Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling



Similar documents
SECTION SHEETING, SHORING AND BRACING

Wastewater Capital Projects Management Standard Construction Specification

SECTION IX SLIP LINING PIPELINES

Construction Specification for Grading

Construction Specification for Sewer Bypass Flow Pumping

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Construction Specification for Concrete Curb and Concrete Curb and Gutter

CHAPTER 6 - SANITARY SEWER

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Section SEWER PIPE INSTALLATION AND TESTING

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Geotechnical Building Works (GBW) Submission Requirements

SECTION 1 GENERAL REQUIREMENTS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

SECTION NONREINFORCED CONCRETE SEWER PIPE

SECTION STORM DRAIN SYSTEM

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

SECTION STORM DRAINAGE SYSTEM

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Section 402. STORM SEWERS

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

SECTION ABANDONMENT OF SEWER MAINS

Design and Construction of Cantilevered Reinforced Concrete Structures

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION GRAVITY SANITARY SEWERS

Section Installation of pipe and casing for sanitary sewer by methods of augering.

DIVISION 4300 STORM DRAINAGE

Series 600: Earthworks

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

LS 2540 SEWER LATERALS AND INSPECTION TEES

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

PART E SPECIFICATIONS

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No M (Supersedes Report No.

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

1. General General Requirements Gravity Sanitary Sewer Testing Requirements...3

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

SECTION EARTH MOVING

Stormwater/Wetland Pond Construction Inspection Checklist

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION 3 SANITARY SEWER DESIGN

METHOD OF STATEMENT FOR STATIC LOADING TEST

C. Section TESTING LABORATORY SERVICE.

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Professional Engineers Providing Structural Engineering Services In Buildings

Section 2100-Trenching and Tunneling

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Special Specification 7021 Water Main and Sewer Line Replacements

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 21

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

NRC INSPECTION MANUAL

SANITARY SEWER SPECIFICATIONS

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

900 SEWERAGE WORK ITEM PIPE SEWERS COMPLETE IN PLACE

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Basements and Deep Building Construction Policy 2014

Prequalification Requirements For Precast Concrete Drainage Products

Developer s/consultants Field Services Guidelines

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

Buildings Department Practice Note for Registered Contractors 38. Registration of General Building Contractors and Specialist Contractors

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

COMMONLY USED RESIDENTIAL BUILDING CODES

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

Repair or Replacement - Band-Aids vs. Surgery

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

Working together to improve beach water quality. Fixing our. public and private. sewers

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

High Strain Dynamic Load Testing of Drilled Shafts

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

Chaudière Crossing Bridge Rehabilitation

Underground Commercial Electric Service

SPECIFICATION FOR CONSTRUCTION OF UNBOUND GRANULAR PAVEMENT LAYERS

What Causes Foundation Leaking?

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Transcription:

Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling OPSS 415.06 EQUIPMENT Section 415.06 of OPSS 415 is amended by the addition of the following paragraph: Any equipment used in the work shall be operated in a manner satisfactory to the Contract Administrator and according to Toronto Municipal Code, Chapter 591 Noise. Modifications to the equipment as deemed necessary by the Contract Administrator shall be at no extra cost the Owner. OPSS 415.09 MEASUREMENT FOR PAYMENT OPSS 415.09.01.01 Tunnel Clause 415.09.01.01 of OPSS 415 is deleted in its entirety and replaced with the following: Measurement will be in metres along the centre line of the tunnel from inside face to inside face of maintenance holes or chambers or from the end of the tunnel where no maintenance hole or chamber is installed. The measurement will not include the distance through any structure including maintenance holes and chambers. Amendment to OPSS 415 (Nov 2012) Construction Specification for Pipeline and Utility Installation by Tunnelling Page 1 of 1 TS 415 April 2013

ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY TUNNELLING TABLE OF CONTENTS 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS 415.04 DESIGN AND SUBMISSION REQUIREMENTS 415.05 MATERIALS 415.06 EQUIPMENT 415.07 CONSTRUCTION 415.08 QUALITY ASSURANCE - Not Used 415.09 MEASUREMENT FOR PAYMENT 415.10 BASIS OF PAYMENT APPENDICES 415-A Commentary 415.01 SCOPE This specification covers the general requirements for pipeline and Utility installation by tunnelling. 415.01.01 Specification Significance and Use This specification has been developed for use in provincial-and municipal-oriented Contracts. The administration, testing, and payment policies, procedures, and practices reflected in this specification correspond to those used by many municipalities and the Ontario Ministry of Transportation. Use of this specification or any other specification shall be according to the Contract Documents. Page 1 Rev. Date: 11/2008 OPSS 415

