A DEEP FOUNDATION COMPARISON: DRIVEN vs BORED PILES. Professor s Driven Pile Institute Logan, UT June 26, 2013



Similar documents
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

High Strain Dynamic Load Testing of Drilled Shafts

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Design and Construction of Auger Cast Piles

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SECTION 411 DRILLED PIERS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

BUTE Department of Construction Management and Technology

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

GLOSSARY OF TERMINOLOGY

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

Table of Contents 16.1 GENERAL Overview Responsibilities

High Capacity Helical Piles Limited Access Projects

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

SECTION 1 GENERAL REQUIREMENTS

Settlement & Vibration Monitoring for Transmission Line Foundation Installation

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Emergency repair of Bridge B421

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Structural Failures Cost Lives and Time

METHOD OF STATEMENT FOR STATIC LOADING TEST

vulcanhammer.net This document downloaded from

Geotechnical Building Works (GBW) Submission Requirements

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

The unit costs are based on the trend line of the 3 low bids for the average quantity.

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

Contractor of the Year

Measuring the Condition of Prestressed Concrete Cylinder Pipe

ATLAS RESISTANCE Pier Foundation Systems

COSMOS 2012: Earthquakes in Action COSMOS 2012

1,045 m length of the Deh Cho Bridge

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

The Installation and Load Testing of Drilled Shafts

Safe & Sound Bridge Terminology

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

Chapter. Restoration of Damaged Structures

6 RETROFITTING POST & PIER HOUSES

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

Now That s IDEAL. Now That s IDEAL. LISTEN. RESEARCH. DESIGN. DELIVER.

CID STREET INFRASTRUCTURE ASSESSMENT

PILE FOUNDATIONS FM 5-134

Paving Capitalization Work Categories and Treatments

Federation of Piling Specialists Testing Datasheet No 1

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

CERTIFIED TECHNICIAN PROGRAM TRAINING MANUAL. Bridge Construction and Deck Repair

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

High-Speed Nondestructive Testing and Intelligent Construction Systems

BRIDGES ARE relatively expensive but often are

POST FOUNDATION REPAIR PERFORMANCE RESIDENTIAL AND OTHER LOW-RISE BUILDINGS ON EXPANSIVE SOILS. The Repair Committee of

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015

IH-635 MANAGED LANES PROJECT, SEG. 3.2

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

C. Section TESTING LABORATORY SERVICE.

Dynamic Load Testing of Helical Piles

The International Workshop on Micropiles, 2007

PDCA Driven-Pile Terms and Definitions

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

INSTALLATION SPECIFICATION FOR DRIVEN PILES

LEADSYSTEMS. Vertical Configuration. Aft Batter Below Grade. Side Batter. Forward Reach. Raised Leads Above Grade. Forward Batter

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

Disputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

US 51 Ohio River Bridge Engineering and Environmental Study

Designed and Engineered to Perform

Moving Small Mountains Vesuvius Dam Rehab

Federation of Piling Specialists July 2010

Durability, Versatility

Bridge Structural Rehabilitation Using FRP Laminates

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

System. Stability. Security. Integrity. 150 Helical Anchor

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY

DESIGNING STRUCTURES IN EXPANSIVE CLAY

APPENDIX G SETTLEMENT

Pro-Lift Steel Pile Foundation Repair

Transcription:

A DEEP FOUNDATION COMPARISON: DRIVEN vs BORED PILES Presented By: Professor s Driven Pile Institute Logan, UT June 26, 2013 Billy Camp, PE, D.GE Technical Principal/Vice President S&ME, Inc. Charleston, SC bcamp@smeinc.com 843-884-0005 PDPI June 22, 2011 Logan, UT

COMMON DEEP FOUNDATIONS (US Practice for Support of Structures) DRIVEN Concrete 10, 12, 14, 18, 24, 30 and 36 square PSC 36 to 66 Cylinder Steel 10, 12 and 14 HP (16 and 18 now being rolled) 8 to 36 + pipe (open or closed) Wood 7 to 10 tip diameter, L<65 Composite PSC top with HP, W, or Pipe section bottom BORED Drilled Shafts 3 to 12 Micropiles 5 to 12 Drilled Displacement 14 to 18 Continuous Flight Auger (CFA) 12 to 24 PDPI

UNIT RESISTANCE DRIVEN Displacement or Low Displacement: Stress Increase strength increase and stiffer response. Disturbance: setup - resistance increase with time. PDPI

Driven Pile Time Dependency

UNIT RESISTANCE DRIVEN Cont. Disturbance: relaxation decreased resistance with time. Disturbance: irrecoverable in some formations (e.g., calcareous sands) Construction method effects rarely a factor. PDPI

Driven Piles Installation Method PDPI

DRILLED SHAFTS UNIT RESISTANCE Excavation reduces stresses strength decrease and softer response. Roughness small scale (concrete vs steel) and larger scale (irregular surface). PDPI

UNIT RESISTANCE DRILLED SHAFTS Cont. Reduced Disturbance: beneficial in some formations (e.g., calcareous sands) Construction method effects can be very important. PDPI

Drilled Shaft Polymer vs Mineral Slurry From Brown et al 2002

Fundamental Difference Point of Manufacture Driven Piles: at steel mill, prestressed yard, or wood yard under factory controlled conditions Uniform, consistent product delivered to the site Highly efficient Drilled Shafts: manufactured on site and in place Complex construction process Significant QA/QC requirements in the field PDPI

Driven Pile Manufacturing

Driven Pile Construction Equipment Crane Hammer & Leads Powerpack (hydraulic or air hammer) Helper Crane (opt.)

