Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria

Size: px
Start display at page:

Download "Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria"

Transcription

1 Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria H. Onukwube Senior Lecturer, Department of Building, University of Lagos, Akoka, Yaba, Lagos. Nigeria. Abstract: Costs and Value are not always well managed by clients. Some Clients are concentrating on the wrong goal lowest tender price rather than best value, but focusing on the initial capital costs of a construction project does not give value for money. Building owners need to think in terms of achieving value by meeting the needs of end users with a higher quality project at lower life costs. This paper presents the results of a study with the objective to establish the importance of various processes used in making decisions and estimating on whole-life costs. To determine the importance of various items of costs in cost management using whole-life approach. The study was carried out through questionnaire survey administered to a population of 30 construction professionals in consulting firms and clients Organisation. The data analysis included a statistical comparison of means and interpretation. It is expected that this study will enable clients to integrate the design and construction processes and also involve the integrated team early in the design as this will facilitate the planning of long term costs over the life of the project. Keywords: Construction Projects, Cost Management, Framework, Nigeria, Whole-life Costing. 1. Introduction Cost Planning and control of building designs were aimed at minimizing initial construction costs alone. However, many users of buildings have discovered that the running costs of buildings usually impact significantly on the occupiers budget (Dale, 1993). There are a number of current trends that are of concern for design professionals, these include: facility obsolescence, environmental instability, operational staff effectiveness, total quality management and value engineering (Kirk and Dell Isola, 1995). Clients are often over optimistic in their estimates of costs and the time required for delivery. In some cases, actual budgets were twice as much as estimates (Mott MacDonald, 2002). If real value for money is to be achieved, then clients must direct their professional advisers not to focus on capital costs only, but to acknowledge the significance of other costs and revenues associated with the acquisition, use and maintenance and disposal of an asset (Ballestry et al, 2004) 390

2 2. Whole Life Costing and Cost Management Framework 2.1 Definitions Several definitions of whole-life costing exists BSI( 1999) defines whole-life costing as a tool to assist in assessing the cost performance of construction work, aimed at facilitating choices where there are alternative means of achieving the client s objectives and where those alternatives differ not only in their initial costs, but also in their subsequent costs. Another useful definition is adopted by the Construction Best Practice Programme (CBPP, 1998a): The systematic consideration of all relevant costs and revenues associated with the acquisition and ownership of an asset. The whole-life costs of a facility (often referred to as through-life costs) are the costs of acquiring (including consultancy, design and construction costs, and equipment), the costs of operating and the cost of maintaining a facility over the whole life through to its disposal. That is, the total ownership costs (AECP, 2003). Cost management is the process of planning, estimating, coordinating, controlling and reporting off all cost related aspects from project initiation to operation and maintenance and ultimately, disposal. It involves identifying all the costs associated with the investment, making informed choices about the options that will deliver best value for money and managing those costs throughout the life of the project, including disposal (AECP, 2003) 2.2 Whole- life Costing As a Decision Making Tool The main use of whole life costing is in the effective choice between a number of competing project alternatives and this is mainly applied during the early design stages (Griffin, 1993). Further to this, the ability to influence cost decreases continually as the project progresses, from 100% at project conceptualization, to typically 20% or less by the time construction commences (Paulson, 1976; Fabrycky and Blanchard, 1991). Furthermore, once the building is completed, there is a slim chance to change the total cost of ownership because the decision to own or purchase a building normally commits users to most of the total cost of ownership (HMSO,1992) % of the cost of running, maintaining and repairing a building is determined at the design stage ( Kirt and Dell Isola,1995; MacKay, 1995) 2.3 Implementation Of Whole- Life Costing In The Construction Industry. Most basic principles of whole life costing are well developed in theory it has however not received a wide practical application in Nigerian construction Industry. Most building sectors in other countries have not fully adopted whole-life costing methodology ( Larsson and Clark; 2000, Wilkinson, 1996;Sterner,2000) although it has been used predominantly in public procurement (Clift and Bourke, 1999). Many researchers (Brandon,1987; Ashworth 1996; Flanagan et al 1989;Ferry and Flanagan; 1991,Al-Hajj, 1996; Bull, 1993;Wilkinson, 1996;Blinta and Sarma, 1997; Smith et al, 1998; Sterner, 2000; among others), have tried to highlight areas causing difficulties in the application of whole-life costing in the industry. Kishk and AlHajj (1999) categorized these difficulties on the part of the industry practices, the client, the analyst and the analysis tools currently being in whole- life costing 391

