Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project



Similar documents
How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Introduction to Microsoft Project 2010

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class.

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

How to make a line graph using Excel 2007

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

Microsoft Access 2010 handout

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Creating Fill-able Forms using Acrobat 8.0: Part 1

Project 2010 Introduction

Using an Access Database

In this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move

Beginning Microsoft Project

Project planning with MindGenius

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

OVERVIEW. Microsoft Project terms and definitions

Revealing the Secrets of Microsoft Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Word Track Changes

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Creating Forms with Acrobat 10

Introduction to Computers: Session 3 Files, Folders and Windows

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

How to Edit an . Here are some of the things you can do to customize your

Basic Microsoft Excel 2007

WEBTrader. User Guide

Introduction to MS WINDOWS XP

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

Workspaces Creating and Opening Pages Creating Ticker Lists Looking up Ticker Symbols Ticker Sync Groups Market Summary Snap Quote Key Statistics

EXCEL Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development

Business Objects Version 5 : Introduction

Website Editor User Guide

Appendix A How to create a data-sharing lab

Microsoft Excel 2013: Headers and Footers

University of Sunderland. Microsoft Project. Basic Guide

Microsoft Access 2010 Part 1: Introduction to Access

Tracking Project Progress

Excel Unit 4. Data files needed to complete these exercises will be found on the S: drive>410>student>computer Technology>Excel>Unit 4

Excel 2003 A Beginners Guide

Computer Training Centre University College Cork

Creating a New Project

Introduction to Microsoft Access 2013

MicroStrategy Desktop

What Do You Think? for Instructors

Creating a Database in Access

Instructions for Creating an Outlook Distribution List from an Excel File

Basic Excel Handbook

Creating and Using Forms in SharePoint

Optimism for Mental Health

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

BusinessObjects: General Report Writing for Version 5

Excel for Data Cleaning and Management

Project Management: Intermediate Microsoft Project 2010

Appointment Scheduler

CI Financial Exception Dashboard. User Manual

PROJECT ON MICROSOFT ACCESS (HOME TAB AND EXTERNAL DATA TAB) SUBMITTED BY: SUBMITTED TO: NAME: ROLL NO: REGN NO: BATCH:

Crystal Reports Payroll Exercise

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

At the top of the page there are links and sub-links which allow you to perform tasks or view information in different display options.

DRUPAL WEB EDITING TRAINING

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Creating a Newsletter with Microsoft Word

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2010 Advanced

CREATING EXCEL PIVOT TABLES AND PIVOT CHARTS FOR LIBRARY QUESTIONNAIRE RESULTS

Introduction to Microsoft Access 2010

Lab 2: MS ACCESS Tables

Planning and Managing Projects with Microsoft Project Professional 2013

Using Adobe Dreamweaver CS4 (10.0)

User Tutorial on Changing Frame Size, Window Size, and Screen Resolution for The Original Version of The Cancer-Rates.Info/NJ Application

MyOra 3.0. User Guide. SQL Tool for Oracle. Jayam Systems, LLC

Internet Explorer 7. Getting Started The Internet Explorer Window. Tabs NEW! Working with the Tab Row. Microsoft QUICK Source

Spreadsheet - Introduction

Planning and Managing Projects with Microsoft Project Professional 2013

All V7 registers support barcode printing, except the Sharp 410/420 1A ROM and that limitation is based upon the register.

Customer Transaction FBL5N

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

TILOS GETTING STARTED & EXERCISES

Module One: Getting Started Opening Outlook Setting Up Outlook for the First Time Understanding the Interface...

FleetFocus M5 Basic Application Navigation Manual

A database is a collection of data organised in a manner that allows access, retrieval, and use of that data.

Planning and Managing Projects with Microsoft Project Professional 2013

Instructions for Formatting MLA Style Papers in Microsoft Word 2010

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Working with sections in Word

Access I Tables, Queries, Forms, Reports. Lourdes Day, Technology Specialist, FDLRS Sunrise

Making Visio Diagrams Come Alive with Data

Microsoft Project Microsoft Project The smart way to learn. Microsoft Project one step at a time!

Microsoft Office 2010: Introductory Q&As PowerPoint Chapter 1

Windows 95. 2a. Place the pointer on Programs. Move the pointer horizontally to the right into the next window.

Most of your tasks in Windows XP will involve working with information

AIM Dashboard-User Documentation

Enhanced Formatting and Document Management. Word Unit 3 Module 3. Diocese of St. Petersburg Office of Training Training@dosp.

