT COOLED COMMERCIAL BUILDING IN INDIA CRITICAL ANALYSIS OF ENERGY, COMFORT AND COST

To be used in conjunction with the Invitation to Tender for Consultancy template.

Components HVAC General Standards HVAC Guidelines HVAC System Selection Life Cycle Cost Analysis

POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, C arastro & A ssociates, C&A# 5747

A guide to Energy Services Companies (ESCOs) on how to participate in the Dubai Buildings Retrofit Program

Effective Cost Management of Building Services in Hong Kong - Managing Sustainability and Costing in Air-Conditioning

Creating Efficient HVAC Systems

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

0 - Initial Services

FACOGAZ Association of European Gas Meter Manufacturers

Developing a Public-Private Partnership Framework: Policies and PPP Units

your comfort. our world. DNSS EcoSave A/C remote monitoring and malfunction prediction

Lesson 36 Selection Of Air Conditioning Systems

ESPC Life of Contract (LOC) Plan:

Design Best Practices for Data Centers

GUIDE TO ICT SERVER ROOM ENERGY EFFICIENCY. Public Sector ICT Special Working Group

Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction

Evaporative Cooling for Residential and Light-Commercial

Temperature control solutions to help you improve business performance

Hong Kong, China. 40 th APEC Energy Working Group Meeting Statement on Notable Energy Developments. (1) Building Energy Codes

Perspectives on Workplace Sustainability

HVAC System Optimization

Evaluating a Materials Course. Ivan Moore

Computational Fluid Dynamics (CFD) Modeling Service

Preparing for Enhancement of Maintenance Servicing for Oil-free Chiller

A proposed Food Safety Management Framework for Catering Services

Design Verification. Introduction

Airflow Simulation Solves Data Centre Cooling Problem

INFORMATION NOTE. Electricity Market in Hong Kong

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

A Guide to the Design Build Process

Maintenance for Energy Efficiency

INVESTORS IN PEOPLE: WHAT S IT ALL ABOUT? Sue Greener and Tom Bourner

Absolute and relative humidity Precise and comfort air-conditioning

UCISA CASE STUDY. Middlesex University succeeds in offshoring core operations to India. Outcomes. Drivers

Creating Credible, Actionable Energy Audits

Analytics Software that allows Small- to Medium-Sized Companies To Get Actionable Data out of Their Financial Statements

BOMA BESt Assessment Overview

Measuring ROI of Agile Transformation

Sealing Gaps Under IT Racks: CFD Analysis Reveals Significant Savings Potential

ASTACEA4 Inspect complex/central air conditioning systems

Transcription:

Energy Efficiency Experience with a Successful Performance Contract Island Place Shopping Centre Dr Leonard Chow 1, Ir Cary Chan 2, Ir K L Chan 3 1 ISPL Consulting Ltd 2 Swire Properties Management Ltd 3 Trane Hong Kong ABSTRACT In 2000, the Electrical and Mechanical Services Department (EMSD) of Hong Kong launched a pilot scheme allowing designated areas to use fresh water for evaporative cooling in air-conditioning systems. This energy saving measure is supported by the industry and is being implemented in many retrofit projects in Hong Kong. The use of fresh water for evaporative cooling would imply either the use of cooling towers and water-cooled chillers to replace air-cooled chillers, or cooling towers to replace air-cooled radiators. Energy savings with short payback period can be achieved. The Island Place shopping centre at North Point Hong Kong was a project involving the changing of air-cooled chillers to water-cooled chillers with cooling towers. It was a performance contract which meant that the contractor used money from his own pocket to supply and install the retrofit project with guarantee on the system performance. In this project, the Contractor employed his in house Consultant to take care of the E&M and structural design package and take up the performance contract for the Client. This performance contract was very successful and professional because the three parties involved trusted each other. Design analysis by the Consultant on the prediction of energy performance of the new system compared with the old one and other engineering studies should be precise and professional. Contract installation by the Contractor should be of good quality and reliable. The Client should be visionary, open and believe in partnership. High confidence in the Consultant and the Contractor with mutual trust and understanding from Client was believed to be the key to success of this performance contract. This paper will take a holistic review of the project including professional design, optimum installation, performance contract management, experience and performance feedback. Page 1 of 16