3 2.4 Construction Industry Limitations The capital cost of construction is usually separated from the running cost. It is normal practice to accept the cheapest initial cost and then hand over the building to others to maintain. Furthermore, there is no clear definition of the buyer, seller and their responsibilities towards the operating and maintenance costs (Bull, 1993). In addition, there is lack of motivation in cost optimization because the design and cost estimating fees are usually a percentage of the total project cost (McGeorge,1993). 2.5 Client Limitations Bull (1993) pointed out that there is also a lack of understanding on the part of the client. This may increase the possibility of subjective decision making. In addition, there are usually multiple aspects of needs, desired by the clients (Chinyio et al, 1998). Most of these aspects cannot be assessed in a strict whole- life cost framework (Kishk et al, 2001), Some of these factors are intangibles such as aesthetics. In some projects, these intangibles are also in conflict with the result of whole life costing (Wilkinson, 1996) 2.6 Analysis Difficulties The major obstacle facing the analyst is the difficulty of obtaining the proper level of information upon which to base whole- life costs analysis. This is as a result of lack of appropriate, relevant and reliable historical information and data (Bull, 1993). Furthermore, cost of data collection is expensive (Ferry and Flanagan, 1991) 2.7 Cost Management and Reporting: Overview Management of the overall cost of the project is the responsibility of the project manager, reporting to the project sponsor. In managing project costs, the main tasks are to: Manage the base estimate and the risk allowance Produce cost reports, estimates and forecasts Operate change control procedures. Maintain an up to date estimated outrun cost and cash flow Initiate action to avoid overspend Issue a monthly financial status Delivering the project at the appropriate capital cost (having considered the implication of quality, programme and whole-life objectives, using value criteria established at the start of the project) Ensuring that, throughout the project, full and proper account is monitored of all transactions, payment and changes. The project sponsor has overall responsibility for the project, including the estimated cost, and will need to be satisfied that appropriate systems for controlling costs are in place and functional. Where significant costs are attached to a design, these must be properly reviewed against the budget decision and properly authorized. For complex projects, there might be delegated levels for each cost centre. Value management and value engineering have an important part to play in influencing cost (AECP, 2003) During construction, instructions issued to the integrated project team, whether for change via a formal change control 392

4 procedure of for clarification of detail, have a much more immediate impact on cost. The project sponsor needs to establish procures for instructions and information that ensure: Instructions are issued within delegated authority Instructions are costed and their impact assessed before use The instructions is justified in terms of value for money and overall impact on the project The cost of all instruction monitored on a continuous basis 3. Objectives of the Study The study seeks to identify the principles of whole-life cost management and basically has two objectives: 1. To establish the importance of various processes used in making decisions and estimating on whole-life costs. 2. To determine the importance of various items of costs in cost management using whole-life approach. 4. Data Collection and Analysis The study was carried out through questionnaire survey. The questionnaire focused on: The profession of the respondents, construction industry experience, framework for making decisions on whole-life costs, estimating whole-life costs and cost management. Most of the questions were derived from journal publication. The respondents were asked to assess the importance of the variables used in the research instrument. A 5-point Likert scale of 1 for not important, 2 for of little importance,3 for somewhat important, 4 for important and 5 for very important was used. Statistical analyses were undertaken using the Statistical Package for Social Sciences (SPSS).The analysis ranked the variables on the importance index. 5. Results and Discussion Thirty questionnaires were collected and were found useful for the study. The demographic characteristics of the respondents are presented in Table

5 1. Variables Profession Table 1: Demographic Characteristics of the Respondents Freq. Cum. Freq. Percentage Cum. Percent Civil Engineer Builder Architect Estate Surveyor and valuers Quantity Surveyor Construction Industry Experience Over 30 years years years years The majority of the respondents (50%) are Quantity Surveyors, the remaining (50%)are Estate Surveyors and valuers, Architects, Builders and Civil Engineers. About 53.4% of the respondents are made up of respondents that have over thirty years experience and those that have less than ten years experience in the construction industry. 5.1 A Framework for Making Decisions on Whole-Life Costs. Importance index for five processes that facilitate decision making in the application of whole-life costs on projects are shown on Table2.From the table the most important process based on the ranking of the Mean Item Score(MIS) are: Integrating the design and construction processes(4.97);this is followed by involving the integrated project team early(4.87).others are :Taking account of the needs of the end users of the facility(4.53);team members responsible for design and construction should work together(4.53);making the sustainability of the completed facility a priority. 394

6 Table 2: A Framework for making decisions on Whole-Life Costs Variables Importance index Integrating the design and construction processes, so that the integrated project team can take responsibility for the cost and quality implications of their design, with input from those who will be responsible for operating and maintaining the facility Involving the integrated project team early on so that they can advice on how the design will affect cost, health and safety during construction and in use, speed of construction and the operational efficiency of the completed facility Taking early account of the needs of the end users of the facility in order to avoid costly design changes at a later stage The team members responsible for design and construction should work together to identify the most cost-effective design over the life of the facility Rank Making sustainability of the completed facility a priority, taking full account of its whole life costs The views of the respondents were based on the importance of the processes in the objectives of whole-life costs. From the surveys all the processes are considered important because all the mean item score are above The ranking only shows that some processes are more important than others. 5.2 Estimating Whole-Life Costs. Importance Index for sixteen variables is shown on Table 3. From the table, the four most important variables in estimating whole- life costs based on the ranking of the Mean Item Scores (MIS) are: ensure the project team is integrated from the outset of the design process (4.97); use techniques such as value management and value engineering to minimize the potential for waste and inefficiency (4.80); ensuring financial reviews at key decision points as this will confirm if the project is still affordable (4.53); determine total investment needed to complete a facility (4.40).The four least important variables are: ensuring that variation orders are properly authorized (3.90); Preparing estimates and cash flow in line with the project programme (3.90); draw up a design brief that is output based with explicit reference to value (3.67); Specify at an early stage any constraints on capital costs. 395

