State Data Center. VMAX Data Migration Guide



Similar documents
Planning and Administering Windows Server 2008 Servers

Planning and Administering Windows Server 2008 Servers

Draft Copy. Change Management. Release Date: March 18, Prepared by: Thomas Bronack

Systems Support - Standard

R3: Windows Server 2008 Administration. Course Overview. Course Outline. Course Length: 4 Day

BridgeConnex Statement of Work Managed Network Services (MNS) & Network Monitoring Services (NMS)

Managing and Maintaining Windows Server 2008 Servers

Planning and Administering Windows Server 2008 Servers

State Data Center (SDC) Plan Update (Draft) June, 2013

M6430a Planning and Administering Windows Server 2008 Servers

Managing and Maintaining Windows Server 2008 Servers (6430) Course length: 5 days

[name of project] Service Level Agreement

Enterprise UNIX Services - Systems Support - Extended

Request for Proposal for Application Development and Maintenance Services for XML Store platforms

For more information, please visit the IST Service Catalog at

IT Service Management

Departmental On-Site Computing Support (DOCS) Server Support SLA

Information Technology Engineers Examination. Information Technology Service Manager Examination. (Level 4) Syllabus

NYSED DATA DASHBOARD SOLUTIONS RFP ATTACHMENT 6.4 MAINTENANCE AND SUPPORT SERVICES

Cisco Change Management: Best Practices White Paper

Course Syllabus. Planning and Administering Windows Server 2008 Servers. Key Data. Audience. At Course Completion. Prerequisites. Recommended Courses

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

Title: DISASTER RECOVERY/ MAJOR OUTAGE COMMUNICATION PLAN

INFORMATION TECHNOLOGY SERVICES IT CHANGE MANAGEMENT POLICY & PROCESS

Change Management Process. June 1, 2011 Version 2.7

Release Management Policy Aspen Marketing Services Version 1.1

Data Center Colocation - SLA

Change Management. Service Excellence Suite. Users Guide. Service Management and Service-now

White Paper August BMC Best Practice Process Flows for ITIL Change Management

Project Implementation Process (PIP)

MANAGED SECURITY SERVICES RESPONSIBILITIES GUIDE July 2013

Service Level Agreement and Management By: Harris Kern s Enterprise Computing Institute

A Systems Implementation Project Planning Guide. Solutions & Project Management Services for Systems & Operations Projects

SAP ERP Upgrade Checklist Project Preparation

Network Computing Architects Inc. (NCA) Network Operations Center (NOC) Services

PHASE 5: DESIGN PHASE

IBM Smartcloud Managed Backup

Policies of the University of North Texas Health Science Center

PHASE 6: DEVELOPMENT PHASE

APPENDIX 5 TO SCHEDULE 3.3

Change Management Process Guide

Request for Proposal Technology Services Maintenance and Support

ESXi Cluster Services - SLA

PHASE 6: DEVELOPMENT PHASE

Configuration, Change, and Release Management Policies and Procedures Guide

Introduction Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons RFC Procedures... 5

OFFICE OF THE CHIEF INFORMATION OFFICER

California Department of Technology, Office of Technology Services WINDOWS SERVER GUIDELINE

BUSINESS SYSTEMS ANALYST I BUSINESS SYSTEMS ANALYST II

ITIL Roles Descriptions

HP Data Replication Solution Service for 3PAR Virtual Copy

Operating and Service Level Objectives

Cloud IU for SharePoint. Service Description

SCOPE: Role Descriptions/Job Profiles

Strategic Transformation and Mainframe Services Project. Project Summary

Information & Technology Management Branch Ministry of Education. Change Management Policy

HP 3PAR StoreServ Data Migration Service

BTInet Backup-to-Disk Managed Backup Service (EMC Avamar) Service Level Agreement (SLA) Table of Contents

Yale University Change Management Process Guide

Information & Technology. Change Management Policy

Business Continuity Planning (800)

ENABIL Managed Services

Service Level Agreement (SLA)

Title: DESKTOP TICKET MANAGEMENT PROCEDURE

IT Security Agency Policies and Procedures

CLOUD SERVICE SCHEDULE Newcastle

Best practices for data migration.

