Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida



Similar documents
Construction Delivery Methods for Texas school districts

CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS

B. Capital Improvement Program (CIP) All capital improvement projects listed as part of the Board s annual approved capital budget.

How To Get Construction Procurement Services

Doniphan-Trumbull Public School BP Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT S. Marion Avenue, Mail Station 2015 Lake City, Florida

Members, Council of Presidents. Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid

Project Delivery Methods & Contract Types CSTM 102 Spring 2013

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS. REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES Risk) FOR

Program Management for School Construction

OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

School Construction Projects

Construction Management and project process

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

COMMUNITY LIBRARY (SUNBURY) RFP for Construction Manager at Risk

PROJECT MANAGEMENT BASICS

5. Whether the timely completion of the project is critical to the university s ability to repay debt service or to meet grant obligations.

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO

The programming, design

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

Puget Sound Regional Council

FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2

Policy Number: Policy Name: Professional Services and Construction Services Procurement

TABLE OF CONTENTS. Prefacej... 1

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO

Puget Sound Regional Council

CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

An organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award.

CHAPTER 4 TYPES OF COST ESTIMATES

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

REPORT TO THE UTAH LEGISLATURE. A Performance Audit of School Building Construction. November Number Audit Performed By:

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

Community Program Directors, All Community Facilities Staff, State Architects and Engineers

Construction Management Standards of Practice

How To Find A Vendor For Parcc, Inc.

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

You & Your Architect A GUIDE FOR A SUCCESSFUL PARTNERSHIP.

C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods

Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153

FINDING AND UTILIZING QUALITY CONSTRUCTION LEADS. Kenneth Borah, Sr. Editor, CDCNews

24 CFR PART Procurement. States. Procurement standards.

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.

Background and Goals for the Project

Evaluating Project Delivery Options

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Project Organization. System and Project Management 1.040/1.401J Nathaniel Osgood

Tel: (617) Fax: (617) OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

REPORT TO UTAH STATE LEGISLATURE. A Performance Audit of Construction Management by Political Subdivisions

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Ocoee, FL July 01, 2016 Advertisement No. 1

Building Capital Projects in Tough Times John Lynch, State of Washington

Request for Proposals Community Engagement and Business Development Consultant Contractor Loan Fund May 16, 2016.

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Proposal. Development of IETF Mail List Archiving, Web-Browsing & Search Tool

Best-Value Procurement Manual. MnDOT Office of Construction and Innovative Contracting (OCIC)

1.040 Project Management

GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES FOR PARTICIPATION IN STATE CONSTRUCTION CONTRACTS

Eanes Independent School District

Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding

Pre-qualification for Construction Services Using a Qualifying System in Publicly Bid Projects

ESCO BASE CONTRACT FOR AS-NEEDED ENERGY PERFORMANCE CONTRACTING SERVICES

VDOT Prequalification. Suzanne Lucas Construction Division

The School Board of Miami-Dade County, Florida Department of Contractor Prequalification Frequently Asked Questions and Answers

Winona State University MINNESOTA STATE COLLEGES AND UNIVERSITIES WINONA STATE UNIVERSITY LAIRD NORTON PROJECT

CONSTRUCTION MANAGEMENT SERVICES for the new REPLACEMENT NORTH DORCHESTER HIGH SCHOOL Dorchester County Public Schools December 9, 2015

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

TABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

REQUEST FOR QUALIFICATIONS By Town of Apex, NC For Architectural Services For The Design of a Senior Services Facility

OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS

New WMHS Construction Management Firm

Procedures for the Selection of Construction Management (CM), CM at Risk and Program Management Services

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES

Hunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR:

FIRST AND FINAL ADDENDUM RFP FOR ROOFING SERVICES FOR DISASTER RECOVERY ASSISTANCE

MEDICAL CAPTIVE INSURANCE COMPANY PROCUREMENT POLICIES AND PROCEDURES

NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS

Among other things, completion of the project will allow expansion at the campus to include 6 th -8 th graders and serve over 1,000 students.