Pile Driving Equipment

Drilled Shaft Manufacturing Excavation Excavation Stability Excavation Cleaning Steel Reinforcement Fabrication Placement of Reinforcing Cage Concrete Delivery Concrete Placement

Drilled Shaft Construction Equipment Drill Rig Helper Crane Spoil Handling (loader, skip pan, etc.) Casing (opt) Slurry Handling (opt) Cage Erection Template Concrete Truck Concrete Pump Truck (opt)

June 22, 2011 Logan, UT Drilled Shaft Construction Process

Consequently Driven piles are generally less expensive General contractors can often self-perform with driven piles Drilled shafts usually require a specialty foundation subcontractor Since drilled shaft QA/QC is all done in the field, oversight & inspection is more complex but critical

Constructability Issues Driven Piles Length revisions are relatively easy (splicing or cut-off of steel piles, cutoff of PSC piles). Minimum penetration requirements (e.g., consideration of scour and liquefaction potential, fixity, uplift) may be hard to meet Drilled Shafts Length revisions are feasible but take time (cage modifications) Minimum penetration requirements are typically not an issue PDPI

Construction Feedback Driven Piles Driving resistance Transferred hammer energy/hammer performance Driving stresses Pile integrity Capacity Drilled Shafts Auger cuttings Observation of bottom cleanliness (sometimes) Concrete volume Shaft profile/geometry (possible but not widely done) PDPI

Redundancy & Loading Issues Driven Piles in general Smaller elements Lower capacity Lower cost More elements used Highly redundant Drilled Shafts in general Bigger elements Higher capacity Higher cost Fewer elements used Little to no redundancy PDPI

June 22, 2011 Logan, UT

June 22, 2011 Logan, UT

June 22, 2011 Logan, UT

Integrity & Reliability Issues Driven Piles Delivered free of defects May be damaged during or infrequently, after installation Damage is typically easily detectable A Driven Pile is a Tested Pile Repair generally consists of adding a new pile Drilled Shafts Defects may occur during construction Damage after construction is possible but rare Defects are not easily quantified Repair is generally very complex PDPI

Driven Pile Damage Handling Fix replace with new pile

Driving Driven Pile Damage Pipe pile toe damaged when trying to penetrate limestone identified during installation via dynamic testing Fix spud through caprock, switch hammers PDPI Crack in PSC pile between mudline and water surface identified during installation via dynamic testing Fix underwater patching w epoxy grout, switch hammers

Post-Installation Driven Pile Damage 3 to 15 ft Pipe group damaged due to ground movement confirmed via low strain dynamic testing Fix drive H-piles in between broken piles

Low Strain Integrity Testing

Sample PIT Data PIT Record from a 98-ft long production pile stored on-site (supported on blocks). 0.13 0.07 0.01 in/s 3: # 1 MA: 1.00 MD: 19. 95 LE: 98. 00 WS: 13500 LO: 0.07 HI: 0.00 PV: 18 T1: 30 T1-0.05 0 10 20 30 40 50 60 70 80 90 ft Toe Vel 0.10 0.05 0.00 in/s 3: # 53 MA: 1.00 MD: 19. 60 LE: 80. 00 WS: 13568 LO: 0.00 HI: 0.00 PV: 0 T1: 21 T1-0.05 Toe Vel 0 10 20 30 40 50 60 70 80 ft PIT Record from a pile laying on the ground with a break at 46 ft.

Records from Broken Pile Group Break If unbroken, no velocity increase before 98 ft, which is the pile toe location

Drilled Shaft Defects Slide from Dr. Dan Brown

Crosshole Sonic Logging E=ρV 2 F c Constant * E 2

Defect or Anomaly Drilled Shaft Case History DOT Project 4.5 ft diameter, 28 ft long shaft (approx 16 cy vol) Dry Method (but Wet) No problems reported on construction logs PDPI

Delayed velocity and low energy

Good Bad Worse Defect: Segregation caused by free-fall placement of concrete through 10 ft of water (as noted by inspector)

Defect or Anomaly Low Energy/Loss of Signal

Anomaly: Minor segregation/channelization due to bleed water inconsequential with respect to shaft performance

Detectable by CSL?