Internal Controls And Good Utility Practices. Ruchi Ankleshwaria Manager, Compliance Risk Analysis

Workshop 5051A: Monitoring and Troubleshooting Microsoft Exchange Server 2007

LEARNING SOLUTIONS website milner.com/learning phone

Online GDR System VENDOR USER GUIDE

SERVICE SCHEDULE INFRASTRUCTURE AND PLATFORM SERVICES

DATA RECOVERY SOLUTIONS EXPERT DATA RECOVERY SOLUTIONS FOR ALL DATA LOSS SCENARIOS.

Storage Area Network (SAN) Services - SLA

Server Monitoring: Centralize and Win

Creating a Business Continuity Plan. What We ll Cover... What is a BCP? Micky Hogue, CRM

Process Description Incident/Request. HUIT Process Description v6.docx February 12, 2013 Version 6

Select IT Consulting Services RFP Technical and Network Support Specialist Services (Lot Group C)

COUNTY OF ORANGE, CA Schedule 2D Service Desk Services SOW SCHEDULE 2D SERVICE DESK SERVICES SOW. for. Date TBD

Best Practices Report

BMC Service Assurance. Proactive Availability and Performance Management Capacity Optimization

Supporting GIS Best practices for Incident Management and Daily Operations

ITD BACKUP MANAGEMENT PROCEDURE

CONFIGURATION MANAGEMENT PLAN

DEPARTMENT OF LABOR AND EMPLOYMENT DISASTER RECOVERY AND BUSINESS RESUMPTION CONTINGENCY PLANNING GUIDELINES

IT General Controls Domain COBIT Domain Control Objective Control Activity Test Plan Test of Controls Results

Microsoft Project Server 2010 Administrator's Guide

Statement of Work. LabTech Implementation Bronze. LabTech Software 4110 George Road Suite 200 Tampa, FL 33634

APPENDIX 3 TO SCHEDULE 8.1

Transcription:

State Data Center VMAX Data Migration Guide Version 1.0 June 26, 2013 Prepared by: Steve Lovaas, Enterprise Projects Client Liaison

Contents DOCUMENT REVISION HISTORY... 3 INTRODUCTION AND PURPOSE... 4 DOCUMENT STRUCTURE... 4 DOCUMENT SCOPE... 5 SECTION 1 SERVER DATA MIGRATIONS... 6 MIGRATION TASKS... 6 APPENDIX A VMAX DATA MIGRATION CHECKLIST... 11 2

Document Revision History Description of Change Page or Section Date Revised Reviser Published first draft All 6/26/13 Steve Lovaas 3

Introduction and Purpose The purpose of this Migration Guide is to define the steps that Consolidated Technology Services (CTS) and customer staff will take to complete readiness tasks necessary for the migration of systems to the State Data Center (SDC). It also contains the migration and post migration tasks needed to fully complete the migration effort. This Guide documents the key activities to be coordinated by the customer s Agency Implementation Coordinator (AIC) in preparation for each system migration. These activities are summarized in a checklist that will be used to track completed activities and when complete signifies that the system is ready for migration scheduling. Completion of these activities is critical to migration success and will help to minimize any unplanned service disruption. The AIC serves as the primary customer contact and is responsible for coordinating the internal customer activities stated in the Guide. When all tasks are complete the AIC will submit customer acceptance for cutover to the CTS Enterprise Projects Client Liaison asserting the customer s readiness to proceed with the migration. This may be provided in the form of a signed checklist or email confirmation. Upon receipt CTS assigned Project Manager will review and either a) confirm readiness or b) return the checklist for further work. After readiness is confirmed by CTS, migration work and related activities will begin. All system migrations are coordinated through an overall project schedule. A Migration Calendar has been published reflecting SDC migration activity. Document Structure As agencies progress through the Guide, they will see prerequisite tasks that: Must be completed internally by the customer agency Must be completed by CTS staff Must be completed in coordination with CTS Each task is prefaced with a table entry that contains a column each for identifying the primary party responsible for completing the work activity, a task number and a relative description. The table below provides a brief sample: Party Task # Task Description Customer 1 Prerequisite task that must be completed by the customer agency CTS 2 Prerequisite task that must be completed by CTS Each table entry will be followed by a more detailed description of the work to be accomplished for that task. Migration tasks have been organized in a general chronological order. Please Note: All migration tasks have been built to include a wide range of scenarios and not all tasks apply to every migration these tasks will be clarified for each migration with the appropriate party during the planning phase. Agency Implementation Coordinators will interface with the CTS Enterprise Projects Client Liaison to review any questions regarding this Guide. 4

