Planning and Scheduling Your Project Using Microsoft Project 2003



Similar documents
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

OVERVIEW. Microsoft Project terms and definitions

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

Microsoft Project 2013 Guide to Task and Resource Planning

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

ELECTRO-MECHANICAL PROJECT MANAGEMENT

MS Project 2007 Quick Guide

Using MS Project in Translation Projects Management

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Resource Allocation in MS Project

Computer Training Centre University College Cork

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

MS Project 2000 Tutorial: Introduction

MSP How to guide session 2 (Resources & Cost)

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Session 6. Microsoft Project. Emanuele Della Valle. Lecturer: Dario Cerizza

Project Management: Tracking Progress and Earned Value with MS Project 2003

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Mastering Microsoft Project B; 3 days, Instructor-led

NE-50413B Mastering Microsoft Project 2010

Project Management Glossary

MICROSOFT OFFICE PROJECT - SYLLABUS

Introduction to Microsoft Project 2010

Planning and Managing Projects with Microsoft Project Professional 2013

PERCEPTION PERT-PAC Using Microsoft Project 2000

Mastering Microsoft Project 2010

Simple Earned Value (Using MS Project 2010)

Creating a New Project

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)

WORK PROGRAM GUIDELINES

Microsoft Project Exam Study Guide

Project Management: Intermediate Microsoft Project 2010

Microsoft Project Activity

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

Microsoft Project 2010 Advanced

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

technical tips and tricks

Lesson 6 - Managing Resources in a Project Plan

MICROSOFT PROJECT II

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Applied Project Management ( APM )

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Developing a Gantt and PERT Chart

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

Software Development & Education Center. Microsoft Office (Microsoft Project 2010)

1 Start a new project

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Project Management Courses

Project 2010 Introduction

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

University of Sunderland. Microsoft Project. Basic Guide

Project Quick Reference. The Assignment Equation. EPM Architects

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

Project planning with MindGenius

MICROSOFT PROJECT TUTORIAL

CDC UNIFIED PROCESS JOB AID

Earned Value Analysis Exercise

Microsoft Project 2007 Level 1: Creating Project Tasks

Mastering Microsoft Project 2013

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Project Management Courses

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

CPM -100: Principles of Project Management

Scheduling Glossary Activity. A component of work performed during the course of a project.

Revealing the Secrets of Microsoft Project

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Applied Software Project Management

QUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012

Microsoft Project Microsoft Project The smart way to learn. Microsoft Project one step at a time!

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

Project Control with ProTrack

4.0 - Using the Microsoft Project Plan

Collaborative Scheduling using the CPM Method

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

Release Notes Assistance PSA 2015 Summer Release

Planning and Managing Projects with Microsoft Project Professional 2013

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

Glossary. Release

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Chapter 2: Project Time Management

CA Clarity PPM. Glossary. Release

ECDL / ICDL Project Planning Syllabus Version 1.0

Project Management Quick Reference Guide for MS Project 2010

Tracking Project Progress

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Transcription:

Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in

Meeting Protocol

Agenda Project File Project Calendar Creating Tasks and WBS Milestones Recurring Tasks Dependencies Lead and Lag times Constraints Deadlines Split Tasks Resources Contouring Over allocations Cost Optimise Plan Earned Value Management

Create a Project File Create a new file Choose one of the templates Complete the summary tab Complete Project Information

Change Project Calendar Working time Week starting (middle east projects will have their weekends on Thursday and Friday) Holidays Staff leave

View Options Change the date format to that used by the client Change the currency symbol, decimal digits to the currency you would use to track the project cost.

General Options Specify the user name, standard and overtime billing rates For Whizible users Uncheck Advice From Planning Wizard

Schedule Options Change the duration from days to hours For Whizible users Uncheck Show Scheduling messages Uncheck Tasks will always honour their constraint dates Click Set as Default

Enter tasks and Duration % Complete, WBS, Task name, work, duration, start, finish, predecessors, resource names Enter tasks and duration Don t enter the start and finish dates. Also enter the notes. Elapsed Duration (ed) is calendar duration Indent tasks to create a logical outline Break large tasks to smaller tasks

Enter tasks and Duration For Whizible users Use the Text 30 field to define Task Type Use the following priority Low (0 to 400) Medium (401 to 600) High (601 to 900) NULL (901 1000) Ignored by Whizible You can assign a Task Calendar to a task. Then the option Scheduling ignores resource calendar

Identify Milestones Identify significant events as milestones [Creating a task of 0 days marks it as a milestone] Indicated by Change Icon

Create Recurring Tasks Weekly team meetings, SQA reviews, Weekly Progress Reporting all recur at predetermined intervals Roll Gantt Bar to Summary Specific task information defined in the Gantt Bar Styles rolls up and shows in the summary task Hide Task Bar Hides the Bar

Specify task dependencies Automatically a finish to-start dependency is created

Task Dependencies You can specify start-to-start, finish-to-finish or start-to-finish

Lead and Lag Times Overlap tasks or enter lead / lag times Lag times are +ve values while lead times are ve values Lag and lead can be entered as a % or absolute values

Constraints Set specific start or finish dates Specify a start date start no earlier than (SNET) constraint is set Specify a finish date -finish no earlier than (FNET) constraint is set Use this feature sparingly

Add Deadlines Deadlines don t affect scheduling mechanisms Microsoft Project will inform you that a task will finish past its deadline. You then have the option of adjusting the schedule to meet that deadline. Drag the green arrow to reset deadlines

Split tasks If work on the task is interrupted and then resumes later in the schedule

Assign Resources Specify type of resource work / material Specify the number of resource units available for this resource in the max. Units field, as a percentage. E.G., Type 300% to indicate three full-time units of a particular resource.