7 Table 3: Estimating Whole-Life Costs. Variables Importance Index Ensure the project team is integrated from the outset of the design process, to enable specialist suppliers to contribute to the design Use techniques such as value management and value engineering to minimize the potential for waste and inefficiency Ensuring financial reviews at key decision points as this will confirm if the project is still affordable Determine total investment needed to complete a facility, such as the cost of design, construction cost and land cost Check how the facility will enhance the core business operations that will take place in the facility Produce an output based specification Rank Planning and controlling both commitments and expenditure within budgets so that unexpected cost over/under runs does not result Compare capital and predicted whole-life costs with the benchmark cost for a similar facility procured in the same way Ensuring that the contracts provide full and proper control and that all costs are incurred as authorized Ensuring that designs meet the scope and budget, delivering quality that is appropriate and conforms to the brief Defining what is to be included in the project and limiting expenditure accordingly Ensuring all expenditure relating to risks is appropriately allocated from the risk allowance and properly authorized Ensuring that variation orders are properly authorized Preparing estimates and cash flow in line with the project programme Draw up a design brief that is output-based with explicit reference to value, involve the users of the facility and others in its development Specify at an early stage any constraints on capital costs Cost Management Importance Indices for twelve items of cost in Cost Management are shown on table4.the ranking of the Mean Item Score (MIS) shows that the four most important variables are: construction costs (5.00); planning costs(4.40);maintenance costs(4.33);consultancy 396

8 costs(4.30),while those that are of little importance are information technology costs(2.93); health and safety costs (2.50). Table 4: Cost Management Variables Importance Index Rank Construction costs Planning costs Maintenance costs Consultancy fees Cleaning cost Cost of operations Cost of in-house resources Security costs Cost of utilities Cost of Alterations Information technology cost Health and safety costs The views of the respondents are based on the importance of these costs in cost management. The result of the survey shows that construction costs is very important, while planning costs, maintenance costs, consultancy fees are important. The ranking shows that some costs are more important than others in cost management of whole-life costs. 6. Conclusion and Recommendation The study has been able to establish the importance of various processes used in making decisions and estimating on whole-life costs. The paper also determines importance of various items of costs in cost management using whole-life approach. It is evident from the study that integrating design and construction processes as well as involving the integrated team early is essential in whole-life costs. The use of techniques such as value engineering and value management to minimize potential for waste and inefficiency is also useful in whole-life costs of projects in Nigeria. In cost management using whole-life approach, ten items of costs are very crucial, with construction costs being the most sensitive. There is need to integrate the design and construction processes and also to involve the integrated team early in the design as this will facilitate the planning of long term costs over the life of the project. This is because long term costs are more reliable indicators of value for money than initial construction costs. In planning for the long term costs emphasis must be placed on the following: construction costs, planning costs, maintenance costs, consultancy fees, cleaning cost, cost of operations, cost of in-house resources, security costs, cost of utilities, cost of alterations. 397

9 References: (AECP, 2003), Achieving excellence in construction procurement guide 07: whole-life costing and cost management. (CBPP, 1998a), Introduction to whole life costing, 15th July, Al-Hajj, A. (1996), Towards a better understanding of life cycle costings in buildings: a simple approach to modeling, Proceedings of the CIB W89 Conference, Beijing, pp , October Ashworth, A. (1996), Assessing the life expectancies of building for life cycle costing, Proceedings of the RICS construction and building research conference (COBRA 96), RICS. Bhuta, C. and Sarma, V. (1997), Life cycle costs and early decision, Building Economist, pp. 4 8, March. Brandon, P. S. (1987), Life cycle appraisal further considerations, in Spedding, A (ed), Building Maintenance Economics And Management, E&FN Spon, London, pp BSI (2000), Building and Constructed Assets: Service Life Planning: General Principles, British Standard Institution. Bull, J. W. (1993), The Way Ahead for Life Cycle Costing in the Construction Industry, in Bull, J. W. (ed) Life Costing For Construction, Blackie Academic and Professional, Glasgow. Chinyio, E. (1998), Evaluation of the Project Needs of UK Building Clients, International Journal Of Project Management, 16 (6), pp Clift, M. and Bourke, K. (1999), Study On Whole Life Costing, BRE Report 367, CRC. Dale, S. J. (1993), Introduction to life cycle costing, in Bull, J. W. (ed) Life Cycle Costing For Construction, Blackie Academic and Professional, Glassgow. Fabrycky, W. J. and Blanchard, B. S. (1991), Life-cycle Cost And Economic Analysis, Prentice-Hall Inc., NJ. Ferry, D. and Flanaga, R. (1991), Life cycle costing a radical approach, CIRIA Report 122, London. Flanagan, R. Norman G. Meadows, J. (1989), Life cycle Costing-Theory And Practice, BSP Professional Books. Griffin, J. J. (1993), Life Cycle Cost Analysis: A Decision Aid, in Bull J. W. (ed), life cycle costing for construction, Blackie Academic and Professional, Glasgow. HMSO (1992). Life-Cycle Costing, HM Treasury, Her majesty s stationery office, London. Kirk S. J. and Dell Isola, A. J. (1995), Life Cycle Costing For Design Professionals, McGrew-Hill Book Company, New York. Kishk, M. and Al-Hajj, A. (1999), An Integrated Framework For Life Cycle Costing In Buildings, Proceedings of COBRA, 1999 The Challenge Of Change: Construction And Building For The New Millennium, RICS, vol. 2, pp Larsson, N. and Clark, J. (2000), Incremental Costs Within The Design Process For Energy Efficient Buildings, Building Research And Information, 28 (5/6), pp Mackay, S. (1999), Building For Life, The Building Economist: pp McGeorge, J. F. (1992), The Quality Approach To Design And Life Cycle Costing In The Health Service, in Bull, J. W. (ed) Life Cycle Costing For Construction, Blackie Academic and Professional, Glasgow, Oladipo, M. A. (2001), A Framework Cost Management of Low Cost Housing, International Conference on Spatial Information for Sustainable Development Nairobi, Kenya, pp. 1 12, October 398

