Employing Appropriate Software for Dam break Analysis and Flood Line rendering



Similar documents
FLOODPLAIN DELINEATION IN MUGLA-DALAMAN PLAIN USING GIS BASED RIVER ANALYSIS SYSTEM

USSD Workshop on Dam Break Analysis Applied to Tailings Dams

2D Modeling of Urban Flood Vulnerable Areas

Using GIS Data With HEC-RAS

COMPARING DSS-WISE- LITE TO OTHER DAM BREACH SOFTWARE

SIMPLIFIED INUNDATION MAPS FOR EMERGENCY ACTION PLANS. National Dam Safety Review Board Emergency Action Plan Workgroup

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

Environmental Data Management Programs

USING DETAILED 2D URBAN FLOODPLAIN MODELLING TO INFORM DEVELOPMENT PLANNING IN MISSISSAUGA, ON

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference

Quality Assurance Reviews of Hydraulic Models Developed for the Central Valley Floodplain Evaluation and Delineation Program

Appendix 4-C. Open Channel Theory

Performing a Steady Flow Analysis

Designing a Basic White Water Canoe/Kayak Course using InfoWorks ICM

A Method Using ArcMap to Create a Hydrologically conditioned Digital Elevation Model

Evaluation of Open Channel Flow Equations. Introduction :

Emergency Spillways (Sediment basins)

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

Using HEC-RAS for Dam Break Studies

HEC-RAS. River Analysis System. Applications Guide. Version 4.1 January US Army Corps of Engineers Hydrologic Engineering Center CPD-70

DAM BREACH MODELING AN OVERVIEW OF ANALYSIS METHODS. Tony L. Wahl, Hydraulic Engineer, Bureau of Reclamation, Denver, CO,

Impact of water harvesting dam on the Wadi s morphology using digital elevation model Study case: Wadi Al-kanger, Sudan

SIMULATION TIGRIS RIVER FLOOD WAVE IN MOSUL CITY DUE TO A HYPOTHETICAL MOSUL DAM BREAK

Modelling of Urban Flooding in Dhaka City

Notable near-global DEMs include

How To Understand And Understand The Flood Risk Of Hoang Long River In Phuon Vietnam

Management of flooding downstream of dams

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

The Alternatives of Flood Mitigation in The Downstream Area of Mun River Basin

Modelling Flood Inundation of Urban Areas in the UK Using 2D / 1D Hydraulic Models

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation)

TVM 4155 Numerical modelling and hydraulics 10. March OpenFOAM homework

Dam-break flood plain model by WMS

3D Model of the City Using LiDAR and Visualization of Flood in Three-Dimension

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used:

Application of Google Earth for flood disaster monitoring in 3D-GIS

DEVELOPING AN INUNDATION MAP STANDARD FOR THE U.S. ARMY CORPS OF ENGINEERS

Interactive comment on A simple 2-D inundation model for incorporating flood damage in urban drainage planning by A. Pathirana et al.

Experiment (13): Flow channel

Estimating Potential Reduction Flood Benefits of Restored Wetlands

AZ EGER-PATAK HIDROLÓGIAI VIZSGÁLATA, A FELSZÍNI VÍZKÉSZLETEK VÁRHATÓ VÁLTOZÁSÁBÓL ADÓDÓ MÓDOSULÁSOK AZ ÉGHAJLATVÁLTOZÁS HATÁSÁRA

Aneeqa Syed [Hatfield Consultants] Vancouver GIS Users Group Meeting December 8, 2010

Guide To Bridge Planning Tools

CLEARWATER DAM BLACK RIVER, MISSOURI MAJOR REHABILITATION STUDY

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African

STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES DIVISION OF WATER RESOURCES GUIDELINES FOR DAM BREACH ANALYSIS

ANALYSIS OF A ANTROPIC INFLUENCES IN A FLOODPLAN

ADDING VALUE TO BOM FLOOD PREDICTIONS (WITHOUT MESSING AROUND WITH MODELS)

