Specification for Pipe Coating Repairs Offshore



Similar documents
NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Wastewater Capital Projects Management Standard Construction Specification

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

WATERPROOFING FOR CONCRETE STRUCTURES

SECTION FIRE HYDRANTS

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 16 BRIDGE DECK WATERPROOFING General Materials Equipment...

POLYURETHANE LINING AND COATING ON PIPE RAW WATER

C. Section TESTING LABORATORY SERVICE.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment:

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

UNIVERSITY OF CHICAGO ELEVATOR PIT LEAK REPAIR

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

CONSTRUCTION PERMIT REQUIREMENTS

Minor Cracks in Horizontal Surfaces

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

A. Work on this project shall consist of, but is not limited to, the following:

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Approved. Property Test/Standard Description. matt (0-35) Flash point ISO 3679 Method 1 27 C calculated IED (2010/75/EU) (calculated)

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS

COATING & WRAPPING OF UNDERGROUND PIPING

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

FIELD COATING OF STEEL PIPE AND FITTINGS INSTALLED UNDERGROUND AND IN SUBSURFACE STRUCTURES

SECTION PRECAST CONCRETE UTILITY STRUCTURES

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality

STANDARD SPECIFICATION SECTION STEEL PIPE, FUSION-BONDED EPOXY LINED AND COATED

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

Field Welding Inspection Guide

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION SANITARY SEWER PIPE

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

DIVISION 4300 STORM DRAINAGE

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

INDEX. Sec. No. Items Page Nos.

PART E SPECIFICATIONS

Pipe and Equipment Insulations. Zeston. PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems

TECHNICAL REQUIREMENTS AND SPECIFICATIONS

How to Build a Printed Circuit Board. Advanced Circuits Inc 2004

Section SEWER PIPE INSTALLATION AND TESTING

4 Installation Requirements

SECTION 560 COATING NEW STRUCTURAL STEEL

Weld Cracking. An Excerpt from The Fabricators' and Erectors' Guide to Welded Steel Construction. The James F. Lincoln Arc Welding Foundation

ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS

Mechanical Installation

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

PIPELINE FIELD JOINT COATING AND FIELD REPAIR OF LINEPIPE COATING

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS

SECTION STORM DRAIN SYSTEM

DESIGN CLARIFICATION (DC)

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

GB Tubulars RECOMMENDED PRACTICE For CASING on LOCATION

SECTION NONREINFORCED CONCRETE SEWER PIPE

SIGMACOVER 300. PRODUCT DATA SHEET December 12, 2014 (Revision of November 1, 2013) DESCRIPTION

SECTION SITE PREPARATION

Property Test/Standard Description. semi gloss (35-70) Flash point ISO 3679 Method 1 34 C IED (2010/75/EU) (calculated)

SECTION 807 PUMP STATION REHABILITATION

SMOOTHMOVE INSTRUCTIONS FURNITURE VAN EPOXY FLOOR FINISH KIT VOC-FREE - NO SOLVENT GENERAL INFORMATION KEY 87269AB

TABLE OF CONTENT

PIPELINE INSPECTION COMPANY LTD. Portable Holiday Detectors. OPERATING INSTRUCTIONS SPY PORTABLE HOLIDAY DETECTORS Models 780, 785, & 790

OFFICE OF CIVIL ENGINEERING UNITED STATES COAST GUARD WASHINGTON, D.C. APRIL 1996 MARINE CABLE, POWER AND CONTROL SPECIFICATION NO.

SECTION CAST-IN-PLACE CONCRETE

Preformed Metal Roofing and Siding

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

SECTION POLYVINYL CHLORIDE (PVC) PIPE

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

NEW ELECTRICAL SUBSTATION Building 300 SECTION ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.

Specification for Fusion Bonded Epoxy for External Pipeline Coating

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Epoxy Crack Injection (the basics)

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

PRE INSTALLATION MANUAL

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

INDUSTRIAL FLOORING INSTALLATION CHALLENGES. James C. Ziegler, ArmorSeal Product Manager Sherwin Williams Cincinnati, Ohio, USA

SECTION STORM DRAINAGE SYSTEM

A comprehensive range

BLACK JACK ALL WEATHER ROOF COATING

1.1.2 Polypropylene The polypropylene must be a white opaque film, 1 2 mil thick. Biaxial orientation is preferred.

SETTLEMENT INSTRUMENTATION & MONITORING

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

Rehabilitation of corroded pipelines and pipes with FibaRoll

DESCRIPTION OF WORK:

Asphaltic Wedge Paving

Transcription:

Specification for Pipe Coating Repairs Offshore Specification for Pipe Coating Repairs Offshore 1 of 6