10 Paulson, B. C. (1976), Designing To Reduce Construction Costs, Journal Of Construction Division, ASCE, 102, pp Smith, D., Berkhout, F. Howes, R. (1998), Adoption By Industry Of Life Cycle Approaches Its Implications For Industry Competitiveness, Kogan Page Ltd., London. Sterner, E. (2000), Life-Cycle Costing And Its Use In The Swedish Building Sector, Building Research And Information, 28 (5/6), pp Wilkinson, S. (1996), Barriers To LCC Use In The New Zealand Construction Industry, Proceedings Of The 7 th International Symposium On Economic Management Of Innovation Productivity And Quality In Construction, Zagreb, pp

INTEGRATING WHOLE LIFE COST INTO THE EVALUATION OF DESIGN-BUILD IN KOREA

INTEGRATING WHOLE LIFE COST INTO THE EVALUATION OF DESIGN-BUILD IN KOREA INTEGRATING WHOLE LIFE COST INTO THE EVALUATION OF DESIGN-BUILD IN KOREA Sung Ho (Kenneth) Park 1 and Roger Flanagan School of Construction Management and Engineering, University of Reading, Reading, UK

More information

The Role of Building Construction Project Team Members In Building Projects Delivery

The Role of Building Construction Project Team Members In Building Projects Delivery IOSR Journal of Business and Management (IOSR-JBM) e-issn: 2278-487X, p-issn: 2319-7668. Volume 14, Issue 1 (Sep. - Oct. 2013), PP 30-34 The Role of Building Construction Project Team Members In Building

More information

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a

More information

IAM Endorsed Training

IAM Endorsed Training IAM Endorsed Training IAM Endorsed Training Asset training and development is a crucial element to ensure your business maintains and develops its capability to deliver first class Asset for its customers

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

T 0845 605 55 56 F 01923 664690 E

T 0845 605 55 56 F 01923 664690 E Who should read this fact sheet? This fact sheet introduces the principles of whole life costing for organisations that are new to the subject or in the early stages of working with whole life costing.

More information

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012. RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as

More information

Introduction. Project Management in New Zealand

Introduction. Project Management in New Zealand AN ANALYSIS OF THE USE OF INFORMATION TECHNOLOGY FOR PROJECT MANAGEMENT IN THE NEW ZEALAND CONSTRUCTION INDUSTRY Dr Suzanne Wilkinson, Senior Lecturer, Department of Civil and Resource Engineering The

More information

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Procurement requirements for reducing waste and using resources efficiently

Procurement requirements for reducing waste and using resources efficiently Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction

More information

Time for change in facilities management. Interserve, Sheffield Hallam and i-fm facilities management research 2013

Time for change in facilities management. Interserve, Sheffield Hallam and i-fm facilities management research 2013 Time for change in facilities management Interserve, Sheffield Hallam and i-fm facilities management research CONTENTS 01 02 03 04 About the facilities deal Outsourcing objectives The role of your brand

More information

How To Design A Project

How To Design A Project Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project

More information

Content, Learning Methods and Assessment of Law on Undergraduate Courses in Construction Management and Surveying

Content, Learning Methods and Assessment of Law on Undergraduate Courses in Construction Management and Surveying CEBE Transactions, Vol. 2, Issue 2, September 2005, pp 32-47 (16) ISSN: 1745-0322 (Online) Content, Learning Methods and Assessment of Law on Undergraduate Courses in Construction Management and Surveying

More information

Procurement and contract strategies

Procurement and contract strategies Achieving Excellence in Construction Procurement Guide 06 Procurement and contract strategies 06 Contents 01 The Achieving Excellence Procurement Guides 02 Introduction 02 Principles 05 Process 18 Annex

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

Certificate in Building Information Modelling (BIM) - Project Management

Certificate in Building Information Modelling (BIM) - Project Management Certificate in Building Information Modelling (BIM) - Project Management Duration: 6 Months Distance Learning Programme Language: English RICS Member: 895.00 + VAT Non RICS Member 995.00 + VAT Course Summary