Department of Energy and Water Supply

Flooding in Urban Areas - 2D Modelling Approaches for Buildings and Fences

Chapter 9. Steady Flow in Open channels

THE UNIVERSITY OF TRINIDAD & TOBAGO

ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2015

Effect of barrages on water level in estuaries

Storm Drainage Systems

Sample Micro Hydro Initial Report

A Flood Warning System for City of Findlay, Ohio

Request for Proposals for Topographic Mapping. Issued by: Teton County GIS and Teton County Engineering Teton County, Wyoming

Prepared by. Drew Davidge

Exercise (4): Open Channel Flow - Gradually Varied Flow

ATTACHMENT 8: Quality Assurance Hydrogeologic Characterization of the Eastern Turlock Subbasin

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT

A Conceptual Software System for Water Allocation, Planning and Catchment Management

Rural Flooding: The Potential Role of Forestry

Ruissellement du Bassin Précipitation Abstractions Hydrogramme Flux de Base. Superposition Routage

SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2

Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets

Open Channel Flow. M. Siavashi. School of Mechanical Engineering Iran University of Science and Technology

CITY UTILITIES DESIGN STANDARDS MANUAL

Outlet stabilization structure

M6a: Open Channel Flow (Manning s Equation, Partially Flowing Pipes, and Specific Energy)

CHAPTER 2 HYDRAULICS OF SEWERS

Hydrologic Engineering Techniques for Regional Water Resources Planning

APPLICATION OF GIS AND REMOTE SENSING IN IRRIGATION NETWORKS MANAGEMENT

MAPPING THE ST. FRANCIS DAM OUTBURST FLOOD WITH GEOGRAPHIC INFORMATION SYSTEMS

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Chapter 13 OPEN-CHANNEL FLOW

Index-Velocity Rating Development (Calibration) for H-ADCP Real-Time Discharge Monitoring in Open Channels

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.

...Eq(11.6) The energy loss in the jump is dependent on the two depths y 1 and y 2 3 = E =...Eq(11.7)

Minnesota State Plan Review Level 2 Hazus-MH 2.1 County Model for Flooding Dakota County Evaluation

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Dam Break Risk Assessment in Baker Valley (Chilean Patagonia)

Head Loss in Pipe Flow ME 123: Mechanical Engineering Laboratory II: Fluids

Geoprocessing Tools for Surface and Basement Flooding Analysis in SWMM

Available in Base or Survey Standard or Survey Professional series with different modules add-ons to suit your technical requirement and budget.

Catchment Scale Processes and River Restoration. Dr Jenny Mant The River Restoration Centre therrc.co.uk

GEOENGINE MSc in Geomatics Engineering (Master Thesis) Anamelechi, Falasy Ebere

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND

The guide uses the example files provided with Flood Modeller. Depending on your operating system these are located at:

Assessment of hydropower resources

HYDROGRAPH ROUTING. E. Input data needed for channel routing include the inflow hydrograph and the channel characteristics

Managing sewer flood risk

Hydraulic Jumps and Non-uniform Open Channel Flow, Course #507. Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC

How To Develop A Flood Risk Map

Transcription:

Employing Appropriate Software for Dam break Analysis and Flood Line rendering 1. Background The specialist field of Dam Safety has been developing in SA since about the 80 s. This has led to a well-developed statutory arrangement at present. Apart from the dam structural safety and (spillway) operational adequacy reevaluation required for DAM SAFETY investigations, the hazard that such a dam hold when it would fail has become one of the prominent parts of this field of engineering. Techniques to analyse the extent of damage that may occur due to the (dam break) flood released out of the dam basin has been developing continuously.

Two Scenarios of possible dam-break situations have been recognised. One being the obvious cause of spillway inadequacy, i.e. flood induced failure, and subsequent washing out of the structure due to erosional action or high dam level hydrostatical (concrete wall) structural collapse. This is thus associated with an extreme incoming flood. Another potential dam-break situation, the so-called sunny-day or clear-sky situation, would be associated with a developing weakness of the dam during normal full-dam operational conditions. Examples are the piping failure of earthfill dams or exceptional earthquake accelerations on concrete dam walls. The latter scenario may be associated with more of a lack of pre-warning of the imminent dam collapse.

