CONTRACT MANAGEMENT - Assessment Tool to determine required leve. Planning & governance People. Handover. Net Risk Level. Risk Likelihood.



Similar documents
How To Manage A Contract

PROGRESS THROUGH PARTNERSHIP MAKING A DIFFERENCE GUIDANCE PERFORMANCE MANAGEMENT FRAMEWORK AND CONTINUOUS IMPROVEMENT

Writing - The Law of a Contract

SAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD4 - Category management in procurement and supply. Level 5 Advanced Diploma in Procurement and Supply

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan

Certification in Humanitarian Supply Chain Management (CHSCM) Competence Model. Final Version 2007

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 795 SESSION DECEMBER HM Revenue & Customs. Customer service performance

Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a project.

Better Practice Contract Management Framework

JHS 166 Terms and Conditions of Public IT Procurement Annex 6. Special Terms and Conditions for Consulting Services (JIT 2015 Consulting)

2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY

Procurement guidance Managing and monitoring suppliers performance

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Outsourcing Four Projects and a Process

ESME'S REPORT ON DURABLE MEDIUM - DISTANCE MARKETING DIRECTIVE AND MARKETS IN FINANCIAL INSTRUMENTS DIRECTIVE

Supply Contract Risks: An Approach That May Be Adopted to Support Client-Supplier Contract Negotiations

General Terms of Provision of Publicly Available Electronic Communications Services by UPC Česká republika, s.r.o. for Households

GN23: Life Insurance Company Takeovers

BAY OF PLENTY COUNCILS BROADBAND BUSINESS CASE STUDY SPECTRUM AUCTION REVIEW. April 2007

How To Manage Asset Management

LEVEL 5. Advanced Diploma in Purchasing and Supply. Senior Assessor s Report. July Risk Management and Supply Chain Vulnerability L5-02

Project Risk Analysis toolkit

Newport City Homes Compensation Policy (P5)

2 Costing and Funding. Project Costs and Funding a Cautionary Note. Preparatory Costs. Project Overheads

MORTGAGE FACTSHEET -1-

Business Ethics and Code of Conduct. Executives and employees. Global Connections Pcl.

Accreditation Application Forms

Contract Management Part One Making the Business Case for Investment

Dealing with risk. Why is risk management important?

Business Continuity Plan Toolkit

contracts consumer protector

Job Description. Supply Chain Development Manager

Who s next after TalkTalk?

So, What Exactly is Risk Management?

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2014

The Mental Health Care Patient Management System (Mentcare)

PROJECT RISK ANALYSIS AND MANAGEMENT

Financial Services Regulatory Commission Antigua and Barbuda Division of Gaming Customer Due Diligence Guidelines for

Outsourcing. Knowledge Summary

Diploma in IT Syllabus IT Service Management

Complaints Standard. for Suppliers. Categorised as Basic (B or F)

Session 402- Contract Management: What is Realistic for My Department?

2 Business, Performance, and Gap Analysis

[INSERT NAME OF SCHOOL] BUSINESS CONTINUITY PLAN

REGULATORY IMPLICATIONS OF CLOUD COMPUTING. Stephen B. Kerr Partner Financial Institutions Group

Management of Accounts Receivable

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

How To Get A Car Hire Out Of Hire In The Gta

Contract Management The Mavericks Won t Like This!

CONTRACTUAL TERMS FREQUENTLY ASKED QUESTIONS

In April 2010, changes to both the GMS and PMS regulations came into force which:

M&LE17 Outsource business processes 1

Procurement guidance Prequalifying suppliers

A guide to business continuity jelfsmallbusiness.co.uk

Development, Acquisition, Implementation, and Maintenance of Application Systems

It may also include denial of use of property, plant and equipment or the inability of employees to attend their place of work.

NOTTINGHAMSHIRE OFFICE OF THE POLICE AND CRIME JOB DESCRIPTION. Project Manager ECINS Development and Implementation 1 year project

CABINET June 2nd 2015 EXECUTIVE SUMMARY OF AGENDA ITEM 6

Target Breach Impact Survey

Evaluating Software Alternatives. Chapter 4 Methods of Software Acquisition. Advantages of Custom Developed Software. Custom Developed Software

AS APPROVED BY CONVOCATION, MARCH 25, (new/amended rules and commentary for rule 2.02)

Part One: Introduction to Partnerships Victoria contract management... 1

CURRENT DATA N/A N/A Refer current budget N/A Existing and new clients Other information:

Secured loans - A guide

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

SAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. D5 - Managing contracts and relationships in procurement and supply

