KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF



Similar documents
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO , SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.

KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

Guidelines for Solar Grid Power Projects

Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India

TARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com

Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation

DRAFT STANDARD POWER PURCHASE AGREEMENT FOR PROCUREMENT OF.. MW SOLAR POWER ON LONG TERM BASIS (UNDER NEW PROJECTS SCHEME) (SECOND BATCH) Between

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE

Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency

Generation Cost Calculation for 660 MW Thermal Power Plants

a) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition?

Case No. 100 of Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member ORDER (SUO-MOTU)

Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background

all that you want to know About Rajasthan Solar Energy

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

KERALA STATE ELECTRICITY REGULATORY COMMISSION

Delhi Solar Energy Policy, 2015

G.O.MS.No. 8 Dated Read the following:-

CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008

RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR

Tamil Nadu WiNd ENErgy ProfilE

Success in Scaling-up Solar Energy in Rajasthan, India

KERALA STATE ELECTRICITY REGULATORY COMMISSION

No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum

Existing Wind Power Policies and Incentives

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/354/2013 (Suo-Motu)

Overview of Rooftop Solar PV Green Bank Financing Model

Wind Power Programme in India

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY

S. No. Year Obligation expressed as percentage of energy consumption (%)

TELANGANA SOLAR POWER POLICY 2015

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Notification No. TNERC/RPO/ 19/1 dated

Marketing Methodology of Solar PV Power Packs

Guidelines for Grid Connected Solar PV Projects (Phase-II, Batch-I)

An Airport Sustainable Energy Strategy

Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading

Telecom Energy Management

POLICY FOR IMPLEMENTATION OF SOLAR POWER BASED PROJECTS IN MADHYA PRADESH, 2012

DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014

Renewable Energy Certificate Mechanism

To whom application is to be filed

Solar Power Plants FAQs

Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013

IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

Draft Jharkhand State Solar Power Policy 2015

COMBINED SUMMARY OF STATE POLICIES FOR SOLAR POWER

DELHI ELECTRICITY REGULATORY COMMISSION

THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

Mercom Capital Group India Solar Market Update

Direct Investment, Synthetic PPA s ABC Member Bulk Procurement. Garrett Sprague, A Better City

Rooftop Solar PV Power : Potential,Growth and Issues related to

BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO , SECTOR 4, PANCHKULA HARYANA

WORKING PAPER. India: Implementing incentives focused on energy. Anuradha R.V., Sumiti Yadava (Clarus Law Associates)

DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION

DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT. No. Dated: October, 2009 NOTIFICATION (DRAFT)

The Rising Sun Grid parity gets closer kpmg.com/in

F. No. 66/185/2016 -WE Ministry of New & Renewable Energy

Solar for Businesses. Getting Started with Solar. Laura Williams, Renewables Project Manager. June 10, 2015

Analysis of state-wise RPO Regulation across India

Rooftop Solar Potential

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI

IREDA-NCEF REFINANCE SCHEME

POWER PURCHASE AGREEMENT BETWEEN SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED

RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS

The progressive growth of the Indian Power Market

CENTRAL ELECTRICITY REGULATORY COMMISSION

AN OVERVIEW OF INDIA S ENERGY SECTOR

In Focus. India s Renewable Energy Certificate Market

Transcription:

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4, 2010 IN THE MATTER OF Jawaharlal Nehru National Solar Mission Tariff for grid connected Solar Plants Tariff Order for Grid Connected Solar PV Power Plants (Above 3 MW), Solar Thermal Plants and Roof Top (PV) and other small solar Power Plants of capacity from 1 MW upto 3 MW ORDER 1. The Government of India has approved a new policy on development of solar energy in the country by launching of the Jawaharlal Nehru National Solar Mission. This Mission is one of the eight key National Missions which comprise India s National Action Plan on Climate Change. It has a twin objective to contribute to India s long term energy security as well as its ecological security. The Solar Mission recommends the implementation in 3 stages leading up to an installed capacity of 20,000 MW by the end of the 13 th Five Year Plan in 2022. It is envisaged that as a result of rapid scale up as well as technological developments, the price of solar power will attain parity with grid power at the end of the Mission, enabling accelerated and large-scale expansion thereafter. The Mission will adopt a 3-phase approach, spanning the remaining period of the 11th Plan and first year of the 12th Plan (up to 2012-13) as Phase 1, the remaining 4 years of the 12th Plan (2013-17) as Phase 2 and the 13th Plan (2017-22) as Phase 3. 1