Specify Resource Groups For each material resource (supplies consumed throughout the project), in the material label field, type a measurement unit for the material resource, such as ton. Resource groups can be used for sorting, filtering, or grouping tasks by resources belonging to a particular group. You can use groups to indicate the department a human resource belongs to or to specify accounting codes for billing purposes.

Change work schedule for Resource Modify the individual resource calendar

Specify Costs for Resource Specify the Standard and Overtime rates

Specify Workgroup Information and availability for Resource Use this to specify long absences e.g. sabbatical leaves Independent of resource calendar

New Base Calendar If a group of resources has the same special working hours and days off, you can create a new base calendar for them

Assign Resources Support for Active Directory / Address Book / Microsoft Project Server Assign multiple resources at once (CTRL and drag) Replace a resource by choosing the resource and clicking replace then reassign a fresh resource A Valid work value can be entered then units = entered work/duration Automatic assignment of resources can be disabled in Tools / Options / General tab

Fix the task duration If a task is 8 hrs duration and 8 hrs work with a single resource adding a second resource reduces the duration to 4 hours (effort driven) Turn this feature off to increase the work to 16 hours Turn off globally in Options / Schedule

Plan Optimisation Duration Compression Crashing Fast Tracking Resource Levelling Heuristics

Edit resource assignments (Assignment Contours) Effective way to remove over allocation (shown in red) Just drag and drop tasks under the resource

Predefined Assignment Contours

Predefined Assignment Contours CONTOURS SEGMENTS 1 2 3 4 5 6 7 8 9 10 Flat Back Loaded 10% 15% 25% 50% 50% 75% 75% Front Loaded 75% 75% 50% 50% 25% 15% 10% Double Peak 25% 50% 50% 25% 25% 50% 50% 25% Early Peak 25% 50% 75% 50% 50% 25% 15% 10% Late Peak 10% 15% 25% 50% 50% 75% 50% 25% Bell 10% 20% 40% 80% 80% 40% 20% 10% Turtle 25% 50% 75% 75% 50% 25%

Automatic Resource Levelling Levelling Order Standard : Considers links, slack, dates and priorities ID Only : Delays task with the highest ID Priority : Priority of tasks takes precedence Level only within the available slack Adjust Individual assignments on a task : To level only over-allocated resources AVOID AUTOMATIC LEVELLING

Manual Resource Levelling Create Delays Remove or Replace resources Reduce Units

Creating Delays

Assign Costs to resources Default rates for all resources can be assigned (Tools / Options / General) If costs change use the Resource Information / Costs Tab and specify the costs with effective dates (useful if a resource gets a salary revision during the course of the project)

Set Fixed Costs Useful when the exact cost associated with a cost is known View / Table / Costs

Define When Costs Accrue Accrual can be prorated, at the start or at the end of a project

Review the cost of tasks and resources From the Resource sheet click View / Table / Cost

Cost distribution over a task Choose View / Task Usage Choose Format / Details / Cost

Resource Costs (Detail) Choose view / resource usage Choose format / details / cost

Resource Costs (Graphical) Choose view / resource graph Choose format / details / cost or Cumulative cost

Cost of Entire Project Choose Project / Project Information / Statistics

View the entire project From the GANT Chart Choose View / Zoom / Entire Project

Check the Project dates Check the project s START and FINISH dates

Identify Critical Path Critical Path Has Zero Slack Tasks can t be delayed without affecting overall schedule Use the GANTT chart wizard to identify the critical path

Viewing Critical Tasks Filter using the menu

Switching Views Choose View / More Views

Different Fields in a View View / More Views View / Table / More tables

Using Filters Interactive Filters can be applied Resource filters cannot be applied to tasks and vice versa

Sorting Tasks Variety of sorts are possible Renumbering tasks permanently Its possible to maintain the hierarchy of the subtasks to its parent task

Grouping Information Variety of Group by options are available

Save the Plan Save the plan with a baseline it helps in tracking your project To save the budget, enter the costs before saving the baseline Interim plans act as checkpoints, upto 10 interim plans can be saved

Earned Value Management Planned Value (PV) or Budgeted Cost of Work Schedule (BCWS) Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) Actual Cost (AV) or Actual Cost of Work Performed (ACWP)

EVM Cost Variance (CV) = EV AC Schedule Variance (SV) = EV PV Cost Performance Index = EV / AC Schedule Performance Index = EV/PV Positive Values are good. Negative Values Bad Ratio s closer to 1 are good

Thank You