Document Scope The SDC migration projects that will impact customers have been organized into service areas to help CTS manage and communicate regarding the migrations. Three SDC migration projects are currently underway: CTS Move Phase 1 - This project will focus on moving selected CTS equipment that best alleviates the heat issue in OB2. This phase will move the following primary areas: o Servers o Messaging o Security o Telecommunications o Network o Mainframes Firewall - This project will replace aged and over-capacity firewalls. It will also deliver enhanced data security services such as enterprise logging and event correlation, and intrusion detection/intrusion prevention. VMAX Data Migrations This project will focus on migrating data from the old storage arrays in OB2 to the VMAX located in the SDC. This Guide addresses VMAX Data Migrations and includes the following: Section 1: Server Data Migrations (including Al A Carte Customers) Section 2: Mainframe Data Migrations The data being migrated in the VMAX Data Migration Project are managed by CTS Storage & Server Administrators, and / or Customer Administrator s. A majority of the tasks performed for these migrations will be performed by CTS in collaboration with the customer. Customer tasks will primarily include: Approving the schedule for the migration Approving new storage quotes Participating in the planning effort Freezing application and system changes prior to the move Verifying the system is performing as expected after the migration 5

Section 1 Server Data Migrations The following tasks apply to storage data migrations: Migration Tasks 30 TO 60 DAYS BEFORE MIGRATION CTS Client Liaison 1 Identify migration team including customer contact(s) CTS Client Liaison 2 Schedule migration planning session(s) The CTS Client Liaison must work with the CTS project manager and the AIC to identify the resources required migrating and validating the system. This data migration team will perform the migration and verification activities. The CTS Client Liaison will facilitate meetings needed to plan and coordinate the migration. CTS & Customer 3 On-boarding process This activity will provide the data migration team with the requirements and migration strategy needed for the data migration. At the end of this activity a quote will be produced for the customer, the quote must be approved before the data migrations can begin. CTS & Customer 4 Perform EMC Grab for SAN connected servers CTS & Customer 5 Update server per the EMC Grab recommendations (if applicable) The EMC Grab must be run to identify any software or driver versions that are incompatible with the EMC storage solution used at CTS. Once the Grab is complete, staff will apply required software updates prior to the migration. CTS & Customer 6 Monitoring & Performance Plan This activity will establish testing, monitoring, and reporting criteria. Before each data migration, the data migration team will: Review an document Test Plans Develop test schedules Establish initial performance baseline 6

CTS & Customer 7 Create Data Migration Plan and Back-out Plan A Migration Plan is needed to guide the migration effort. The Back-out Plan will be used in case a problem arises that cannot be resolved during the migration window. Escalation contacts and decision making timeframes will be identified as part of the Back-out Plan. CTS & Customer 8 MEET: data migration planning session(s) CTS & Customer 9 Agree upon migration date / time for move CTS and the Customer will meet to review and refine high-level move, test, and back-out plans. A migration script will be used and customized, when necessary, to fit each application. This may require multiple meetings depending on the complexity of the migration. The date and time (window) for migrating data must be coordinated with all impacted parties (CTS and the Customer). This becomes the target date of the move. CTS 10 Submit change request for migration A change request must be submitted to CTS s internal change management system. This provides documentation required to migrate data. 7 TO 30 DAYS BEFORE MIGRATION CTS Storage Admin 11 Provision VMAX Storage This activity will provision the storage on the VMAX as well as presenting the storage to the server environment. CTS & customer 12 Verify server (system) backup CTS & customer 13 Verify database (business data) backups The server and database backup / recovery process needs to be exercised to verify that the backup is working and current. CTS will test this function as it could be needed in a recovery scenario. 7

1 TO 7 DAYS BEFORE MIGRATION CTS & Customer 14 Verify the VMAX storage is ready to migration Before the data migration, pending updates must be applied to the servers. The CTS Server Admin will check for these and commit or remove them if applicable. CTS & Customer 15 Freeze all changes (Application, Database, O/S, etc.) The system must be stable prior to the migration. All application, database and operating system changes should be frozen one week prior to the migration. This simplifies troubleshooting in the event problems occur (avoids potential causes). The Customer must lead this activity for components controlled by the Customer. CTS & Customer 16 MEET: migration planning session CTS & Customer 17 Confirm Migration Schedule and Plan (Go/No Go) CTS and the Customer will meet to finalize the migration, test and back-out plans. This includes the migration script and is the final check-in prior to the migration day. CTS will check-in with the Customer to verify, confirm and make final adjustments (if any) to the schedule and migration plan. 1 DAY BEFORE MIGRATION CTS & Customer 18 Create full system backup A full system backup is needed just prior to the migration. This might be needed in case a problem occurs that requires a system recovery. MIGRATION DAY CTS & Customer 19 Assemble Migration Team The CTS Server Admin will assemble the migration team to start the process. This is the final go/no go point. 8

