PORTABLE GENERATORS AND OSHA CONSTRUCTION REGULATIONS



Similar documents
Electrical Grounding. Appendix C

ELECTRICAL - WIRING DESIGN AND PROTECTION SELF INSPECTION CHECKLIST

ELECTRICAL INSPECTION BULLETIN (Effective )

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23

Title: Grounding and Bonding Rev-01

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE

Electrical Hazards. Power Tools. Extension Cords

Top Commercial / Residential Electrical Requirements *

Common Electrical Hazards in the Workplace Including Arc Flash. Presented by Ken Cohen, PhD, PE & CIH (Ret.)

Application Bulletin NEC Reference Guide for SolarBridge-Enabled AC Module Installers

Chapter 9. Bonding and Grounding

Electrical Safety Plugs What are the different types of plugs? Extension Cords What are some potential hazards involving extension cords?

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

ELECTRICAL SAFETY. The standard unit for measuring electrical current.

Enphase Microinverters and Ungrounded Renewable Energy Systems: Canadian Electrical Code Compliance

Reverse-feed applications for circuit breakers

4.5 Transformer Connections

How Much Voltage Drop Is Acceptable?

Errata NFPA 70. Proposed 2014 Edition

IMPLEMENTING THE NEW ELECTRICAL SAFETY REQUIREMENTS

Mike Holt s Illustrated Guide to. Rule , Articles 445, 700, 701, and 702. Based on the 2011 NEC

Services. Three Phase Service

Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port

misconceptions about arc-flash hazard assessments

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority

November Stray Voltage Test Procedure for Electrical Contractors

The Service Entrance. Technical Terms Drip loop Insulator Meter Meter enclosure

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.

**ATTENTION** WE DO NOT PROMOTE OR ENCOURAGE YOU TO DO YOUR OWN ELECTRICAL WIRING!!! IT IS BY FAR THE MOST DANGEROUS THING YOU CAN ATTEMPT

Grounding & Bonding Why it is done And How to Install Properly

Guidelines on the Short Circuit Current Rating for Industrial Control Panels

Electric Service Guide for Commercial Construction

Are you aware. Outline

SAFETY AND HEALTH STANDARD KUC ELECTRICAL STANDARD Effective Date: 04/4/12 Standard: 15.1 Document Number: KUCSH0065 Rev: 06

Evaluating Water-Damaged Electrical Equipment

Exploring the Necessity of the Hot Hipot Test

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

Best Methods for Safe Hipot Testing

Residential Electrical System Aging Research Project. Dave Dini Sr. Research Engineer Underwriters Laboratories

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

CSA Z32 TESTING GUIDELINE AND PROCEDURES

City of Riverside Building & Safety Division Phone: (951)

MONTGOMERY COUNTY EXECUTIVE REGULATION Offices of the County Executive. 101 Monroe Street. Rockville, Maryland 20850

Siemens STEP 2000 Course Basics of Electrical Products

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

Commercial/Industrial Electricity

ELECTRICAL SAFETY: QUALIFIED/NON QUALIFIED

Fundamentals of Power

NEC 2014 Code Changes

Dielectric Withstand Testing in a Production Environment

Guidance on Proper Use of EXTENSION CORDS, POWER STRIPS & SURGE PROTECTORS

Motor Protection Voltage Unbalance and Single-Phasing

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

Video Camera Installation Guide

IntelliBrite Controller (For IntelliBrite Pool, Spa and Landscape Lighting Fixtures) Installation and User s Guide

Questions and Answers for Heating and A/C Contractors

HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE

San Diego Area Chapter International Code Council

Evaluating Water-Damaged Electrical Equipment

CHAPTER 2 EXAMPLES AND TABLES

Evaluating Water-Damaged Electrical Equipment

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

How To Plan Out An Array Of Solar Panels

Protect your home and family with Advanced Technology from Cutler-Hammer

Model 1756 Test Lead Kit

2012 Canadian Electrical Code, Part I (CEC) Top Fifteen changes

Chapter 24. Three-Phase Voltage Generation

Analyzing Electrical Hazards in the Workplace

Photovoltaic System Grounding

Construction Electrical Terminology. Electricians

Electrical Practices for Construction Work

MODULE 1 INTRODUCTION TO ELECTRICAL SAFETY

Electrocution Hazards

Charging what can be more simple? SAE J1772

STREETLIGHT SYSTEM GROUNDING AND BONDING

City of San Diego Residential Photovoltaic Systems Inspection Guidelines

Three-Phase Electric Power Distribution for Computer Data Centers

Exhibit C Design Review Guidelines

Electrical Wiring Methods, Components and Equipment for General Use. Approved for Public Release; Further Dissemination Unlimited

