Geotechnical Building Works (GBW) Submission Requirements

Similar documents
A GUIDEBOOK TO THE CHANGES IN BUILDING CONTROL 2007/2008. Building and Construction Authority

LICENSING OF BUILDERS - Simplified Guide

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Section 2100-Trenching and Tunneling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Pro-Lift Steel Pile Foundation Repair

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

BUTE Department of Construction Management and Technology

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

SECTION SHEETING, SHORING AND BRACING

Safe & Sound Bridge Terminology

Guide to Carrying Out Engineering Works within Road Structure Safety Zone and Engineering Activity on Land adjoining Public Streets

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

Emergency repair of Bridge B421

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Design and Construction of Cantilevered Reinforced Concrete Structures

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Elevating Your House. Introduction CHAPTER 5

Tunnelling & Underground. Specialists

Construction Technology 3

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

Business Unit. Tunnelling & Civil Engineering. Infrastructure solutions from a single source.

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

The Building Trades Protection Act

Beacon Hill Sewer District Standard Specifications

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Construction sites are dewatered for the following purposes:

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

CHAPTER 2 QUANTITY TAKE-OFF

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Foundation design to Eurocode 7

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

ATLAS RESISTANCE Pier Foundation Systems

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

King Post Wall Information

SECTION STORM DRAINAGE SYSTEM

PDHonline Course S151A (1 PDH) Steel Sheet Piling. Instructor: Matthew Stuart, PE, SE. PDH Online PDH Center

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

SECTION 5: SANITARY SEWER SYSTEM DESIGN

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

SERVICES 2015 ISO 18001

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

PERIODIC STRUCTURAL INSPECTION OF EXISTING BUILDINGS GUIDELINES FOR STRUCTURAL ENGINEERS

FY08 SEWER POINT REPAIRS BID TABULATION

Section 402. STORM SEWERS

BRIDGES ARE relatively expensive but often are

Excavation & Trenching Procedure

Estimating Trench Excavation

hs2 Ground A non-technical guide

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

IH-635 MANAGED LANES PROJECT, SEG. 3.2

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

Page & Turnbull imagining change in historic environments through design, research, and technology

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

HOUSE BUILDING DIGEST

SECTION STORM DRAINAGE TABLE OF CONTENTS

Buildings Department Practice Note for Registered Contractors 38. Registration of General Building Contractors and Specialist Contractors

Introduction to Minimal Excavation Foundations

SECTION EARTH MOVING

Interim Advice Note 105/08 Implementation of Construction (Design and Management) 2007 And the withdrawal of SD 10/05 and SD 11/05

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Pipes and Fittings for Gravity Sewer Mains. SewerMAX

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

NOTES FOR GUIDANCE ON THE METHOD OF MEASUREMENT FOR HIGHWAY WORKS

Transcription:

Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015

Content : 1. General Definitions 2. What is geotechnical building works? 3. Submission requirements for ERSS 4. Examples of GBW (Excavation Works) 5. Examples of GBW (Tunneling Works) 6. Examples of GBW (Foundation Works) 7. Examples of non-gbw

Geotechnical Aspects General Definitions An analysis of the geological structure and earth materials of the site of the geotechnical building works and its influence on the geotechnical building works An analysis of the ground-water regime and its influence on the wall stability and integrity of the geotechnical building works over time; and Such other applications of earth sciences to and engineering aspects of the geotechnical building works as may be prescribed Earth Retaining Structure Any structure, structural system or other means used to maintain the shape of excavation during construction, earth filling or cutting

General Definitions Geotechnical Engineer, PE(Geo) A professional engineer who is registered under the Professional Engineers Act (Cap. 253) as a specialist professional engineer in the specialised branch of geotechnical engineering Specialist Accredited Checker, AC(Geo) An accredited checker who is registered under section 16 to undertake the work of an accredited checker as regards the geotechnical aspects of any geotechnical building works

What is Geotechnical Building Works (GBW)? Tunneling Works Any excavation or other building works to make a tunnel with a diameter, width or height or more than 2 m Excavation Works and Earth Retaining Structures Any excavation, or other building works to make a caisson, cofferdam, trench, ditch, shaft, well with a depth of more than 6 m Any building works for constructing, altering or repairing any earth retaining structures in or for a trench, ditch, shaft, well with a depth or height or more than 6 m Any earthwork or other building works for constructing or stabilising a slope with a height of more than 6 m (measured as vertical distance between the highest level to the lowest level of the slope) Foundation Works Foundation for buildings of 30 or more storeys