As per the above Policy, the solar power purchase obligation for States may start with 0.25% in the phase I may go up to 3% by 2022. This can be complemented with a solar specific Renewable Energy Certificate (REC) mechanism to allow utilities and solar power generation companies to buy and sell certificates to meet their solar power purchase obligations. Under Jawaharlal Nehru National Solar Mission (JNNSM) guidelines for selection of new Grid Connected Solar Projects under Phase I the minimum project capacity shall be 5 MW and 20MW in case of Solar Photo Voltaic Projects and Solar Thermal Project respectively. The maximum capacity for each project of Solar Photo Voltaic technology would be 25 MW and 100 MW for Solar thermal technology. The evacuation under this scheme will be 33 kv and above. For each MW installed capacity of solar power for which a PPA is signed by NVVN, the Ministry of Power (MoP) shall allocate to NVVN an equivalent amount of MW ( upto a maximum of 1000 MW ) capacity from the unallocated quota of NTPC coal based stations and NVVN will supply this bundled power to the Distribution Utilities. 2. The mission also encourages rooftop solar PV and other small solar power plants, connected to LT/11 KV grid, to replace conventional power and diesel based generators. The distribution utility will pay the tariff determined by the State Electricity Regulatory Commission for the metered electricity generated from such applications. Under the Solar Mission, a normative Generation Based Incentive will be payable to the utility and would be derived as the difference between the solar tariff determined by the Central Electricity Regulatory Commission for the concerned solar generation technology less an assumed base price of Rs. 5.50/kWh with 3% annual escalation. Funds will be disbursed through Indian Renewable Energy Development Agency (IREDA), a PSU under MNRE. The distribution utilities will be entitled to account such electricity generated and consumed within their license areas for fulfillment of RPOs. 3. The Ministry of new and renewable energy (MNRE), Government of India with a view to encourage solar power generation announced the Generation based incentive programme for Grid Interactive Solar photo Voltaic (PV) Power Generation and Grid Interactive Solar Thermal Power Generation projects during January 2008. KSERC 2

published the Kerala State Electricity Regulatory Commission (Power Procurement from Solar Plants by Distribution Licensees) Regulations, 2008, providing terms and conditions and the procedure for determination of tariff of Solar PV power plants. The levelised tariff including incentive receivable at 12% discount rate was Rs 15.18/Unit. In order to avail the generation based incentive the projects should have been completed on or before 31-12-2009. 4. In pursuance of the Regulation, the Commission, by this order, based on the financial principles and technology specific parameters as per CERC order dated 26-02-2010,determines the tariff for FY 2010-11 and FY 2011-12 in the case of solar photovoltaic power projects and for FY 2010-11, FY 2011-12 and FY 2012-13 for solar thermal power projects subject to the condition that power purchase agreement (PPA) for such Solar PV and Solar thermal power projects shall be signed before 31.3.2011 and the entire capacity shall be commissioned on or before 31.3.2012 in the case of solar PV projects and on or before 31.3.2013 in the case of thermal projects 5. The Commission has published draft notification on the Tariff Applicable to Solar PV Power Projects including Roof Top and other small projects and Solar thermal Power Projects on 8-07-2010 In response to the above notification comments from the following stakeholders were received. (a) (b) (c) Malankara Plantations Limited, Kottayam. Binani Zinc Limited, Binanipuram. Kerala State Electricity Board. Public hearing was held 21-07-2010. Representatives of the above stakeholders and KSE Board attended the hearing and offered their comments/suggestions on the norms specified in the draft order. Commission upon hearing all the parties having carefully considered the issues involved orders as follows. 3

The tariff determined by the Commission in this Order shall be applicable to the following projects located within Kerala State and selling electricity to the distribution licensees within Kerala State only. (a) Solar PV Power plants (Above 3 MW) for which purchase agreements are signed by 31-03-2011 and projects are commissioned by 31-03- 2012. (b) Solar Thermal Plants for which power purchase agreements are signed by 31-03-2011 and projects commissioned by 31-03-2013. (c) Roof Top and other small Solar Power Plants of capacity from 1 MW up to 3 MW connected to the Distribution Network (below 33 kv) for which power purchase agreements are signed by 31-03-2011 and projects are commissioned by 31-03-2012. The MNRE s draft guidelines for Rooftop PV and other small Solar Power Plants connected to distribution network (below 33 kv) under the Jawaharlal Nehru National Solar Mission specified that the Solar project schemes from States wherein Tariff tenure for duration of 25 years with tariff structure on levelised basis has been determined by SERCs shall alone be considered to be eligible to participate in this Programme. 6. Therefore, Commission orders the following Levelised Tariff based on the norms as per Annexure I by carrying out levelisation for useful life duly considering the discount factor for time value of money. The discount factor considered for this purpose is equal to the weighted average cost of the capital on the basis of normative debt: equity. 4

