Sewer network renovation using glass-fiber reinforced (GRP) pipe liners



Similar documents
PIPE REHABILITATION. Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

Pipeline Replacement using Relining

Section SEWER PIPE INSTALLATION AND TESTING

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Module 3 : Sewer Material. Lecture 3 : Sewer Material

Module 3: Sewer Material Lecture 3: Sewer Material

Introduction to Pressure Pipe Rehabilitation with CIPP

TRENCHLESS TECHNOLOGY GUIDELINES CLOSE FIT THERMOPLASTIC LINING

SASTT contact details:

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Always. Reliable. Tight. Wall sleeves Versatile solutions for building entries. cablepipebuildingentry+

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Puddle Flange. FRANK Puddle Flange

Wastewater Capital Projects Management Standard Construction Specification

As Good as New: Relining with h Pipes

Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014

SECTION NONREINFORCED CONCRETE SEWER PIPE

ElastoFlake & ElastoTec

Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

Waste Collection Systems

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

The surface roughness of the polyurethane lining is 10 times lower than cement-lined pipes.

TECHNICAL SPECIFICATION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

BKP Berolina Polyester GmbH & Co. KG. Berolina-Liner System Lightspeed in gravity pipe rehabilitation!

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

ENGINEERED SOLUTIONS. A2 Liner Pipe for Trenchless Technology

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

DISTRIBUTION PIPING MATERIALS: BUILDING HYDRONIC SYSTEM MANAGEMENT. Jim Riley, Texas A&M University February 10, 2015

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Installation of Large Diameter Buried Pipes

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

Flowtite Jacking Pipe

SECTION ABANDONMENT OF SEWER MAINS

SPR PE Steel Reinforced Liner

Oil and Gas Pipeline Design, Maintenance and Repair

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

Pipes and Fittings for Gravity Sewer Mains. SewerMAX

Product Systems AQUAFIN-IC CEMENTITIOUS CRYSTALLINE PENETRATING WATERPROOFING. Waterproofing Specification

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STANDARD SPECIFICATIONS SECTION SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT

SECTION GRAVITY SANITARY SEWERS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Rehabilitation or Replacement? That Is The Question

PRESSURE PIPE REHABILIATION CIPP TECHNOLOGIES

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION STORM DRAINAGE TABLE OF CONTENTS

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION

FAULTS FOUND IN SEWER PIPES, CAUSES AND REMEDIES

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

WATERPROOFING SikaProof -A TECHNOLOGY

BUTE Department of Construction Management and Technology

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

SikaProof A Technology

Plastics Engineering SYSTEM BEKAPLAST. Mechanically anchored thermoplastic lining for extreme conditions

INSTALLATION OF INSITUFORM LINER

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

Sewer Rehabilitation Design Requirements

GENERAL SPECIFICATIONS AND GUIDELINES FOR INSTALLATION MASTERLINER CURED-IN-PLACE PIPE SYSTEMS

Guide to working on Public Sewers

جامعة البلقاء التطبيقية

Water Main Lining A Sustainable Alternative to Open Cut Replacement

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Embedded Parts Introduction - Anchors

RENEW. A Water Main Cleaning and Lining Program Designed to Improve Water Quality and Service

Structural Lining for Water Mains. Presenters: Stephen Marcino, PE and Micah Blate, EIT (JMT)

HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

DRAINAGE PIPE REPAIR & RELINING SOLUTIONS

Drain & Tank Cleaning

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

4 Steps for Quality Sewer Performance in Perpetuity

REHABILITATION METHOD FOR INCREASING FLOW VELOCITY AND REDUCING SEDIMENTATION

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Elevating Your House. Introduction CHAPTER 5

Letty Arvide-Gomar, PE

SECTION STORM DRAINAGE SYSTEM

Asbestos in the home. for you - for your community - not for profit

For drinking water pipe distribution systems, both main and supply lines Sewer and discharge pipe systems

Transcription:

