DECISION PROCESS AND OPTIMIZATION RULES FOR SEISMIC RETROFIT PROGRAMS. T. Zikas 1 and F. Gehbauer 2



Similar documents
AFAD DEPREM DAİRESİ BAŞKANLIĞI TÜRKİYE KUVVETLİ YER HAREKETİ ve ÖN HASAR TAHMİN SİSTEMLERİ ÇALIŞMA GRUBU. (Rapid Estimation Damage)

THE DISASTER MANAGEMENT TOOL (DMT)

Seismic Risk Assessment Procedures for a System consisting of Distributed Facilities -Part three- Insurance Portfolio Analysis

CHAPTER SEISMIC RISK MITIGATION PRACTICES IN SCHOOL BUILDINGS IN ISTANBUL, TURKEY

Seismic Risk Evaluation of a Building Stock and Retrofit Prioritization

NORSAR/International Center of Geohazards (ICG) Kjeller, Norway. International Conference on Open Risk Analysis Cambridge, UK June 2009

SEISMIC RETROFITTING OF STRUCTURES

Determination of source parameters from seismic spectra

APPENDIX B Understanding the FEMA Benefit-Cost Analysis Process

Catastrophe Modeling: A New Approach to Managing Risk

Life Cycle Cost Analysis (LCCA)

PROHITECH WP3 (Leader A. IBEN BRAHIM) A short Note on the Seismic Hazard in Israel

Structural Retrofitting For Earthquake Resistance

COST-BENEFIT ANALYSIS - TOOL FOR ALLOCATION OF FINANCIAL RESOURCES FOR MAJOR PROJECTS

Disaster Risk Assessment:

Using Cost-Benefit Analysis to Evaluate Mitigation for Lifeline Systems Research Objectives Howard Kunreuther, Chris Cyr Patricia Grossi Wendy Tao

Contents. Specific and total risk. Definition of risk. How to express risk? Multi-hazard Risk Assessment. Risk types

CONCEPT FOR AN INTEGRATED DISASTER MANAGEMENT TOOL

Scope of Insurance Premium for Residential Houses against Seismic Risk in Japan

Probabilistic Benefit-Cost Analysis for Earthquake Damage Mitigation: Evaluating Measures for Apartment Houses in Turkey

Section 6 Benefit-Cost Analysis

GESKEE Database an Innovative Tool for Seismic Risk Assessment and Loss Scaling

STRATEGY OF WATER SUPPLY NETWORK RESTORATION WITH REDUNDANCY INDEX

Development of Seismic-induced Fire Risk Assessment Method for a Building

Advanced GIS for Loss Estimation and Rapid Post-Earthquake Assessment of Building Damage

Building a Spatial Database for Earthquake Risk Assessment and Management in the Caribbean

Security Risk Assessment and Mitigation Prioritization

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California Prepared By

Seismic Risk Prioritization of RC Public Buildings

EARTHQUAKE DISASTER GIS AND SPATIAL-TEMPORAL PATTERN OF EARTHQUAKE DISASTERS IN CHINA1

Disaster Risk Mitigation in Palestine Nablus, February 26 th Dr. Paola Ceresa

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

SOFTWARE FOR GENERATION OF SPECTRUM COMPATIBLE TIME HISTORY

CONTRASTING DISPLACEMENT DEMANDS OF DUCTILE STRUCTURES FROM TOHOKU SUBDUCTION TO CRUSTAL EARTHQUAKE RECORDS. Peter Dusicka 1 and Sarah Knoles 2

Metodologie di valutazione del rischio sismico per grandi impianti industriali

SEISMIC CAPACITY OF EXISTING RC SCHOOL BUILDINGS IN OTA CITY, TOKYO, JAPAN

CEE Earthquake Resistant Design. General Information

Benefit-cost analysis of the seismic risk mitigation for a region with moderate seismicity: The case of Tiberias, Israel

Probabilistic Risk Assessment Studies in Yemen

Chapter 11 Building Information Systems and and Managing Projects

Educational simulation in construction project risk management Setting the stage

PROJECT RISK MANAGEMENT

EVALUATION OF SEISMIC RESPONSE - FACULTY OF LAND RECLAMATION AND ENVIRONMENTAL ENGINEERING -BUCHAREST

CAPRA - Comprehensive Approach to Probabilistic Risk Assessment: International Initiative for Risk Management Effectiveness

