Evaluating the effects of communication in construction project delivery in Nigeria



Similar documents
Causes And Effects Of Poor Communication Between The Client And Contractor During Construction Projects In Nigeria

Formal Communication Channels: Upward, Downward, Horizontal, and External

Conceptualizing Total Quality Management (TQM) for Improving Housing Areas for the Urban Poor

ASSESSING THE MANAGEMENT OF HUMAN RESOURCES IN SECONDARY SCHOOLS BY MALE AND FEMALE PRINCIPALS IN RIVERS STATE OF NIGERIA

An Evaluation of the National Teachers Institute s Manpower Training Program for Teaching Personnel in Mid-western Nigeria

Cash flow is the life line of a business. Many start-up

Running Head: 360 DEGREE FEEDBACK 1. Leadership Skill Assessment: 360 Degree Feedback. Cheryl J. Servis. Virginia Commonwealth University

AN APPROACH FOR EVALUATING THE SATISFACTION OF A CONSTRUCTION PROJECT TEAM

Methodological Approaches to Evaluation of Information System Functionality Performances and Importance of Successfulness Factors Analysis

Model of Learning Organizational Development of Primary School Network under the Office of Basic Education Commission

The influence of communication on administration of secondary schools in Delta State, Nigeria

The Role of Building Construction Project Team Members In Building Projects Delivery

Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria.

Performance Appraisal System of the Academics of Public and Private Universities of Bangladesh: An Empirical Study

THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy

Project Management Practices: The Criteria for Success or Failure

Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria

Communication skills impact on sustainable and green project management

A Theoretical Perspective on Leadership Development in the Construction Industry

Report on Moravian MBA Program Learning Objectives Related to Communication Behaviors of Students. Data Sources and Instrument Information

Talent Management: Effect on Organizational Performance

Obstacles to Integrating Forensic Accounting in the Accounting Curriculum: The Case of Bahrain

King Fahd University of Petroleum and Minerals

Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E

Managing Successful Software Development Projects Mike Thibado 12/28/05

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

Hansani Chathurika Dassanayake a a University of Peradeniya, Sri Lanka. hansanidassanayake@gmail.com. Abstract

Leadership Competency Self Assessment

NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS

Running Head: HUMAN RESOURCE PRACTICES AND ENTERPRISE PERFORMANCE. Pakistan. Muzaffar Asad. Syed Hussain Haider. Muhammad Bilal Akhtar

Business Continuity Management Planning Methodology

Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia

Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey

Leader s Interpersonal Skills and Its Effectiveness at different Levels of Management

The Impact of Implementing SAP System on Human Resource Management: Application to Saudi Electricity Company

Higher Education: Quality, Quality Assurance, the Concept and its Elements and HERQA s Focus Areas

DOI: /IJARBSS/v3-i12/421 URL:

LSBU Leadership Development Strategy

CIOB Awarding Organisation. CIOB Level 4 Certificate and Diploma in Site Management (QCF) Syllabus. October 2013

Community Colleges. Measuring Internationalization. AMERICAN COUNCIL ON EDUCATION The Unifying Voice for Higher Education

INTRODUCTION TO RAPID PRODUCT DEVELOPMENT (RPD)

Information Technology Project Oversight Framework

Elite Sport Development Strategy through Systems View and Sport Development Model

Effects of Project Management on the Performance of a Construction Firm in Nigeria

Created Actual Completion. Last Modified

Management Accounting Practices: A Comparative Analysis of Manufacturing and Service Industries

Managing effective sourcing teams

The importance of using marketing information systems in five stars hotels working in Jordan: An empirical study

University of Cambridge: Programme Specifications MASTER OF STUDIES IN INTERDISCIPLINARY DESIGN FOR THE BUILT ENVIRONMENT

The integrated leadership system. ILS support tools. Leadership pathway: Individual profile APS6

Procurement guidance Managing and monitoring suppliers performance

Network Patterns and Analysis: Underused Sources to Improve Communication Effectiveness

TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL

Causes, Effects and Minimization of Delays in Construction Projects

Introduction. Project Management in New Zealand

PEOPLE INVOLVEMENT AND THEIR COMPETENCE IN QUALITY MANAGEMENT SYSTEMS * Jarmila ŠALGOVIČOVÁ, Matej BÍLÝ

FEASIBILITY STUDY ON KNOWLEDGE MANAGEMENT PROCESSES IN EDUCATION ORGANIZATION

Soft Skills Requirements in Software Architecture s Job: An Exploratory Study

PROFESSIONAL SATISFACTION OF TEACHERS FROM KINDERGARTEN. PRELIMINARY STUDY

Relationship model and supporting activities of JIT, TQM and TPM

Role Description Business Analyst / Consultant - ICT

THE IMPORTANCE OF KNOWLEDGE MANAGEMENT IN ORGANIZATIONS WITH EMPHASIS ON THE BALANCED SCORECARD LEARNING AND GROWTH PERSPECTIVE

Project success depends on

Case Study: Ten Document Needs for Schedule Litigation Support

COMMUNICATION BARRIER IN MALAYSIA CONSTRUCTION SITES

Effectiveness of Customer Relationship Management Programs

Comparison of Teaching Systems Analysis and Design Course to Graduate Online Students verses Undergraduate On-campus Students

Benchmarking in the contact center: Tips for managing what you measure

DIRECTORATE OF ESTATES & FACILITIES

ACM Courses. Management and Organization Department. Ramon V. del Rosario College of Business. De La Salle University.

Role Description Senior Business Analyst / Senior Consultant - ICT

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Equality, Diversity, Cohesion and Integration Impact Assessment

UoD IT Job Description

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

THE LINK BETWEEN ORGANIZATIONAL CULTURE AND PERFORMANCE MANAGEMENT PRACTICES: A CASE OF IT COMPANIES FROM ROMANIA

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

THE RELATIONSHIP BETWEEN CONTRACT ADMINISTRATION PROBLEMS AND CONTRACT TYPES Bill Davison and Richard J. Sebastian*

ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS OCTOBER 2013 VOL 5, NO 6 Abstract 1. Introduction:

Desirable Attributes and Skills for Graduating Construction Management Students

CDC s Policy Analytical Framework. Centers for Disease Control and Prevention Office of the Associate Director for Policy

Management Information Systems Role in Decision-Making During Crises: Case Study

TECHNICALS LEVEL BUSINESS

SOFTWARE ESTIMATING RULES OF THUMB. Version 1 - April 6, 1997 Version 2 June 13, 2003 Version 3 March 20, 2007

EFFECTIVE ARMY BRIEFING

Rjopes Research Journal in Organizational Psychology & Educational Studies 3(3) Rjopes

EFFECT OF TOTAL QUALITY MANAGEMENT ON THE PERFORMANCE OF BREWERY INDUSTRY IN NIGERIA: AN EMPIRICAL STUDY OF SELECTED BREWERIES IN LAGOS STATE, NIGERIA

Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved

Systematization of Requirements Definition for Software Development Processes with a Business Modeling Architecture

Automated Photo Enforcement Review August 27, 2014

OTC Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

Thirugnanam Navaneethan (1)

Project Management. On-Site Training and Facilitation Services. For more information, visit

BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS

Transcription:

Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication in construction project delivery in Nigeria 1 Luka Goji Tipili, 2 Patricia Oyiza Ojeba and 3 Muhammad Sa'adiya Ilyasu 1 Quantity Surveying Department, Faculty of Environmental Technology, Abubakar Tafawa Balewa University, Bauchi- Nigeria, 2 Quantity Surveying Department, Faculty of Environmental Technology, Abubakar Tafawa Balewa University, Bauchi- Nigeria 3 Architecture Department, Faculty of Environmental Technology, Abubakar Tafawa Balewa University, Bauchi-Nigeria Corresponding Author s E-mail: taruye@yahoo.com or sandyilyasu@gmail.com Accepted 2 nd June, 2014 All construction project execution requires communication between professionals in all the various stages of construction. These professionals transfer appropriate and relevant information to develop a buildable design that meets the client s requirements. As the project unfolds and the design is realized, information in the form of drawings, specifications and construction methods must be communicated from one expert to another. Therefore, using an appropriate communication method and communication medium to resolve construction and design problems is essential. The research sampled 40 professionals working in the construction industry in Bauchi, Nigeria. The study established that within the Nigeria construction industry, there is a strong appreciation of the importance of project communication and its effects within the industry. In spite of that, there have been many hindrances to effective communication on construction projects in Nigeria. These include; unclear communication objectives, unclear channels of communication, ineffective reporting system, ineffective communication between the parties on the project, stereotyping and language difficulties. Finally, the research established that poor communication had resulted in project delays, project cost overrun and project abandonment. Project communications/communication management was also shown to strongly affect the performance of professionals within the construction industry. Keywords: Effective Communication, Nigeria Construction industry, Communication Channel, Construction Project Delivery INTRODUCTION Although managers in different industries and sectors undertake diverse tasks and activities, it has long been recognized that they spend most of their time involved in communication (Baguley, 1994). If viewed as a fundamentally social activity, communication activities can include engaging in conversations, listening to colleagues, networking, collecting information, directing subordinates, writing letters or transferring information through electronic devices such as telephones or computers. Hence, in many ways the communication affectivity of managers defines their performances as managers; superior performance demands superior communication. This introductory chapter defines the concept of communication and its importance in the context of the contemporary construction industry. It outlines the role and importance of the project manager in the communication process and discusses the way in which the issues central to effective communication are explored within this text. Thus, it provides a contextual backdrop to the ways in which communication will be explored in relation to the construction industry in the remaining section (Carlsson, B.). Communication plays a vital role in all stages of construction such as design, production, organization and management. Statistics show that over fifty percent of projects are unsuccessful. One of the many factors that contribute to the failure of these projects is poor or insufficient communication. Information must be properly managed, transferred and understood so that the various aspects of the project can be assembled to realize the design. In Nigeria, the construction professionals who are regularly engaged in the industry are Architects, Quantity Surveyors (QS), Geodetic Engineers (GE), Structural Engineers (St.E), Electrical

49. Tipili et al., Engineers (EE) and Services Engineers (SE). Statement of the problem Ineffective communication management system in construction project delivery in Nigeria is the major cause of failures associated with construction projects. The role of communication in construction projects cannot be over emphasized as various professionals in the construction industry must communicate effectively in any given project for it to be successful. As such, the problems of communication in construction project delivery in Nigeria are enormous. As the project unfolds and the design is realized, information in the form of drawings, specifications and construction methods must be communicated from one expert to another.(foley, 2005), and communication poorly managed will lead to de-motivated workforce, design errors, slowdown in the entire job and failure in production. Therefore, using an appropriate communication management system to resolve construction and design problems is essential. LITERATURE REVIEW Construction industry Construction is the physical act of carrying out designs created by engineers or architects. The construction industry is important to the public, as business owners need buildings and offices from which to work, people need homes to live, children need schools to attend. Construction workers are responsible for erecting structures that offer safety protection and convenience. The need for construction professionals to communicate throughout all the stages of construction is inevitable. A successful project demand that professionals involved are experienced, appropriate, have the same mindset, are team players with complimentary skill sets and are managed to bring out their best work to meet the vision and goals of the project. Furthermore, communication between these professionals is an integral part of the construction process in any successful project. Given that construction is such a fragmented, dynamic and disparate sector, effective communication becomes essential for the successful delivery of performance goals (productivity, profitability and repeat working opportunities (Dainty et.al, 2006). Scope of work and details of construction are communicated by means of drawings, contract documents, addenda and specifications (Mehra, 2009). Therefore, the need for professionals within the construction industry to effectively communicate with each other in order to accomplish their production and social functions within the organizations cannot be overemphasized and the effects of communication and communication management has a great impact on any project delivery. Nigerian constructions industry Organized construction contracting in Nigeria began in the 1940s with few foreign companies coming into operation (Gorse, 2002). The major source of capital formation in the construction industry is from the public sector, with the traditional approach in the major infrastructure procurement process of funding through annual capital budgetary provision. However, with the rising emphasis and growing interest of stakeholders in bridging Nigeria infrastructure gap, the future growth of construction as a tool for sustainable economy is somewhat optimistic. The construction industry in Nigeria is a multibillion dollar industry with hardly any year befalling successful contractors who bid for construction projects, the last few years has witnessed increasing patronage and profits for most construction companies in Nigeria. Challenges facing the Nigeria construction industry Major milestones over the decade which includes self sufficiency in cement production which guarantees material price stability, procurements, health and safety, access to credit, project abandonment, escalating cost of projects cost and projects failing to meet client s expectations are major challenges facing the Nigeria construction industry amongst other factors. While Some specialists will be able to visualize aspects of the building with a high degree of accuracy, possibly with little information, other aspects of the building will hold little relevance unless the information is conveyed in a way which allows them to develop an understanding (mental model), hence, communication is extremely relevant in the management of projects. Communication channels During a project, communication can occur in various directions depending on who is communicating. There is upward communication to management from ones organization and the customer s organization. Lateral communication takes place with customers and within project teams. Machinery needs to be put in place for further communication to take place, either downward communication (from superior to sub-ordinate), horizontal communication (between colleagues) or upward communication (from sub-ordinates to superior).