Integrity & Reliablity Summary Pile problems easily identified via testing Repair generally possibly via replacement/supplementation Shaft problems often hard to quantify Remedy of shaft problems may be very difficult PDPI

Vibration Misconception Construction Activities generate vibrations Pile driving often inappropriately penalized because of its consistent auditory alert Structures and soil are much more tolerant of vibrations than people

Vibration Criteria Slide from Ed Hajduk PDPI Upper blue line is most commonly used

Peak Vertical Particle Velocity, in./sec PDPI Peak Vertical Particle Velocity, mm/s 10 Human Perception Thresholds Formation of hairline cracks in plaster and drywall joints 1 Very Disturbing Strongly Perceptible/ Disturbing 100 10 Approx PPV that will induce 0.01% strain in a very loose sand (Vs of 500 fps) 0.1 Perceptible 1 0.01

Oriard s and NAVFAC Criteria (from Oriard, 1999) (from NAVFAC DM-7, 1986)

Largest Vibration-Related Claims in Charleston, SC St. Philips Church: Extraction of drilled shaft temporary casing with vibratory hammer French Huguenot Church: Pavement demolition with large track-hoe

Driven Piles vs Drilled Shaft Foundation Selection Case Histories PDPI

Indian Inlet River Replacement Bridge Design Build Existing Bridge Replacement Bridge Scour concerns no foundations in inlet Larger main pier footings = longer span length (expensive) Two DB teams: winning team used all driven piles, other team used drilled shafts

Indian Inlet River Cont. Skanska: voided 36 sq. PSC piles Self-performed Higher resistance factor Faster Less expensive PDPI

Main Piers

Boeing 787 Second Assembly Line PDPI

MAIN BUILDING Eave Height = 101 610 Continuous Truss 460 Clear Span 16 Thick Floor Slab Utility Tunnel Foundation Alternates in Bid Documents 24 Pipe Piles - 2, 3, 4 and 5 pile groups HP 14 x73 2, 4, 5, and 7 pile groups PDPI Lowest Cost Foundation 4 & 5 dia. Drilled Shafts compressive load 2300 kips uplift 547 kips lateral load 350 kips

SC 802 Bridge over Broad Creek Beaufort, SC New bridge adjacent to existing bridge (c. 80s) Existing bridge on driven H-Piles and PSC piles New bridge design requirements Much larger seismic hazard New bridge foundations Driven PSC piles on approaches Drilled shafts at higher bents PDPI

Existing Bridge PDPI June 22, 2011 Logan, UT

Existing Bridge PDPI June 22, 2011 Logan, UT

Power Plant Expansion Major expansion of existing power plant All original structure supported on 3 or 4 diameter drilled shafts (due to karst concern)

June 22, 2011 Logan, UT Units 3 & 4 2007 & 2009 $1.4 billion Unit 2 1983 Unit 1 1995

June 22, 2011 Logan, UT Sample Profile

June 22, 2011 Logan, UT Sample Profile

Coring Comparison Previous Methods Triple-Tube Coring

June 26, 2013 Logan, U Coring Comparison Cont. Previous Methods Triple-Tube Coring

Foundation Design Part 1 3 or 4 Diameter Drilled Shafts Rock Sockets: fs=12ksf 300 ton Design Load PDPI

Drilled Shaft Lateral Response Moment Shear Loose Sand/Soft Clay Santee Limestone

Change Since Units 1 & 2 Design New Design Event in Building Code Prior Codes: 10% prob of exceedance in 50 yrs IBC: 2% prob of exceedance in 50 yrs (w 2/3 factor) PDPI

Sa (g) PDPI Seismic Hazard Differences Pineville Response Spectra 1.20 1.00 2/3 of 2% Probability Event 0.80 0.60 0.40 0.20 10% Probability Event 0.00 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 Period (sec)

Foundation Alternatives Larger Shafts Ground Improvement Driven Piles Flexible Reduced Liquefaction Potential PDPI

Driven Pile Model F internal F Inertial from superstructure Mat Displacement Piles: Mat moves with soil Reduced Liquefaction Reduce LQ Potential due to Densification Santee Limestone

Foundation Design Part 2 Driven Piles Bearing on the Santee Limestone 14-in. square PSC Piles: 100 Ton Design Load 12-in. square PSC Piles: 70 Ton Design Load Savings of $6 to $8 million on Unit 3 Savings of 1 to 2 months on Unit 3

Construction 20,000+ PSC piles driven 30 piles per rig per day PSC Pile Manufacturers: Tekna & Palmetto Pile Driving Foundation Costs > $100 million

June 22, 2011 Logan, UT

June 22, 2011 Logan, UT

June 22, 2011 Logan, UT

Summary Driven Piles Simplicity Cost Reliability Drilled Shafts Capacity Geologic Versatility PDPI

Thanks for Listening???? Billy Camp, PE, D.GE Technical Principal/Vice President S&ME, Inc. Charleston, SC bcamp@smeinc.com 843-884-0005