CTS Storage Admin 20 Send notification of the start of the Data Migration The CTS Server Admin will notify CTS staff and management the start of the data migration. CTS Migration Team 21 PERFORM MIGRATION: Execute Data Migration Plan The data migration team will start the data migration process. CTS & Customer 22 Perform system and application-level verification or initiate back-out Once the data has migrated to the SDC, the data migration team will perform system verification. This includes verifying the appropriate processes are running; network connectivity is working and executing other test scenarios. If issues occur that cannot be resolved within the negotiated migration window, CTS will notify the Customer that the Back-out Plan must be executed and the migration rescheduled. Customer 23 Notify Customer that application-level validation is complete or initiate back out plan. Once the Customer has completed their system validation and check-out, they will notify CTS of the results of their testing. If successful, the Customer will approve the completion of the data migration by notifying the CTS Server Admin. If unacceptable or unsuccessful, the Customer will notify the CTS contact to execute the Back-out Plan. CTS & Customer 24 Send notification of the end of the Data Migration The CTS Server Admin will notify CTS staff and management the end of the data migration. POST MIGRATION CTS 25 Generate post migration performance benchmarks CTS staff will monitor system performance up to one week after the data migration(s) and report any problems. 9

CTS & Customer 26 Verify that the VMAX is performing satisfactorily Not all problems will show up in the verification steps listed above. Once the system is under a workload, performance or other problems may show up. If this occurs, the Customer should immediately report the problem to the CTS Service Desk. CTS staff will contact the Customer after the migration to verify the system is performing satisfactorily. If performance or other problems occur, a problem ticket will be reported to the CTS Service Desk. CTS Service Owner 27 Adjust Billing The CTS Service owner will work with the Customer and the billing group to update any impacted billing processes. CTS Storage Admin 28 Decommission the old storage Once the system is performing as expected after the migration, the old storage will be decommissioned. 10

Appendix A VMAX Data Migration Checklist Agency Technical Lead Server Name MIGRATION TASKS FOR VIRTUAL SERVERS 30 TO 60 DAYS BEFORE MIGRATION Party Task # Task Description Complete? CTS Client Liaison 1 Identify Migration Team including customer contact(s) CTS Client Liaison 2 Schedule Migration Planning Session(s) CTS & Customer 3 On-boarding process CTS & Customer 4 Perform EMC Grab for SAN connected servers CTS & Customer 5 Update server per the EMC Grab recommendations (if applicable) CTS & Customer 6 Monitoring and Performance Plan CTS & Customer 7 Create Data Migration Plan and Back-out Plan CTS & Customer 8 Create Migration and Back-out Plan CTS & Customer 9 Agree upon migration date / time for move CTS 10 Submit change request for migration 7 TO 30 DAYS BEFORE MIGRATION CTS Storage 11 Provision VMAX Storage Admin CTS & Customer 12 Verify server (system) backup CTS & Customer 13 Verify database (business data) backups 1 TO 7 DAYS BEFORE MIGRATION CTS & Customer 14 Verify the VMAX is ready to migrate CTS & Customer 15 Freeze all changes (Application, Database, O/S, etc.) CTS & Customer 16 MEET: Move planning session CTS & Customer 17 Confirm Migration Schedule and Plan (Go/No Go) ONE DAY BEFORE MIGRATION CTS & Customer 18 Create Full System Backup MIGRATION DAY CTS & Customer 19 Assemble Migration Team CTS Storage 20 Send notification of the start of the Data Migration Admin CTS Migration 21 PERFORM MIGRATION: Execute Data Migration Plan/Script Team CTS & Customer 22 Perform system and application-level verification or initiate back-out plan Customer 23 Notify the Customer to begin validation or initiate back-out plans CTS & Customer 24 Send notification of the end of the Data Migration POST MIGRATION CTS 25 Generate post migration performance benchmarks CTS & Customer 26 Verify that the VMAX is performing satisfactorily CTS Service 27 Adjust Billing Owner CTS Storage 28 Decommission the old storage 11

Admin Agency: Name: Signature: Date: AGENCY VALIDATION 12