Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry



Similar documents
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge

PROJECT RISK ANALYSIS AND MANAGEMENT

Integrated Risk Management As A Framework For Organisational Success. Abstract

Project Risk Management Single Subject Certificate Syllabus Levels 1&2 4 th Edition

Managing construction procurement risks

Risk Management Policy and Framework

Understanding risk exposure using multiple hierarchies. Introduction

PROGRAM RISK MANAGEMENT

Project Governance a board responsibility. Corporate Governance Network

CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT

Amajor benefit of Monte-Carlo schedule analysis is to

ISO, CMMI and PMBOK Risk Management: a Comparative Analysis

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

Contract Management. Brief 22. Public Procurement. September 2011

Determination of risk identification process employed by NHS for a PFI hospital project in the UK

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

Managing Overall Project Risk. Abstract

Risk Management Policy

RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES

Issues in Information Systems

Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey

Project Management. [Student s Name] [Name of Institution]

WORK HEALTH AND SAFETY

CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS

Risk Management of Construction - A Graduate Course

Five steps to Enterprise Risk Management

A Risk Management Standard

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

Corporate Risk Management Policy

Version Adoption by Council: 2013 Resolution Number: 2013/177 Current Version: V1.0 Administered by: Governance Coordinator

The Risk Management strategy sets out the framework that the Council has established.

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

Polish Financial Supervision Authority. Guidelines

PM in construction industry

An Approach to Proactive Risk Classification

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2

Charities & Not for Profit Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management

Portfolio Risk Management: aligning projects with business objectives to deliver value

Use a Risk Breakdown Structure (RBS) to Understand Your Risks

AN EVALUATION OF CONSTRUCTION CASH FLOW MANAGEMENT APPROACHES IN CONTRACTING ORGANISATIONS. Paper presented at

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I

Using Risk Assessment to Improve Highway Construction Project Performance

Project Risk Management. Presented by Stephen Smith

Update on Programme Management Controls & Risks

Project Risk Management in Automotive Industry. A Case Study

Darryl Anderson PROJECT MANAGEMENT Harbour Authority Associa9on of Bri9sh Columbia March 6, 2014

P3M3 Portfolio Management Self-Assessment

Year 2000 Business Continuity Planning: Guidelines for Financial Institutions Introduction

Care Providers Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management

Changing Perceptions and the Skills Required by Security Managers

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan

How To Manage A Contract

Palisade Risk Conference, 2014

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

Important Factors for Success of Public Construction Projects

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

AFTRS Health and Safety Risk Management Policy

Project management skills for engineers: industry perceptions and implications for engineering project management course

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY ENTERPRISE RISK MANAGEMENT FRAMEWORK

Factors Affecting the Accuracy of Pre-Tender Cost Estimates in the Gaza Strip

ICT Project Management

PROJECT CASH FLOW FORECASTING: A MATHEMATICAL APPROACH

A SYSTEMS MODEL OF PROJECT MANAGEMENT

What is Human Resource Management?

Risk Management Policy

Risk Management in Infrastructure Projects in India

ARCTIC DIALOGUE GREENLAND

Project Zeus. Risk Management Plan

PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY

Tendering to Public Sector Organisations

CONTROLLED DOCUMENT. Number: Version Number: 4. On: 25 July 2013 Review Date: June 2016 Distribution: Essential Reading for: Information for:

Chapter 1 Introduction to Contract Management and Administration

AACE International Recommended Practices

Extending the Risk Process to Manage Opportunities

Consultancy Services Proposal

Project Diagnostics Assessing the Condition of Projects and identifying Poor Health

So, What Exactly is Risk Management?

