Appendix 2e. DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE Internal Audit Service to the GLA. Follow up Review Performance Management Analytical Review



Similar documents
Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework

Appendix 2e. DIRECTORATE OF AUDIT, FF RISK AND ASSURANCE Internal Audit Service to the GLA. Follow up Review of Sickness Monitoring and Control

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Borders NHS Board. Appendix NEW ARRANGEMENTS FOR HEALTHCARE GOVERNANCE. Aim

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA INTERIM REVIEW OF ROYAL ALBERT DOCK PROCUREMENT

M O P AX. i Y/k (7. annual value of the services is circa E80m. The overall FM service has been worked up into 5 packages.

PROCEDURE Transaction Monitoring and Audit. Number: G 0811 Date Published: 6 June 2013

DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE. Appendix 2a FOLLOW UP REVIEW OF CORPORATE BUSINESS CONTINUITY

Policy: D9 Data Quality Policy

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK

NORTHAMPTON GENERAL HOSPITAL NHS TRUST PERFORMANCE MANAGEMENT STRATEGY

Sickness Reporting Audit Final Report

Report 7 Appendix 1d Final Internal Audit Report Sundry Income and Debtors (inc. Fees and Charges) Greater London Authority February 2010

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA

INFORMATION GOVERNANCE POLICY

Business Continuity Management Policy

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA

Reducing healthcare associated infections: An organisational perspective A summary of best practice

Corporate Health and Safety Policy

ESSEX FIRE AUTHORITY. Internal Audit Progress Report. Audit Sub-Committee Meeting: April 2012

Data Quality. Carlisle City Council Audit January 2009

The Integration of Strategic Planning and Portfolio Management

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Appendix 1b REVIEW OF CHEQUE HANDLING PROCESS

RISK MANAGEMENT STRATEGY

Essex Fire Authority. Fleet Management. Internal Audit Report (4.12/13) 28 February 2013 FINAL. Overall Opinion

The GCSB has a major change programme underway that reflects the recommendations of the Compliance Review.

External Performance Assessment Improvement Plan 2006/8 - Monitoring 6

The Annual Audit Letter for West Mercia Police and Crime Commissioner and Chief Constable

Audit Committee means the audit committee established by resolution of the Board in accordance with clause 2 of these Terms.

Corporate Performance Management

Appenidx 1a. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF HOUSING COMPLIANCE AUDIT PROGRAMME

MEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL.

Appendix 1C. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA PAYROLL CONTROL FRAMEWORK

Job Description. Director of Fundraising and Marketing

How To Manage Risk In Ancient Health Trust

Policy. VBA Enterprise Risk Management. Governance Unit

Human Resource Change Management Plan

Data Quality Policy. Appendix A. 1. Why do we need a Data Quality Policy? Scope of this Policy Principles of data quality...

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers

Job Description. Regularly reviews workflow operations and ensures contracted KPIs and service standards are met.

Procurement and Contract Management Strategy

PART A OVERVIEW INTRODUCTION APPLICABILITY... 1 PART B LEGAL PROVISIONS LEGAL PROVISIONS (Please refer to the BAFIA for the

Annex A: SLA Performance Summary Q1 Q2, 2013/14 BaNES CCG

TERMS OF REFERENCE OF THE AUDIT COMMITTEE

JOB DESCRIPTION POSITION DETAILS REPORTING RELATIONSHIPS SUPERVISOR 1 FUNCTIONS OF THE POSITION 2 ORGANISATIONAL CONTEXT. Chief Financial Officer

Multicultural Council of Tasmania GUIDE FOR MANAGEMENT COMMITTEE MEMBERS

CHAPTER SEVEN PERFORMANCE MANAGEMENT

Mexan Limited Terms of Reference for Audit Committee

Recorded Crime in Scotland. Scottish Government

INFORMATION GOVERNANCE POLICY

Federal Deposit Insurance Corporation Improvement Act 1

AQTF Essential Conditions and Standards for Continuing Registration AUDIT REPORT

LUKHANJI MUNICIPALITY PERFORMANCE MANAGEMENT FRAMEWORK

DIRECTORATE OF AUDIT, RISK AND ASSURANCE

I have reviewed the request and am satisfied it is correct and consistent with the Mayor s plans and priorities. It has my approval.