Table of Contents 1.0 SCOPE... 3 2.0 REFERENCE DOCUMENTS... 3 3.0 MATERIALS... 3 4.0 EQUIPMENT AND LABOR... 4 5.0 INSPECTION... 4 6.0 REPAIRS... 4 Specification for Pipe Coating Repairs Offshore 2 of 6

1.0 SCOPE This specification shall govern the materials, application, inspection and repair of pipe coatings offshore. The work includes the furnishing of all labor, materials, tools and equipment and the performance of all operations and incidentals necessary for the repairs. As used in this specification, the following definitions shall apply: COMPANY: CONTRACTOR: The firm responsible by contract for the installation of the pipeline system. CONTRACT: Signed work agreement between COMPANY and CONTRACTOR. CONTRACTOR shall obtain COMPANY's written approval for any deviations from the requirements of this specification or specifications, standards and drawings referenced herein or elsewhere in the CONTRACT. In case of conflict between documents, the order of precedence given in the CONTRACT shall govern. This document is not intended to be all inclusive, and the use of the requirements set forth does not relieve the CONTRACTOR of his responsibility to supply a product capable of performing its intended service. 2.0 REFERENCE DOCUMENTS The coating repairs shall be applied in accordance with the latest editions and addenda of the following codes and standards. National Association of Corrosion Engineers COMPANY Specifications Corrosion Prevention Coating Coal Tar Enamel Pipeline Field Joint Materials Field Joint Installation Corrosion Prevention Coating Neoprene 3.0 MATERIALS 3.1 General All repair material shall be furnished by the CONTRACTOR and shall conform to the specifications referenced herein and the requirements of this specification. The repair materials shall be stored and used so as to prevent damage or deterioration. Repair materials which have become contaminated with foreign matter or have deteriorated shall not be used. 3.2 Above Water Repair Materials Coating Three Layer Polypropylene Coal Tar Enamel Concrete Weight Neoprene Repair Materials Shrink Sleeves or Hot Melt Patch Compound Compatible with Plant Applied Coating Coal Tar Enamel or Shrink Sleeves Mastic and Ancillaries Neoprene Split Sleeves and Ancillaries Field Joint As specified for Respective Coatings in Specification RP 02 74 Recommended Practice, High Voltage Electrical Inspection of Pipeline Coatings Prior to Installation 3.3 Underwater Repair Materials Specification for Pipe Coating Repairs Offshore 3 of 6

For underwater repair work, the repair system and materials shall be proposed by the CONTRACTOR. The repair system shall provide performance equal to the design coating in all respects. These include but are not limited to corrosion prevention, impact protection and pipe stability. Complete details of such repair system and materials shall be submitted to the COMPANY for approval before they are used by the CONTRACTOR. For Corrosion Prevention Coating repairs made underwater, a polyamide cured epoxy such as Dimet 410T or other COMPANY approved equivalent solvent free epoxy suitable for underwater application shall be used. Complete details and manufacturer's literature shall be submitted by CONTRACTOR to COMPANY for approval prior to repairs being made. 4.0 EQUIPMENT AND LABOR 4.1 Condition of Equipment CONTRACTOR shall furnish all necessary equipment and tools. All equipment and tools shall be of good quality, maintained in good operating condition and suitable for use to apply materials required by this specification. All equipment shall be subject to approval by the COMPANY. 4.2 Holiday Detector The electrical equipment used to test the coating shall be portable, low amperage, adjustable voltage, pulse type holiday detector employing an audible signaling device. The holiday detector shall be furnished with a coil spring electrode or a suitable brush type electrode. 4.3 Labor The CONTRACTOR shall provide supervision and adequately skilled labor for repair operation. The CONTRACTOR shall provide necessary facilities for COMPANY supervision and inspection of all the work. 5.0 INSPECTION Coatings shall be inspected offshore as and when required by the applicable specifications. During laying operations, the CONTRACTOR shall visually check all coated pipe for damage to the coating before lowering the pipe into the water. The coating shall also be inspected following an abandonment and recovery procedure. Epoxy coated pipe shall be inspected with a coil spring type holiday detector as per NACE RP 02 74 in conjunction with the visual inspections. For concrete coated pipe, if cracking of the concrete in the overbend is sufficiently severe as to indicate that concrete may be falling away from the submerged pipe (on the stinger or in the suspended span), an inspection of the submerged portion of the pipe shall be made as soon as reasonably practicable. If during the inspection it is apparent that concrete is falling away from the submerged portion of the pipe, laying shall be stopped immediately and the damaged joints of pipe shall be removed or repaired in accordance with the COMPANY's instructions. 6.0 REPAIRS Repairs methods shall be outlined for the respective coatings below. Repairs shall use materials compatible with the material being repaired as given in Section 3.2. 6.1 Three Layer Polypropylene Coating For holidays and damaged areas greater than 2 square inches repairs shall be made with shrink sleeves. Pipe cleaning and shrink sleeve application shall be governed by relevant portions of COMPANY Specification 2136600 SP 022, Field Joint Installation. Specification for Pipe Coating Repairs Offshore 4 of 6