Health, Safety and Environment Management System

POL ENTERPRISE RISK MANAGEMENT SC51. Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT:

PROJECT RISK MANAGEMENT

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

Global framework. Safety, health and security for work-related international travel and assignments

STAGE 1 COMPETENCY STANDARD FOR PROFESSIONAL ENGINEER

Incorporating Risk Assessment into Project Forecasting

Bridgend County Borough Council. Corporate Risk Management Policy

University of Nottingham Emergency Procedures and Recovery Policy

TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL

WFP ENTERPRISE RISK MANAGEMENT POLICY

Dr J B Yang and Mr M Sonmez, Manchester School of Management, UMIST, Manchester, M60 1QD Tel: jian-bo.yang@umist.ac.

IT Risk Closing the Gap

Analysis of Risk- Response based on Railroad Construction Project. Author s Details: (1) Ploywarin Sangsomboon- (2) Song Yan

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

and Risk Tolerance in an Effective ERM Program

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

Distributor Liability Contract Risk Management THOMAS DOUGLASS APRIL 15, 2015

Sensitivity of an Environmental Risk Ranking System

Guidance Note: Corporate Governance - Board of Directors. March Ce document est aussi disponible en français.

RISK MANAGEMENT FOR INFRASTRUCTURE

STAG Technical Database Section 13

Transcription:

CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1 School of Construction Management and Engineering, University of Reading, Reading RG6 6AW, UK 2 School of Mechanical, Aerospace and Civil Engineering, University of Manchester, Manchester M60 1QD, UK 3 Government of the Sultanate of Oman, PO Box 2272, PC 112 Ruwi, Sultanate of Oman ABSTRACT Risk management in a project context is a formal process that enables the identification, assessment, planning and management of risks throughout the project lifecycle. This paper reviews risk management practices within project environments in Oman. A survey of construction organizations reveals that the majority of these companies relies on intuition, subjective judgment, and experience in assessing project risks. Furthermore, it has been revealed that their risk management practices are based on ad hoc fire-fighting basis rather than formal and systematic risk management processes. The focus of such organizations is on the avoidance of risk as a process and not mitigating the circumstances which give rise to the occurrence of risk. The reasons behind these common practices are: (a) lack of familiarity with formal risk management concepts and methods; (b)

550 CIB World Building Congress 2007 lack of expertise; and (c) lack of incentives to carry out risk analysis exercises. KEYWORDS: Risk, Risk Management, Construction Industry. 1. INTRODUCTION The increasing failure of many construction projects in meeting deadlines, cost and quality targets and the competitive threat posed by globalisation all put risk management high in the agenda for forward thinking organisations. This concept has been a subject for serious academic study because of inherent time and cost overruns associated with construction projects. Risk management is a formal process that systematically enables the identification, analyses, and management of risks throughout a project lifecycle (PMBOK, 1996). The management of risk is one of the most important issues facing the majority of construction firms in Oman s construction industry today. The concept of risk management is relatively new and has not yet been practiced by most contractors with the exception of subjective judgement and practical experience; this resulted in poor definition of the project objectives, inadequate cost estimates and adversarial relationships between these companies and their clients. Risk refers to factors affecting project outcomes and the probability of occurrence of each outcome. Risk Management is about minimising disturbance to the project, and ensuring every thing goes according to plan to meet project objectives. It provides a disciplined environment for proactive decision making to assess continuously what could go wrong, determine which risks are important to deal with and implement strategies to deal with those risks. Therefore, managing risk is actually managing the organisation s activities and resources to mitigate the impacts to the achievement of a project s goals and objectives. Recent events in the Sultanate of Oman of opening doors to foreign investments especially in the gas and tourism sectors and joining regional and global free trade organisations is expected to yield an unprecedented growth in construction activities. Oman is in desperate need for development projects in many areas, especially in the fields of petrochemical and gas industries, water, wastewater collection and distribution, roads and highways infrastructure, tourism and residential projects. As a result, an unprecedented number of large-scale projects are currently under construction and in the planning and contract award stage. The construction industry is one of the major sectors in Oman and has played a significant and distinct role in Oman s economic and social development. Its contribution to the Gross Domestic Product (GDP) was 3% in 2004 and is projected to increase to 10% by 2020 (Oman Chamber of Commerce and Industry, 2005). In order for this industry to sustain a