415.01.02 Appendices Significance and Use Appendices are not for use in provincial contracts as they are developed for municipal use, and then, only when invoked by the Owner. Appendices are developed for the Owner s use only. Inclusion of an appendix as part of the Contract Documents is solely at the discretion of the Owner. Appendices are not a mandatory part of this specification and only become part of the Contract Documents as the Owner invokes them. Invoking a particular appendix does not obligate an Owner to use all available appendices. Only invoked appendices form part of the Contract Documents. The decision to use any appendix is determined by an Owner after considering their contract requirements and their administrative, payment, and testing procedures, policies, and practices. Depending on these considerations, an Owner may not wish to invoke some or any of the available appendices. 415.02 REFERENCES When the Contract Documents indicate that provincial-oriented specifications are to be used and there is a provincial-oriented specification of the same number as those listed below, references within this specification to an OPSS shall be deemed to mean OPSS.PROV, unless use of a municipal-oriented specification is specified in the Contract Documents. When there is not a corresponding provincialoriented specification, the references below shall be considered to be to the OPSS listed, unless use of a municipal-oriented specification is specified in the Contract Documents. When the Contract Documents indicate that municipal-oriented specifications are to be used and there is a municipal-oriented specification of the same number as those listed below, references within this specification to an OPSS shall be deemed to mean OPSS.MUNI, unless use of a provincial-oriented specification is specified in the Contract Documents. When there is not a corresponding municipaloriented specification, the references below shall be considered to be the OPSS listed, unless use of a provincial-oriented specification is specified in the Contract Documents. This specification refers to the following standards, specifications, or publications: Ontario Provincial Standard Specifications, Construction OPSS 517 Dewatering of Pipeline, Utility, and Associated Structure Excavation Ontario Provincial Standard Specifications, Material OPSS 1350 OPSS 1440 Concrete - Materials and Production Steel Reinforcement for Concrete 415.03 DEFINITIONS For the purpose of this specification, the following definitions apply: Certificate of Conformance means a document issued by the Quality Verification Engineer confirming that the specified components of the Work are in general conformance with the requirements of the Contract Documents. Page 2 Rev. Date: 11/2008 OPSS 415

Engineer means a professional engineer licensed by the Professional Engineers of Ontario to practice in the Province of Ontario. Pipeline means to include sewers, culverts, watermains, and forcemains. Quality Verification Engineer (QVE) means an Engineer retained by the Contractor qualified to provide the services specified in the Contract Documents. Rock means natural beds or massive fragments, or the hard, stable, cemented part of the earth's crust, igneous, metamorphic, or of sedimentary origin, which may or may not be weathered and includes boulders having a volume of 0.5 m 3 or greater. 415.04 DESIGN AND SUBMISSION REQUIREMENTS 415.04.01 Design Requirements The primary liner shall be designed to support all soil and hydrostatic pressures and to withstand any additional loads caused by grouting or jacking thrusts. The primary liner design and access shaft details shall bear the seal and signature of an Engineer. 415.04.02 Submission Requirements When any of the following information is not specified in the Contract Documents, it shall be submitted to the Contract Administrator for review a minimum of 14 Days prior to commencing tunnelling operations: a) Design criteria. b) Materials. c) Construction shaft and portal details. d) Tunnelling method. e) Face support and other temporary support details. f) Primary liner and support design details. g) Material mixture for filling voids and procedures. h) Tunnel boring machine information, if applicable. i) Type and strength of rock bolts, if applicable. j) Lighting and ventilation details. k) Settlement monitoring plan. l) Excavation and dewatering plan. m) Testing and monitoring plan. Page 3 Rev. Date: 11/2008 OPSS 415

415.05 MATERIALS 415.05.01 Concrete Concrete shall be according to OPSS 1350 and with a nominal minimum 28-Day compressive strength of 30 MPa. 415.05.02 Steel Reinforcement Steel reinforcement for concrete work shall be according to OPSS 1440. 415.05.03 Primary Liner The primary liner shall be as specified in the Contract Documents or according to the Contractor's submission. 415.05.04 Rock Bolts Rock bolts and nuts shall have a minimum tensile strength of 400 MPa. 415.06 EQUIPMENT The Contractor shall select and use Equipment and associated methods compatible with the selected dimensions of the tunnel and with the subsurface and groundwater conditions at the site. 415.07 CONSTRUCTION 415.07.01 General The location of tunnels shall be established from the plan, lines, elevations, and tolerances as specified in the Contract Documents. All reference points necessary to construct the tunnel and appurtenances shall be laid out prior to commencement of the tunnelling operation. The Contract Administrator shall be provided with the assistance and access necessary to check the layout of the tunnel and associated appurtenances. 415.07.02 Construction Shafts Construction shafts shall be provided at locations as specified in the Contract Documents or according to the Contractor's submission. Shafts shall be maintained in a drained condition. A secure fence shall be installed around the perimeter of the construction shaft area with gates and truck entrances. The fence shall be removed upon completion of the work. 415.07.03 Stability of Excavation The construction methods, plant, and procedures employed shall ensure that the excavations are stable, free from disturbance, and maintained in a drained condition. Page 4 Rev. Date: 11/2008 OPSS 415