October Safety Subject

Short Circuit Current Calculations

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

HPS Universal. Single and Three Phase Potted. Buck-Boost Transformers. Buck-Boost Applications & Standard Specification... 80

MANCON Human Resources Workers Compensation or ext 312 or

Arc Fault Circuit Interrupters Frequently Asked Questions

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL (352) ; FAX: (352)

Buck - Boost Transformers

Department of Labor and Industry Electrical Licensing

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

Section B: Electricity

Transcription:

PORTABLE GENERATORS AND OSHA CONSTRUCTION REGULATIONS Monograph by: John Grizzy Grzywacz, Professor OSHA National Training Institute Arlington Heights, Illinois Contributing: Michael Kovacic, President TMK and Associates Chardon, Ohio Rev: 3/05 Portable generators used on construction sites have been much misunderstood, at least with respect to the regulatory requirements. There are three regulatory references to portable generators used in 29 CFR 1926, OSHA's Construction Standards. The first deals with the Grounding Electrode (ground rod or earthing electrode). The second reference lists the criteria for GFCI (Ground Fault Circuit Interrupter) exemption and the third addresses the Neutral Conductor Bonding requirement. These requirements are three distinctly separate issues and should not be confused or combined. This monograph addresses and explains each. Where adopted by OSHA, the National Electrical Code (NEC ) reference is also listed. The NEC should be referenced directly for additional clarification. I. Generator Grounding Electrode Exemption (system grounding) 29 CFR 1926.404(f)(3) Portable and vehicle-mounted generators (i) Portable Generators. Under the following conditions, the frame of a portable generator need not be grounded and may serve as the grounding electrode (NEC Article 250.34 2005 Edition). This reference uses the term grounding electrode, which is code language for a system ground or the intentional connection of an electrical system to the earth or our surroundings. In other words, a ground rod is not required and, in fact, may create a hazard. The conditions referenced in 1926.404(f)(3)(i) are: A) The generator supplies only equipment mounted on the generator and/or cord and plug connected equipment (i.e. saws, drills, lights, etc.) through the receptacles mounted on the generator, AND B) The grounding pin(s) of the generator-mounted receptacles are connected to the generator frame and the equipment grounding conductors of the portable equipment plugged into the generator are continuous to the generator frame. (See Figure 1) 1

Generator Figure 1 Drill case electrically connected to generator frame via equipment grounding conductor The principle function of the system ground, or grounding electrode (ground rod), is lightning protection for equipment (see NEC Article 250.4(A)(1) Electrical System Grounding). The likelihood of lightning striking a portable generator supplying some hand tools on a construction site is unlikely, to say the least. So, aside from the unlikelihood of a lightning strike, why eliminate the ground rod? Because the ground rod potentially introduces an electrocution hazard! Depending upon the internal wiring of the generator winding to the frame (see Figure 2), this hazard is introduced by creating an improved path for current to return to its source in the event of short circuits or insulation failure in equipment. So, just treat the generator frame as the ground rod and leave it at that, which this regulation permits. Generator Electrical fault to case Earth/Ground Figure 2 From a historical perspective, the grounding electrode (which is also a system ground) is required for other reasons and was the earliest grounding requirement in the National Electrical Code, becoming mandatory in the 1913 edition. The main purpose of grounding (earthing) the system at the neutral of 2