Summary of Solar Power Tariff for Projects qualified under Jawaharlal Nehru National Solar Mission Sl No Particulars Tariff (Rs/kWh) Tariff if accelerated depreciation is availed (Rs/kWh) 1) Solar PV Power plants ( Above 3 MW) for which purchase agreements are signed by 31-03-2011 and projects are commissioned by 31-03-2012. 17.91 14.95 2) Solar Thermal Plants for which power purchase agreements are signed by 31-03-2011 and projects commissioned by 31-03-2013. 3) Roof Top (PV) and other small Solar Power Plants of capacity from 1 MW up to 3 MW connected to Distribution Network ( below 33 kv) for which power purchase agreements are signed by 31-03-2011 and projects are commissioned by 31-03-2012. 15.31 12.85 17.91 14.95 The levelised tariff indicated in the above chart shall be inclusive of thegeneration Based Incentive (GBI) calculated with a base rate (effective net cost to the Discom) of Rs.5.50 / kwh (or the modified base rate with escalation factor of 3% per annum) available under the scheme of Roof Topand Small Solar Power Projects and shall be subject to the terms and conditions stipulated in the scheme. The developers are to provide electricity to Licensees at these rates for a period of 25 years without any escalation. Sd/- Sd/- Sd/- M.P. Aiyappan C. Abdulla K.J.Mathew Member Member Chairman By Order of the Commission Secretary 5

Annexure- I Norms for Solar PV Plant and Solar Thermal Plant 1. Capital Cost Capital cost is one of the most important parameters for solar power tariff determination. The cost of a solar power project is mainly dependent on the cost of PV modules / plant and machinery, technology adopted, location of the site and capacity. Therefore, Commission fixes a capital cost of Rs. 16.90 Crores / MW for solar photovoltaic power plants and Rs. 15.30 Crores / MW for solar thermal power project as per CERC norms for FY 10-11. 2. Capacity Utilization Factor (CUF) CUF is the ratio of actual energy generated by the Solar PV / Thermal project over the year to the equivalent energy output at its rated capacity over the yearly period. CUF for Solar PV project depends on solar radiation and number of clear sunny days. Further, the CUF depends on site specific parameters like ambient conditions, conversion efficiencies of PV cell, etc The Central Electricity Regulatory Commission has considered average number of clear sunny days of around 300 and daily average global solar radiation to be around 5.8 kwh/sq.mtr/day. Commission adopts a CUF of 19% for solar PV project and 23% for solar thermal project with auxiliary consumption factor 10% as per CERC norms 3. Debt - equity ratio As per the guide lines specified in the tariff policy for financing of future capital cost of projects, a debt: equity ratio of 70:30 is adopted. 6

4. Term of the loan CERC regulation has proposed loan tenure of 10 years and the same is adopted. 5. Interest rate on Loan CERC has adopted Long Term Prime Lending Rate (LTPLR) of State Bank of India (SBI) prevalent during the previous year plus 150 basis points. Considering the above, Commission adopts an interest rate 13.39 %. 6. Interest on Working Capital The Central Electricity Regulatory Commission has included the following components in working capital. (i) Operation and Maintenance expenses for one month; (ii) Maintenance spares @ 15% of the O&M expenses, (iii) Receivables equivalent to 2 months of energy charges for sale of electricitycalculated on the normative CUF; CERC fixed an interest rate equivalent to average State Bank of India short term PLR during the previous year plus 100 basis points. Considering the above, Commission proposed to adopt an interest rate of 12.89 % on working capital 7. Return on equity The Commission proposes to adopt pre-tax RoE of 19% for the first 10 years and 24% from 11 th year onwards for all solar power projects. 8. Plant Life Commission proposed to consider the plant life of 25 years for the solar power projects as per CERC Norms 9. Depreciation of plant and machinery Depreciation rate 7% for first 10 years and 1.33% for the remaining years for solar projects. 7

10. Operation and Maintenance Commission decides O&M costs as Rs 9.5148 Lakhs/MW/year with escalation factor 5.72% for Solar PV Power Projects and Rs 13.74 Lakhs/MW/year with escalation factor 5.72% for Solar Thermal Power Plant. The cost plus levelised tariff for 25 years for Solar PV plants Including Roof Top and other small Solar Power Plants of capacity from 1 MW up to 3 MW is 17.91 Rs/Unit and the benefit of accelerated depreciation ( if availed ) works out to 2.96 Rs/Unit. The net applicable tariff shall be Rs 14.95 /Unit. The Cost plus levelised tariff for Solar thermal Plants shall be 15.31 Rs/Unit and the benefit of accelerated depreciation (if availed) works out to Rs 2.46/Unit. The net applicable tariff shall be Rs 12.85/Unit 8