CIB World Building Congress 2007 551 positive performance and achieve a continuous improvement for the coming years and to meet the demands of the comprehensive development, it is required to adopt Project Management tools and techniques such as Risk Management. With this, the construction industry will hopefully, be able to play an important role in contributing to the betterment of the Gross Domestic Product and the growth of investment made in the tourism and other economic sectors in addition to its contribution in employing the national cadre for generating income and raising the living standards of the individuals and ultimately achieving economic wellbeing for the Omani society. The construction industry is key to Oman s development. This paper reviews risk practices within project environments in Oman. It presents the results of a questionnaire survey of the largest contractors involved in the Omani construction industry, concerning the usage of risk management technique. It aims to identify and assess the construction risks and to understand how these risks are currently being managed, particularly those related of time and cost. 2. RISK AND RISK MANAGEMENT Risks are present and inherent in all businesses and transactions; we live with it and learn to manage its influence on our lives. Construction activities are not an exemption to this influence. According to Chapman and Ward (1997): All projects involve risk the zero-risk project is not worth pursuing. Organisations which better understand the nature of these risks and can manage them more effectively cannot only avoid unforeseen disasters but can work with tighter margins and less contingency, freeing resources for other endeavours, and seizing opportunities for advantageous investment which might otherwise be rejected as too risky. Risk refers to factors affecting project outcomes, is related to a range of outcomes and the probability of occurrence of each outcome. A number of researchers have attempted to define risk from various perspectives. Although Healy (1982) and Smith (1999) expressed risk as an exposure to economic loss or gain from being involved in the construction process, other researchers (Flanagan and Norman, 1993) regarded risk as a potential for unwanted negative consequences of an event or activity. Furthermore, Bufaied (1987) and Boothroyd and Emmett (1998) described risk in relation to construction as a variable in the process of a construction project whose variation results in uncertainty as to the final cost, duration and quality of a project.

552 CIB World Building Congress 2007 Risk Management is concerned with minimizing disturbances to projects and ensuring everything goes according to plan to meet project objectives. It provides a disciplined environment for proactive decision making to assess continuously what could go wrong, determine which risks are important to deal with and implement strategies to deal with those risks. Therefore, managing risk is actually managing the organisation s activities and resources to mitigate the impacts to the achievement of a project s goals. A growing number of construction organisations especially in the developed world have recognized the increasing importance of risk management. Many of these have established risk committees which are often chaired by a board member or a risk facilitator who is responsible for providing strategies, techniques and specific approaches to recognize and confront any threat faced by an organisation in fulfilling its objectives. According to Smith (2003), competent contractors, in addition to their professional competence, must demonstrate high competence in managing risks to avoid potential disastrous outcomes. He argues that risk management can be considered as an essential part of a continuous and structured project planning cycle which: Requires acceptance that uncertainty exists; Generates a structured response to risk in terms of alternative plans, solutions and contingencies; Is a thinking process requiring imagination and ingenuity; and Generates a realistic (and sometimes different) attitude in project staff by preparing them for risk events rather than letting them be taken by surprise when they arise. Simon et. al. (1997) suggest that, at its most fundemantal level, risk management involves identifying risks, predicting how probable they are and how serious they might become, deciding what to do about them and implementing these decisions. This is further endorsed by Smith (1999) who presents a process involving four steps for managing risks: 1. identification of risks; 2. analysis of implications; 3. response to minimize risk effects; and 4. allocation of appropriate contingencies. Of course, the objective of risk management is not to create a totally risk free business or project, as no such risk-free environment exist, but to raise the awareness of all the stakeholders of a project or business of both negative and positive risks associated with their activities. This will help then to better calculate risks and to manage these effectively and efficiently throughout the life of a project.