Dam-break flood lines are required over the range of river downstream over which it has a significant influence. The criteria typically used to define the end of influence downstream, are as follows: o The position where the flood level do not substantially overtop the river bank o The dam-break flood attenuated to less than the general maximum allowed flood level for typically a new town development, i.e. typically the 100-year flood for the overall catchment. Another related criterion often used is the position where the dam-break peak flow has attenuated to the dam basin incoming flow peak typically say the RMF. o The position from where no more substantial development occurs downstream in the potentially flooded area. Constraints to the level of analysis to be done is created by o Available time or budget. o The degree of development downstream of the dam will also indicate what level of analysis (or depth of study) needs to be done. Smaller Category II dams would typically require only a simplified analysis say with SMPDBK.

o The great uncertainties involved in the estimation of the magnitude of dam-break that may occur (water levels downstream found to be insensitive to flow variations in any way) o The low resolution of topographic maps that is often only available. o The analysis described below could be considered more suitable for higher levels of analysis. The aim of this presentation is to provide a basic framework and understanding for the reader to start a dam break analysis with HEC-Ras. It is intended to be useful for both the beginner and the more experienced dam break analysis.

2. Software & Data Software has been developed to give increasingly accurate and timeefficient results. The mechanistic SMPDBK software has been the most popular so far for smaller dams. Full hydrodynamic software is also been developed and generally applied. These include DAMBRK/FLDWAV, Mike 11 and HEC-Ras. At present the inclusion GIS/DTM utility software*) is becoming increasing popular due to the time-efficiency thereof. Though 2D hydrodynamic software is becoming more feasible within the constraints mentioned above, the focus here is on the 1D analysis done by the software above. A few situations have been identified where a 2D analysis could be required. *) GeoRas, RiverCAD, Aquaveo WMS etc.

Available DATA in terms of image or digital maps, varies from: 1:50000 (20m contour) maps (- employ for level calibration of SRTM), 5 m contour Orthophoto image maps, 5 m DTM digital files (available in shp format), 25 m grid DEM files, 90 m grid satellite DEM files (SRTM) level needs calibration (typically 3 to 6 meters), to aerial surveyed maps (Lidar for example). Where only a single case needs to be analysed it could be worthwhile to employ CAD software to abstract cross-section dimensions and manually read in the figures into HEC-Ras Geometric window as shown in the abstract below. Otherwise there is efficient GIS/DTM software available to enhance the abstraction of the river data for direct input into HEC-Ras. The same software is then again employed to plot flood lines from the resulting flood levels from the (HEC-Ras) hydrodynamic analysis.

3. Features of HEC-Ras employed The analytical procedure for various dam cases is usually very casespecific, but the general approach thereof is presented below. A General Basic procedure involved in doing a dam-break analysis is first shown below. With this presentation it is assumed that the reader has adequate knowledge of doing at least a Steady State Analysis with HEC-Ras. The use of GIS/DTM utilities does not fall in the scope of this presentation, but is only referred to occasionally. The focus here is on Dam-break analysis only. Additional features found useful will be presented afterwards.

RELEVANT SEQUENTIAL MENU ITEMS FOR DAM BREAK ANALYSIS 1 Geometric Data 2 Steady Flow Input 3 Run Steady Flow Analysis 4 Unsteady Flow Input 5 Run Unsteady Flow Analysis 6 Stage & Flow Hydrographs 7 View (Longitudinal) Profiles 8 View Cross-sections 9 Summary Output tables

1. GEOMETRIC DATA PAGE/WINDOW Cross-Section Editor Upstream vs Downstream Section PONGOLAPOORT DAM MANUAL INPUT FROM CAD CROSS-SECTION MEASUREMENTS ON 20 METER BACKGROUND IMAGE

Berg River Dam: Illustration of Cross-section dimensions from CAD for FLDWAV

DE HOOP DAM AUTOMATIC RIVER CROSS-SECTION DATA IMPORT FROM GIS/DTM UTILITY SOFTWARE

1.2 PONGOLA DAM ARCH WALL -

1.2.1 Dam wall Definition 1.2.2 Flood Gates detail

1.2.3 BREACH DATA

1.3 Tables/Friction definition Typical values recommended SMPDBK summarised. - The Manning roughness coefficient for out-of-bank flows may be estimated to be 0.04 to 0.05 for a cross section located in an area where the overbank is pastureland or cropland, 0.07 for a moderately wooded area, and 0.10 to 0.15 for a heavily wooded area, Built up areas about 0,10. Overall resistance of whole cross-sections can be simply selected as similar for the high flow stage usually involved here..