50. Glob. J. Environ. Sci. Technol. Figure 1: The Three Communication Channel of the Project Manager (Adopted from Keyton, 2011) Table 1: Designation of respondents DESIGNATION FREQUENCY PERCENTAGE% CUMMULATIVE PERCENTAGE% Quantity Surveyor 13 0.33 0.33 Project Manager 7 0.18 0.51 Architect 9 0.23 0.74 Others 11 0.28 1.00 Total 40 1 (Mehra, 2009) stated that communication will always involve more than one person. In the figure 1, the number of communication channels required to communicate with five other team members in a team of six is shown. RESEARCH METHODOLOGY This research covers project participants in construction projects, primarily Quantity surveyor, Architects, Project Managers and others who are part of construction projects team. The study collected data from construction professionals with an experience from 5- year and 15 years above. Data collection was done through a questionnaires self administered on 50 project participant, 40 were returned. The research results can be generalized to a larger population within acceptable error limits. The question which this research sorts to explore was how much effect communication/ communication management has on construction project delivery in Nigeria, and how professionals in the industry communicate. A 3-point ranking system low, moderate, and high were utilized where the respondents were asked to indicate from the list of how communication is achieved currently on site, how much effect each has and how frequent those occurs. RESULTS AND DISCUSSIONS From the table 1 above, 33% of the respondents representing thirteen (13) respondents were quantity surveyors, 18% 0f the respondents were project managers which represent 9 respondents, while 23%

51. Tipili et al., Figure 2: Pie- Chart for Designation of Respondent Table 2: Working experience of the respondents YEARS FREQUENCY PERCENTAGE% CUMMULATIVE PERCENTAGE% 0-5years 13 0.33 0.33 6 10 years 10 0.25 0.58 11 15 years 9 0.23 0.81 Above 15 years 8 0.20 1.0 Total 40 1 Table 3: Amount of effects of communication in construction project delivery Effects_of Low Medium High Mean Variance standard Rank communication in 0% (50%) (100%) deviation projects Inexperience 0.00 0.10 0.80 0.90 0.22 0.47 1 Delay 0.03 0.14 0.70 0.87 0.17 0.41 2 Site meetings 0.05 0.20 0.55 0.80 0.12 0.34 3 Late dissemination 0.10 0.19 0.53 0.82 0.11 0.33 4 Unclear channel 0.18 0.17 0.50 0.85 0.10 0.32 5 Language problem 0.10 0.23 0.45 0.78 0.09 0.30 6 Training operatives 0.43 0.19 0.20 0.82 0.09 0.29 7 were Architects and 28% represents other professionals such as Builders, engineers, and clerk of works. Figure 2 above From the table 2 above, it shows that; a. 13 respondents are below 5 years in working experience representing 33% b. 10 respondents are between 6-20 years in working experience representing 25% c. 9 respondents are between 11-15 years in working experience representing 23% d. Only 8 respondents are above 30 years in working experience representing The following factors of communication that affect construction project has been ranked on the order of highest effect (7) to least effects (1) in Table 3. Inexperience interpretation of working drawings can cause a failure in building components With regards to inexperience interpretation of work drawing can cause a failure in building components. 80% of the respondents responded high for that statement, with 20% answering very medium for the