NEGAUNEE PUBLIC SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS

PROCUREMENT UNDER GRANTS

CM/GC Guidelines FOR PUBLIC OWNERS. A Joint Publication Building Your Quality of Life. AGC Publication Number 2912 NASFA Publication Number F-3007

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR

Hemingford Public Schools District 10 P.O. Box 217 Hemingford, NE (308) Buildings and Sites

8.OFFER DUE DATE: 2:00pm September 18, PAYMENT DISCOUNT TERMS

CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER

ADVERTISEMENT FOR BIDS DUCKETT CREEK SANITARY DISTRICT TP1 CLARIFIERS #1 AND #2 REHABILITATION

Morgan Hill Unified SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS. October 19, 2015

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

Request for Proposal CONSTRUCTION MANAGEMENT

Lawrence University Procurement Policy for Federally Sponsored Projects

Transcription:

Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida Young H. Kwak, Ph.D. 1 and Randall Bushey, P.E. 2 Abstract The traditional method of contracting for the construction of a residential or commercial development, infrastructure, schools, and government facilities has been the low bid approach. There are other project delivery methods which have been successfully utilized in the State of Florida. Design/Build is the most widely understood alternative project delivery method and is currently successfully employed in many construction projects throughout Florida and the world. A need to mix the best of both of these project delivery methods and provide greater owner interaction in the design and construction process lead to the development of the Construction Management at Risk (CM@Risk) project delivery method. The purpose of this paper is to familiarize the audience with the CM at Risk process. First it compares its benefits with the traditional and design/build approaches. Then, the paper explores the benefits of the CM@Risk project delivery method for the construction of Stormwater Treatment Area 3/4 (STA 3/4), the largest of the STAs in the Everglades Construction Project. Low Bid Project Delivery Method The traditional low bid method of project delivery has the owner hiring the A/E after the conceptualization of the project. The design team conducts site investigations, prepares the preliminary design alternatives, and completes the design. After owner approval, the design team prepares bid documents and assists the owner in selection of a contractor to construct the project. 1 Assistant Professor, Project Management Program, Department of Management Science, The George Washington University, Washington, DC 20052. kwak@gwu.edu 2 Stormwater Treatment Area ¾ Project Manager, South Florida Water Management District, West Palm Beach, Florida 33416-4680. rbushey@sfwmd.gov

The contractor selects his subcontractors and proceeds to construct the project from an interpretation of the plans and as clarified through Requests for Information to the owner and the architect/engineer. The traditional process requires the selection of the contractor based solely on the low bid and ability to meet the bid qualifications, e.g., M/WBE contract goals, bond and insurance requirements, etc. The bid price is the lowest price that the owner will get and usually escalates due to plan interpretations and errors, changing site conditions, and owner modifications to the project due to contractor phasing, material selection, and construction methodology. However, the low bid approach does not select contractors on the basis of qualifications or proven ability to perform on previous similar projects. Design/Build Project Delivery Method The Design/Build method of project delivery has been employed on numerous projects and has a proven record of success. This delivery method requires the owner to have a clear understanding of the project goals and the aesthetic and functional construction details. The process mixes the low bid and the qualifications of the contractor A/E firm into the selection process. The owner s ability to select from various designs at the bidding process reduces the time required to complete the project. The owner s involvement in the design is limited, but quality of construction can be improved through the selection process. CM at Risk Project Delivery Method The CM@Risk delivery method has some of the benefits of the Design/Build method (improved quality based on qualifications of the design build team, and fast-track construction capability). The CM@Risk process is based on team building between the owner, the design architect/engineer, and the contractorconstruction manager from the beginning of the project conceptual design through the final construction and operation or occupancy of the facility. The team approach provides for input from all of the team members throughout the design and the construction phases. This method of delivery provides for flexibility in the implementation of design changes late in the design process without impacting construction schedules and final delivery dates. The ability of the CM to input constructability reviews, construction phasing, material availability, and cost estimating throughout the design process reduces the probable occurrences of change orders, project construction delays, and increased project costs due to contractor identification of these elements in the design phase instead of the construction phase. CM at Risk The Process and The Benefits The selection of the architect/engineer is the initial step in the project. The CM@Risk method of construction develops a team comprising of the owner, the

