Electrical Method Statement. Guidance Note 8



Similar documents
Plumbing Method Statement

Circuit Electrical Testing

The Electrical Safety Regulation (pre and post 1 January 2014)

Electrical Contractors Association

GUIDANCE ON ELECTRICAL INSPECTIONS

Level 2 NVQ in Installing Electrotechnical Systems

TRAINING RESOURCE MANUAL NATIONAL SPECIALISED ELECTRICAL WORK RECORD OF WORK EXPERIENCE AND TRAINING UEENEEP024A UEENEEP017A. EE-Oz Training Standards

MEM18084A Commission and decommission split air conditioning systems

CONTRACTOR INDUCTION HANDBOOK

Level 3-4 NVQ in Lighting for Film and Television

Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR

Health and Safety Policy

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004

RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016

THE ELECTRICAL CONTRACTOR SAFETY PROGRAM GUIDE

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

HEALTH & SAFETY POLICY

A guide to our training courses and premises

APPLICATION FOR RENEWAL OF LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION (Please read Explanatory Notes before completing the Forms)

Pontyclun Electrotechnical Training Ltd. (P.E.T. Ltd.)

Sakhalin Energy Investment Company LTD. Corporate Procedure For Lifting Operations Over Live Process Areas

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

The Electrical Contractor Safety Program Guide

Technical Overview Add-on Sensors - Smoke Alarm. Get yours direct at:

Assessment Guidance for Mentors Expert Witness Advisors (EWA) Assessors and Internal Verifiers

OHS Training Guidelines

Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool

Contractor Connect Scheme Electrical Contractor and Worker Handbook

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

QUALIFICATION HANDBOOK

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW

SERVICE MANUAL 12VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOFTOP UNITS ONLY

REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER

Policy for the Management of Asbestos in Buildings

OH&S Management Systems Audit Checklist (NAT, E3)

Release 1. BSBWHS508A Manage WHS hazards associated with plant

WHS CONTRACTOR MANAGEMENT PROCEDURE

QUALIFICATION HANDBOOK

National Occupational Standards for Health & Safety Stand Alone Units. Unit HSS8: Review health & safety procedures in workplaces

Lifting Equipment - Work equipment for lifting or lowering loads and includes its attachments used for anchoring, fixing or supporting it.

Good Research Practice

Event Management Guidelines. Month Event Management Guidelines (Month, 2011)

WHS Contractor Management Procedure

USER S MANUAL HSC-24A

Building Services Engineering Technician

WHS Contractor Management Procedure

This Guidance Notes is prepared by the Occupational Safety and Health Branch, Labour Department. This edition July 2004

WORKING IN CONFINED SPACES GUIDELINES

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

ASBESTOS POLICY MANAGEMENT PLAN

ASBESTOS POLICY AND PROCEDURES

REPLACEMENT AIR CONDITIONING UNITS FOR BRITISH EMBASSY RESIDENCE

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation

School of Engineering University of Glasgow

Corporate Standard. Contractor Management

LETTINGS POLICY. Claverham Community College. Adopted by the Governing Body on. Date. Signed

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION PAGE 1

Scope: Communications and Electronic Systems addressed in this section include:

R156. Commerce, Occupational and Professional Licensing. R156-55b. Electricians Licensing Act Rule. R156-55b-101. Title. R156-55b-102. Definitions.

CoolWave r 2 Phase Control Board and Cable Replacement Kits

1.1. EMERGENCY PROCEDURE On discovering a fire or being informed of an emergency;

FPICOT2221A Trim and cross cut felled trees

SERVICE MANUAL FOR 12 VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOF TOP UNITS ONLY

Training Management Guidelines

Contents. Company Name: XTP Recruitment Ltd ( the Company ) Policy No. XTP002. Policy Name: Model Health and Safety Policy. Date: January 2014

Blast management plan template

Level 3 Certificate in the Certification of Electrical Installations (Design, Erection and Verification of Electrical Installations) ( )

Employee Health and Safety Induction Training Record

Asbestos Management Policy (Version 3)

Guide to Assessment and Rating for Regulatory Authorities

Air Conditioning Equipment

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Greenhouse Assembly Instructions

Asbestos Policy & Procedure

Cooktop Low-Profile Ventilation Hoods

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

WHS CONTRACTOR MANAGEMENT PROCEDURE

Confined Spaces Safe Working Practices

DOCUMENTED PROCEDURE MANUAL

NATIONAL DIPLOMA IN ARCHITECTURAL TECHNOLOGY

Unit ID: 482 Domain AUTOMOTIVE ELECTRICAL AND ELECTRONICS Title: Install and repair electrical lighting system of vehicles Level: 2 Credits: 6

Document Title: Supply of Clinical Trials Investigational Material: Dispensing, Returns and Accountability

CPC40912 Certificate IV in Plumbing and Services

Safe Work in Confined Spaces

Loss Prevention Standard

Health and safety regulation... a short guide

Fire Safety Log Book

Preventative Maintenance & Statutory Testing

OHSMS Implementation Guide

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

Six steps to Occupational Health and Safety

SYSTEMS SILVER APPROVAL CRITERIA

Transcription:

Electrical Method Statement Guidance Note 8 1

Electrical Method Statement A Basic Guide to preparation Introduction This Guidance Note gives practical information about creating a method statement. A completed sample template has been included in Appendix 1 and a blank template in Appendix 2. If you wish to use the template in Appendix 2 to construct your own documents, you must ensure that all references to Santia Accreditation have been removed and the final documents are clearly incorporated into your existing safety management system. A method statement is an ideal way of recording the hazards involved in a specific work activity and communicating the risk and precautions required to all those involved in the work, including those undertaking the work and their immediate managers. A method statement should be developed in conjunction with a risk assessment and together these demonstrate a safe system of work. The method statement needs be clear, no longer than necessary, and not over complicated. The document should avoid ambiguities or generalisations, which could lead to confusion, and layout a step-by-step sequence of work to describe how the activity is to be carried out safely. Format The actual format is dependent on the work being undertaken and the organisational arrangements in place but generally the following headings should be present: Organisation/company in control of the operation Named individual responsible for the activity and its safety Name of method statement originator and authorisation date Arrangements for changing/deviating from method statement General description of activity Location of activity including access and restrictions General working environment considerations, e.g. temperature and wind speed Protection of others, e.g. members of the public Emergency procedures, including location of emergency equipment Identity of operatives (and any specific training or certification required) Requirements for Personal Protective Equipment Plant and equipment used, including safety precautions and restrictions Materials information e.g. hazard information and storage/transport requirements Work sequence, including associated risks and required control measures for each stage Safety checks/clearances at specific stages Final clearance that activity is completed to specification Any other additional information that may be relevant. 2

The list above is not exhaustive and a method statement may or may not include each and every item. However, as a minimum it must achieve the following objectives: It should be up to date, identifiable and its source accountable. It should contain the sequence of works. It should identify the associated risks and control measures. It should state actions/authorisation required to deviate from method statement. Appendix 1 is a sample method statement for electrical works. It can be as simple or as detailed as the job/risk requires, so long as it meets the four main objectives. 3

Appendix 1 Electrical Method Statement Contract Manager: Joe Bloggs Site Supervisor: David Jones Originator: Joe Bloggs Position: Contracts Manager Date: 01/11/2013 Strict adherence to this method statement is critical to the health and safety of all engaged in the work. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Modifying/Extending/Relocating Existing Lighting Circuits and Points (Single Core Cables in Trunking and Conduit). Location and Access: (attached plan as appropriate) Main Office Area. Working Environment & Restrictions: Open Plan Office. Only Electrical Contractors permitted to be present during operation. Existing sections of ceiling will be removed by others. Protection of others: Work undertaken out of hours. Only contractors and client representative present. Emergency Procedures: Normal site evacuation procedure to apply. Operatives/Competence: C&G Qualified Electricians. Personal Protective Equipment: Safety Footwear, Gloves, Goggles Plant & Equipment: Podium Steps, Cordless Drill. Materials Handling/Storage & Safety Information: All material in manageable individual lengths. 4

Critical Stages: (must be undertaken in correct sequence) 1. On arrival site contact made and site induction undertaken 2. Work area cleared for safe access 3. Final circuit arrangements will be determined as indicated on the installation drawings 4. Obtain Permit to work 5. Circuits to be modified will be identified, isolated from the electrical supply by the turning off the relevant circuit protective devices and fuses removed, danger label fitted and circuit verified dead. 6. Existing luminaries will be unplugged and removed to allow access to ceiling roses as required 7. Ceiling roses will be disconnected and removed 8. All wiring contained within the conduits will be pulled back to the nearest convenient point and left neatly coiled 9. The existing conduit/trunking installation will be amended to suit the new layout as indicated on the installation drawings 10. When the amended conduit installation is complete the cables will be drawn back in 11. Circuits will be rewired/amended as necessary to suit the new layout 12. The complete circuit will be tested in accordance with B.S.7671 17 TH Edition I.E.E. Wiring Regulations prior to connection. 13. Accessories/equipment will be second fixed. Luminaires will be replaced and repositioned/new luminaries will be installed. 14. When all accessories are fitted and it is safe to do so the circuits will be re-energised and danger label removed 15. Final live tests will be carried out 16. Site will be cleared and equipment replaced. 17. Site contact notified of work finished. 18. Cancel permit to work Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date: 5

Appendix 2 Blank Method Statement Template Contract Manager: Site Supervisor: Originator: Position: Date: Strict adherence to this method statement is critical to the health and safety of all engaged in the work. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Location and Access: (attached plan as appropriate) Working Environment & Restrictions: Protection of others: Emergency Procedures: Operatives/Competence: Personal Protective Equipment: Plant & Equipment: Materials Handling/Storage & Safety Information: Critical Stages: (must be undertaken in correct sequence) Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date: 6

Copyright Santia 2014 This publication may be freely reproduced, except for advertising, endorsement or commercial purposes. 7