52. Glob. J. Environ. Sci. Technol. Table 4: Effects of communication management on construction project delivery. Effects communication projects of in Low (0%) Medium (50%) High (100%) Mean Variance standard deviation Plan & strategies 0.05 0.25 0.45 0.75 0.09 0.94 1 Plan reviewed 0.05 0.22 0.45 0.72 0.08 0.92 2 On-going 0.00 0.13 0.75 0.88 0.19 0.44 3 communication Meetings 0.25 0.13 0.65 1.03 0.17 0.41 4 Unclear objectives 0.00 0.15 0.70 0.85 0.17 0.41 4 Clarified roles 0.03 0.20 0.56 0.79 0.12 0.34 6 Communication media 0.04 0.22 0.53 0.79 0.11 0.33 7 Unclear channels 0.15 0.27 0.33 0.75 0.07 0.26 8 Rank same statement. Ranking first (1) amongst other factors has the greatest effect on construction project delivery. Poor and distorted information will affect the level of work done on site Poor communication had often resulted in project delays, project cost overrun, project abandonment etc. however, 3% ticked low, 27% answered medium for that statement. An overwhelming majority of 70% ticked high, that poor and distorted information relayed do affect the level of work done onsite. It ranked second (2) which highly affect construction projects Site meeting is important channel of communication between the consultants and contractor on site From the table 1 above, 55% of all the respondents said that site meetings is of high importance in channels of communication between the consultants and contractors on site, while 40% said that site meetings is of medium importance in communication channels between the contractors and the consultants and 5% of the consultants ranked it low. Overall, amongst other factors of communication that affect construction project, site meetings ranked third (3). Late dissemination of information will affect output on site negatively Finally, 53% of the respondent also agreed that late dissemination of information will affect work output on site negatively, and 38% ticked medium on that same statement. Ranking fourth (4) amongst other factors of communication that affects construction project delivery. Unclear channels of communication results in project. Unclear channels of communications results in project delay. Also 50% of the respondents ticked high, while 33% ticked medium that the sort of language used among operatives is very essential for effective communication onsite. While 17% ticked low. It ranked fifth (5) amongst other factors which affects construction projects Training of operatives is necessary for onsite communication With regards to training of operatives being necessary for on-site communication, 20% answered high while, 38% answered medium and 43% said low. It ranked (1) as the least factor that affects construction projects. Communication plans and strategies established at the outset of projects do improve project From the Table 4 above, 45% respondents scored high (1) that communication plans and strategies established at the outset of projects do improve project communication, while 50% respondents ticked medium (0.5) and 5% respondent ticked low (0), and this communication management tool ranked first (1) on the 2 above having great effect on construction project delivery. Communication plan reviewed regularly and adjusted is necessary for project success Also, on the issue of communication plan reviewed regularly and adjusted is necessary for project success