1.4 Tools/Cross-section Interpolation very useful to obtain stable solution.

2. Steady Flow Data Input to check data Boundary Conditions PONGOLAPOORT DAM Downstream Condition - Sea Level Maputu Bay

3. STEADY FLOW ANALYSIS

4.UNSTEADY FLOW DATA

5. UNSTEADY FLOW ANALYSIS RUN Options/Output Locations for hydrograph plots

6. STAGE & FLOW HYDROGRAPHS PLOT PONGOLA POORT DAM Cross-section upstream of wall

7. PROFILE PLOT CONDITION WITH UPSTREAM HEADING SURGE IN GORGE UPSTREAM

8. VIEW BREACH DEVELOPMENT SIMULATION CROSS SECTION-WISE

9. SUMMARY OF OUTPUT RESULTS BASIC SOURCE FOR DELIVERABLES FILE COPY TABLE => EXCEL FOR EXAMPLE OPTIONS INCLUDE INTERPOLATED CROSS-SECTIONS - DEFINE TABLE

DEFINE TABLE

Further Features to expedite the process and help with finding satisfactory results: In the case where cross-sections is extracted from DTM map files of relative large contour spacing, say 5 or 20 m, GIS utility software creates unrealistic flat terrain downstream between the contours. To manage this, the crosssection lines can be place just downstream of the position where the contour runs through the river thalweg. The interpolation facility of HEC-Ras can then be used to define the riverbed in between for an initial run. Ideally hard breaklines should be used to define the river thalweg between the contour river crossings in cases like the above-mentioned, else the pilot channel feature in HEC-Ras can be used to serve as guide to manually adapt the cross-section of the in-between sections. These would however need to be adapted again every time a new updated set of river data is imported from a GIS/DTM utility. GIS software procedures (for ArcGIS) has been developed elsewhere to expedite automatization of this riverbed generation.

When importing cross-sections from a DTM utility software Point Filtering would be mostly required to limit the volume of data used in the routing analysis.

Run a Steady State flow analysis with a number of flow value that cover the range of expected flow over the length of reach to check for any errors or unrealistic results. To expedite the analysis, leave out the bank station definition. Employ the River bank estimation feature in the Geometric Data page in the Tools/Channel bank stations tab. The water level from a low steady flow value which would remain inside the river channel, say the 2-year to 5-year flood, will then be used in the software to define the bank stations.

First only run the analysis without the Post Processing. Use the Hydrograph tab to test for reasonableness of results. Check for Smooth hydrographs up to the end of the model reach. When running the Post Processing part in the analysis, a longitudinal water level simulation run will be of value to identify where instabilities still exists.

In order to hydrodynamically include the dam basin in the overall model of the study, three approaches for dam pool routing can be used: 1. Ideally topographic surveys may be available from which appropriate crosssection can be extracted giving an accurate result of the basin depletion during the dam wall breaching and afterwards. 2. Such topographic maps of the dam basin is however often not available. A reasonable simplified representation of the basin which should have fairly satisfactory depletion reaction during the dam-break, can be made. Employing a simple geometric shape like a horizontally positioned pyramid can be used. The length (height) of the pyramid then equals the length of the basin and the end surface area near the dam wall is calculated according to the volume of a pyramid corresponding to the basin volume. A triangular shaped end shape is usually appropriate. See shape employed previously for De Hoop dam below. Other simplified shapes can be used to give a fair representation of the basin as shown in the second figure of the upper part of Pongolapoort dam basin.

Simplified Pyramidal dam basin representation at De Hoop dam Wide opening up dam basin of Pongola poort dam

It has been experienced that a simplified synthetic compilation of the dambreak flood hydrograph by empirical formulae determination of the peak flow and volume of basin (and flood) represented by a triangular hydrograph flow distribution, gives satisfactory results as well.