Keywords: energy performance contract; computational fluid dynamics; measurement and verification. 一 个 成 功 的 能 源 效 益 应 用 在 表 演 合 约 港 运 城 购 物 中 心 周 冠 雄 博 士 1, 陈 永 康 工 程 师 2, 陈 家 龙 工 程 师 3 1 智 能 安 全 顾 问 公 正 行 有 限 公 司, 2 太 古 地 产 管 理 有 限 公 司, 3 特 灵 香 港 摘 要 在 二 零 零 零 年, 香 港 政 府 机 电 工 程 署 在 特 许 区 域 推 动 一 个 把 使 用 水 作 为 蒸 发 性 冷 却 空 调 系 统 的 先 头 计 划, 这 个 节 能 计 划 获 得 香 港 各 界 广 泛 支 持 使 用 水 作 蒸 发 性 冷 却 是 指 把 风 冷 涷 机 转 为 水 冷 涷 机, 或 空 气 散 热 器 转 为 水 塔 短 回 报 期 的 节 能 计 划 便 容 易 达 成 香 港 北 角 港 运 城 购 物 中 心 是 采 用 把 风 冷 涷 机 转 为 水 冷 涷 机 的 工 程 这 是 一 份 节 能 表 演 合 约, 承 建 商 动 用 自 己 的 资 金 去 安 装 冷 涷 机 提 供 了 节 能 表 演 保 证 本 工 程, 承 建 商 聘 请 他 的 顾 问 作 机 电 及 结 构 设 计 本 节 能 表 演 合 约 非 常 成 功 及 专 业, 主 因 是 三 方 面 都 互 相 信 任 设 计 由 顾 问 担 当, 把 预 计 的 新 能 源 表 演 与 旧 的 比 较, 此 分 析 必 须 精 准 及 专 业 承 建 商 也 必 须 富 有 高 质 素 及 可 靠, 业 主 必 须 有 远 见, 开 明 及 深 信 合 作 伙 伴, 成 功 之 路 便 是 业 主 的 高 度 信 任 承 建 商 及 专 业 工 作 本 论 文 内 容 包 括 专 业 设 计, 最 佳 效 果 的 安 装, 节 能 表 演 合 约 管 理, 经 验 及 表 演 反 馈 关 键 词 : 节 能 表 演 合 约 ; 计 算 流 体 学 动 力 ; 量 度 及 核 实 Page 2 of 16

1. INTRODUCTION In 2003, the chose to adopt a performance contract for this project. To implement performance contract, there are a lot of requirements in order to make it successful. In this project, there were requirements and objectives that were well set out at the beginning of the contract. The Consultant had to be well experienced in energy analysis and their prediction should be of the highest degree of accuracy. The Contractor had to be well experienced with the objective of cost effectiveness with the selection of the highest energy efficient equipment. For the Client, they had to be professional in project management and contract administration. Also, they had to be open and believe in the concept of partnering. 2. HIGH PRECISION ANALYSIS ON PREDICTION OF ENERGY SAVINGS To begin with, there were many methods available for energy analysis. The available software tools in the market did have a lot of weaknesses, such as too analytically focus, without making reference to the actual operation feedback, no correlations with the existing and predicted, variations at peak load and partial loads, etc. All these lead to unrealistic predictions. The analysis, methodology and tools carried out in the project were tailor made and designed by the Consultant. The following sections illustrate the approach and the important concept in design and prediction. 2.1 Methodology To start the energy analysis, a lot of consultants quickly used the energy programmes. In fact, this kind of approach should be avoided. A proper analysis should follow a 20 steps systematic methodology. It was named SELAB by the author. This is presented in Fig. 1A & 1B. A better approach is to firstly carry out structural analysis after site visit, water chiller combination options and space planning. From past experience, structural constraint is the critical factor. With this, structural analysis had to go first before the energy analysis. Page 3 of 16

The feasibility study shall include the following step-by-step approach. Structural Analysis Electrical Distribution Assessment Noise Assessment Equipment Lifting Assessment Electrical Bills Analysis Energy Analysis Equipment Assessment Environmental (including Computational Fluid Dynamics) Analysis Additional Water Consumption Assessment Prediction Report [Fig.1A - SELAB Methodology Flow Chart, Part 1 of 2] Page 4 of 16

[Fig.1B - SELAB Methodology Flow Chart, Part 2 of 2] By the end of the study, a professional report was produced with contents including plant desriptions, selection criteria, system schematic and layout, analyses of structural, electrical distribution, acoustic, environmental, equipment lifting, water, electrical bill, energy saving, assumptions, result, conversion costs, payback period, life cycle costing, joint venture partners, risk assessment and controls, etc. Page 5 of 16