53. Tipili et al., Table 5: Importance of communication channels in construction project delivery? Communication channels very often 100% often Not often 0% mean variance standard deviation 50% Site Review Meetings 1.00 - - 1.00 0.33 0.58 1 Notice board 0.7 0.15-0.85 0.17 0.41 2 Project Annual Report, 0.5 0.2 0.04 0.74 0.10 0.31 3 Formal Communication (emails, phone 0.5 0.19 0.05 0.74 0.10 0.31 3 calls) Work breakdown structure 0.5 0.16 0.07 0.73 0.09 0.31 3 Project Status Report 0.45 0.19 0.07 0.71 0.08 0.28 7 Customer Satisfaction Survey 0.38 0.19 0.1 0.67 0.06 0.25 8 Record management system 0.35 0.21 0.09 0.65 0.06 0.24 9 Social Gathering 0.35 0.2 0.1 0.65 0.06 0.24 9 Public Relations 0.33 0.13 0.17 0.63 0.052 0.23 11 Resource breakdown structure 0.23 0.3 0.07 0.6 0.05 0.22 12 Team Meetings Discussions 0.30 0.21 0.11 0.62 0.05 0.22 12 Organization breakdown structure 0.28 0.21 0.12 0.61 0.05 0.21 14 Employee suggestion Scheme 0.25 0.13 0.20 0.58 0.04 0.20 15 Performance evaluation scheme 0.25 0.19 0.10 0.54 0.04 0.19 16 Project Business Case 0.20 0.13 0.22 0.55 0.04 0.19 16 Meeting Suppliers / Customers 0.10 0.16 0.23 0.49 0.03 0.17 18 Rank, 45% respondents scored high (1), 44% respondents scored medium (0.5) and 5% respondents scored low (0), and ranking second (2) has the highest effect on construction project. On- going communication between project team members and its stakeholders improve project success When asked how does on-going communication between project team members and its stakeholders improve project success? 75% people ticked high (1) and 25% people ticked medium (0.5) and it ranked third (3). Meetings help overcome communication barriers and increase performance level Meetings help overcome communication barriers and increase performance Level 65% people ticked high (1) and 10% people ticked medium (0.5) and 25% ticked low and it ranked fourth (4) Unclear objectives between project proponents and its stakeholders leading to project failures and disputes 70% people ticked high (1), and 30% people ticked medium (3) on the issue of unclear objectives between project proponents and its stakeholders leading to project failures and disputes and it ranked fourth (4). Clear communication clarifying roles of stakeholders drawn in the project plan improve successes in project delivery When asked how clear communication clarifying roles of stakeholders drawn in the project plan improve successes in project delivery, 56% people scored it high (1), while 40% people agreed medium (0.5) and 3% persons said low and it ranked sixth (6). Appropriate communication media for specific purposes/audiences are necessary 53% respondents ticked high (1), 43% respondents ticked medium (0.5), 4% respondent s ticked low (0) and 1 respondent ticked very low (1) when asked how appropriate communication media for specific purposes/audiences are necessary. It ranked seventh (7). Unclear communication channel affect project objectives 33% people also scored high (1), 53% people scored medium (0.5), 15% people scored low (0), when asked how unclear communication channel affect project objectives and it ranked eight (8). From the responses gotten concerning the effects of communication management on construction project delivery, an overwhelming majority agreed that communication management has great significant effects on construction project delivery in Nigeria. From the channels of communication responses as seen in Table 5 above, it shows that site review meeting

54. Glob. J. Environ. Sci. Technol. ranked first as an important factor in construction project delivery. CONCLUSION From the responses gathered from project professionals within the construction industry in Nigeria, there was a strong appreciation of project communication and its effects within the industry. With regards to the specific communication issues, there were unanimous agreements of the importance of each on communication on project site. For instance, many of the professional respondents agreed that site meetings are an important channel of communication between the consultants and contractors thus, has a significant effect on construction project delivery Nigeria. Further, all the players within the industry agreed that lack of proper communication management has a great effects on construction project delivery. For instance communication plan reviewed regularly and adjusted becomes necessary for project successes. Within the Nigerian construction industry, there is a strong appreciation of the significance of project communication/communication management and its effects within the industry. Indeed, various levels and channels of communications have been established within the construction industry, for example, communication between consultants and contractors. This research has shown that, project communication strongly affect the performance of professionals within the construction industry. Therefore, clearly establishing and managing the structures of communication on project must always be on the agenda of team leaders and management before the commencement of every project. Baguley P (1994). Effective Communication for Modern Businesses, McGraw- Hill, London Carlsson B, Josephson PE, Larson B (2001). Communication in Building Projects, Empirical results and future needs, in proceedings of CIB, World Building New zealand, paper HTP 29 Dainty A, Moore D, Murray M (2006), Communication in Constructio Theory and Practice. London, Taylor and Francis Foley J, Macmillan S (2005). Patterns of Interaction in Construction ream meeting Co-Design, 1(1), 19-37 Gorse CA (2002). Effective interpersonal communication and group interaction During construction management and design meeting, Ph.d Thesis, University of Leicester Keyton J (2011). Communication and organizational culture: A key to understanding work experiences. Thousand Oaks, CA: Sage. Project management handbook (2007). Communication management Mehra S (2009) Project communication Management. Accessed from the website: http://www.scribd.com/doc/7875707/project-communication- Summary-by-Sachin-Mehra. REFERENCES Albrecht T, Hall B (1991). Facilitating talk about new ideas: the role of personal Relationships in organizational innovation, Communication Monographers, 58, 273-88 Aishawi M, Underwood J (1999). The application of Information Technology in the Management of Construction, RICS Research, London