More information

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0

More information

Project manager services

Project manager services Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism

More information

Check. They re Chartered. Chartered Project Managers

Check. They re Chartered. Chartered Project Managers Check. They re Chartered. Chartered Project Managers The Society of Chartered Surveyors Ireland is the leading organisation of its kind in Ireland for professionals working in the property, land and construction

More information

Evaluating the effects of communication in construction project delivery in Nigeria

Evaluating the effects of communication in construction project delivery in Nigeria Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication

More information

Achieving Excellence in Construction. A manager s checklist. Construction projects

Achieving Excellence in Construction. A manager s checklist. Construction projects Achieving Excellence in Construction A manager s checklist Construction projects Construction projects A manager s checklist This document outlines the key questions that a Senior Responsible Owner (SRO)

More information

ESTIMATING SERVICE LIVES USING THE FACTOR METHOD FOR USE IN WHOLE LIFE COSTING Estimating service life

ESTIMATING SERVICE LIVES USING THE FACTOR METHOD FOR USE IN WHOLE LIFE COSTING Estimating service life ESTIMATING SERVICE LIVES USING THE FACTOR METHOD FOR USE IN WHOLE LIFE COSTING Estimating service life K.BOURKE BRE Ltd., Centre for Whole Life Performance, UK H.DAVIES Hywel Davies Consultancy, UK Durability

More information

Accounting Problems of Research and Development

Accounting Problems of Research and Development Accounting Problems of Research and Development KATA T. SZILÁGYI Department of Business Economics, Institute of Economic Science Eszterházy Károly College, Egészségház u. 4, Eger 3300, Hungary szkata@ektf.hu

More information

RESEARCHING WHOLE LIFE VALUE METHODOLOGIES FOR CONSTRUCTION

RESEARCHING WHOLE LIFE VALUE METHODOLOGIES FOR CONSTRUCTION RESEARCHING WHOLE LIFE VALUE METHODOLOGIES FOR CONSTRUCTION Das Mootanah 1 1 Construction Industry Research and Information Association (CIRIA), Classic House, 174-180 Old Street, London EC1V 9BP, UK Whole

More information

PROCUREMENT & LOGISTICS DEPARTMENT

PROCUREMENT & LOGISTICS DEPARTMENT PROCUREMENT & LOGISTICS DEPARTMENT Tender/OJEU Procedure Overview This procedure applies to all purchases over 50,000 not covered by existing contracts and should be followed in conjunction with the Tender/OJEU

More information

Royal Institute of British Architects. Procurement policy. Building teams achieving value

Royal Institute of British Architects. Procurement policy. Building teams achieving value Royal Institute of British Architects Procurement policy Building teams achieving value November 2001 RIBA Procurement Policy The RIBA is committed to construction procurement that: R provides the best

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

ACT ACCOUNTING POLICY. Capital Works

ACT ACCOUNTING POLICY. Capital Works ACT ACCOUNTING POLICY Capital Works FOR REPORTING PERIODS ENDING ON OR AFTER 30 JUNE 2006 TABLE OF CONTENTS 1 Introduction... 3 1.1 APPLICATION... 3 1.1.1 This Policy... 3 1.1.2 Relationship to International

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

Flooring materials life-cycle costing for educational facilities

Flooring materials life-cycle costing for educational facilities Flooring materials life-cycle costing for educational facilities Helena Moussatche and Jennifer Languell The authors Helena Moussatche is an Assistant Professor at the Department of Interior Design, University

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries

Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries O O FANIRAN School of Civil and Environmental Engineering The University of New South Wales Sydney

More information

Strategic Asset Management Framework

Strategic Asset Management Framework STRATEGIC ASSET MANAGEMENT Strategic Asset Management Framework (Second Edition) Achieving better value for South Australians from our investment in State assets Government of South Australia First edition

More information

Very Smart People. www.mms.co.uk. August 2013. Evaluating Flood Risk: Buyers and Lenders. www.mms.co.uk

Very Smart People. www.mms.co.uk. August 2013. Evaluating Flood Risk: Buyers and Lenders. www.mms.co.uk Very Smart People www.mms.co.uk August 2013 Evaluating Flood Risk: Buyers and Lenders www.mms.co.uk Index What is the concern? 1 Availability of Flood Insurance 1 Types of flooding 2 Flood risk assessment

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

Asset Management Policy

Asset Management Policy Asset Policy DETAILS Council Admin Effective from: July 2015 Contact officer: Executive Coordinator Strategic Asset, Corporate Asset Next review date: June 2017 File reference: LG343/1045/03/01 ispot #

More information

DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM

DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM Joanna Poon, Keith Potts and Patricia Cooper School of Engineering and the Built Environment University of Wolverhampton Wolverhampton WV1 1SB UK

More information

NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS

NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS THE AUSTRALIAN INSTITUTE OF QUANTITY SURVEYORS THE AUSTRALIAN INSTITUTE OF QUANTITY SURVEYORS NATIONAL COMPETENCY STANDARDS