For holidays and damaged areas less than 2 square inches the pipe cleaning and coating repair of fusion bonded epoxy may be performed using a hot melt patch stick instead of the shrink sleeves. The hot melt patch compound shall be compatible with the parent coating and approved by the COMPANY. The area to be repaired shall be cleaned and heated according to manufacturer's instructions. The adjacent coating area shall also be roughened to provide a key for the repair. Any dust shall be wiped off. The compound shall be applied to a minimum thickness of 16 mils using manufacturer's recommended procedure. Repair shall be reinspected as described for the epoxy coating above. 6.2 Coal Tar Enamel Coating Pipe cleaning and coating repair for coal tar enamel shall be as per COMPANY Specification 2136600 SP 018, Corrosion Prevention Coating Coal Tar Enamel. In cases where it is possible to apply shrink sleeves entirely around the pipe, shrink sleeves may be used. Pipe cleaning and application of shrink sleeves shall be as per the relevant portions of COMPANY Specification 2136600 SP 022, Field Joint Installation. 6.3 Concrete Coating Repairs to the damaged concrete coating shall be made as follows: (a) Damage of less than 1 square foot (where the remaining coating is sound and the reinforcement is not exposed) will be acceptable without repairs. (b) Should the damaged area be more than 1 square foot and less than 3 square feet, the concrete remaining in place over the area shall be removed to expose the reinforcing steel mesh throughout the damaged area. Edges of sound concrete coating shall be undercut to provide locking for the hot mastic replacement material. No more than two such repairs may be made on any joint, and no more than three consecutive joints may contain such repairs. In the event that more than three consecutive joints require repair, then the CONTRACTOR must immediately adjust his laying procedures to prevent further damage. (c) Should the damaged area be more than 3 square feet and affect a length of pipe no longer than 3 feet, the coating containing the damage shall be removed around the entire circumference of the pipe. Repairs shall be made by satisfactorily restoring or replacing the reinforcing before applying the hot mastic. A hot mastic filler shall be placed in the sheet metal form such that the repaired surface is flush with the adjacent concrete coating. The width of the sheet metal form shall be such that when filled with mastic the weight of the mastic will not cause the form to sag more than 1" and result in an uneven contour of the coated/repaired surface. In no case shall the sheet or reinforcement metal touch anodes. Only one such procedure may be performed on any one joint of pipe. Not more than two joints in any ten consecutive joints may be repaired in this manner. (d) In cases where damaged areas are greater than those specified in the above paragraph, the joint containing the damage shall be removed and disposed of according to COMPANY's instructions. Before resuming laying operations, the CONTRACTOR shall reassess his laying procedures and equipment, and make whatever corrections are necessary to ensure that excessive damage to the concrete coating does not occur again. Specification for Pipe Coating Repairs Offshore 5 of 6

(e) Where concrete is removed to a depth which exposes the pipeline corrosion coating, and visual inspection indicates that there may be damage to the corrosion coating, the wire reinforcement shall be removed and the CONTRACTOR shall inspect the corrosion coating with a holiday detector as per NACE RP 02 74. Should there be any damage done to the corrosion coating, the CONTRACTOR shall repair it and retest it as per Section 6.2 above. 6.4 Neoprene Coating Pipe cleaning and coating repair of neoprene coating shall be performed as per Project Specification 17001 INSTL SPL/ OSPL 6103, Field Joint Installation. If coating damage is too great to be repaired with the neoprene material in one split sleeve the joint shall be rejected. For small holidays or damaged areas, a patch may be cut from the split sleeve to fit the cleaned area rather than removing a strip around the entire circumference of the pipe. All repairs must be covered completely with a shrink sleeve. Adequate time shall be allowed for epoxy bond material to cure to a degree suitable for handling before passing the repair over barge shoes. Additional heating of the shrink sleeve may be employed to accelerate curing, however temperatures shall be kept within manufacturer's recommended limits for all components. 6.5 Field Joint Coating Pipe cleaning and field joint repairs shall be performed as per COMPANY Specification 2136600 SP 022, Field Joint Installation. 6.6 Underwater Repairs For underwater repair of damaged coatings, repair procedures shall be submitted by CONTRACTOR to COMPANY for approval before use by CONTRACTOR. For repair of corrosion coating underwater, pipe cleaning procedures shall be given detailed consideration. Specification for Pipe Coating Repairs Offshore 6 of 6