STAG Technical Database Section 13

Preferred Practice Notes

Contract Management. Brief 22. Public Procurement. September 2011

PERFORMANCE BONDS WORK FOR YOU

A checklist for project managers

Risk assessment. made simple

TEC Capital Asset Management Standard January 2011

Programme Delivery & Performance Management


A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF WHOLE-OF-LIFE COSTING

My landlord wants me out protection against harassment and illegal eviction. housing

Scrim And Texture Data Collection Contract Management S Chamberlain

Step by Step Project Planning

IRM CERTIFICATE AND DIPLOMA OUTLINE SYLLABUS

Managing Risk Control Environment and Responsibilities

Introduction to Procurement and Step by Step Guide

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02)

Project Time Management an essential element to project success

The essential guide to leasing for education

Enterprise Content Management (ECM)

Certificate in Construction Project Management

Performance Monitoring

Tender forms and letters 1. Final accounts 7 Cost items 7 Presenting the final account 9. Retention and defects liability period 11.

Financial Advice Guide for your Business

HMG Guidance. Customer Service Telephone Lines. Use of Number Prefixes

APPLICATION OF THE KING III REPORT ON CORPORATE GOVERNANCE PRINCIPLES

Practical experience component achieved. Principal. Principal. Principal. Total

How to use Service Level Management To save money

CONTRACT MANAGEMENT FRAMEWORK

SYSTEMS ANALYST (INTEGRATION & DEVELOPMENT) BASED IN C2K CENTRE, BELFAST

Preparing for the future:

Test Plan Evaluation Model

ITIL Introducing service transition

Contract Management. Better Practice Guide. February 2001

Transcription:

CONTRACT MANAGEMENT - Assessment Tool to determine required leve No. Contract Risk Likelihood Risk Impact Net Risk Level Value Opportunity Handover Planning & governance People 1 Provision of Strategic Highways resurfacing, new works and operational services 3 3 9 9 High 2 Building maintenance 3 Cleaning Services 1 1 1 1 Very Low 4 Vehicle leasing Home to school transport for 5 pupils with special educational needs (Taxis) 6 Print Services 7 Mobile phones 8 9 10 Supply of bibliographical and audio visual materials (Library books) Mechanical and Electrical Works Mailing Services to Revenues and Benefits

ol to determine required level of CM Planning & governance People Relationships Performance Payment Risk Contract Development Supplier development Supplier relationship mgnt Market management

Market management CPS 'Owner' Contract Manager Allison Robertson Derek Churchard Heather Boyd Derek Churchard Jonathan Guy Allison Robertson Jackie Hill Jackie Hill Derek Churchard Allison Robertson

Risk & Additional Value Assessment For each contract, the Contract Manager needs to assess the potential benefits of CM. This can be done using two dimensions. Benefits derived from effectively managing the risk inherent in the contract. Potential additional value that can be obtained from effective CM. As risk level increases, the benefits which may be derived from reducing these risks through enhanced CM also increase. A contract that has little inherent risk attached to it and little opportunity for additional value would not need or justify a large amount of CM resources, as the benefits that could be achieved from greater CM would be small. This may be the case even if the annual expenditure on a contract is substantial, although small improvements on a major contract can, of course, be significant. Even if contract risk is low, the potential to generate additional value from the contract can justify increasing levels of CM resources and activities. Extra value could come, for example, from cost reduction through process development, or from persuading a supplier to increase service levels without additional cost. Contract Management priorities Value opportunity Key Contract Management increasing focus on development, strategy Mid-level Contract Management increasing focus on risk, change, relationships Basic Contract Management focus on administration, performance Contract risk Identifying contract risks The initial stage in any risk management process is to identify the key risks. In the case of service contracts, the key risks can be categorised into three broad areas. Service failure the most obvious and common risk is that the supplier does not deliver the service to the standard or timeliness specified in the contract. Service failure can range from a relatively minor shortfall against required service levels to complete failure. Minor failure could be driven by, for example, SMBC providing unclear specifications, a lack of supplier capability, or a supplier cutting corners to improve profitability. In extreme circumstances, financial or other problems could cause the supplier to go out of business, unilaterally withdraw from the contract, or be unable to deliver the service.

