How To Know What Caused A Tunnel Collapse



Similar documents
Impacts of Tunnelling on Ground and Groundwater and Control Measures Part 1: Estimation Methods

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Washington ,

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Coxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report

Wastewater Capital Projects Management Standard Construction Specification

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Soils, Foundations & Moisture Control

Construction sites are dewatered for the following purposes:

Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions

METHOD OF STATEMENT FOR STATIC LOADING TEST

COST AND PERFORMANCE REPORT

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

KWANG SING ENGINEERING PTE LTD

Liner system design for tailings impoundments and heap leach pads

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

Guidelines For Sealing Groundwater Wells

c. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Rehabilitation of Existing Foundation Building to Resist Lateral and Vertical Loads

REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Specifications for Residential Property Owners Connection to New Public Sewer

Pile test at the Shard London Bridge

WILLOCHRA BASIN GROUNDWATER STATUS REPORT

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Trench Rescue by Buddy Martinette

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

ENCE 4610 Foundation Analysis and Design

Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report. October 2011

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

REPAIRS TO DAMAGED SEWERS

Flowtite Jacking Pipe

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

MINIMIZING DEFECTS OCCURRENCES ON SFRC TUNNEL SEGMENT OF KLANG VALLEY MRT PROJECT

Soil behaviour type from the CPT: an update

SECTION NONREINFORCED CONCRETE SEWER PIPE

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Repair or Replacement - Band-Aids vs. Surgery

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

APPENDIX K PIPE INSPECTION

CPT interpretation in marine soils less than 5m depth examples from the North Sea

FREDERICK SHERRELL LTD

Sewer Rehabilitation Design Requirements

Drained and Undrained Conditions. Undrained and Drained Shear Strength

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Commercial Roof Inspection Form

IS THAT LINER THICK ENOUGH?

Understanding Septic Tank Systems

GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S HOUSTON, TEXAS

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

CPTic_CSM8. A spreadsheet tool for identifying soil types and layering from CPTU data using the I c method. USER S MANUAL. J. A.

Section SEWER PIPE INSTALLATION AND TESTING

Assessment. Ian Uglow Technical Director, SLR Consulting 7 th October 2010

APPENDIX G SETTLEMENT

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

SEWER CLEANING, INSPECTION AND ASSESSMENT

Cone Penetration Testing in Geotechnical Practice. Tom Lunne Peter K. Robertson John J.M. Powell

Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy

Designed and Engineered to Perform

SECTION SHEETING, SHORING AND BRACING

Emergency Spillways (Sediment basins)

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

QUESTION TO AUDIENCE

Pro-Lift Steel Pile Foundation Repair

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

Validation of methods for assessing tunnelling-induced settlements on piles

Installation of Large Diameter Buried Pipes

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Preventing water damage in the basement

A case study of large screw pile groups behaviour

Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns

PILE FOUNDATIONS FM 5-134

Soil Mechanics. Soil Mechanics

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008

How To Map A Lake In The North Of The Holland (Fiji)

A Guide to Structural Waterproofing

FY15 Gravity Sewer and Manhole Rehabilitation

Septic Records and Maintenance Guidelines

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

Structural Damage Due to Floods

Sewer systems: Failures and rehabilitation

JOHNSON STREET BRIDGE REPLACEMENT PROJECT

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Numerical Simulation of CPT Tip Resistance in Layered Soil

APPENDIX A PRESSUREMETER TEST INTERPRETATION

Transcription:

An unusual tunnel collapse, the Hull Wastewater Transfer Tunnel Australian Tunnelling Society Wednesday, 26th March, 2014 Steve Macklin Principal Tunnel Engineer/ Engineering Geologist, GHD Melbourne