Submission Requirement for ERSS All permanent or temporary building works that involve Excavation/ERSS 1.5 m** deep Appointments Required Qualified Person (QP) Accredited Checker (AC) Plan approval is not required 1.5 m** < Excavation/ERSS 4 m deep QP(ST) AC is not required 4 m < Excavation/ERSS 6 m deep QP(ST) AC Excavation/ERSS > 6 m deep and not classified as GBW: e.g. excavation for sewer manhole associated with pipe diameter of 2 m or less Excavation/ERSS > 6 m deep and classified as GBW. E.g. basement excavation. QP(ST) QP(ST) QP(Geo) AC AC AC(Geo) Notes: Plan approval is not required for insignificant building works listed on First Schedule of Building Regulation 3A. ** If the structure that retains earth is not constructed of reinforced concrete or steel, then the applicable depth is 1 m instead of 1.5 m. Planning approval is no longer required for any retaining wall or earth-retaining structure for supporting the face of an excavation made for the purpose of constructing any pile cap, footing, sump, lift pit or trench, provided that the size of these structures does not exceed 10 square meters in area and 2 meters in depth.

GBW Submission Requirements Plans Submission (a) Plans approval is required for GBW - To attach ERSS_GBW_Annex A - To include site investigation report with PE certification (b) Require Permit to commence work - to attach ERSS_GBW_Annex B - Commencement of work: to notify BCA During Construction Stage - To implement ERSS_GBW_Annex C and D at site - To submit ERSS_GBW_Annex E to BCA monthly

Advisory Note 1/09 on ERSS Key points Movement control limit Critical limit

Use of Ground improvement within retaining wall In view of uncertainty in using ground improvement, ground improvement shall be limited to soil improvement work only and shall NOT be used as part of retaining wall especially acting as cantilever retaining wall. This is in line with COI report and BCA s Advisory Note 1/09. If grout mixed piles are present within the retaining wall, as a minimum the following conditions shall be met: a) all wall forces such as bending moments and shear forces shall be resisted by a separate structure system (such as soldier piles steel section inserted within the grout mixed pile, a separate analysis for obtaining wall forces shall be carried out with steel section only with grout mixed piles ignored in this analysis) b) separate structural laggings (concrete, timber, or steel) shall be provided between structural wall member.

Appointment of QPs and ACs QP(D) Independence of QP is essential to avoid situations of conflict of interest COI Report 2005 Developer QP(S) QP(Geo)(D) Builder Supervision QP and his team shall not be a partner, an officer or an employee of the developer or builder QP(Geo)(S) AC* AC(Geo)* *shall not have any financial or professional interest on the project *shall be appointed by developer including for ERSS(GBW) submission Instrumentation contractor

Examples of Geotechnical Building Works (Excavation/earth retaining structures)

Basement Excavation Works: Open cut method Single tier open cut slope H > 6 m GBW

Basement Excavation Works: Open cut method Multi-tier open cut slope in stiff soils D <2h1 h2 H > 6 m H = h1 + h2 h1 GBW

Excavation Works: Earth Retaining System H > 6 m H > 6 m Note: Besides retaining wall and strutting supporting system, ground improvement layer is also need to be submitted as part of the GBW(ERSS) system. Ground improvement layer GBW

Excavation Works in sloping ground Existing ground level h2 H = h1 + h2 h1 H > 6 m Note: For computation of excavation depth of GBW, H is computed from where the excavation started and to the final formation level GBW = Earth retaining & support system, slope

Excavation Works in sloping/varying ground H > 6 m 6 m H > 6 m H > 6 m H < 6 m H < 6 m GBW = Earth retaining & support system Non-GBW GBW

Excavation Works: Basement Construction Excavation depth = H h1 H > 6 m GBW H = h1

Excavation Works: Basement Construction GBW Localise pits shall also be submitted as part of the main GBW plan

Excavation Works: Construction of Basement structures H > 6 m GBW = Temporary earth retaining & support system Basement structures which is within the excavation support system, is not GBW