Performance management system. Chapter

Business Continuity Policy

Performance Management and Service Improvement Framework

Policy Checklist. Head of Information Governance

Head of Engineering Job Description

Cambridgeshire Constabulary. Data protection audit report

Job Description. To participate in department shifts including early and late cover, night duties and weekends as required.

Councillor role descriptions

TRANSPORT FOR LONDON SAFETY, HEALTH AND ENVIRONMENT ASSURANCE COMMITTEE

National Drug and Alcohol Treatment Waiting Times Report

Information Governance Strategy and Policy. OFFICIAL Ownership: Information Governance Group Date Issued: 15/01/2015 Version: 2.

CHINA PIONEER PHARMA HOLDINGS LIMITED

How To Manage A Hospital

POLICY. Performance Monitoring of Service Providers

Draft consolidated budget : Finance and legal advice

Business Continuity Plans Of Hammersmith & Fulham borough

IT and Corporate Services Officer Job Description

FINAL INTERNAL AUDIT REPORT

Corporate Services Team Senior Leadership Team Program Managers Team Leaders Program staff Back office staff All staff Australia wide

Treasury KPIs a Powerful Management Tool

CORPORATE RISK MANAGEMENT POLICY

FINANCIAL MANAGEMENT & CORPORATE GOVERNANCE WORKING PARTY MINUTES P R E S E N T

EAST AYRSHIRE COUNCIL. No Goals Target Date Progress & Comments

Tracking Campaigns for Local Authorities. Lucian Glenny Web Analyst

HONG KONG ENVIRONMENTAL ELECTRICAL APPLIANCE COMPANY. Environmental Procedure

Cumbria Constabulary. Business Continuity Planning

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes

Shropshire Community Health Service NHS Trust Policies, Procedures, Guidelines and Protocols

RISK MANAGEMENT FRAMEWORK

Post-Recognition Monitoring Report

Printed copies of this document may not be up to date. Ensure you have the latest version before using this document.

Best Practice Policy

Central Alert System (CAS) Policy and Procedure Document Summary

DRAFT EARLY RETIREMENT

Capital Works Construction Project. [Insert Project Title] [Insert Sponsoring Agency]

JOB DESCRIPTION. I.C.T Application Systems & Workflow Manager

We propose that further follow up work is performed in this respect and reported to the next meeting of the Audit Panel.

Data Quality Audit Commission report

DEPARTMENT OF TRANSPORT

YM72 Policy Communications Officer. Application Pack

Supplier & Contract Management System (SCMS)

Senate. SEN15-P17 11 March Paper Title: Enhancing Information Governance at Loughborough University

Information Governance Policy

Self-Assessment Checklist for Audit Committees

Subject: Recruitment Administrators Report Number: 9

Transcription:

Appendix 2e DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE Internal Audit Service to the GLA Follow up Review Performance Management Analytical Review

EXECUTIVE SUMMARY 1. Background 1.1 This audit follows up the progress made towards implementing the four agreed recommendations from the audit of Performance Management Analytical Review that was completed in September 2014. 2. Audit Assurance Substantial There is particularly effective management of key risks contributing to the achievement of business objectives. 3. Key Findings 3.1 The overall control framework for Performance Management Analytical Review has improved. Since the original review three recommendations have been fully implemented and one has been partly implemented. 3.2 Functional Bodies KPI leads have been formally reminded by GLA Governance and Performance of the need to provide timely and complete performance data and that where problems arise they should be reported to GLA Governance and Performance so that this information can be included in the quarterly Finance and Performance Monitoring Reports to the Budget Monitoring Sub-Committee. 3.3 Data on Special Constables and Met Volunteers is now being received from MOPAC/MPS for the Number of volunteering opportunities taken up by volunteers through Team London KPI. However, MOPAC/MPS has still not supplied the required data for the Number of jobs created through GLA Group investment and associated spend KPI. GLA Governance and Performance will continue to liaise with MOPAC/MPS to obtain this data. 3.4 Performance and data owners at Functional Bodies have been reminded by GLA Governance and Performance of the need to follow good data quality principles and asked to ensure data providers within their owner organisations are aware of and compliant with the published GLA Data Quality Framework and the Use of Statistics Code of Practice. 3.5 GLA Governance and Performance actively raises awareness of the requirements of the GLA s Data Quality Framework by reviewing and suggesting amendments to the Definition Forms submitted by Performance Leads. In addition, all KPI Information Sheets, which includes detailed definitions and calculation methodologies, have been published on the GLA website. 3.6 Where provisional and estimated data is used instead of actual data, this is clearly flagged up in the commentary to the Quarterly Finance and Performance Reports to the Budget Monitoring Sub-Committee. February 2015 Performance Management Analytical Review Follow Up 1