References: Chamley et al (2000) North America Tunneling Conference, Boston June 2000. Published AUA News September 2000. Caiden, Chamley & Covil (2005) RETC Proceedings, 2005 BTS Informal Discussion at the ICE, November 2001, Tunnels & Tunnelling, March 2002 Machon & Stevens (2004) - Proc. Institution of Civil Engineers, GE3 Grose & Benton (2005) Proc. Institution of Civil Engineers, GE4 Various (2006) - Discussion: Proc. Institution of Civil Engineers, GE2 Munks, Chamley & Eddie (2004) Proc. North American Tunnelling 2004 Brown (2004) - Proc. Institution of Civil Engineers, GE3 Tunnels & Tunnelling March 2002

The project The failure The investigation Possible causes Remediation Implications for the insurance industry Lessons learned Questions (steve.macklin@ghd.com) An unusual tunnel collapse, the Hull Wastewater Transfer Tunnel

The project 10.6km tunnels 10No. Shafts 7.5m to 12.5m int. diam. 2No. Jet grout maintenance blocks 6No. De-watering & comp. air stops 3.6m ID lining: 6No. Trapezoidal Segments, 1m long, 250mm thick Segments cast vertically location 50M contract to construct a 10.6km long tunnel for Yorkshire Water's 200M Humbercare sewage collection and processing scheme.

The project 1 2 3 4 5 6 1. Medium dense silty, fine to medium alluvial SAND (non-tidal aquifer) 2. Firm to stiff and friable PEATY CLAY/SILT, with fragments of timber, aquitard, k h 400k v 3. Upper alluvial SILTY FINE SAND grading down to GRAVELLY SAND to SANDY GRAVEL 4. Soft to firm to stiff thinly LAMINATED CLAY (aquiclude, k h 10k v ) 5. Dense fine AEOLIAN SAND 6. glacial SAND AND GRAVEL (tidal aquifer) HOLOCENE PLEISTOCENE

The project The failure The investigation Possible causes Construction News, 14 September 2000 Remediation Implications for the insurance industry Lessons learned Questions. All tunnels leak to some extent, but when I was told of the enormity of this situation I couldn't understand what could have gone wrong

Failure sequence: The failure 19:00 R2403 2L/min leak right knee 23:30 7L/min 00:30 black organic smelling water, leaking around circle joint 01:30 sand filling invert, rings buckling 02:20 invert heaving, re-bolting attempted 02:45 manrider derailed and abandoned 03:00 segments crazing and spalling 03:30 tunnel abandoned 04:00 water main burst, ground cracking, shaft sinking 07:30 tunnel inspected, filled with fine sand 60m diameter depression - maximum 2.6m settlement the volume of the settlement depression was about 2600m 3 - tunnel filled with fine sand/silt approx. 200m either side of shaft

The project The failure The investigation Possible causes Grose & Benton, 2005 Remediation Implications for the insurance industry Lessons learned Questions The investigation into the cause of the collapse demanded.. urgent answers. Clearly, future tunnelling, and the previously constructed tunnel, were at risk until conclusions were available regarding the cause

The investigation So why did an apparently stable, grouted-up lining fail weeks after construction? Was it: Something in the ground conditions (e.g. peat compressibility, mobile sands)? Hydrogeological effects (e.g. damming, tidal fluctuations in water pressure)? A design flaw (e.g. segment capacity, shear pad failure, gasket bypassed)? Construction problems (e.g. ring damage during shaft entry, removal of circle joint bolts, annulus grouting, shaft disturbance)?

The investigation A comprehensive investigation was undertaken, this included: New ground investigations including: 22 BHs, 71 CPTs, PM tests Triaxials, Rowe Cells, oedometer, Pollen & species analysis, C 14 dating (Uni Hull) and LOI (in peat); Atterbergs; PSD; SEM (aeolian sand); dispersivity (laminated clay); water chemistry; Centrifuge (Cambridge Univ. Eng. Dept.); Hydro (piezo, 2No. Pump tests, tracer Uni Sheffield) lining design checks 2D and 3D FEA modelling of possible failure mechanisms Witness statements to reconstruct sequence of events Examination of available construction records