CIB World Building Congress 2007 553 3. THE STUDY This study is based on an intensive research of the Omani construction industry to understand current methods used for managing risk and identify the most common risk factors particularly those contributing to time and cost overruns. To realize these objectives a questionnaire survey was personally distributed to 60 contractors representing the largest construction contractors listed in the Omani Government Tender Board (Oman Tender Board, 2005). The personal delivery approach was deliberate to ensure that respondents fully understood the aim of the study and that no part of the questionnaire was ambiguous to any of the respondents. In the following sections, the results of this survey are discussed in more details. 4. THE QUESTIONNAIRE SURVEY A total of 43 responses were received resulting in a 72% response rate to the questionnaire survey. This is much higher than the average acceptable response rate of 20-30% (Akintoye and Fitzgerald, 2000). The reasons for such a high response rate are believed to be the distribution method and also the nature of the investigation with Omani construction professionals realizing the importance of this study to their practices. The respondents to the questionnaire were executive directors, qualified project managers or chief engineers with at least 10 years of experience. The survey included 32 risk factors, Table 1. Respondents were asked to indicate the significance of each of these factors on a 3-point Likert scale as follows: 1 = not significant 2= moderately significant 3= highly significant The data collected from the questionnaire was used to compute a Severity Index for each of the risk factors. Severity Index computations were used to rank the factors according to their significance in affecting time and cost overruns. The results from this computation will be discussed in the analysis and discussion section. Severity Index analysis is a technique used for measuring the relative importance of a group factors. The index is calculated using the equation illustrated below (Elhag et. al., 2005): 3 S.I. = ( wi fi)/ n 100% i= 1

554 CIB World Building Congress 2007 Where i represents the rating of each point on the scale: 1-3, fi the frequency of responses, n the total number of responses and wi the weight for each rating. Table 1: Significance of Risk Factors on time and cost overruns Type of Risk Severi ty Ranking Index Financial Capability / failure 82.95 1 Management team ( Suitability, experience, performance ) 81.4 2 Variation orders & Additional works (magnitude, timing, interference level) 80.62 3 Accuracy of project programme 79.84 4 Material prices / availability / supply / quality 79.84 4 Delayed Permits issuance 79.07 5 Inspection, testing & approval of completed works (toughness / quality requirements) 79.07 5 Quality of design & specification 78.29 6 Subcontractors performance 78.29 6 Level of communication within the contractor organisation 77.52 7 Project Risk Management in Oman 7 Delayed payment by client 77.52 7 Level of uncertainty of soil / underground condition 77.52 7 Labour cost / availability / supply / performance / productivity 77.52 7 Accident / safety 75.97 8 Quality of finishing 74.42 9 Completeness & timeliness of project information (design, drawings, specification) 74.42 9 Contractor Current Work Load 72.87 10 Delayed payment to subcontractors 72.87 10 Plant costs / availability / supply / condition / performance 72.1 11 Site access / Work space 69 12 Third party delays 68.99 13 Stability of Market Conditions 68.22 14 Delayed claims & dispute resolutions 66.67 15

CIB World Building Congress 2007 555 Disasters i.e. fire, flood,.etc 65.9 16 site conditions / site topography 65.9 17 Exchange rate fluctuations 65.12 18 Adverse weather conditions 63.57 19 Client access and working hours restriction 59.69 20 Government regulations / policy ( health & Safety, fire etc ) 58.91 21 Inflation 58.14 22 Labour disputes 55.04 23 New technology 53.49 24 5. THE ANALYSIS The survey reveals that financial capability of contractors, suitability and experience of the management team and the magnitude and timing of additional works and variation orders are the top 3 most significant risk factors affecting time and cost overruns. The least significant factors in order of importance are inflation, labour disputes and new technology. The survey of Omani construction organizations also reveals that there is a need to engage construction organizations in a systematic process of risk management which would foster intuitive judgement and experience. Despite the existence of risk management guides such as PRAM (Simon et. al., 1997) and RAMP (1998), there is no evidence that these have had any impact in the Omani construction industry. One reason for this is believed to be the onerous nature of implementing such programmes. PRAM (Simon et. al., 1997) is a comprehensive risk management guide that through experience has shown that the level and kind of communication it generates can lead to significant cultural changes within an organization that are complex and difficult to predict. This by all means is very beneficiary indeed but could be why construction organizations are reluctant to adopt. Cultural change is often perceived as a threatening exercise to existing practices. On the other hand, RAMP (1998) has been developed to aid in decision making and risk management at strategic rather than project level. Furthermore, it places particular emphasis on financial implications and therefore the framework targets sponsors, lenders and investors rather than project managers. There is clearly a need to develop a framework for Omani construction organization that would serve as a practical first-step guide to promoting the concept of risk management at project level which could be used in the short term by construction organizations with a view of implementing a full-scale onerous risk management programme such as