The construction methods, plant, and materials employed shall prevent the migration of soil material into tunnels or shafts. 415.07.04 Tunnelling An individual with previous experience in the construction of tunnels shall supervise the work at all times. The tunnelling method shall be suitable to deal with changing ground conditions that may be encountered during the progress of the work. Methods of excavating the tunnel shall be capable of fully supporting the face and shall accommodate the removal of boulders and other oversize objects from the face. The tunnel shall be kept sufficiently dry at all times to permit work to be performed in a safe and satisfactory manner. 415.07.05 Dewatering Dewatering shall be according to OPSS 517. 415.07.06 Primary Liner The primary liner shall be installed so that the exterior is as tight as possible to the excavated surface of the tunnel and allows the placement of the full design thickness of the secondary lining. All voids between the primary lining and the surface of the excavation shall be filled. If an unexpanded liner is used, the space outside the liner plates shall be grouted at least daily. Tunnels excavated in sound rock shall be supported in a manner that prevents scaling and unravelling of the rock and also protects the rock from weathering or deterioration. Tunnels excavated in unstable rock shall be supported by means of rock bolts or an anchoring system in a manner that safely sustain the tunnel crown and walls. 415.07.06.01 Primary Liner Support Systems Primary liner support systems shall minimize ground movement into the excavation, ensure stability, and maintain strength of the ground surrounding the excavation. Primary liner support systems shall be compatible with encountered ground conditions, method of excavation, method of groundwater control, and with the placement of permanent liners. Primary liner support systems shall prevent weathering, deterioration, loosening, or unravelling of ground surfaces exposed by excavation. 415.07.07 Secondary Liner The secondary liner shall be as specified in the Contract Documents. The void outside the finished secondary liner shall be filled as specified in the Contract Documents or according to the Contractor's submission. 415.07.08 Testing and Monitoring Testing and monitoring shall be as specified in the Contract Documents or in accordance to the Contractor s submission. Page 5 Rev. Date: 11/2008 OPSS 415

415.07.09 Certificate of Conformance A completed Certificate of Conformance shall be submitted to the Contract Administrator upon completion of the work. The Qualification Verification Engineer shall affix his or her seal and signature to the completed Certificate of Conformance confirming that the following are in general conformance with the requirements of the Contract Documents: a) Work b) Material and installations c) Inspection, testing, and test results 415.07.10 Management of Excess Material Management of excess material shall be according to the Contract Documents. 415.09 MEASUREMENT FOR PAYMENT 415.09.01 Actual Measurement 415.09.01.01 Tunnel Measurement of tunnel shall be by length in metres along the centreline of the tunnel from centre to centre of maintenance holes or chambers or to the ends of the tunnel, where no maintenance hole or chamber is installed. 415.09.01.02 Rock Excavation in Tunnelling Measurement of rock excavation in tunnelling shall be by volume in cubic metres based on the neat lines of the tunnel as shown in the Contract Documents. 415.09.02 Plan Quantity Measurement When measurement is by Plan Quantity, such measurement shall be based on the units shown in the clauses under Actual Measurement. 415.10 BASIS OF PAYMENT 415.10.01 Tunnel - Item Rock Excavation in Tunnelling - Item Payment at the Contract price for the above tender items shall be full compensation for all labour, Equipment, and Material to do the work. Page 6 Rev. Date: 11/2008 OPSS 415

Appendix 415-A, November 2008 FOR USE WHILE DESIGNING MUNICIPAL CONTRACTS Note: This is a non-mandatory Commentary Appendix intended to provide information to a designer, during the design stage of a contract, on the use of the OPS specification in a municipal contract. This appendix does not form part of the standard specification. Actions and considerations discussed in this appendix are for information purposes only and do not supersede an Owner s design decisions and methodology. Designer Action/Considerations This specification was written to encompass the requirements for the construction of pipelines, drainage conduits, or other utility pipe installations by the tunnelling method. It is not intended to be a specification for other tunnelling applications such as the transportation industry, mining, hydro electric, petroleum exploration industry, etc. Engineering design based on geotechnical pre-design information is essential prior to the use of this specification for tunnelling projects. The experience of the tunnelling Contractor is of prime importance. The designer may recommend prequalification of bidders. The designer should specify the following in the Contract Documents: - Primary liner requirements. Alternatively, the designer may elect that the Contractor is responsible for determining the primary liner design details. (415.05.03) - The plan, lines, elevations, and tolerances required for the tunnelling project. (415.07.01) - Location of required construction shafts. Alternatively, the designer may elect to specify that the Contractor is responsible for determining shaft locations to suit the method of construction. (415.07.02) - The appropriate secondary liner type, class, dimensions, etc. (415.07.07) - The method of verifying the product installation. This may include reporting information from the tunnelling machine, daylighting, trace wire, survey, acoustic or magnetic location, GPS, closed-circuit television (CCTV) inspection, or mandrel tests. The designer should also specify the applicable leakage, infiltration, exfiltration, or pressure test requirements for the installation. This may apply to either the primary and secondary liner or just the secondary liner. (415.07.08) The designer should provide benchmark and reference points for laying out the project. The designer should specify if the shafts are to remain in place or be removed upon completion of the project. If the shafts are to remain in place, further details should be provided as to how they should be covered or remain accessible for future use. The designer may wish to consider including a process regarding payment for failed tunnelling attempts in the Contract Documents. The designer should ensure that the General Conditions of Contract and the 100 Series General Specifications are included in the Contract Documents. Related Ontario Provincial Standard Drawings No information provided here. Page 7 Rev. Date: 11/2008 OPSS 415