Excavation Works: Construction of Basement structure Note: a)the plan submission for the temporary retaining wall and permanent basement structure shall be submitted under the same ST and to be submitted as GBW (not submit as piling) H > 6 m As temporary retaining wall also serves as permanent retaining system of basement structure, GBW = Temporary and permanent earth retaining & support system including basement slab

Excavation Works: Drainage Works H > 6 m Box Culvert GBW = Temporary earth retaining & support system Box culvert which is within the excavation support system, is not GBW

Slope: A & A of existing slopes GBW = Slope or retaining wall with retained/stabilised height exceed 6 m Stabilize slope height H > 6 m Plan submission is required for both temporary and permanent stages of ERSS(GBW) For excavation involving hill slope (with reinforcing or strengthening works), QP and AC are required for plan submission if the affected slope height exceed 4 m. If the constructed or stabilised slope height exceed 6 m, QP(Geo) and AC(Geo) are also required for plan submission.

Independent retaining wall retaining on existing hill slope Constructed slope Retained height H1> 1.5 m H > 6 m Plan submission is required for both temporary and permanent stages GBW = Slope or retaining wall with constructed retained height exceed 6 m

Earth Retaining Structures (retaining existing slopes/high ground) H > 6 m GBW = Earth retaining wall

Earth Retaining Structure: Retaining wall H > 6 m GBW = Earth retaining wall

Earth Retaining Structure: Road Abutment H > 6 m GBW = Road abutment

Earth Filling Works: Embankment/Dam H > 6 GBW = Earth embankment/dam

Earth Filing Works: Retaining Walls GBW = Caisson H > 6 m

Excavation Works: Utilities pipes (such as sewers, water and gas pipes) with diameter larger than 2 m and its associated shafts or manholes H > 6 m Utilities pipes >2m dia. GBW = Temporary earth retaining & support system Utilities pipes or manholes which is within the excavation support system, is not GBW

Examples of Geotechnical Building Works (Tunneling Works)

Tunneling Works: Bored Tunnels/Jacked-in tunnel Bored tunnels D > 2m GBW = Permanent (tunnel lining) and temporary tunnel support system

Tunneling Works: Cut-and-cover Tunnels Cut-and-cover tunnels H > 6 m GBW = Temporary earth retaining & support system Tunnel box structure, which is within the excavation support system, is not GBW

Tunneling Works: Mined Tunnel Mined tunnel w h h, w >2 m GBW = Temporary tunnel support system Permanent tunnel structure which is within the tunnel support system, is not GBW

Examples of Geotechnical Building Works (Foundation Works)

Foundation of High-rise H 30 storey H 30 storey GBW = Raft foundation GBW = Caisson, barrette piled foundation or Piled raft foundation

Examples of Non Geotechnical Building Works

Building Works: Small area shaft and trenches Plan area < 10 m2 Plan area < 10 m2 Excavation for shaft Excavation for trench Any excavation for shaft and trenches with plan area of the excavation not exceeding 10 square metres (e.g. trench excavation for diaphragm wall, excavation for bored piles) is exempted from the requirements of geotechnical building works (GBW). For example, an excavation for a small shaft with plan area less than 10 sq m is exempted from the requirement of GBW but still subjected to ERSS submission requirements.

Insignificant Building Works: Utilities such as Sewers, water and gas pipes with diameter of 1m or less Excavation depth utilities pipes 1m dia. Submission requirement for utilities within construction site together with other building works: H 4 m ERSS plan to be submitted by QP H> 4 m ERSS plan to be submitted by QP and AC Utilities pipe Plan to be submitted by QP Any trenches for the purpose of laying sewers/utilities (including its associated shaft or manholes) not exceeding 1m in diameter in conjunction with any public sewerage/utilities system is classified as insignificant work which requires no plan submission. This exemption does not apply to cases where the trenches for the purpose of laying sewers/utilities (diameter less than 1m) are within a construction site where the size of trench exceeds 10 square metres or exceeds 2m in depth.

Excavation Works: Utilities pipes (such as sewers, water and gas pipes) with diameter larger than 1 m and not greater than 2 m and its associated shafts or manholes Excavation depth H 1m < Utilities 2m Submission requirement: H 4 m ERSS plan to be submitted by QP H> 4 m ERSS plan to be submitted by QP and AC Utilities pipe Plan to be submitted by QP and AC

For enquiries: BCA Hotline: 18003425222 Email: bca_enquiry@bca.gov.sg