the transformer secondary was to prevent high (primary) voltages from being applied to premises wiring (homes) due to a breakdown of insulation between the transformer primary winding and secondary winding. A primary-to-secondary short would apply thousands of volts to the premises, whereby causing an insulation failure in the wiring and a subsequent fire. The requirement was precipitated by the insurance companies and their concern about fire loss. This system ground is different than the equipment grounding requirements which did not appear in the NEC until 1947, and which are for people protection. More specifically, the purpose of the equipment grounding conductor (code language) is to prevent electrocution in the event of a fault (short circuit) in the equipment that energizes the frame or enclosure of that equipment. The grounding requirements in the OSHA regulations are found in 1910.304(f) and 1926.404(f). More specifically, 1910.304(f)(1), (2), (3) and (7) as well as 1926.404(f)(1), (2), (3), (4), (5), (10) and (11) all address system grounding. The remaining references, 1910.304(f)(4), (5) and (6), as well as 1926.404(f)(6), (7), (8) and (9) all speak to equipment grounding requirements for the prevention of electrocution. In summary, the installation of grounding electrodes (ground rods) on portable generators is discouraged because they introduce a potential electrocution hazard, it serves no other purpose and the codes do not require it. II. Generator GFCI Exemption The second OSHA regulatory reference on portable generators is the GFCI exemption. 29 CFR 1926.404(b)(1)(ii) reads, "Receptacles on a two-wire, single-phase portable or vehicle mounted generator rated not more than 5kW, where the circuit conductors on the generator are insulated from the generator frame and all other grounded surfaces, need not be protected with ground-fault circuit interrupters. This same exemption was formerly in NEC Article 305-6(a) Exception, but was removed in the 2002 NEC as well as the 2004 NFPA 70E. This means that under these conditions, you do not need the normally required GFCI's on a generator. There are three conditions or criteria listed in the regulation and the generator must meet all three conditions in order to qualify for GFCI exemption. The criteria are simply these: 1. The generator must be two-wire, single phase. Reference to two wires does not include grounding or equipment grounding conductors. Only the conductors or wires which are normally current-carrying circuit conductors are to be considered. This restriction eliminates three-wire generators which have a neutral conductor. The neutral conductor is the center tap of the output winding, which also allows a reference point for dual voltages such as 120v/240v. In a two-wire supply there can only be one voltage derived. Therefore, a 120v/240v generator must be a three-wire generator and cannot meet these criteria. Also, 3Ø (three phase) generators, which are typically fourwire, cannot meet this exemption. Incidentally, a three-wire, or dual voltage (120v/240v) generator must have the neutral wire connected to the frame. This will be covered in more detail in the next section. Additionally, a two-wire system/generator (see Figure 1) has no neutral wire; both wires are normally current carrying. A true neutral would be a center-taped wire on a transformer (such as a 120v/240v single-phase, three-wire system), which carries the unbalanced current in a dual-voltage system. 2. The generator must be not over 5kW (kilo-watts/thousand watts). The size of the generator can be obtained from the manufacturer s nameplate on the generator, which includes the electrical specifications. Reference should be made to 29 CFR 1926.403(g) "Marking. Electrical equipment shall not be used unless the manufacturer's name, trademark, or other descriptive marking by which the 3

organization responsible for the product may be identified is placed on the equipment and unless other markings are provided giving voltage, current, wattage, or other ratings as necessary. The markings shall be of sufficient durability to withstand the environment involved." (NEC Article 110.21-2005 Edition). The purpose of this requirement is to minimize capacitive coupling or capacitive reactance effects where alternating current at 60 Hertz could pass between the case of a generator and the winding, even with no direct electrical connection between the winding and the case. This effect could result in a path for current to flow back to its source, causing an electrocution in the event of a fault or in the equipment or damaged equipment cord plugged into the generator. This electrical effect becomes possible with windings of larger physical magnitude, as is the case when the generator is over 5kW (see Figure 3). The bottom line is that if the generator is over 5kW, then it cannot meet the exemption requirements and must be GFCI protected. Generator Over 5kW Electrical fault to case Generator sitting on ground No ground rod or electrical connection from winding to frame/case of generator Earth/Ground Figure 3 3. The circuit wires must not be connected to the generator frame, case, or other grounded surfaces. The two wires must be insulated or isolated and not electrically connected to the frame or other grounded surfaces. This refers only to the two conductors which are normally current-carrying. This does not refer to the equipment grounding conductor (See Figure 4). Bonded to frame Not isolated Conductors insulated/isolated from generator frame meets criteria Figure 4 4