2.2 Tool & Concept The author used his software called BEMX for the energy analysis of the conversion from air-cooled chillers to water-cooled chillers. The software contained a huge database used for energy analysis for different building types such as office buildings, shopping malls, hotels, etc. The database is normalized for used with different building type application. The principle analysis of the software is diagrammatically given in Fig. 2A & 2B. The advantage of this analysis is based on actual electrical bills. It always makes use of the PEAK running & part load characteristics which results in better prediction of results. It also uses a procedure: from KWh (Existing) to Cooling Load to KWh (New) employing the simple concept and the first principles in HVAC. The software had been trial tested for many years and the results were consistent and of high precise predictions. [Fig.2A BEMX Programme Flow Chart, Part 1 of 2] Page 6 of 16

[Fig.2B BEMX Programme Flow Chart, Part 2 of 2] 2.3 Computational Fluid Dynamics (CFD) There were concerns of the nuisance generated from the cooling tower exhaust after installation to the surroundings. The parameters to be investigated were air flow velocity, air temperature and moisture content. The new cooling tower exhaust would be compared with the existing air-cooled chiller exhaust. An analysis would be necessary to predict the three parameters at the nearest residential receiver point. To accurately predict the result, a computational fluid dynamic study was carried out. It was found that there was not adverse effect on the resultant air flow at the nearest residential receiver. The result is given in Fig.3. Page 7 of 16

[Fig.3 Result of CFD Analysis] Residential Building Building Exhaust Outlet 3. IMPLEMENTATION OF SYSTEMS 3.1 Contract The contract arrangement was a design and built contract with performance guarantee. The contractor was responsible for the design, supply and installation of the new water cooled chiller plant. The contractor did not only include the E&M design, but also the structural, acoustical and environmental analysis and evaluation. In this project, the contractor employed his consultant to take up the task. The contractor needed to calculate the estimated electrical savings based on the cooling load profile (Methodology was referred to Section 2.1) and performance of new equipment. Comparing with the overall capital costs and interest charge, the payback period could be calculated. Once the payback period had been confirmed, the contractor could only be paid from the savings of electrical consumption/bills within this payback period. The owner of the building would pay the same amount of money stated in the benchmark of annual electrical bills throughout the agreed payback period. However, if the operating parameters were changed, there would be some formulae to adjust the benchmarking annual electrical bills. Page 8 of 16

Strategically, the contractor made the most cost effective design of the system to bring the best value to the stakeholders. Conversely, all options that could improve the efficiency of the system were considered. A very important factor that needed to be addressed was the reliability of the system. If the system broke down during the payback period, the savings would be affected and no extension of payback period was granted because of this situation. Therefore, making the system to be the most efficient, robust and reliable at the optimum costs would be the key success factor of this project. All equipment and associated accessories used in this project had to be approved by the client. A proposed list of equipment was submitted during the tender stage. The client compared the scope of supply amongst the tenderers together with the relevant payback periods. 3.2 Installation The replacement schedule was chosen from end of the year to the period before the hot summer of the following year. To maintain the continual operation of the plant, the installation was divided into 2 phases. Project meetings were arranged regularly to review the design, progress and approval. Everything was discussed during the project meetings and prompt decisions were made. This could totally shorten the time for approval and communication. The client and the contractor somehow developed the trust and applied win-win strategy in the discussion of all disputes and arguments. Fairness and reasonableness were always the pillars of the negotiation. After the completion of the installation of the phase 1, the contract allowed 2-3 weeks for trial run and fine tuning of the system. Once the system was smoothly operated, the installation of phase 2 started. The savings of electrical charge from phase 1 was also recorded until the practical completion of the whole project. These savings were put into a pool for the expenses of variation of orders. The payout was agreed by the client and contractor together. The surplus was kept by the client and shared by two parties once the practical completion was confirmed. When everything was in the stable conditions, the payback period started and the data base of the electrical consumptions and savings were orderly recorded for comparison. Page 9 of 16