design team, and the CM/contractor. This team is established in the early stages of the project. Team building through partnering is a key element in the project s success. The A/E firm is contracted through project completion, which includes site investigations, alternative analyses, cost estimates, detailed design, construction bid documents, and construction management services. The selection of the CM/contractor is similar to that under which the design consultant was selected. The CM submits a response to the owner s Request for Proposals. The response highlights the CM s personnel to be assigned to the project, previous experience on projects similar to the one being advertised, financial resources (Some state law requires the CM to have liquid assets equaling 1/20 th of the construction value), local office to service the project, and the CM s approach to the project. The CM is contracted for the design phase to conduct document review, constructability reviews, cost estimating and scheduling. The negotiated compensation is based on actual hours, overhead and profit. At 50% to 75 % detail design documents complete stage, the CM negotiates a Guaranteed Maximum Price (GMP) for the entire project. The GMP is composed of work, overhead, profit, and a contingency (usually 2 5%). The contingency goes back to the owner if it is not required for the project. The owner and the A/E are directly involved in the determination of the GMP through cost estimating at the 30%, 60%, and 90% design levels. The interaction of the CM with the design consultant during the design phase of the project enables the CM to input cost and construction details that should improve the GMP calculations and attain the project goals. The subcontractors are pre-qualified by the CM using the pool of contractors prequalified by the owner, with the goal of meeting the M/WBE goals of the contract and to have quality contractors in the specialty areas required to complete the project. The subcontractors are encouraged to participate in the design phase through periodic updates by the CM and communicate on the construction details. This interchange of ideas provides team building with the subcontractor pool and reduces the risk by the subcontractor when they are required to bid on the project. The CM s tasks include the development of separate trade bid packages to meet the overall project schedule. The construction of the project is the responsibility of the CM and the subcontractors selected through the pre-qualification low bid process. The reduction of the possibility of bid protests through the CM selection and the prequalification of the subcontractors, and the reduction of Request For Information s and change orders due to CM and subcontractor review involvement in the design phase are significant benefits to the CM at Risk project delivery method.

The implementation of the CM at Risk allows the fast tracking of the project if it is required to meet financial, legal or legislative time schedules. After a GMP is negotiated and the detailed design is completed for critical elements of the project, selected stand-alone elements of the project can be put on a fast track for construction. The CM Team (Owner, Consultant, and CM/contractor) has the ability to selectively complete designs, bid packages, and construction management teams necessary to meet the goals of the project. CM@Risk is an integrated concept that needs to be reflected in the owner s contracts with the CM Team. The process requires the communication and coordination of the entire team throughout the design, construction, and certification/start-up phases of the project. The CM@Risk and the Design/Build project delivery methods are being used as the preferred method by many school systems in the State of Florida. The State of Florida has continuous construction activities underway for its numerous agencies, departments, commissions, and legislative organizations. The Department of Management Services (DMS), Division of Building Construction, has the responsibility to manage the construction for these entities. About 10 years ago, they looked for a better method of project delivery than the low bid method, the State standard, and the project delivery method required under the State procurement laws. DMS is assisting these local government entities in the CM@Risk or Design/Build project delivery systems. DMS is providing training to the construction management staffs of the local school boards, cities, and counties so they can implement these project delivery systems on future projects. CM at Risk Application to STA 3/4 Design and Construction The CM@Risk process is a delivery system which has the opportunities to meet the Program goals of STA 3/4. The CM@Risk delivery system is like a threelegged stool with the project being the seat and the three legs being the CM Team. All three components are necessary to support the project goals. All three legs must support their share of the stool weight and function as a single Team. The CM@Risk delivery method reduces the real time required to complete the project from conception to completion. Time and dollars are saved in the solicitation of contractors and the reduced uncertainties encountered with the CM process when compared to the traditional delivery method of low bid. The application of the CM at Risk delivery method for the STA is compared in table 1.