9.1 Performance data is not always being received from all functional bodies which could undermine the ability to accurately demonstrate performance. 2 All functional bodies are reminded of the requirement to provide timely data to the responsible data owner and any non-compliance is noted in the Finance and Performance Monitoring Report. Ongoing efforts are already being made to secure complete data for KPIs. A reminder will be sent to all data and performance owners asking them to a) remind functional bodies of the need to provide timely and complete data, where relevant; and b) to ensure that where this does not happen the Governance & Resilience Unit is informed and issues are flagged in the Monitoring report. Partly A reminder e-mail was sent to all functional bodies KPI leads by the Corporate Governance Manager in September 2014 reminding them of the need to provide timely and complete performance data. In addition the e-mail requests that KPI leads inform GLA Governance and Performance of data that is not timely and complete so that this information can be included in the quarterly Finance and Performance Monitoring Reports to the Budget Monitoring Sub-Committee. Data on Special Constables and Met Volunteers is now being received from MOPAC/MPS for the Number of volunteering opportunities taken up by volunteers through Team London KPI. However, MOPAC/MPS has still not supplied the required data for the Number of jobs created through GLA Group investment and associated spend KPI. Further Recommendation Governance and Performance should continue to liaise with the MOPAC/MPS KPI lead and MOPAC Chief Operating Officer to ensure that data for the Number of jobs created through GLA Group investment and associated spend KPI is provided. Governance and Performance will continue to liaise with MOPAC/MPS KPI lead and MOPAC Chief Operating Officer to ensure the required data is received. Target Date Ongoing 9.2 It is not clear as to whether all sources of data have been identified. 3 Data sources for all KPIs are reviewed to ensure that all relevant sources of data are being used. A reminder e-mail was sent to all functional bodies KPI leads by February 2015 Performance Management Analytical Review Follow Up 2

9.7 External partners are not always made aware of the GLA s data quality requirements leading to the risk that it is not possible to provide an assurance that all data received is complete and accurate. Work has already taken place to identify data sources, and contacts, to feed into the volunteering KPI. This recommendation is closely linked to that above. The Governance & Resilience unit will therefore at the same time provide a reminder to all data and performance owners of the need to ensure all relevant data sources are being used. 3 All external partners who provide the GLA with performance data are provided with a summary of the requirements of the Data Quality Framework and the Use of Statistics Code of Practice. The Data Quality Framework is clear on the need to ensure partners follow good data quality principles. However, performance and data owners will be reminded of this requirement and asked to in turn ensure partners are compliant with the key aspects of both the the Corporate Governance Manager in September 2014 asking them to make an assessment of the completeness of their data and report any issues identified to GLA Governance and Performance. Governance and Performance report that all data source have now been identified and are, with the exception of MOPAC/MPS data for Number of jobs created through GLA Group investment and associated spend KPI, being provided and incorporated into KPIs. Performance and data owners at Functional Bodies were reminded of the need to follow good data quality principles via e-mail and asked to ensure data providers within their owner organisations are aware and compliant with the GLA Data Quality Framework and the Use of Statistics Code of Practice. In addition, Governance and Performance raises awareness of the requirements of the GLA s Data Quality Framework by reviewing and suggesting amendments to the Definition Forms submitted by Performance February 2015 Performance Management Analytical Review Follow Up 3

framework and the Use of Statistics Code of Practice. Leads. 9.9 By not making it publicly clear the means by which KPI data is generated could undermine confidence in the validity of the performance data which is being produced and reported. 2 The detailed definition behind each KPI is published so it is clear on what basis each KPI is calculated. The Finance & Performance Monitoring Report and the Mayor of London s Annual Report should make it clear when provisional or estimated data is used in the place of what would normally be confirmed data. All KPI Information Sheets have been published on the GLA website. Quarterly Finance and Performance Reports to the Budget Monitoring Sub- Committee make it clear in the commentary when provisional and estimated data are used. KPI Information Sheets will be published. December 2014 February 2015 Performance Management Analytical Review Follow Up 4