3.3 Performance Indicators The performance indicators were definitely the savings in electrical bills. If the savings exceeded the previous estimation, then the overall performance was good. However, the client would also look at the design of the chiller plant, the quality of the installation works and the project management of the contractor. The reliability of the system was another indirect performance indicator. In addition, good after sales service and maintenance service of the contract were part of the performance. The performance indicators were also related to the number of outstanding defects or arguments. If the project was running smoothly without too much unsolved issues, then the client was happy and the customer satisfaction was high. This was very important to this kind of performance contract because it would last for 5 ~ 6 years for collection of money from savings of electrical bills. Keeping good and harmonized working relationship with the client or the property management company was essential. There were many operating parameters that would affect the electrical consumption. Formulae had pre-set and agreed during the tender stage and stated clearly in exhibits. All variances in operating parameters were anticipated in the contract early stage and be calculated from the formulae and be adjusted as necessary. This arrangement reduced a lot of arguments in future and enhanced the greatest harmony. 3.4 Buffers & Others Putting buffers in capital cost or payback period could allow variances in installation works and operating parameters during the installation and operation stages respectively. When the contractor submitted the proposal at tender stage, the design of the system was not fully considered in details especially in the change over stage of the system. Once the tender was awarded, the contractor would start the detailed design. The client would also give suggestions and expectations to the design of the system because they were the end users of the system. Although there were demands in increasing the standard of the installation works, the system would perform better and the end user felt satisfactory. Page 10 of 16

The buffer was used to meet the end user s expectations that could improve the performance of the system. It was important that the client should not ask for unreasonable requirements. There were many performance contracts done by other contractors. However, most of them did not achieve a happy ending. The contractor wanted to earn as much money as possible. The owner also wanted to have the highest standard. With this in mind, there were conflicts already in the business point of view. If everything could state clearly well before hand, then conflicts would be reduced to a practical minimum. By nature, performance contracts do not wish to lead to unhappy endings. That is why setting the buffer was so important to reduce these conflicts. With such, it would slightly extend the payback period to longer time but still at reasonable acceptance. The most important thing for performance contract to succeed was to build up the mutual trust and communication in the project team. Everybody worked on the same target but not on their personal issues. Choosing the right customer was the success of the first step. 4. A REVIEW ON PERFORMANCE CONTRACTS Energy Performance Contracting (EPC) has been adopted in the western world for a long time already, however the take-up rate in Hong Kong has remained low. The principle of EPC is for contractor to enter into a performance contract with a client. The project will usually involve either new installations or modification works which can generate long term savings to the client. The contractor will guarantee the savings and get back the investment and their profit through savings within an agreed time period. 4.1 Prerequisites In theory, a client will only be interested in adopting an EPC if they perceive that there is a net benefit out of an EPC. This includes both competitive advantages of the contractor over the client and comparative advantages of the client s limited resources. The obvious ones are listed below: - Resources which include the particular technical knowledge and internal expertise which would be less cost effective for the client to acquire. - Better risk management as a result of the particular technical knowledge and Page 11 of 16

experience of the contractor. Risk can hence be better assessed and managed. - Lower financial cost obtained by the contractor. Sometimes, the client may even have difficulties in seeking funding for the project such as in multi-ownership buildings. That is, if the client knows the technology, knows the chances of success of the project and has the funding and other associated resources available that can give a better return over other opportunities, there would not be an interest for the client to adopt EPC. 4.2 Barriers to EPC While availabilities of technical resources and financial cost are easy to determine, the risk management is a more subjective and complicated matter which becomes the major barriers to EPC. The followings will cause risks to a client or contractor which are difficult for the either parties to assess and manage. - Complex and rigid contractual term and conditions. - Difficulties in the measurement and verification (M & V) of performance as a result in the changing parameters. - Trust between client and contractor. As a result of the above, clients are reluctant to adopt EPC and/or contractors need to add on a high premium to off set the risk. This will also incur added insurance and financial costs. Both parties will need substantial administrative efforts to manage the contract and the extensive measurement and verification requirements. If the contract can be established so that the risks can be reduced, there are more chances that the client will adopt EPC and the contract can be carried out more cost effectively. 4.3 The Contract Management for the Project The EPC is established with a mind to address for the above mentioned Page 12 of 16

problems. (a) Contract Awarding Process Invitation for proposal Selection of contractors Establishing of contact details and M & V Project management Award of contract (b) Invitation for Proposal and Selection of Contractor. A few contractors were requested to submit a proposal for the project. The document given to the contractor includes: Detailed requirements: giving the contractors the contract constraints and performance that the contract needs to work within. At the same time, contractors are given the flexibilities to propose options that can give the best value to the client. Submission / criteria for selection Requirements for submissions are listed out which includes: - System design drawings - Estimated energy consumption profile and savings with detailed calculations. - Assumptions for all calculations. - Performance characteristics of chillier including part load performance under various conditions. - Plant optimization, control and operation strategies. - Estimated cost with detailed breakdown, payback period and life cycle cost. - Risk assessment and control, etc. The criteria for selection are also spelt out in the document so that the contractors can better formulate their strategy and proposal. Page 13 of 16