Keynote 2: What is Landslide Hazard? Inventory Maps, Uncertainty, and an Approach to Meeting Insurance Industry Needs

SIESMIC SLOSHING IN CYLINDRICAL TANKS WITH FLEXIBLE BAFFLES

PROJECT RISK MANAGEMENT

Integrated Earthquake Risk Assessment

PERFORMANCE BASED SEISMIC EVALUATION AND RETROFITTING OF UNSYMMETRICAL MEDIUM RISE BUILDINGS- A CASE STUDY

Seismic Isolated Hospital Design Practice in Turkey: Erzurum Medical Campus

ISTANBUL EARTHQUAKE RISK AND MITIGATION STUDIES

Client: Nederlandse Aardolie Maatschappij Arup Project Title: Groningen 2013 Seismic Risk Study - Earthquake Scenario-Based Risk Assessment

Appendix F Benefit-Cost Analysis of Flood Protection Measures

QUANTITATIVE RISK ASSESSMENT FOR ACCIDENTS AT WORK IN THE CHEMICAL INDUSTRY AND THE SEVESO II DIRECTIVE

Distributed computing of failure probabilities for structures in civil engineering

EDUCATION AND TRAINING

An evaluation of the fire safety emergency cover toolkit

ACUTE CARE HOSPITAL RESOURCE ALLOCATION PROBLEM UNDER SEISMICALLY DAMAGED TRANSPORTATION SYSTEMS

Mapping landslides for the insurance industry lessons from earthquakes

Using GIS for Assessing Earthquake Hazards of San Francisco Bay, California, USA

Applying GIS in seismic hazard assessment and data integration for disaster management

SEISMIC DESIGN OF MULTI-STORY BUILDINGS WITH METALLIC STRUCTURAL FUSES. R. Vargas 1 and M. Bruneau 2 ABSTRACT

AN ABSOLUTE EARTHQUAKE RISK INDEX FOR INSURANCE PURPOSES

PRODUCTIVITY & GROWTH

Life-cycle cost analysis for nuclear power plants with seismic isolated system

Technical #2 Discussion

Managing sewer flood risk

RESIDENTIAL RETROFITTING IN İSTANBUL REALITIES IN BAKIRKÖY. D.C. Hopkins 1, R.D. Sharpe 2, H. Sucuoğlu 3, D. Kubin 4, and P.

G. Michele Calvi IUSS Pavia

NONLINEAR BEHAVIOR AND FRAGILITY ASSESSMENT OF MULTI-STORY CONFINED MASONRY WALLS UNDER CYCLIC LOADS

VULNERABILITY FLOOD STANDARDS. VF-1 Derivation of Residential Structure and Contents Flood Vulnerability Functions

SEISMIC ANALYSIS AND RETROFITTING OF R.C.C STRUCTURE

PACIFIC CATASTROPHE RISK ASSESSMENT AND FINANCING INITIATIVE

HOW TO EVALUATE BUILDINGS AND DETERMINE RETROFIT COSTS

Presentations. Session 1. Slide 1. Earthquake Risk Reduction. 1- Concepts & Terminology

Design Example 1 Design Spectral Response Acceleration Parameters 11.4

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I

AP Physics 1 and 2 Lab Investigations

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge

Transportation Asset Management

OECD RECOMMENDATION CONCERNING GUIDELINES ON EARTHQUAKE SAFETY IN SCHOOLS

Plotting Earthquake Epicenters an activity for seismic discovery

Developing a hazard risk assessment Framework for the New Zealand State Highway Network

Earthquakes: Risk & Insurance Issues

Client: Nederlandse Aardolie Maatschappij Arup Project Title: Groningen 2013 Structural Upgrading Study

Earthquake Resistant Design and Risk Reduction. 2nd Edition

Modeling Flood Perils and Flood Insurance Program in Taiwan

BENEFIT-COST ANALYSIS Financial and Economic Appraisal using Spreadsheets

Toma Danila Dragos. National Institute for Earth Physics Romania

Locating the Epicenter and Determining the Magnitude of an Earthquake

TRAINING SYSTEM AND INFORMATION NETWORK FOR EARTHQUAKE DISASTER MITIGATION

EARTHQUAKE RISK MITIGATION IN SWITZERLAND SUCCESSES, FAILURES AND CHALLENGES IN A COUNTRY OF MODERATE SEISMICITY

Overview. NRC Regulations for Seismic. Applied to San Onofre Nuclear Generating Station. NRC History. How we Regulate

sensitivity analysis. Using Excel 2.1 MANUAL WHAT-IF ANALYSIS 2.2 THRESHOLD VALUES

Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) ext. 8779; FAX (514) ;

A Methodology for Calculating the Opportunity Cost of Layered Sovereign DRFI Strategies

RISKSCAPE TUTORIAL 4: 200 YEAR ANNUAL RETURN INTERVAL (ARI) HEATHCOTE RIVER FLOOD EVENT: MITIGATING IMPACTS ON CHRISTCHURCH BUILDINGS

WP 7: Build prototype software

Evaluation of Fire Protection Capacity in Disasters Based on Disaster Resilience Curve

Transcription:

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation Oct. 4-6, 2007, Bucharest, Romania DECISION PROCESS AND OPTIMIZATION RULES FOR SEISMIC RETROFIT PROGRAMS T. Zikas 1 and F. Gehbauer 2 ABSTRACT In earthquake-prone areas public authorities are dealing with the decision process of initiating retrofitting programs for a large building stock. By means of a cost-benefit-analysis decision makers can quantify all impacts of various investment alternatives to a society in monetary terms and make recommendations based on the net present value. In the case of seismic retrofit decisions the input variables, such as costs of alternative seismic upgrade levels, direct and indirect damage, and casualties, are influenced by many uncertain factors. This paper will analyse standard decision criteria under the aspect of uncertainty and introduce a probabilistic cost-benefit-analysis for seismic retrofit programs. The implication of influencing factors is analysed with Monte Carlo simulation and sensitive analysis. The presented methodologies are integrated in the loss estimation software EQSIM which has been developed by the Collaborative Research Center 'Strong Earthquakes: A Challenge for Geosciences and Civil Engineering' at the University of Karlsruhe in Germany. INTRODUCTION Residential, commercial and industrial buildings in many vulnerable cities worldwide are often built with poor construction quality and an insufficient design policy. Decision makers are dealing with the question of installing rehabilitation programs to reduce future loss and casualties caused by large earthquakes. An appropriate technique to evaluate different retrofitting options is the method of cost-benefit analysis. The analysis includes a systematic cataloguing of all impacts as benefits and costs, converting these impacts into monetary units, and then calculating and comparing the net benefit of different alternatives with the option of doing nothing (status quo) (Boardman et al., 2001). The benefit of mitigation efforts is the reduced damage of buildings and infrastructure and the avoided casualties. Fig. 1 shows the exemplary loss before and the reduced loss after mitigation from future earthquakes and the initial cost of retrofitting. Figure 1. Loss from future earthquake events and the avoided loss in case of retrofitting. 1 Doctoral Candidate, Institute for Technology and Management in Construction, Karlsruhe, Germany 2 Professor, Institute for Technology and Management in Construction, Karlsruhe, Germany

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 473 Costs and especially benefits of retrofitting projects arise over the whole life cycle of a building, so future impacts must be discounted to their present value to be comparable. The net present value computes the difference between the present value of the benefits and the present value of the costs. Thus, the best alternative is the one with the highest net present. All Projects with a positive net present value are assumed to be worthwhile. STEPS OF A COST-BENEFIT ANALYSIS Basically, with a cost-benefit analysis decision makers evaluate projects which have an impact on society. The attractiveness of a rehabilitation project is calculated by comparing the loss with and without mitigation. Several procedures for the analysis exist and are described in more detail in (Boardman et al., 2001). For earthquake mitigation programs with alternative projects and restricted budget, the following procedure is suggested: Step 1 Seismic Hazard Definition annual probability of exceedance, site hazard Step 2 Define building inventory and mitigation alternatives e.g. structure type, area, occup. Step 3 Mitigation cost and benefit estimates (FEMA 156) Step 4 Probabilistic damage estimation before and after mitigation based on capacity-spectrum method Step 5 Calculate the net present value (probabilistic) Step 6 Sensitivity analysis Using Monte Carlo with probability distribution Step 7 Decision for best alternative based on NPV and sensitivity analysis Figure 2. Procedure for a cost-benefit analysis (adopted from Smyth et al., 2001).