Sewer network renovation using glass-fiber reinforced (GRP) pipe liners The BONEX method 1./ Antecedents Several hundred or thousand kilometers is the total length of the communal and industrial sewer network built and operated below the ground of every civilized city of long history (in Budapest, the network is approx. 4,500 km long). Even industrial facilities can feature networks whose length adds up to several tens of kilometers. In most cases, these networks are badly worn, obsolete and their condition is about to deteriorate beyond repair in the foreseeable future. Normally new pipes are laid to substitute for the worn sewers. However, this approach gives reason to concern because it is extremely expensive, hinders traffic within the given district of town or the factory premises and can greatly impede or paralyze the manufacturing processes. Usually, no sufficiently large area is available to build a new sewer running parallel with the old one. Therefore, the so-called No-Dig renovation technologies have gained ground and importance all over the world during the last ten to twenty years. A renovation process introduced in 1983 and named the BONEX method has offered proper solution to each of the three major problems inherent in the worn or wrecked sewers: corrosion resistance, water-tightness and loadability. 2./ Description of the BONEX method Sewers are renovated by introducing pipe liners. According to the BONEX approach, the maximum length of each liner section is 6 meters. The pipe liners wall thickness is calculated using static dimensioning methods. In fact, the liner section is a highstrength, sand-filled and glass-fiber reinforced pipe made of polyester and provided with pipe socket and spigot of special design. To guarantee proper sealing at the pipe socket, a rubber ring of triangular or semi-circular cross-section is glued to the spigot in the pipe factory. When installed and pressed against the pipe socket at the site, this rubber ring flattens to ensure proper water-tightness. Upon request from the customer, artificial resin putty or a combination of rubber ring and resin putty can be used to guarantee proper sealing. The pipe s wall thickness is determined to meet the expected load (the greater from the injection pressure and the payload in operation) and in function of the expected life specified by the customer (e.g. 100 years). To insert the pipe liners, only a single starting trench must be digged in the

middle of the normally 500 meters long sewer section in need of renovation. The pipe liners are placed in the cunette opened above the sewer shoulder and, then, are introduced (by applying an alternating pull-and-push motion) into the existing pipe, using a winch installed above the last shaft along the pipe-section to be re-lined. In case of passable (man-sized) pipe sections, the technology can be modified by carrying each pipe liner handed down in the starting trench separately to the intended place where the end of the liners can be matched and fixed. In these cases, an anti-friction drop-shaped rubber ring or a ring of circular crosssection is normally used to seal the pipe sockets. Having put the pipe liners in place, the gap between the liner and the old sewer pipe is filled by injecting cement grout. Until completion of the process, the branching pipes and house sewers are temporarily plugged, to prevent the cement grout from penetrating in these pipe sections. In case of passable or climbable pipe sections, the plugs are installed from inside the pipe and, later, removed when the cement grout has consolidated. In case of non-climbable pipe sections, plugging and subsequent re-opening of the house sewers is done from a properly selected point, i.e. from outside the sewer to be relined (e.g. from the cleaning shaft of the house or the building s basement, etc). Auxiliary devices of proper design are available for the insertion and removal of the temporary plugs and for cutting through the cement grout and the pipe liner. During the re-lining process, the sewage normally running in the main sewer and the presently plugged branch sections is delivered by pumping into a section of the main sewer yet in operation. The renovated sewer section can be put again in operation the day following the day of injection. 3./ Manufacture of pipe liners Pipe liners are manufactured using program-controlled filament winding machines and mechanic or hydraulic tools. Firstly, a stripping layer is applied to the mould, followed by a gel-coat free from glass-fibers, and a layer of plastic saturated with resin or a layer of glass-fiber fleece. The useful wall thickness consists of glassroving layers previously pulled through a resin-bath, then, a layer of sand is applied between each layer of glass-roving. The weight of glass and sand can vary between 25 and 40 per cent, respectively, but their aggregate mass percent shall not exceed 65% (the rest is the weight of resin). The thermal expansion co-efficient of a pipe wall of this structure is a good match to that of concrete. Accordingly, the composite material consisting of the pipe liner, the injected cement grout and the old concrete pipe shall not be subjected to considerable longitudinal stresses caused by temperature changes. The useful pipe wall surface is coated with a resin-free layer and the outer surface is sprayed with sand. The sand granules get embedded in the resin and, thus, are bound to the pipe wall.