STA requirement CM @ Risk benefit Traditional approach Allows fast tracking - component construction as the detail design is complete and the bid packages are developed Construction of the STA by 1 Oct 2003 in operation which requires a 6 12 month grow-in period for the cattails to develop Design and peer review of the 30%, 60%, & 90% detail designs are required to ensure quality and constructability CM is contracted to fulfill the peer review and the constructability review with significant input to schedule and construction phasing Provides for opportunities to bid elements separately but requires the management of numerous prime contractors A separate peer review consultant is hired to conduct the reviews at the designated phases contractors are not part of the review - a construction phasing plan is not possible without the contractor (s) on board Construction bid protests have been a major concern for the attainment of project schedules in other STAs Construction dollars are limited for the project control of design and construction costs are essential to the successful completion of the project The CM is hired through the CCNA process based on qualifications and is on board throughout the design and construction phases The GMP for the project is negotiated in the 75% design phase and is fixed for the entire project it will not be exceeded without the owner requesting a change order Thee is no control of the bid protest possibility with this delivery method the contractor is not on board until the detail design is compete and the bid packages are advertised The low bid price for each of the construction contracts can not be determined except through the cost estimates until the actual elements are bid. These are the lowest construction price contractor cost increases due to changing site conditions and plan interpretations are more likely under this delivery method The design requirements need to include the flexibility to include the implementation of supplemental technology to attain the 10 ppb concentration of phosphorus Significant elements of the previous STA construction can be implemented economically such as the operation of an on-site batch plant, the direct contracting with a blaster to ensure standardized economic application and technical quality, and the requirement of single design cross sections for specific levees Minority and women owned business opportunities are written into the projects through contract percentage goals of M/WBE participation Value engineering can be a critical element of the design process to enable the contract to proceed with the highest quality and within the approved schedule The CM method provides the flexibility to implement the supplemental technology late in the design process and during the construction Economic and technical requirements of the project can be instituted in the design and the construction phasing with the CM as peer review role and as the prime contractor subcontractors will have the same understanding of the construction phasing through the pre-qualification process Enhancement of the opportunities to include mentoring of the M/WBEs is an attractive element of the CM role in the construction of the STA improved performance of the M/WBE firms can be identified in past CM delivery methods for projects increased monitoring and upfront owner involvement Value engineering is accomplished during the design process which minimizes the possibilities of project delay due to value engineering after the design is completed and the contractor has started construction The traditional method will not provide the opportunity to modify the design late in the design process and into construction without the contractor fully involved in the design process the ability to implement changes in the construction methodology or schedule are limited Options for these contract elements can be alternatives in the bid process but final selection of the methodology and phasing are the responsibility of the low bidder the owner in the past has resisted the opportunity to require construction methods indicating that the bids would reflect the limited contracting environment The contract goal for M/WBE participation is the only opportunity for program enhancement within the low bid process pre-qualification of the M/WBE subcontractors is not an option under the current process of certification and prime contractor selection of these companies Value engineering can only be a contractor input after the contract is awarded and the contractor and subcontractors have started construction delays in production can be the result of cost savings at this late phase in the project Table 1. Application of the CM at Risk Delivery Method for the STAs

Summary The application of CM @ Risk for the construction of STA 3/4 is considered an alternative project delivery method that provides opportunities for time and cost savings. The selection of the CM/contractor will allow selection of the most qualified CM/contractor who will assume roles of peer reviewer and construction manager. The time required by certain aspects of this delivery method and the opportunities to reduce the time for construction through fast tracking and construction sequencing provide the buffer needed to meet the deadline. This method also provides the opportunity to be flexible for the implementation of supplemental technology, should the research provide clear direction as to the technically feasible and cost effective alternative. Although the same facility or project was not constructed using both the traditional and the CM @ Risk methods, a cost comparison could be accomplished. Costs in terms of initial, operational, and maintenance would tend to favor the CM quality and reject the low bid traditional method of project delivery. References 1. Interviews with Centex Rooney Construction Company Vice Presidents H. Jessie Brewer, on 20 Nov 98, in West Palm Beach, Florida; and Bill Scaringe, P.E., on 25 Nov 98 in Tallahassee, Florida 2. DMS presentation to the SFWMD Governing Board on 10 October 98 by Harold Barrand 3. Discussion with DMS staff in Tallahassee on 25 November 98 FAC Chapter 60D-5 and Request for Qualification document received and information received on the DMS web site 4. Presentation by Bill Charvat, AIA, at the AIA Florida Chapter Annual Meeting, in Boca Raton, 5 October 98 5. Palm Beach Post Article, Low bid not always first choice for schools, by Mary Ellen Flannery, 29 November 98 Request for Qualification Negotiated Fee, Guaranteed Maximum Price, Construction Management Contract Approach - DMS Aug 98 6. Chapter 60D-5: Procedures for Construction Contract Bidding, Award, Negotiation, and Changes Florida Administrative Code DMS implementation