More information

Certificate in Construction Project Management

Certificate in Construction Project Management Certificate in Construction Project Management Duration: 6 Months Distance Learning Programme Language: English RICS Member: 895.00 + VAT Non RICS Member 995.00 + VAT Course Summary As a result of the

More information

The Key Performance Indicator Evaluation Process (KPI Process)

The Key Performance Indicator Evaluation Process (KPI Process) The Key Performance Indicator Evaluation Process (KPI Process) Aims Continuous improvement Quantitative and qualitative consultant, contractor and supply chain evaluation Identification and commendation

More information

LONDON BOROUGH OF HAVERING

LONDON BOROUGH OF HAVERING LONDON BOROUGH OF HAVERING CORPORATE ASSET MANAGEMENT PLAN 2015-2019 Sections LONDON BOROUGH OF HAVERING CORPORATE ASSET MANAGEMENT PLAN CONTENTS 1 Introduction and Context 2 Corporate Vision 3 Policy

More information

PROPERTY & ASSET MANAGEMENT PERFORMANCE IN

PROPERTY & ASSET MANAGEMENT PERFORMANCE IN PROPERTY & ASSET MANAGEMENT PERFORMANCE IN THE UK Results from the REMark survey 2013 Bob Thompson Steph Yates Abstract The objective of this paper is to look at the performance of Property and Asset Management

More information

CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT

CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: pawarchaitali071@gmail.com 2 Asso.

More information

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective

More information

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES CAPITAL ASSET MANAGEMENT PROJECT PROCUREMENT PROCEDURES AND GUIDELINES June 2003 Updated June 20, 2003 Ministry of Education Province of British Columbia TABLE OF CONTENTS EXECUTIVE SUMMARY... iii 1.0

More information

Date: 7 February 2013

Date: 7 February 2013 Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties

More information

Fixed Assets Policy. Control over Assets

Fixed Assets Policy. Control over Assets Fixed Assets Policy Author Financial Control and Compliance The United Kingdom s international organisation for educational opportunities and cultural relations. We are registered in England as a charity.

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

GUIDANCE ON ASSET VALUATION

GUIDANCE ON ASSET VALUATION GUIDANCE ON ASSET VALUATION Introduction This guidance should be read in conjunction with the text in the Government Financial Reporting Manual (FReM) about the application of FRS 15 by entities covered

More information

CAPITAL WORKS GUIDANCE DOCUMENT

CAPITAL WORKS GUIDANCE DOCUMENT COMMUNITY BUILDINGS TRANSFER PROGRAMME CAPITAL WORKS GUIDANCE DOCUMENT This document has been prepared to assist and advise management groups of community buildings who are involved in Durham County Council

More information

Procurement & Supply Chain Management

Procurement & Supply Chain Management New Skills. New Thinking Procurement & Supply Chain Management Supply Chain Effectiveness Audit - Implementing lean processes in your supply chain 20 September 2012 Auckland 24 September 2012 Wellington

More information

Leeds City Council Procurement Strategy October 2013

Leeds City Council Procurement Strategy October 2013 Leeds City Council Procurement Strategy October 2013 Contents 1. Introduction 2. Background 3. Our ambition 4. Our strategy 5. Who we will work with 6. What we will achieve and how we will achieve it 7.

More information

How are companies currently changing their facilities management delivery model...?

How are companies currently changing their facilities management delivery model...? Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy

More information

Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry

Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1

More information

This document will be made available in different languages and formats on request, including Braille and audio formats.

This document will be made available in different languages and formats on request, including Braille and audio formats. Policy Title: Policy Manual Section: Policy Number: Performance Standards References: Factoring Housing Management HM21 AS5:2 Date Approved by Management Committee: 25 November 2010 Next Review Date: 3

More information

Rider Levett Bucknall. Taxation Services Executive Summary. state of mind

Rider Levett Bucknall. Taxation Services Executive Summary. state of mind Rider Levett Bucknall Executive Summary state of mind The Service Property tax relief - advice, claims and negotiations; Types of relief - land remediation relief, capital allowances and enhanced capital

More information

REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan])

REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan]) 65 REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan]) (See also General Regulations) Any publication based on work approved for a higher degree should

More information

Corporate Real Estate - The Future of Business

Corporate Real Estate - The Future of Business Flexible Real Estate Perception Vs. Reality Contents Introduction Key findings 1. A decade of research avoidance 2. Meeting and training venues it s real estate True business hospitality the market demands

More information

Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria.

Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. ISSN: - Vol. Issue, January - Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. Abdulrahman Haruna, Sani Usman Kunya, Musa Mohammed Department of Building Technology

More information

MSc Portfolio (Property and Construction) STUDENT HANDBOOK

MSc Portfolio (Property and Construction) STUDENT HANDBOOK MSc Portfolio (Property and Construction) STUDENT HANDBOOK 2013-2014 PREFACE Welcome to the School of Architecture, Design & Construction. This Programme Handbook contains important information relating

More information

THE INFORMATION AUDIT AS A FIRST STEP TOWARDS EFFECTIVE KNOWLEDGE MANAGEMENT: AN OPPORTUNITY FOR THE SPECIAL LIBRARIAN * By Susan Henczel

THE INFORMATION AUDIT AS A FIRST STEP TOWARDS EFFECTIVE KNOWLEDGE MANAGEMENT: AN OPPORTUNITY FOR THE SPECIAL LIBRARIAN * By Susan Henczel INSPEL 34(2000)3/4, pp. 210-226 THE INFORMATION AUDIT AS A FIRST STEP TOWARDS EFFECTIVE KNOWLEDGE MANAGEMENT: AN OPPORTUNITY FOR THE SPECIAL LIBRARIAN * By Susan Henczel Introduction Knowledge is universally

More information

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent

More information

Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia

Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia Anisur Rahman 1 and Muhammad T. Attar 2 1,2 Griffith School of Engineering, Griffith University, Gold Coast Campus, QLD

More information

A Guide to Reviewing Outsourced Contracts. By James Milner - Ember Public Sector Solutions

A Guide to Reviewing Outsourced Contracts. By James Milner - Ember Public Sector Solutions A Guide to Reviewing Outsourced Contracts By James Milner - Ember Public Sector Solutions Introduction from James Milner, Director EPSS Outsourced contracts in the public sector are now commonplace. Unfortunately

More information

Project Management Handbook 2014. "To Understand the Causes of Things"

Project Management Handbook 2014. To Understand the Causes of Things Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders

More information

NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013. Contract for the Collection and Disposal of Clinical Waste: Award Recommendation.

NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013. Contract for the Collection and Disposal of Clinical Waste: Award Recommendation. 13/123 NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013 Title Contract for the Collection and Disposal of Clinical Waste: Award Recommendation Executive Summary Collection and Disposal of Clinical Waste across

More information

If walls could talk. With expertise and planning, property has the potential to reduce costs, generate revenue and. www.nps.co.

If walls could talk. With expertise and planning, property has the potential to reduce costs, generate revenue and. www.nps.co. Asset Management 2 If walls could talk People will always be the public sector s greatest asset. But with growing demand and year-onyear funding cuts, property and its effective management has become increasingly

More information

A. Statement of Accountability

A. Statement of Accountability A. Statement of Accountability National Savings is an Executive Agency of the Chancellor of the Exchequer and a Government Department. The Agency manages the issue and distribution of National Savings

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

STRATEGIC COST MANAGEMENT ACCOUNTING INSTRUMENTS AND THEIR USAGE IN ALBANIAN COMPANIES ABSTRACT

STRATEGIC COST MANAGEMENT ACCOUNTING INSTRUMENTS AND THEIR USAGE IN ALBANIAN COMPANIES ABSTRACT STRATEGIC COST MANAGEMENT ACCOUNTING INSTRUMENTS AND THEIR USAGE IN ALBANIAN COMPANIES Marsel Sulanjaku Lecturer at A.Xhuvani University ALBANIA Ali Shingjergji Lecturer at A.Xhuvani University ALBANIA

More information

EMPOWERING THE CLIENT IN THE BRIEFING PROCESS

EMPOWERING THE CLIENT IN THE BRIEFING PROCESS EMPOWERING THE CLIENT IN THE BRIEFING PROCESS Lindsay Castell 1 Construction Management Department, Curtin University of Technology, Perth, Western Australia Accurately identifying the client s requirements

More information

MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT

MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT CONTENTS Foreword ------------------------------------------------------------------------ 3 Executive Summary ---------------------------------------------------------

More information

Procurement Systems and Project Organisation Model for Low Cost Housing

Procurement Systems and Project Organisation Model for Low Cost Housing Procurement Systems and Project Organisation Model for Low Cost Housing Murtala A. OLADAPO, Nigeria Key words: Procurement systems, project organisation, sustainable, low-cost housing. ABSTRACT Procurement

More information

PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS

PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS Professor P.A. Bowen and Associate Professor K.S. Cattel, University of Cape Town K.A. Hall, The University of New South Wales Associate

More information

Sustaining Local Assets. Local government asset management policy statement

Sustaining Local Assets. Local government asset management policy statement Sustaining Local Assets Local government asset management policy statement December 2003 ISBN 0 646 42106 9 Authorised by the Victorian Government Address: Local Government Victoria Department for Victorian

More information

THE BMW GROUP GUIDE TO FLEET FUNDING.

THE BMW GROUP GUIDE TO FLEET FUNDING. THE BMW GROUP GUIDE TO FLEET FUNDING. The way vehicles are funded in a fleet context varies widely and there are two main methods for acquiring vehicles for your fleet: Outright purchase over a fixed period

More information

Income & Expenditure Units (Treasury)

Income & Expenditure Units (Treasury) Income & Expenditure Units Income & Expenditure Units Treasury Cluster Real Estates Unit City Fleet Unit Finance staff reconciling payments made for Municipal services Income & Expenditure Units (Treasury)

More information

ACCOUNTING FOR CONSTRUCTION CONTRACT AS7 (Revised-2002) Applied in accounting for construction contracts in the financial statements of contractors.