474 T. Zikas Step 1 Seismic Hazard Definition The first step defines the seismic hazard. Important is the source and frequency of earthquake events, the maximum magnitude and the recurrence relationship. The site hazard is defined by using different attenuation functions for ground motion expected at certain distances from the source to the sites depending on the soil type. Generally, ground motions are expressed as maximum intensity, peak ground acceleration, peak ground velocity, or spectral accelerations, and depend on the earthquake source, the seismic wave propagation and the site response. The frequency of Vrancea events in moment magnitudes with as the number of events per year is given by (Wenzel and Lungu, 2000): log 4.1 0.78 Table 1. The number of earthquake events with various magnitudes and for different time periods. Mw Years 10 25 50 75 100 250 500 6.0 3 7 13 20 26 66 132 6.5 1 3 5 8 11 27 54 6.8 1 2 3 5 6 16 31 7.0 0.44 1 2 3 4 11 22 7.2 0.30 1 2 2 3 8 15 7.4 0.21 1 1 2 2 5 11 7.6 0.15 0.37 1 1 1 4 7 7.8 0.10 0.26 1 1 1 3 5 The annual probability of earthquake events is a key input in the cost-benefit formulation for the expected net present value in step 5. Step 2 - Define building inventory and mitigation alternatives The inventory information is required in order to conduct any earthquake damage assessment. Similar buildings should be grouped into a set of building classes based on, e.g. structural parameters, occupancy, height, and design codes. The building inventory of Bucharest in the EQSIM application contains 1305 buildings with all kinds of building classes and occupancies. The area is located in the inner city between Piata Roamana and Bodul Unirii. For each building the database contains detailed information about the structural type, occupancy, building year, area, and more.

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 475 For each building, one of the following alternative objectives can be distinguished: A0: do nothing A1: risk reduction A2: life safety A3: damage control A4: immediate occupancy The option risk reduction includes only rehabilitating parts of a structure without considering any life-safety performance. The life safety objective allows for unrepairable damage of the building as long as life is not at risk. The damage control objective has a greater performance than life safety objective and protects features or functions of the building. Immediate occupancy allows for only minimal earthquake damage and disruption, and is reserved for critical or hazardous facilities and is not a part of the calculation. Piata Romana B-Dul Unirii Figure 3. Test area in Bucharest. Step 3 Mitigation costs and benefit estimates For all alternatives the costs to implement the mitigation measure must be specified. The highest costs are most likely to occur for the structural retrofit and they depend on the performance objective, such as life safety, risk reduction, damage control or immediate occupancy. The seismic rehabilitation cost estimation is based on (FEMA 156, FEMA 157), in which more than 2000 seismic rehabilitation projects were analysed. Basically, the building construction year, the performance objective of the rehabilitation, the seismic zone, the building class and the building area are used for the estimation. The mitigation method is not part of this analysis framework. Table 2. Estimation of average seismic rehabilitation costs for pre code buildings in high seismic zone and alternative performance objectives. risk reduction life safety damage control immediate occupancy building area < 100 m² > 100 m² < 100 m² > 100 m² < 450 m² > 450 m² Q1 $9,79 $182,01 $114,20 $182,12 $78,04 $415,48 $118,83 Mean $24,22 $278,24 $202,57 $278,24 $153,06 $525,05 $209,89 Q3 $58,02 $439,16 $362,63 $439,16 $279,53 $707,93 $297,51 Estimation $/m² in 2002 dollars One general benefit of seismic rehabilitation results from reducing the risk of death. Thus, it is necessary in the analysis to evaluate and monetize the benefit of saving human lives. One measure which economists use to estimate the value of life is how much people are willing to pay to reduce their risk of death. Boardman suggest a plausible range between $2.5 million and $4.0 million in 1999 dollars. The sensitivity of the value should be analysed with Monte Carlo in step 6. Alternatively, appropriate values for Romania could be surveyed.

