Decision Method for Unit Rehabilitation. John Yale Hydro Plant Engineering Manager Chelan County PUD



Similar documents
Chelan County PUD. Rock Island Rehabilitation Powerhouse One Units B5 to B8

MICRO HYDRO POWER GENERATING EQUIPMENT

Frequently Asked Questions (FAQs) on Hydropower

HydroHelp 1 AN EXCEL PROGRAM DEVELOPED FOR TURBINE-GENERATOR SELECTION FOR HYDROELECTRIC SITES

CHAPTER 3 RESEARCH DESIGN

Excitation.

ASSET MANAGEMENT WHAT MAKES SENSE FOR HYDRO?

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS

In the business world, the rearview mirror is always clearer than the windshield. - Warren Buffett

Mini & Micro Hydro Power Generation. EBARA Hatakeyama Memorial Fund Tokyo, Japan

Performance of Gangrel Hydroelectric Power Plant A Case Study

with engineered reliability

This document contains information proprietary to Mitsubishi Electric Corporation. It is submitted in confidence and is to be used solely for the

Chapter 11 Cash Flow Estimation and Risk Analysis

Wolf Creek Hydropower Rehabilitation Analysis Report

How To Calculate Discounted Cash Flow

Harnessing the power of water

e7/ppa Workshop on Renewable Energy - TEST ANSWER -

Verification of Short Circuit Test Results of Salient Poles Synchronous Generator

Harnessing the power of water with engineered reliability

FINANCIAL AND RISK ANALYSIS WITH RETSCREEN SOFTWARE. SLIDE 1: Financial and Risk Analysis with RETScreen Software

Institut für Energietechnik Department of Energy Systems. Hydroelectric power. Elias Bartos 2/7 2010

Course 3: Capital Budgeting Analysis

HYDROMATRIX Jebel Aulia - Sudan

Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes

300 MW Variable Speed Drives for Pump-Storage Plant Application Goldisthal

ACST829 CAPITAL BUDGETING AND FINANCIAL MODELLING. Semester 1, Department of Applied Finance and Actuarial Studies

How To Make A Kamperdine Turbine

Hydroelectric Power (3 Semester Hours)

US Department of Energy, Bonneville Power Administration US Army Corps of Engineers, North Pacific Division

What are the Benefits?

Planning Reserve Margin (PRM)

Risk Analysis Overview

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P Turbidity Monitoring Plan

Workshop on Rehabilitation of Hydropower

FINANCIAL EVALUATION OF ENERGY SAVING PROJECTS: BUILDING THE BUSINESS CASE

Performance Analysis of Thermal Power Station: Case Study of Egbin Power Station, Nigeria

SYNCHRONOUS MACHINES

Design and manufacturing of Crossflow, Pelton, Kaplan and Francis turbines

Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station

Adıgüzel Hydroelectric Power Plant Modeling and Load-Frequency Control

VESI JA ENERGIA VIENTITUOTTEENA. Fortum Miko Olkkonen Senior Executing Manager, Hydro Projects Fortum Power & Heat Oy

MODELLING AND SIMULATION OF MICRO HYDRO POWER PLANT USING MATLAB SIMULINK

Turbo generators Best quality for thermal power plants

UCCS ENSC/PES 2500: Renewable Energy Spring 2011 Test 3 name:

Performance Improvement of Pump-turbine for Large Capacity Pumped Storage Power Plant in USA

Quantitative Methods for Finance

Solutions to Chapter 8. Net Present Value and Other Investment Criteria

HYDROELECTRICITY and DAMS

Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14

03 The full syllabus. 03 The full syllabus continued. For more information visit PAPER C03 FUNDAMENTALS OF BUSINESS MATHEMATICS

Transportation Asset Management

Chapter 18. Web Extension: Percentage Cost Analysis, Leasing Feedback, and Leveraged Leases

How To Build A Powerhouse

Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is

Simulation and Lean Six Sigma

Risk Analysis and Quantification

China s Small Hydropower in Rural Energy Development

Pricing complex options using a simple Monte Carlo Simulation

CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING

How To Cost To Build A Powerhouse In Manitoba

Energy Storage Systems and Role for the US Grid

DECISION PROCESS AND OPTIMIZATION RULES FOR SEISMIC RETROFIT PROGRAMS. T. Zikas 1 and F. Gehbauer 2

A LAYMAN S GUIDE TO SMALL HYDRO SCHEMES IN SCOTLAND

Simulation for Speed Control of the Small Hydro Power Plant Using PID Controllers

Mechanical and electrical rebuilding of a turbine generator for phase-shift operation

Husum Wind Energy 6th of June Johannes Ritter Partner Solution Matrix

Tony Wong & Vivek Chaudhri

PROJECT RISK MANAGEMENT

Dually Fed Permanent Magnet Synchronous Generator Condition Monitoring Using Stator Current

PRESENTATION TITLE. Corps of Engineers Agreement with. Columbia Riverkeeper Regarding Hydropower Plant Discharges