4. Sources of Dam break parameter estimation: a) SANCOLD Guideline

b) SMPDBK Peak flow calculation: Instantaneous failure:

c) Empirical models Summarised and evaluated by Wahl (2001)

Those models marked above that have been judged as well rated, has been applied with satisfactory results in various cases. In general the breach-width and failure time have been successfully used in HEC-Ras and the Peak flow estimations mentioned above used to verify the analytical results

5. Case Studies & Deliverables with Recommendations The items listed above have been taken from the HEC-Ras manual as well experience with applications in numerous cases over time. Case studies: Experience with challenges and practical application development over time. Impofu dam (2013)

Pyramidal dam basin shape

Spit at estuary downstream of marina. A 2D analysis may be worthwhile here. Simply assumed that sand spit would wash out rapidly.

Fika Patso (Phutadidjaba Qwa-Qwa) (2013) Pyramidal dam basin

Development close to river

Attenuation due to storage clearly evident in position downstream with relative large tributary. Compare Peak flow to flow at maximum water surface at chainage 21 000 to 23 000 m

De Hoop (2014) Complicated topographical model End of Influence 300 km downstream at Phalaborwa Barrage due to lack of substantial development downstream. Small volume of breached Phalaborwa Barrage plays insignificant role.

Nhlaralumi River (Timbavati NR) (2014) This was a set of four earthfill dams, 5 to 9 m high, situated over a reach of 10 km on the Nhlaralumi River which all failed due to flooding in 2012. This occurrence was simulated by a System analysis in one model. Relative good resolution topographic DEM maps at 25 m grid spacing was available. An Empirical parameter prediction according to the methods mentioned above proved to closely correspond to Surveys of the breached dam walls. The figure below show the HEC-Ras representation of the dam wall profiles with fully developed breaches.

Resulting flood levels compare with observed without an iterative process. Surveyed marks at right flank of Argyle #2 probably left during dropping flow.

Small Length of dambreak flood influence downstream. (Increasing inflow from tributaries over reach assumed) All dams are planned to be rebuilt. The upper two was previously classified as Category I dams, while the lower two is recommended to be classified as Category II.

Shiloh (21 m) & Seroala (12 m) (2014) These studies served as trial run for first level analyses. Shiloh 90 m grid DEM Seroala (Thaba Nchu)

Topographical maps 90 m & 25 m DEM Downstream structures Development: Shiloh passing through town of Whittlesea. Loskop (2014) Topographical map 25 m DEM Bridge effect considered due to high development. Modelled as both bridge structure and in-line structure to employ dam-break feature of HEC-Ras. Minor increase of 6 to 17 % in flow obtained. Very little effect on water level. Effect at Flag Boshielo At entering this dam the peak is substantially reduced from 14000 m3/s to 10000 m3/s. The fuse plug breaching could however again cause a minor increase in flow. Dam level can rise to 0,6 m below NOC.

Doorndraai (2015) Triangular Dam-break flood synthetically compiled from empirical prediction and dam storage volume. Bridges assumed to play no role. Proportion of Flow area on overbank employed to judge end of influence. Little development far downstream.

Deliverables: The deliverables from the analysis can to a large extent be obtained from the output table. The required items would usually entail the following: a) Water level reached b) Water depth the accuracy of such values is very dependent on the quality of the topographic map. Quite often low accuracy/resolution of riverbed level prevent a reliable values. c) Velocity Due to highly two dimensional velocity distribution in river flow, 1D analyses cannot accurately predict the velocity distribution over the width of the section and especially so on the overbank flow. The average velocity output in the channel can however still serve as good indication. d) Travel time this is an important factor in the compilation of preparedness plans. The arrival time of the flood, i.t.o. for example reaching of the river bank level need to be determined from the hydrograph output at the cross-sections required.

e) A further related factor would be the period of inundation which also can be determined from the hydrograph output. The period is required to plan post-flood remedial activities to get services functional again. f) For assessing the possible damage and lives lost the rate of water depth rise at some characteristic depth, would be useful. g) Plotted flood lines. Mark out chainages. Various cases evaluated can be indicated in separate colours for distinction on the same map. Generation of.kmz Google Earth files is very useful as the development changes along the flooded area.