476 T. Zikas Step 4 Probabilistic damage estimation before and after mitigation The basic source parameters of a seismic event in Step 1 include event date, time, magnitude, epicenter location and focal depth. The damage estimation with EQSIM is based on seismic response spectra. These spectra can either be obtained from recorded time histories or they may be calculated with earthquake specific parameters. For the second case, the peak ground acceleration can be calculated with local attenuation functions. Local soil conditions and building codes, such as EC 8, are then used to transform PGA to standardized response spectra. The building behavior for different building classes is described by capacity curves. These curves compare the spectral displacement of a building class with the spectral acceleration. To find the relevant spectral displacement for a specific earthquake scenario, the capacity spectrum method is used. In the capacity spectrum method the elastic response spectrum of the earthquake is transformed to different inelastic response spectra. For these inelastic spectra the intersections with the capacity curves are calculated. If the ductility of the building class equals the ductility of the inelastic demand spectrum, the respective spectral displacement is determined. For details of the capacity spectrum method see e.g. (ATC, 1995) or (Freeman, 1998). From spectral displacement values the damage probabilities can be calculated by means of fragility curves. These curves depend on the building type, too, and contain for possible displacement values the probabilities for a building to be in a certain damage class. If the determined maximum displacement is used, the damage probabilities can easily be drawn from the fragility curve. Because this method computes only possible damage distributions, different calculation methods, such as Monte Carlo, worst case scenario or expected value, can be applied to calculate a deterministic damage state for each single building from the inventory. For the damage estimation after mitigation, capacity curves and fragility curves from other regions with various assumptions are taken and analyzed (Smyth, 2004). For example, one assumption could be that a retrofitted building has the same seismic behavior as a new constructed building. Also capacity curves are transformed and modified using probability distributions. But more accurate curves for retrofit techniques in Bucharest based on the local buildings, have to be developed. The methodology for casualty estimation is based on the HAZUS methodology (NIBS, 2001). The casualties can be calculated for three different scenarios (day, night and rush hour) and are separated into four injury severity classes. As the input, the casualty estimation methodology requires the damage state probabilities of the different building classes, information on the distribution of building classes in the study region and population distribution data. To estimate the human losses casualty rates are used. The casualty rates describe the probability for occupants of buildings to be in any of the four injury severity levels at the time of an earthquake. These probabilities are given per building class for the five possible damage states of buildings. The calculation estimates the casualty probabilities for each building class and the deterministic casualties and injuries for all buildings. The direct economic losses caused by the damage of the buildings contain the costs of repair and the replacement costs. The probabilities for being in the damage state are calculated for all buildings and are expressed in monetary terms using local economic data. Each of the four damage levels has associated costs consisting of the percentage loss of the value of structure and the number and value of lives lost. It is assumed that the only damage level in which lives are lost is the total collapse case. In this case, the number of lives in this building will be assumed to be lost. The replacement value of the structure is calculated with a percentage given for the four damage cases. For the major and total collapse state the percentage are 100%, while for slight damage we set 1% and for moderate damage 20%. The total replacement costs are reported for each building and can also be summarized into the different building classes or occupancy classes.

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 477 To compare damages caused before and after mitigation, the following factors can be used: The Damage Factor, denoted DF, before and after an alternative : DF / The Mean Damage Factor (MDF) is defined as the mean losses of a building stock with similar structure to the same intensity i: 1 The Damage Ratio (DR) is the ratio of the damaged buildings to the total number of the buildings: Other indicators to quantify the seismic damage, are the Probable Loss indicator, the Scenario Loss and the Probable Maximum Loss. Fig. 4 shows the Damage Ratio for all buildings with different magnitudes in the test area and the damage ratio for 257 pre code buildings. In Fig. 5 the Damage ratio for the complete damage is shown. 100% 80% DR for 257 Pre Code Concrete Buildings Damage Ratio 60% 40% 20% DR 90%, Median, 10% 0% 6,00 6,40 6,80 7,20 7,60 Figure 4. Damage Ratio for all buildings and concrete C1/C2/C3 buildings.

478 T. Zikas 12% Damage Ratio 10% 8% 6% 4% 2% DR Complete Damage 90%, Median, 10% 0% Step 5 Benefit-cost analysis Figure 5. Damage Ratio for complete damage. The net benefit of a project,, is calculated by subtracting the sum of the costs from the sum of the benefits : Benefits of retrofitting measures derive from future earthquakes over the life cycle period of a building, and most of the costs typically occur when the project starts. The decision maker has to compare benefits and costs that appear in different time periods. For this reason, all benefits and costs should be discounted to their present value to compare projects with different time frames. The discount rate is often set by a public authority. By adding the present value in period 0,1,2,, denotes the life cycle of the building and the discount rate, the present value of the costs,, is given by: 1 1 1 C 1 0,1,, Similarly, the present value of the benefits is: 6,00 6,40 6,80 7,20 7,60 1 1 1 1 0,1,, Respectively, the difference between the present value of the benefits and the present value of the costs equals the net present value, denoted with, and formulated by the following basic equation for a cost-benefit analysis:

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 479 1 1 C T NPV B C 1 i Assuming that costs occur only in the present and benefits arise constantly over time with a constant discount rate, the equation simplifies to: 1 C 11 Several types of uncertainty for the earthquake consequences exist, and it is reasonable to divide the future in terms of a number of distinct contingencies. The probabilities of occurrence in each of the contingencies should be integrated in the analysis. Modeling the uncertainty starts with the specification of a set of contingencies, such as the costs and benefits with different strong magnitudes or the event time. With the specification and their probabilities it is possible to calculate the expected net benefit (Boardman, 2001). The expected net benefit,, is given by: Where for contingencies, be the benefits and be the costs under contingency, are the assigned probabilities. The sum of the probabilities,,, must be one. The expected value of the net present value is given by the formula: With this equation the expected net present value for different magnitudes and other contingencies can be calculated. Also, the specific time of the earthquake occurrence should be varied, because the case with an event with a magnitude of 7.2 in year 5 and the same earthquake 20 years later has a strong influence on the net present value. Step 6 Sensitivity analysis The inputs of a quantitative analysis are often incomplete because of a lack of data or knowledge, and alternative interpretations of these inputs can be made. Significant uncertainty exists in the modeling of earthquake consequences and the decision process of mitigation projects. Magnitudes of future earthquakes and the produced severity of ground motion can t be predicted precisely. Also, the performance of the building structure and the resulted damage cannot be calculated very accurately, the economic consequences and the development after a strong earthquake are unknown, too. Thus, the variability in the input

480 T. Zikas parameters of the loss estimation has to be taken into account with Monte Carlo simulation (MCS). Fig. 6 shows the uncertain elements in the decision process. Figure 6. Uncertainty in the decision process for rehabilitation projects. Adopted from [Grossi et al., 1999]. To examine the influence of each uncertain factor on the net present value, each uncertain factor has to be analysed within a range of possible values. The factors can be defined with minimum values or with a density function. So, on each simulation loop the values change and their influence can be analysed. Exemplarily, some distributions are shown: Discount rate:,, The direct costs of a retrofitting alternative can be expressed as triangular distribution for alternative at time : The associated probability density function is:,,,,,,,,,,,,,,,, With Monte Carlo simulation several scenarios are generated. The variety of parameters and their consequences on the complete damage state is shown in Fig. 7:

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 481 Figure 7. Monte Carlo simulation over the damage state complete. Step 7 Decision for best alternative Finally, once the input parameters and their influence on the net present value are analysed, the alternative with the highest expected net present value should be chosen. Often alternative projects are compared in terms of benefit-cost ratios, but a project with the largest net present value does not necessarily have the best B/C ratio. For example, consider that project A with costs of 1 million Euro and benefits of 10 million Euro has a benefit-cost ratio of 10, project B with costs of 5 million Euro and benefits of 15 million Euro has a larger net benefit, but the ratio is only 5. Although the costs of project B are higher, the project with the largest net benefit should be selected. Under budgetary constraints and more than two projects, a combination of those alternatives should be chosen which maximize the net present value. Relying on ranking the alternatives based on their benefit-costs ratios would not maximize the investment benefit. Furthermore, if the same cost or benefit elements in all examined alternatives would be removed by the analyst, such as costs for the building site equipment or costs for service disruption, to simplify the calculation, the highest benefit-cost ratio could swap between the alternatives. EQSIM FRAMEWORK EQSIM is a client/server application and divided into three main parts. The information component is integrated in Google Earth and so accessible over the Internet via Web browser. The inner city of Bucharest with over 1300 buildings is modeled in 3D and exact information about housing population, occupancy, structure, and storey can be retrieved. By clicking on the information point of a specific building, up to five building pictures about the original building state can be viewed. Potential losses from future earthquake are calculated with the simulation part of EQSIM. The simulation component is responsible for estimating potential losses from historical and hypothetical earthquakes. The calculation is based on the capacity-spectrum method. A more detailed description about the used methodology for the structural damage and casualties can be found in (Fiedrich, 2002). Based on the structural damage and casualties direct and indirect losses are summarized. The decision support component assesses retrofit projects for an urban area and evaluates these projects through Monte Carlo simulation as described in the previous section.

482 T. Zikas Figure 8. EQSIM architecture and components. All results of the simulation are stored in the database and adequate thematic maps for Google Earth are created to visualize the results of the scenario. Additionally, reports for spreadsheet applications can be used to analyse the damage scenarios. Figure 9. EQSIM Screenshot (Google Earth view).