Building and Using Spreadsheet Decision Models

525-MVA Generator-motor and Thyristor Starter Put into Service at the Tokyo Electric Power Co., Inc. s Kannagawa Hydroelectric Power Station

Simulation and Risk Analysis

Capital Expenditure Forecast (CEF11)

Basics of Electricity

Using simulation to calculate the NPV of a project

Motor Fundamentals. DC Motor

CARNEGIE MELLON UNIVERSITY CIO INSTITUTE

6.0 Results of Risk Analyses

Capital Budgeting Techniques: Certainty and Risk

REHABILITATION OF HYDROPOWER

Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions

AirCost LCCA Software An overview of AAPTP Paul M. Dalbey, P.E.

The Economics of Culvert Replacement: Fish Passage in Eastern Maine

Activity 3.7 Statistical Analysis with Excel

Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection

Call Centre Helper - Forecasting Excel Template

CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS

Replacement Generators to Modernize and Uprate Power Trains Limited by the Generator

Transcription:

Decision Method for Unit Rehabilitation John Yale Hydro Plant Engineering Manager Chelan County PUD

Public utility in Washington State, 1936 1,988 MW nameplate Two dams, three powerhouses on the Columbia River One dam and powerhouse on Lake Chelan Total generation 9,000 GWHr 48,000 electric customers Ages from 1928 to 2011 The PUD! 2

Rock Island Puget Power Oldest plant on the Columbia River 1933 First Powerhouse 4 propellers 22MVA 6 Kaplan 25MVA 2 units rehabilitated 2008-2010 Second Powerhouse added 1979 8 bulbs 54MVA 3

Rocky Reach Initial construction 1956-1961 7 Kaplan 108MVA Rehabilitated and uprated to 120MVA 1997 2003 Expanded in 1968 1971 4 Propellers 132MVA Rehabilitated, converted to Kaplan and uprated to 148 MVA 1998 2003 4

Chelan Hydro Washington Water Power 1926 1928 2 Francis 28MVA Acquired 1955 Rehabilitated 2009-2011 Uprated to 37MVA 5

Unit Rehabilitation Decisions Equipment is aging Equipment still runs Management wants an IRR or NPV What s it based on? All future generation? No future generation? Only the generation increase? 6

Traditional Approach Quantify increases: Capacity Efficiency Fish benefits Green value Enter into Economic Model 7

Economic Model Insert revenues or benefits Costs Results 8

Sample Case Four 65 year old vertical Kaplan Turbines Issue - The generators are near end of life, rotor-stator contact is likely. Alternatives: Rehab the generator now, turbine later Complete rehabilitation now Two runner options Rebuild New with increased capacity 9

Results 10% Efficiency Increase 10

Rehabilitation Result With Energy 11

Traditional Approach Results Recommendation: Replace generator, wait on the turbine. 12

Problem Without energy, value of increased capacity and energy is not sufficient negative NPV and IRR Assumes all value of energy after rehabilitation What about age and condition of the unit? What about risk of not doing the turbine? 13

Problem - Ignores Risk It will fail, but when and how? Run to Fail is an option Can you accept the consequences? Failure and Consequence Analysis Identify likely failures Identify consequences Quantify effects Include in model 14

1 5 Risk/Value Based Approach Value of continued operation Cost of forced outage Lost energy/capacity/flexibility Disruption Reputation Collateral impacts Physical damage Workforce Contracts

Model Development Step 1 Define Alternatives Step 2 Define Values Step 3 Risk Evaluation Step 4 Build Model Step 5 Turn the Handle! 16

Step 1 Define Alternatives 1 Run To fail and 1a Retire 1b Rehabilitation 1c Rehabilitation with New runner 2 Generator now, turbine later and 2a Retire 2b Runner rehabilitation 2c New runner 3 Complete rehabilitation, reuse runner 4 Complete rehabilitation, new runner 17

Step 2 Define Value Increased generator efficiency Increased turbine efficiency, two runner options Increased capacity Increased operating flexibility Green value of increased efficiency/capacity Avoided risk 18

Step 3 - Risk Evaluation Forced versus planned outage Length Disruption Risks - rotor stator contact Major generator is wiped out, some collateral damage, $5,000,000 Minor only parts to be rehabilitated are damaged, collateral damage limited to disruption, $500,000 Catastrophic failure Significant shaft damage, turbine collides with discharge liner, headcover rupture, flooded powerhouse, $25,000,000 19

Step 4 Build Model Build out economics for each alternative Assume rehabilitation date (planned) Decision tree provides optimum decision Model failures Modes Probabilities Consequences 20

