How to Design and Build a Fence/G traverse Bridge or Graffiti Project

Similar documents
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Table of Contents 16.1 GENERAL Overview Responsibilities

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

COSMOS 2012: Earthquakes in Action COSMOS 2012

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

ENCE 4610 Foundation Analysis and Design

Table of Contents. July

Safe & Sound Bridge Terminology

Geotechnical Building Works (GBW) Submission Requirements

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

Informational Workshop Public Meeting Kanawha Falls Bridge Project

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Washington ,

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations

BUTE Department of Construction Management and Technology

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

The unit costs are based on the trend line of the 3 low bids for the average quantity.

3.1 Historical Considerations

SECTION 5: SANITARY SEWER SYSTEM DESIGN

PILE FOUNDATIONS FM 5-134

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

How To Model A Shallow Foundation

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Porous Pavement Alternatives Cost Analysis

SECTION EARTH MOVING

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

EXECUTIVE SUMMARY CHAPTER 6

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

BRIDGES ARE relatively expensive but often are

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Soils, Foundations & Moisture Control

Chapter 7 Substructure Design General Substructure Considerations Foundation Design Process

4.11 Geologic and Soil Resources

Block and Gravel Inlet Protection (BIP)

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Emergency repair of Bridge B421

Soil Screw Design Manual Edition 2

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S HOUSTON, TEXAS

Project Manager & Key Staff Standards for Technical Proposals Projects using Level A and/or Level B prequalification disciplines

90 Brighton Road, Surbiton, Surrey

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

Design and Construction of Auger Cast Piles

How To Design A Foundation

CIVL451. Soil Exploration and Characterization

Caltrans Geotechnical Manual

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Designed and Engineered to Perform

5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

How To Check For Scour At A Bridge

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

SECTION 1 GENERAL REQUIREMENTS

Preliminary Foundation Evaluation Oakland Army Base Reuse Study

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

AUSTRALIAN PAVING CENTRE

Evaluating the Condition of Seawalls/Bulkheads

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

The URETEK Deep Injection Process (UDI) For Roadways and Building Structures

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS

Dewatering - Time and Cost Relief by way of Trenchless Construction

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

Section 2100-Trenching and Tunneling

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

Prattsville Berm Removal Project. 1.0 Project Location

3 Tappan Zee Bridge Rehabilitation Options

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Alternatives Presentation Meeting Middlebury WCRS(23)

Division 2 Section Section 02795

817 - PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS & END SECTIONS SECTION 817

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Contractor of the Year

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

Transcription:

Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos

Project Location Project Limits: The Grand River east to Fuller Ave.

Project Description 1.75 miles of full depth road reconstruction with additional third through lane and merge weave lanes 4,000 feet of soldier pile & lagging Retaining Wall Replacement of five structure crossings: Coit Avenue over I-196 Eastern Avenue over I-196 Lafayette Avenue under I-196 Diamond Avenue over I-196 Fuller Avenue over I-196

Project Description Project Cost: $40 Million Schedule: Design Phase Summer 2007 Spring 2009 Bid Letting September 2009 Construction Start April 2010 Substantial Completion - November 2010

Project History Original freeway designed in 1962 and opened by 1964 Typical urban depressed limited access roadway Original bridges constructed as three or four span structures Substructures Pile supported abutments (40 ton CIP Concrete) and spread footing piers and abutments

Original Bridges Coit Avenue

Original Bridges Lafayette Avenue

Original Bridges Eastern Avenue

Original Bridges Diamond Avenue

Original Bridges Fuller Road

Site Constraints 130 ft. St. Isidore Church Constructed in 1897 130 ft

Photo courtesy of mlive.com

Site Constraints Grand Rapids Medical Mile: Van Andel Institute, Grand Rapids Community College's Calkins Science Center, Spectrum Health's Butterworth Hospital complex, Grand Valley State University's Cook-DeVos Center for Health Sciences, and Michigan State University Secchia Center Medical School

Photo courtesy of MDOT Grand Rapids TSC

Geotechnical Investigation Coit Ave., Lafayette Ave., and Eastern Ave. bridge designs began in 2006, at the beginning of when MDOT fully adopted the AASHTO LRFD Design Method. Final Geotechnical Investigation included performing borings for substructures, retaining walls, roadways, and signs. In total 17 bridge borings, 12 retaining wall borings (and 15 misc. borings (signal poles, signs, ITS) were performed over a 2 year period.