Information to contractors To allow contractors to better estimate the savings, the vendors were given the existing chiller plant operation methods, one year operating data and electricity bill record for the past two years. (c) Establishing of Contract Details and M&V Methods The contract details and M&V methods are established jointly with the contractor. This is to ensure that both sides understand the details in full and those agreed are practical and cost effective to both parties. The performance is benchmarked with a reference year with 8 operation parameters including set point of leaving water temperature, daily operation hours, the situation to run air-cooled chillers, set point of indoor temperature, building usage, occupancy rate, maintenance hours of air-cooled chillers, and the unit rate of electricity charge. An allowable variance to each parameter is stated so as to reduce the M&V efforts in tracing the changes in the operation parameters. Should the operation parameter falls outside of the stated allowable variance, simple formulae for calculation of additional costs were agreed. 4.4 Result On the whole, the contract was implemented smoothly. Little effort were spent by both parties on M&V as a result of a well thought through and simple contract details and M&V methods established jointly between the two parties. One critical success factor is the trust between the client and the contractor and the demonstration of expertise and professionalism during the whole process. 5. CONCLUSION The key to success of this performance contract demands a number of professional and contractual factors. These factors had to be performed at high standards, otherwise there will be no chance to succeed. Strong technical analysis in methodology and programming tools leads to high precision on prediction report. Well experienced installation work with the objective of cost effectiveness and the selection for the highest energy efficient equipment is absolutely needed. Page 14 of 16

Contract buffers implementation into the contract to eliminate all possible arguments is extremely important. The client has to be open, strong belief in partnership and high capability in contract administration. Finally, the highest mutual trust and understanding between the parties concerned are the key to succeed. 6. REFERENCE Barney L. Capehart, Wayne C. Turner and William J. Kennedy, Guide to Energy Management, 2005. James P. Waltz, Management, Measurement & Verification of Performance Contracting, 2003. 7. AUTHORS (i) Ir Dr Leonard Chow was graduated at the Mechanical Engineering Department with First Class Honours at the Imperial College of Science and Technology, UK. He practices as a Mechanical and Building Services Engineer for over 24 years. Subsequently, he obtained his Master MSc and PhD degree in Mechanical Engineering in 1988 and 2001 respectively. Dr Chow is currently a Certified Energy Manager in USA, chartered engineer in UK, a registered professional engineer in Hong Kong and a chartered professional engineer in Australia. He establishes his own company ISPL Consulting Ltd in the mid 1995 and celebrates the 11 th year anniversary in 2006. His company is the consultants in Mechanical, Structure, Safety and Environmental (Energy & IAQ) aspects with about 25 employees. In the recent years, Dr Chow wrote three books, namely Intelligent building Index version 3.0, Air Duct Cleaning version 1.0 and Building Commissioning Management Practice Guide M1. He wrote over 30 technical papers and conducted over 10 seminars in Hong Kong, Japan, Mainland China and Singapore. (ii) Ir Cary W H Chan is a professional engineer. He is currently the Head of Technical Services of Swire Properties Management Limited who is responsible for overseeing the operation and maintenance of Swire Properties investment portfolio. His major interests are on energy and environment conservation. Over the years, a lot of energy saving Page 15 of 16

initiatives have been successfully implemented with substantial improvements in energy performance of their buildings. In the past few years, Mr. Chan has been sharing his experience through publications in professional journals and talks at technical seminars. (iii) Ir K L Chan got Bachelor degree in Mechanical Engineering from the University of Hong Kong in 1985. Later on, he continued his study and got two Master degrees in Building Services Engineering from the University of Hong Kong and Business Administration from the University of Leicester in 1994 and 1995 respectively. Ir K L Chan is a Chartered Engineer in Hong Kong and UK. He is also members of HKIE, AEE, Ashrae and IMechE. Over the past 19 years, Ir Chan is working for the Sales Office of the Trane Company from USA in Hong Kong at different positions. Now, he is the Operations Director of Trane Hong Kong. Ir Chan is experience in the design and application of various types of air conditioning system of buildings in Hong Kong. He is currently the President of the Hong Kong Air Conditioning and Refrigeration Association Ltd. - END OF PAPER - Page 16 of 16