The part of the sand granules that protrudes from the resin padding gets embedded in the injected cement grout. This intermediate layer allows, on the one hand, for proper composite action between the old pipe and the newly integrated pipe liner and, on the other hand, for the even distribution of minuscule tensions that may arise from minor thermal expansion, if any. Normally, the pipes are manufactured to meet requirements of five quality grades in four categories of resistance to chemicals, as shown below: Category Type Description I. N Normal II. É Food industry quality III. V Resistant to chemicals IV. D/A Increased resistance to chemicals, up to + 30 o C V. D/B Increased resistance to chemicals, up to + 80 o C 4./ Implementation a./ Preparations On-site preparation of implementation of the technology begins with the installation of a portable or temporary duct needed to deliver sewage by pumping furthermore with the installation and commissioning of the sewage pumps and the necessary automatic control system. Then, the sewer section in need of renovation is removed from service and is flushed. Removal of any foreign object is the final task of preparation. b./ Application of the pipe liners After having prepared the starting trench, a pilot pipe is pulled through the sewer section, to make sure of smooth passage of the train of pipe liners. The pipe liners are then introduced and applied according to the above described process. When the cement grout (the filling material) has set, the individual houses sewer connections can be re-established. In case of passable (man-sized) pipe sections, the lining can be drilled and cut through from inside while, in case of non-passable sections, this job can be done from the garden shaft or the basement of the house, depending on the design of the local system. Special drilling equipment is used to complete this job. After having commissioned the re-lined sewer section, the temporary duct and delivery pump system is dismantled and re-deployed at the next section to be renovated. The key phases of implementation are mechanized or automated, in order to improve the productivity and to decrease the costs of the process, compared to those of the traditional approach. Depending on the local circumstances, 10 to 15 pipe liners can

be installed in each shift, i.e. 60 to 90 meter long sections can be completed using 6 m long pipes. Of course, also the time required for the preparation and dismantling phases should be taken into consideration. c./ Quality control of the renovated/improved section In general, quality control of the renovated sewer sections comprises verification of adherence to the design dimensions and, primarily, the impermeability properties. Standards and other technical specifications stipulate the permissible rate of exfiltration and infiltration of the concrete sewer. As the glass-fiber reinforced polyester pipe ( GRP grade) is perfectly water-impermeable and the number of pipe connections is by 50 to 66 percent less (due to the longer pipe sections) than in the case of traditional concrete pipes, the aggregate water-tightness of the GRP-sewer surpasses by far all the respective requirements. Since this method has been used for a relatively short time (i.e. several decades), no statistically meaningful life expectancy data are available regarding the re-lined sewer sections. However, the known substantial difference between the chemical resistance of pipes made of concrete versus glass-fiber reinforced polyester and in possession of the domestic and foreign experiences (20 and 30 to 40 years, respectively), we have reason to assume that the expected life of the GRP pipe liners shall significantly exceed that of any newly laid concrete pipeline. 5./ Advantages vs. disadvantages a./ Advantages The pipe material resists to any corrosion potentially caused by the delivered fluids or the groundwater of any concentration, The pipe liner shall take over all stresses and load from the old and obsolete concrete pipe (which latter can, from now on, be considered an empty underground tunnel). The life of the pipe liner can be adjusted according to the customer s discretion, Due to the pipe liner s extremely favorable friction coefficient, the transport throughput of the renovated sewer shall increase, accompanied by the decrease to almost nil of the degree of deposit accumulation. This latter feature is of outstanding importance in cutting the subsequent maintenance costs to a minimum. The applicability of this method is independent from: the size/dimensions of the sewer in need of renovation (non-passable, mansized, climbable) the shape or cross-section of the sewer (circular, ovoid, frog-mouth, dragon, etc.) the material of the original/old pipes (concrete, reinforced concrete, earthenware, brick, cement asbestos, steel, cast iron, plastic) the weather or climatic conditions (cold, hot, wet or arid)

the type of surface preparation technology (no surface roughening is needed; to the contrary, the surface must be smoothed, dried, de-dusted, degreased, etc.). The branch sewers and the houses can be reconnected to the renovated and relined sewer without any digging or causing any disturbance to surface traffic, in case of both the passable and the non-passable sewers. The renovation process does not disturb or impede the operation of any other public utility network, running parallel with or perpendicular to the route of the sewer (water, gas, distance heating, electric power supply, telephone, etc.). The rate of progress of renovation with the Bonex technology substantially exceeds that of any competing approach and the cost of implementation is significantly lower than that of another project of identical capacity and implemented under similar conditions but involving the digging of long trenches. If necessary, also the access shafts can be provided with the same corrosion protection or can be lined with glass-fiber reinforced polyester coat. BONEX is capable of completing the entire renovation process, from the current status assessment of the old pipeline, through the preparation of the detailed implementation plans, up to the installation and commissioning phase. b./ Disadvantages The single disadvantage is the price of the technology compared to that of the competing approaches. Notwithstanding, the higher cost is undoubtedly offset by the disproportionately higher value added (due to the load bearing capacity) and the wellfounded expectations concerning the considerably longer life of the utility.