Since these wires or conductors are internal to the generator, the only way to effectively determine if they are, in fact, electrically isolated is to measure their continuity to the frame using an electrical continuity tester, or ohmmeter. These types of tests are always made with the generator off - never to a live or energized circuit. The continuity test can be made from either blade of the receptacle (not the ground pin) to the case/frame of the generator. Be sure the test lead of the tester is penetrating the paint, rust, and all other contaminants on the generator case when making the measurement. If the test indicates continuity, then the wires are connected to the case and do not meet this third criteria for isolation, therefore the generator must be GFCI protected. It does not matter which receptacle blade is selected to make this measurement. The only difference is that one blade will be connected to the case through the generator windings, while the other blade will be connected directly to the case. Since the resistance of generator windings is typically below 10 ohms, both blades will indicate continuity if they are not isolated, whereby requiring GFCI protection. This requirement eliminates a return current path, preventing an otherwise lethal condition in the event of an equipment short circuit or insulation failure. The end result is that if the generator meets all three conditions or criteria, then even if one of the normal current-carrying conductors in a portable tool faults and energizes the case of the tool, no current path back to the source (generator winding) will exist to present an electrocution hazard to a person holding the tool. Furthermore, if the generator meets these three conditions, the generator does not need a GFCI. Remember, the generator must meet all three conditions to permit this GFCI exemption. As previously mentioned, this GFCI exemption was removed for the 2002 Edition of the NEC. As a result, the local electrical inspectors, as the Authorities Having Jurisdiction or AHJ s as they are referred to, will no longer accept this exemption and will require the use of GFCI s on portable generators used for temporary wiring such as on construction sites per Article 590 of the 2005 NEC. Although the exemption still appears in the OSHA construction regulations, this author suspects that it will eventually be totally eliminated and the required use of GFCI s will prevail in all cases. III. Neutral Conductor Bonding Requirements for Generators. The third and final issue for discussion can be found in 29 CFR 1926.404(f)(3)(iii) "Neutral conductor bonding. A neutral conductor shall be bonded to the generator frame if the generator is a component of a separately derived system." This reference can be found in 1996 NEC Article 250-6(c) and 250-34 in the 1999 Edition. Although slightly modified for the 2002 Edition the reference is still located in NEC Article 250.34(C). Consider this question. Is a generator on a construction site supplying only cord-and-plug-connected equipment (saws, drills, lights, etc.) through the receptacles mounted on the generator considered a separately derived system? The answer is a resounding Yes! It is always a separately derived system under those conditions and consequently the neutral must be bonded (electrically connected) to the frame of the generator. For a more detailed explanation of why it s a separately derived system, we must examine the NEC in more detail. NEC Article 100 definitions of Premises Wiring (System) and Separately Derived Systems clarify this. Premises Wiring Systems include temporary lighting and power circuits extending from the source to the outlet. This would encompass our generator supplying cord-and-plug lights and tools on a construction site. A Separately Derived System is a generator which does not have any electrical connection to any other system. An emergency backup generator with its neutral permanently connected at the panelboard to the neutral supplied from a local utility company, with only the hot or ungrounded conductors being switched in for emergency backup in case of power failure, would not be considered a separately derived system. Further clarification on when a generator is not a separately derived system can be found in the 1996 NEC, Article 250-5(d), FPN No. 1, or in the 2005 NEC, Article 250.20(D), FPN No.1. 5

Perhaps the most definitive information comes from the CMP (Code Making Panel) recommendations and amendments to the 1974 NEC. Prior to 1974, this generator issue was addressed in both NEC Article 250-26(a) and Article 445-8 (Article 445 covers generators) Grounding. Code Making Panel #22 (as well as CMPs #5 and #11) proposed that the frames of generators be bonded to the neutral. The proposed amendments, including justification to the CMP, were not documented very thoroughly in those days. However, extensive research revealed this supporting comment which was the proposal to the 1974 CMP, "The required bonding (neutral conductor to frame) for portable or cord and cable connected wiring systems supplied from portable generators will provide an assured fault current path to actuate the circuit or system overcurrent device for user protection in the event of multiple faults and insulation failure. Without this bonding (electrical connection of the neutral to the frame of the generator) a multiple fault condition would expose persons to a 240- volt potential. (See Figure 5) This path will satisfy the intent of NEC Article 250.2 & 250.4(A)(5), 2005 Edition (previous editions see Article 250-51). 120/240v Generator X X Fault to case X X Fault to case 240-Volt outlet 120-Volt outlet Two faults create a 240v exposure and a current path, resulting in electrocution Earth/Ground Figure 5 In summary, remember, the Generator Grounding Electrode (system grounding) Exemption (I), the Generator GFCI Exemption (II) and the Neutral Conductor Bonding Requirements for Generators (III) are all mutually exclusive and have nothing whatsoever to do with each other. Each issue needs to be examined one at a time for its applicability with respect to the code requirements, or more simply stated, examine each generator for all three issues to ensure it meets the codes. 6

John Grizzy Grzywacz served as the OSHA Region II Training Director from 1988 to 1995 based in the New York City Regional OSHA Office. In January 1995 John accepted a faculty position at the OSHA National Training Institute and gave up Manhattan residency for the quiet suburbs of Des Plaines outside of Chicago. John trains OSHA compliance officers, State Plan Safety and Health Investigators, corporate safety and health directors, and other federal agencies in numerous areas including OSHA policy, safety and health regulations, safety and health management systems, legal aspects of investigations, and enforcement strategies. Currently John is called upon to investigate nearly a dozen electrical fatalities and accidents yearly and is consulted with on many more investigations nationwide. John received his teaching credentials from the State University of New York and is licensed by the New York State Department of education. John is also a certified electrical inspector. Prior to his arrival at OSHA John had been both an educator and administrator for various public and private schools for nearly a decade, and currently has over 25,000 hours of platform experience. John held the position of electronic department chairman and Deputy Director of Education at a New York City proprietary school for four years. In addition to being a nationally recognized seminar leader and educator, John has taught at Purdue University, University of Southern California at San Diego, Texas A & M University, and the New York State University System, just to name a few. John has found time to write and produce training videos and has works published in video, print and film. 7