International Symposium on Strong Vrancea Earthquakes and Risk Mitigation 483 Figure 9 shows a screenshot from EQSIM in Google Earth. On the left side the damage states 1-5 are clustered with graduated colors. On the main window the test area in the inner city of Bucharest with three-dimensional buildings is shown. On the bottom of the picture, the EQSIM frontend is shown, where the input parameters are defined and the simulation can be started. CONCLUSION This paper outlined some research topics around EQSIM and the decision support for rehabilitation programs. The decision process as shown is complex and many uncertainties in the input parameters exist. Huge efforts have to be made to gather all input data. With sensitivity analysis the most influential parameters can be found, in order to specify these values more accurately in a next step. With EQSIM a very powerful application exists which is also open for other regions. The information, simulation and decision support components are accessible over the internet and via Google Earth. It is possible to see 1304 buildings in the centre of Bucharest in 3D and to get detailed information about construction type, construction year, height, occupancy, occupants and more. The earthquake simulation component can be configured and started with Web2.0 technology and simulation results like structural damage, casualties and economic losses can be viewed and analysed directly in Google Earth. Once having the economic and financial losses after an earthquake the user can calculate the costs of retrofitting alternatives for specified buildings and compare the different alternatives. Moreover, the software is connected with more applications developed by the CRC, for instance the resource allocation system for the emergency operating center during earthquake events. Further developments will refine the cost calculation to more region specific data and the dynamic optimization to maximize the net present value. Additionally, a user management system and a front end should be integrated to allow for affected people to enter own data, such as inventory data, lease prices, and incomes. ACKNOWLEDGMENTS This study was carried out in the Collaborative Research Center (CRC) 461 Strong Earthquakes: a Challenge for Geosciences and Civil Engineering at the Universität Karlsruhe (TH), which is funded by the Deutsche Forschungsgemeinschaft (German Research Foundation) and supported by the state of Baden-Württemberg and the Universität Karlsruhe (TH). REFERENCES Applied Technology Council (ATC) (1995) Seismic Evaluation and Retrofit of Concrete Buildings, ATC 40 Report Vol. 1, Applied Technology Council, Redwood City, California, USA. Boardman, A., Greenberg, D., Vining, A., and Weimer, D. (2001) Cost-Benefit Analysis: Concepts and Practice (2nd Edition), Upper Saddle River, New Jersey: Prentice Hall, USA. Emergency Management Agency 156 (1995) Typical Costs for Seismic Rehabilitation of Buildings, Second Edition, Volume 1: Summary, prepared by the Hart Consultant Group, Washington, D.C., USA. Emergency Management Agency 157 (1995) Typical Costs for Seismic Rehabilitation of Buildings, Second Edition, Volume II: Supporting Documentation, prepared by the Hart Consultant Group, Washington, D.C., USA. Fiedrich, F., Gehbauer, F., Leebmann, J., Lungu, D., Markus, M. and Schweier, C. (2002) EQSIM: A New Approach to Damage Estimation, International Conference Earthquake Loss Estimation and Risk Reduction, Bucharest, Romania.

484 T. Zikas Freeman, S.A. (1998) The Capacity Spectrum Method as a Tool for Seismic Design. In 11th European Conference on Earthquake Engineering, Paris, A.A. Balkema, Rotterdam. Grossi, P., Kleindorfer, P. and H. Kunreuther (1999) The Impact of Uncertainty in Managing Seismic Risk: The Case of Earthquake Frequency and Structural Vulnerability, Risk Management and Decision Processes Working Paper 99-03-26, Department of Operations and Information Management, The Wharton School, Pennsylvania, USA. National Institute of Building Sciences (NIBS) (2001) Earthquake Loss Estimation Methodology,Technical Manual, Washington D.C., USA. Smyth, A.W., G. Altay, G. Deodatis, M.Erdik, G. Franco, P. Gülkan, H. Kunreuther (2004) Probabilistic Cost-Benefit Analysis for Earthquake Damage Mitigation: Evaluating Measures for Apartment Houses in Turkey, EERI Earthquake Spectra, 20, p.171-203. Wenzel, F. and Lungu, D. (2000) Risk Assessment for Romania, In: Proceedings volume. 2nd EuroConference on Global Change and Catastrophe Risk Management, Laxenburg, Austria.