ACCOUNTING FOR CONSTRUCTION CONTRACT AS7 (Revised-2002) Applied in accounting for construction contracts in the financial statements of contractors. ACCOUNTING FOR CONSTRUCTION CONTRACT AS7 (Revised-2002) 1) Applicability of the Standard Applied in accounting for construction contracts in the financial statements of contractors. Where a Construction

More information

Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the

Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the Division of Revenue Act March 2015 1 JOB DESCRIPTION JOB

More information

Efficiency Review by Sir Philip Green

Efficiency Review by Sir Philip Green Efficiency Review by Sir Philip Green Key Findings and Recommendations The Government is failing to leverage both its credit rating and its scale 1 Introduction I was asked by the Prime Minister in mid

More information

2.6 Select a. procurement route. cabe. Contents

2.6 Select a. procurement route. cabe. Contents 2.6 Select a procurement route 2.6.1 Procurement routes Procurement is the purchasing of products, work and services. It is more important than its unglamorous name suggests and plays a major part in any

More information

The Characteristics of Public Real Estate Asset Management and Maintenance Practice in New Zealand Council Community Buildings

The Characteristics of Public Real Estate Asset Management and Maintenance Practice in New Zealand Council Community Buildings The Characteristics of Public Real Estate Asset Management and Maintenance Practice in New Zealand Council Community Buildings Zulkfli Sapeciay 1, Suzanne Wilkinson 2, Seosamh Costello 3 Abstract Asset

More information

The Public Contracts Regulations 2015 Guidance on Awarding Contracts

The Public Contracts Regulations 2015 Guidance on Awarding Contracts The Public Contracts Regulations 2015 Guidance on Awarding Contracts 1 P a g e Crown Commercial Service, Customer Service Desk: 0345 410 2222 www.gov.uk/ccs follow us on Twitter connect with us on LinkedIn

More information

EXAM EXEMPLAR QUESTIONS

EXAM EXEMPLAR QUESTIONS Level 4 Diploma in Procurement and Supply D1 - Contexts of procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 9 QUALIFICATIONS 2013 QUESTIONS AND MARKING SCHEME

More information

Delivery Management Guidelines Delivery Process 2 - Project Management

Delivery Management Guidelines Delivery Process 2 - Project Management Delivery Management Guidelines Delivery Process 2 - Project Management Version control Version 9-1 Date 2010-10-18 Status Approved The IDMS Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure

More information

What is effective Design Management?

What is effective Design Management? What is effective Design Management? Design Management is becoming increasingly recognised as critical to the success of complex construction projects. However, the role of the Design Manager is poorly

More information

Rent to Buy 2015 to 2017

Rent to Buy 2015 to 2017 Rent to Buy 2015 to 2017 BIDDING PROSPECTUS September 2014 Rent to Buy Contents Page Number Ministerial Foreword 2 Chapter 1 Overview of the fund 3 Chapter 2 The funding model 4 Chapter 3 Bidding requirements

More information

place-based asset management

place-based asset management place-based asset management Managing public sector property to support aligned local public services TOWN HALL CIPFA, the Chartered Institute of Public Finance and Accountancy, is the professional body

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

ROYAL MALAYSIAN CUSTOMS GOODS AND SERVICES TAX GUIDE ON VALUERS, APPRAISERS AND ESTATE AGENTS

ROYAL MALAYSIAN CUSTOMS GOODS AND SERVICES TAX GUIDE ON VALUERS, APPRAISERS AND ESTATE AGENTS ROYAL MALAYSIAN CUSTOMS GOODS AND SERVICES TAX GUIDE ON VALUERS, APPRAISERS AND ESTATE AGENTS CONTENTS INTRODUCTION... 1 Overview of Goods and Services Tax (GST)... 1 GST AND VALUERS, APPRAISERS AND ESTATE

More information

Capital Asset Management Framework. Overview

Capital Asset Management Framework. Overview Capital Asset Management Framework Overview Introduction Table of Contents Introduction 1 The Framework 2 Guiding Principles, Guidelines & Tools 3 Conclusion 6 Appendix The Capital Process 7 The government

More information

Accounting for Fixed Assets

Accounting for Fixed Assets 96 Accounting Standard (AS) 10 Accounting for Fixed Assets Contents INTRODUCTION Paragraphs 1-6 Definitions 6 EXPLANATION 7-17 Identification of Fixed Assets 8 Components of Cost 9 Self-constructed Fixed

More information

CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT

CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT SHAMIL NAOUM and DANIEL FONG Department of Property, Surveying and Construction, London South Bank University, 103 Borough Road, London, UK, SE1 0AA. naoums@lsbu.ac.uk

More information

REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan])

REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan]) 64 REGULATIONS FOR THE DEGREE OF MASTER OF SCIENCE IN CONSTRUCTION PROJECT MANAGEMENT (MSc[ConstProjectMan]) (See also General Regulations) Any publication based on work approved for a higher degree should

More information

Good Practice Framework. Performance Management

Good Practice Framework. Performance Management Good Practice Framework Performance Management Decision Gatewa y Good Practice Framework Strategic Planning STRATEGIC PLANNING Policy Context Needs Assessment Strategic Review Outcomes Continuous Improvement

More information