Reputational damage even if the service is provided as specified in the contract, there is a further risk that the supplier in some manner causes harm to the SMBC s reputation. For example, the supplier may act illegally or in a manner that conflicts with SMBC policy. Supplier problems could result in sensitive or personal information not being kept secure, or a supplier may be dealing with vulnerable citizens where poor performance would have operational implications and cause reputational damage to SMBC. Additional cost this category of risk covers cases where the contract costs more than expected or budgeted, and those costs do not represent value for money. The amounts paid to the supplier may increase as a result of changes in the quantity or quality of the services delivered or their prices. For example, user demand may be higher than expected. In such cases, additional costs may be reasonable and offer value for money. But it is vital that processes are well managed so that value for money is tested and achieved on this additional expenditure. SMBC s internal costs may also increase. For example, poor user perception of the service could lead to more work being done internally by SMBC staff rather than by the supplier, with consequent additional costs. Quantifying contract risks Once the core risks associated with a contract have been identified, the scale or importance of each The risk likelihood needs to (probability) be quantified. of the This risk can materialising. be done by assessing two elements. The impact if the risk does materialise. The likelihood of the risk (probability) Understanding the likelihood of the risk materialising is key to assessing its relative importance. A risk may have a huge potential impact, but if the likelihood of it happening is The technical or operational complexity of the services being delivered. very small, it may not be worth devoting much effort to managing or reducing the risk. In terms of The service complexity contracts, of the a variety terms of and factors conditions can influence of the contract. the likelihood More complex, of the key or risks non-standard, materialising. terms and conditions require more effort to understand, control and update than do concise or standard terms and conditions. The number of changes required to the contract over its duration. The number of internal users or other stakeholders within SMBC. The extent of the geographic area covered by the contract. The extent to which one party feels they are disadvantaged by the terms and conditions, or the commercial terms, increasing the likelihood of disputes. The nature of the supplier itself and its business model. The probability of supplier failure or performance issues may depend on: o the supplier s internal business configuration, for example, there is higher risk if a supplier provides services from a single site that is vulnerable to supply interruption; o the supplier s dependency on key staff, third party suppliers or other key stakeholders in the delivery of the service; o the experience of the supplier in working with the particular customer organisation or in the sector concerned, for example, a supplier who has never worked in the public sector is likely to carry inherently more risk as a supplier to SMBC than one who is experienced in that sector; and o the supplier s experience in delivering the service in question. The impact of the risk

Along with the likelihood of the risk materialising, the overall importance of the risk is dependent on the impact were the risk to materialise. A risk with a significant potential impact is clearly more serious and worthy of attention than one that has only a limited effect. Impact can be considered under the three key risk headings identified above. 1. Service failure can generate a wide range of potential impacts. At the extreme, a service failure by a critical supplier could mean SMBC has in turn to stop providing services. Poor supplier performance could result in SMBC not achieving policy objectives, or in the public who use the service suffering delays and inconvenience. A less serious service failure (perhaps a service that does not fully meet the standard or specification required) could generate a more minor loss of efficiency or effectiveness within SMBC. 2. Reputational issues can also have an impact on SMBC. While damage may arise from service failure as described above, this is not necessarily the case. A service contract may be delivered to specification but if, for example, the supplier is found to be using illegal immigrants, there will be reputational damage and impact for SMBC as well as for the supplier. Quantifying such an impact is, however, often difficult. 3. Additional cost is the third key potential impact. The impact of contract expenditure being greater than forecast or budgeted can be considerable, whether it occurs through poor control, changing requirements, or through unbudgeted but contractually allowed price increases (for example, where the charges are uprated for inflation). The internal costs of SMBC can also be affected, whether direct CM costs or wider costs driven by contract issues. In general terms, the risks associated with a high value contract will usually have greater potential impact, but the specific terms of each contract can also affect the potential costs. Identifying opportunities for additional value In addition to managing risk, the other aim of enhanced CM is capturing additional value, above and beyond that defined in the original contract. Additional value generally falls under the headings of service or cost; reputational added value is more unusual although not impossible to achieve. In terms of service, extra value can arise from a supplier providing higher service levels than expected or specified, at no additional cost. This may have a value to SMBC, although this is not always the case. A 99 per cent service level may be more than adequate, and achievement of 99.5 per cent may bring no further value. For example, a call centre reducing the time it takes to answer calls by five seconds may not even be noticed by the callers. A service provided in a different or innovative manner can also bring value to SMBC and may not always have a cost to the supplier. Indeed, there may be alternative service delivery models that provide a win-win opportunity: lower costs to the supplier and better service to SMBC and/or the end customer. Value improvement through lower costs may come about through contractual mechanisms, such as benchmarking against market prices, or through negotiation with the supplier. Cost reduction may also arise from supplier or mutual action that enables SMBC to refine its own internal process or reduce other costs. The potential for value improvement in a contract can be assessed in a similar way to assessing the risks. Opportunities need to be identified and then quantified in terms of their feasibility (similar to the likelihood assessment under the risk heading) and their potential size or impact.