556 CIB World Building Congress 2007 PRAM in the long term. This framework would provide a pragmatic bird s eye view of all the stages essential in a risk management exercise together with guidance on quantitative and qualitative tools and techniques that could be used at each stage. The authors are in the final stages of developing such a framework that would enable the construction industry in Oman to further contribute towards development of the economy and social systems. 6. CONCLUSIONS This paper reviews risk practices within project environments in Oman. It presents the results of a questionnaire survey of the largest contractors involved in the Omani construction industry, concerning the usage of risk management technique. It has been revealed that the majority of construction organisations in Oman have no formal risk management procedures in place. It has been suggested that such procedures are based on an ad-hoc fire-fighting basis rather than formal and systematic risk management processes. The focus of such organizations is on the avoidance of risk as a process and not mitigating the circumstances which give rise to the occurrence of risk. The survey shows that the most significant risk factors found are (a) Contractor Financial Capability; (b) Management team (Suitability, experience, performance); (c) Variation orders and Additional works; and (d) Accuracy of project programme. The risk category Inflation, Labour disputes and new technology received the lowest ranks due to low inflation rate and the industry is not influenced by any power group such as labour unions and minor labour disputes are handled by the Ministry of Work Force.

CIB World Building Congress 2007 557 7. REFERENCES Akintoye, A., and Fitzgerald, E., 2000, A Survey of Current Cost Estimating Practices in the UK. Construction Management & Economics, 18(2), 161-72. Boothroyd, C. and Emmett, J., 1998, Risk Management A Practical Guide for Construction Professionals, (London: Witherby & Co. Ltd). Bufaid, A., 1987, Risks in Construction Industry: their causes and their effects at the Project Level, PhD Thesis, (The University of Manchester: UK). Chapman, C. and Ward, S., 1997, Project Risk Management Processes, Techniques and Insights, (London: Chichester, John Wiley & Sons). Cohen, M. and Palmer, G., 2004, Project Risk Identification and Management, AACE International Transactions. Elhag, T.M.S., Boussabaine, A.H., Ballal, T.M.A., 2005 Criticial determinants of construction tendering costs: Quantity Surveyors' standpoint. International Journal of Project Management. 23(7), 538-545. Flanagan, R. and Norman, G., 1993, Risk Management and Construction, (Oxford: Blackwell Scientific Publications). Healy, J., 1982, Contingency Funds Evaluation, Transaction of American Association of Cost Engineers, B3.1 B3.4. Oman Tender Board, 2005, Classifications of Contractors, www.tenderboard.gov.om (accessed 05.2005). Project Management Institute - PMI, 1996, A Guide to the Project Management Body of Knowledge, (USA: PMI). RAMP, 2005, RAMP: risk analysis and management for projects : a strategic framework for managing project risk and its financial implications, (London: Thomas Telford). Simon, P., Hillson, D. and Newland, K., 1997, PRAM-Project Risk Analysis and Management Guide, (UK: APM). Smith, N., 1999, Managing Risk in Construction Projects, (London: Blackwell Science). Smith, N., 2003, Appraisal, Risk and Uncertainty, (London: Thomas Telford).