Uses Economic Spreadsheet Spreadsheet model for each alternative Plus one for operating time (value) prior to failure or rehabilitation Economic Justification Model Service life 40 Discount Rate 7.0% Run To Failure, year 2021 General inflation rate-future benefits & costs 2.5% period = 0 1 2 3 4 5 6 7 8 Benefits (1) Real Input Input scale growth 2015 2016 2017 2018 2019 2020 2021 2022 2023 $ Revenue est 2021 1,491,396 100% 0.5% 1,377,127 1,436,443 1,479,934 1,491,396 1,522,459 0 0 0 Revenue-Add'l energy option 3 yes 10.0% 56,462 58,894 60,677 61,147 62,421 0 0 0 Revenue-Add'l energy option 4 no 8.0% 0 0 0 0 0 0 0 0 Include Encroachment % of Revenue? yes 36% 0% 0 0 0 0 0 0 0 0 $ Powerex contract value YES 315,000 0.5% 316,575 318,158 319,749 321,347 322,954 0 0 0 REC value no $ - 0.5% 0 0 0 0 0 0 0 0 Cost if B1 - B4 Retired $ - 0 0 0 0 0 0 0 0 Value if U unit is out $ 400,000 0.5% 0 0 0 0 410,101 0 0 0 Value if C unit is out $ 125,000 0.5% 62,813 126,253 126,884 127,519 64,078 0 0 0 Subtotal of Benefits (2) 0 1,812,976 1,939,748 1,987,244 2,001,409 2,382,013 0 0 0 Costs (1) 1. Stator, Exciter, Controls, Greaseless turbine pit 2021 0 0 0 0 0 0 0 0 0 0 0 0 2. Add rotor rim and pole 2021 0 0 0 0 0 0 0 0 0 0 3. Add runner rebuild 2021 0 0 0 0 0 0 0 0 0 0 4. Use new runner 2021 0 0 0 0 0 0 0 0 0 0 Contingency 2021 0 0 0 0 0 0 0 0 0 0 Rotor rim & pole replace 2021 0 0 Rehab old turbine and hub 2021 0 0 Retirement Costs 2021 0 0 0 0 0 0 0 0 0 0 0 Backout inflation, Andritz fixed $, except new runner 76% 0 0 0 0 0 0 0 0 0 0 0 Add PUD real growth 24% 0 0 2.0% 0 0 0 0 0 0 0 0 0 Retirement Costs 2021 0 0 0 0 0 0 21 0 0 0 0 0

Decision Tree Method Uses separate economic model for each alternative Incorporates decisions and risks Mathematically models the alternatives, shows optimal decision path Not real $ 22

23

Sample Case Issue - The generator is near end of life, rotorstator contact is likely. Alternatives: Run to Failure, then rehabilitate Rehabilitate the generator now, turbine later Complete rehabilitation now 24

Sample Case Assumptions First Unit Rehabilitation - 2016 Rehab Frequency - 1 years Failure year, after - 1st 2018 Failure frequency, years - 1 Probability a unit fails before rehab B8 25%, B7 16%, B6 4%, B5 9% Cost of Unit Failure Catastrophic $ (25,000,000) - 1% Major $ (5,000,000) - 50% Minor $ (500,000) - 49% Cost of turbine failure Major $ (2,000,000) - 1% Minor $ (500,000) - 99% 25

Decision Tree 26

Decision Tree 27

Static Results (based on assumptions) Not Real Money! Recommendation: Complete Rehabilitation, reuse runner 28

Includes Risks, but Wait! Static values Best judgment of when and how severe Or is it? Evaluate Static Values Monte Carlo Simulation Sensitivity Analysis 29

Monte Carlo Input range or distribution of values Simultaneous variations Requires good model and computer Really tough by hand 30

Input 31

Output 32

Sensitivity Vary Range of Input Find out what makes the decision different and by how much One-way Two-way 33

Sample Case Sensitivities 34

$(160) $(140) $(120) $(100) $(80) $(60) $(40) $(20) $- -2% 0% 2% 4% 6% 8% 10% 12% Change in Expected Value(%) Change in Expected Value(%) One-Way on Risk Figure 1 Sensitivity to Consequence of Catastrophic Failure Figure 2 Sensitivity to Probability of Catastrophic Failure 200% 100% $35M 200.0% 100.0% 0% 0.0% -100.0% -100% -200% -200.0% -300.0% ~1.5% -300% $ Millions -400.0% Run To Fail Complete Rehabilitation 35

0% 2% 4% 6% 8% 10% $ Millions Concequence of catastrophic failure (B43) Two-Way Risk of Catastrophic Failure $- $(20) $(40) $(60) $(80) $(100) $(120) $(140) $(160) Run To Fail Complete Rehabilitation 36

Risk/Value Approach Incorporates risk of failure Quantifies discussion of when will it fail? Condition as an indicator of risk of failure becomes part of the equation Quantifies risk of delay Utilizes Excel and macros or add-in 37

Comparison Traditional approach Without energy negative economics With energy recommended generator now, turbine later (ignores risk) Risk/Value approach Quantifies risk of delay Values Run to Failure Recommends generator and turbine based on turbine risk 38

39