The investigations Centrifuge tests limited by modelling simplifications required, however confirmed: Tunnel buoyancy caused longitudinal deformation relative to fixity at the shaft softening/ disturbance of soil local to the shaft Circle joint opening If laminated clay in invert stays intact NO FAILURE But if fine single size SAND gains access FAILURE

The project The failure The investigation Possible causes Remediation Grose & Benton, 2005 Implications for the insurance industry Lessons learned Questions A relatively unusual feature of the collapse was that there was no immediately obvious cause.. usually the blame is attributed to some design or construction aspect or.. adverse ground conditions. but in this case all seemed satisfactory

Possible causes Consequence of longitudinal movement: top hat incident? shear pads failure? Nib crushed gasket bypassed?

Possible causes Highly mobile fine sand silt in: In Holocene alluvium laminated clay Aeolian sands Previous problems: Hull Tidal Surge barrier (Fleming et al 1980 and McMillan, 1984) Shaft tremmie problems with trapped silt sludge (T4) Problems with ground anchor holes piping Possible glacial disturbance providing water path in laminated clay The peat/organic clay: Disturbance and softening during shaft construction? Loss of confinement due to buoyancy, compression? leakage & consolidation at the early stages? Groundwater pressure: Failure at HIGH TIDE damming by tunnel 2bar in lower aquifer but... Upper aquifer no tidal response so lower pressure

The project The failure The investigation Possible causes Brown, 2004 Remediation Implications for the insurance industry Lessons learned Questions. The use of liquid nitrogen to create a stable environment in which to rebuild the tunnel was a technically challenging option. Cost and programme implications were significant

Remediation 40m 75m W2 W1 E1 E2 E3 Re-mining using AGF to form 1.5m ice-walls around tunnel

The project The failure The investigation Possible causes Remediation Implications for the insurance industry Lessons learned Questions Underwriters reluctant to Insure Tunnel Projects without adoption of Joint Code of Practice please provide your views and comments June 2003, E-Mail from AON, KCRC s Insurance Brokers (Jesudason HKIE, download March 2014)

Insurance implications Chamley et al (2000): The Construction All Risks (CAR) insurance policy covered both client and contractor - protected against the damage repair costs. ACCELERATION INSURANCE addressed the measures necessary to get the construction back on track to meet the completion date. Where the CAR policy does not cover the remedial works and programme mitigation costs, the COST OVER-RUN INSURANCE limited the clients financial liability. Client saw little impact and the anticipated outturn cost was within the original estimate.

Insurance implications Munich Re - Wannick (2006) BTS closed face tunnelling report on Hull and Portsmouth collapses May 2002 BTS ABI JCOP published September 2003 - International Tunnelling Insurance Group (ITIG) by 2005

The project The failure The investigation Possible causes Covil et al (2005) Remediation Implications for the insurance industry Lessons learned Questions four key risks during construction are safety (life and economic), cost, time and quality. These can all be identified, assessed, valued, mitigated and then apportioned to the appropriate project stakeholder

Lessons learned Carry out detailed geo-hazard risk assessments and risk management processes early (e.g. identifying previous issues with the mobile sands ) Keep on top of TBM data logging never know when you need the data note the Closed Face working party (2002) recommendations (4.2) Ensure annular grouting and take a zero tolerance to leaks Smooth transition from rigid shaft to flexible tunnel design for permanent bolts or some other means Are shear pads (for build accuracy) a good idea? Distance between EPDM gasket and extrados? Segment design and casting adequate cover and joint quality Monitoring (e.g. ground movement, water pressures) in critical locations - difficult around a working shaft but this is a key risk area Design for sufficient redundancy / robustness avoid false economies

The project The failure The investigation Possible causes Grose & Bentley (2005)_Discussion Remediation Implications for the insurance industry Lessons learned Questions buoyancy and tidal variations caused repeated cyclic movement of the tunnel even with a fully grouted annulus. This. may have created both a path for the sand to travel towards the tunnel and compromised the gasket.

www.ghd.com