Generalized Soil Profiles Lafayette Bridges: Loose sand fill down to 15 25 ft.± Dense to extremely dense sand to 85 ft.± (EB/south side) V. stiff to hard clay strata within similar extremely dense sand to 90 ft.± (WB/north side) Coit Bridge: Surficial sand fill down to 5 ft.± Loose to med. dense sand to 40 ft.± Alt. layers of hard clay and v. dense sand, 40 to 90 ft.±

Eastern Bridge: Surficial fill down to 5 ft.± V. loose to med. dense sand, increasing to med. dense to v. dense to 75 ft.± (with cobbles/boulders!) Hard clay/clayey silt to 100 ft.± Diamond Bridge: Loose to med. dense sand, transitioning to extremely dense to 100 ft.± (occ. clay layers below 50 ft.) Fuller Bridge: Loose to med. dense sand to 9 to 17 ft. ± depth Alt. sand, clay, silt, and gravel strata to 95 to 115 ft.± (occ. cobbles below 50 ft.) strength increasing with depth (extremely dense/hard)

Foundation Design Designed per AASHTO Load Resistance Factor Design Manual Section 10.7.3 Preliminary Options: Driven H Piles HP14x73 at 600 kips nominal resistance HP12x53 at 400 kips nominal resistance Spread footings Service and Strength Limit State considerations Benefit of depressed freeway and prior loading

Foundation Selection Criteria Vibration considerations Limiting vibrations to adjacent sensitive structures 100 year old Church Medical Facilities (underground tunnels) Considerations for Shakedown Settlement (Service Limit State) Overlaying new structure footprint versus existing. Strength Limit State Looser soils with groundwater

Pile Foundation Design Iteration Pile Size and Maximum Nominal Pile Driving Resistance (R ndr ) selection Per MDOT Bridge Design Manual 7.03.09.1 Estimate Pile Tip Depth/Elevation Per AASHTO LRFD Sec. 10.7.3.8.6. Refine Estimated Pile Tip Depth/Elevation based on structural loading Perform lateral pile analysis and determine Point of Fixity Again refine Estimated Pile Tip Depth/Elevation based on structural loading

Spread Footing Design Iteration Determine the Bearing Elevation of the footing Provide the Service Limit State and Strength Limit State soil pressures (preliminary design) Provide effective footing widths based on site constraints and preliminary design loading (ranges of B and associated bearing resistances). Evaluate the strength limit state of the soils per AASHTO LRFD Sec. 10.6.3 Evaluate the service limit state of the soils per AASHTO LRFD Sec. 10.6.2

Specific Example Fuller Bridge & Wall Collaboration FOUNDATION SELECTION H-piles and pipe piles considered, but not preferred due to vibrations adjacent existing structure for part-width construction. Concerns with spread foundations due to loose sand soils and high groundwater at bearing elevation in some locations. Improvement options included extending footing deeper, remove and replace, or in-situ densification.

Soil and groundwater limitations related to both design and potential impacts during construction were discussed with the Bridge Engineer in order to design an appropriately-sized spread foundation that achieves the required resistance, minimizes differential settlement, and can also be practically constructed.

A spread foundation option was ultimately selected, achieved through a remove and replace operation. Where excavations encountered groundwater, large aggregate was worked into the subgrade for stabilization.

CONSTRUCTION ISSUES Temporary Retaining Wall for Part-Width construction Retained soil generally consisted of uniformly graded sand or sand fill (consistent with MDOT Class II or III sand gradations). Due to concerns with vibrations, a cantilever soldier pile/lagging wall system was selected.

RETAINING WALL ALONG I-196 URS worked closely with Somat to develop active and passive earth pressures for 4000 of soldier pile wall Large storm sewer was to be installed in front of the retaining wall after the wall was constructed. The pipe was to be located as close as 20 feet to the wall face. The pipe invert was to be situated at about 10 feet below the base of the exposed wall face. Excavation below the wall would compromise the passive resistance relied on in the retaining wall design. A temporary stabilizing berm was to be placed.

Conceptual Cross-Section

Summation Having the knowledge of subsurface conditions (or potential) during the planning/ pre-design phase has time-saving and cost-saving benefits to your project. Maintaining project-long (and open) communication between geotechnical and structural engineers is mutually beneficial.

Photo courtesy of MDOT Grand Rapids TSC

Photo courtesy of mlive.com

Photo courtesy of mlive.com

Photo courtesy of mlive.com

Photo courtesy of MDOT Grand Rapids TSC

Photo courtesy of MDOT Grand Rapids TSC