Transcription:

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary, request departmental network attached storage (NAS) space for your project following the instructions on this web page, http://www.computing.vt.edu/infrastructure_services/nas/. 3. Access the departmental network attached storage (NAS) space for your project following the instructions on this web page, http://www.computing.vt.edu/infrastructure_services/nas/. How to create task dependencies between projects First way, if using a Master project 1. Open the Master.mpp project plan file. 2. On the View menu, click Gantt Chart. 3. If not already expanded, in the Task Name column, click the little plus sign next to each project name you want to create a dependency between, to see all of that projects tasks. For example, to create a dependency between ProjectAlpha and ProjectBravo, click the little plus sign next to each of these projects to show its tasks. 4. In the Task Name field, select two or more tasks you want to link in the order you want to link them. For example, if a task in your project is dependent on the completion of a task in another project (finish to start), select the task in the other project first, hold down the CTRL key, then select the dependent task in your project. 4.1. To select nonadjacent tasks, hold down CTRL, and then click the tasks you want to link. 4.2. To select adjacent tasks, hold down SHIFT, and then click the first and last tasks you want to link. 5. Click the Link Tasks icon on the standard toolbar or choose Edit > Link Tasks. 6. Microsoft Project creates a finish to start task link by default. You can change this task link to startto start, finish to finish, or start to finish by: 6.1. Selecting the task that is linked to an external predecessor. (external predecessor: A relationship in which the start date of a task in your project depends on the finish date or completion of a task in another project.) 6.2. Click Task Information on the standard toolbar or choose Project > Task Information, and then click the Predecessors tab. 6.3. Select a different dependency type in the Type column. 7. When finished close the master project and be sure to save the changes to all Yes to all or each of the changed projects. ITPMMSProjectDependencies.doc Page 1 of 5 Last revised: 10/13/2008 10:14 AM

Second way, open each project file 1. Open both projects, the project containing the task you want to link to and the project containing the task you want to link from. 2. On the Window menu of your project, click Arrange All. 3. In the Task Name field, click the task for which you want to create a dependency to an external predecessor. For example, if a task in your project is dependent on the completion of a task in another project, the task in the other project is an external predecessor. 4. Click Task Information on the standard toolbar or choose Project > Task Information, and then click the Predecessors tab. 5. In the ID column, type the filename (the.mpp file) and ID number of the external predecessor, separated by a backslash. For example, ProjectBravo\1 for Task ID 1 in a file named ProjectBravo.mpp. 6. To change the task dependency (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish to start [FS], Start to start [SS], Finish to finish [FF], and Start to finish [SF].), to a type other than the default finish to start, select a different dependency type in the Type column. s a. By default, you are notified if data in an externally linked project has changed. The external predecessors and successors and impacts to your schedule are displayed when you open a project with external links, and you can choose to accept any or all changes. b. If you want to unlink tasks, select the tasks you want to unlink in the Task Name field, and then click Unlink Tasks on the standard toolbar or choose Edit > Unlink Tasks. The tasks are rescheduled based on links to other tasks or constraints. c. The externally linked task appears dimmed in the task list. Double clicking a task with an external successor (successor: A task that cannot start or finish until another task starts or finishes.) or an external predecessor (predecessor: A task that must start or finish before another task can start or finish.) opens the project containing the external task if the project is available. a. Do not use the Microsoft Project, Linked Fields (using Paste Link) technique to create task dependencies. Otherwise, telling which task is linked to which becomes difficult. Viewing task dependencies between projects If using a Master project 1. Open the Master.mpp project plan file. 2. On the View menu, click Gantt Chart. ITPMMSProjectDependencies.doc Page 2 of 5 Last revised: 10/13/2008 10:14 AM

3. If not already expanded, in the Task Name column click the little plus sign next to each project name to see all of that projects tasks. 4. If not already open, display the Formatting toolbar by choosing View > Toolbars > Formatting. 5. From the Filter drop down menu near the right side of the Formatting toolbar choose Dependencies. (Dependencies is a custom filter that must be added to the project plan.) 6. Only external Predecessors and Successors (plus their associated summary tasks) are displayed using this filter. 7. If the graphical Gantt bar chart (with the horizontal bar graphs) is not visible on the right side of the project window then: 7.1. Move the slider for the Gnatt bar chart window to the left or right to correspond with the start or finish date of the desired task until the bar graphs are visible. 7.2. If the slider is not visible, move your cursor to the left edge of the vertical scroll bar until the pointer becomes a double arrowed, double vertical line. Click and drag to the left to display the Gantt bar graphs. 8. Hover the mouse pointer over any of the link lines between dependent tasks to view detailed information about that link. Notice that in the information displayed is the ID (or Task) number of both the From: and To:, linked tasks. This tells you which task is linked to which. 8.1. If you double click a link line the Task Dependency popup displays similar, but not as detailed information. 9. When finished choose All Tasks from the Filter drop down menu on the Formatting toolbar. tasks (because they re hidden by the filter). From the project file 1. Open your project.mpp project plan file. 2. On the view menu, click Gantt Chart. 3. If any of Project, External Task, Predecessors, and Successors columns are not displayed insert them by right clicking the column header to the left of which you want to insert one of these columns, and then choose Insert Column, or from the menu bar choose Insert > Column. 3.1. In the Column Definition popup, select the Field Name drop down menu and choose Project, External Task, Predecessors, or Successors. (Hint: Once the Field Name drop down is selected or highlighted type the first few characters of the desired column name to quickly find that column in the list.) 3.2. Repeat the step above until the Project, External Task, Predecessors, and Successors columns are displayed. Method 1, using the custom Dependencies filter 4. If not already open, display the Formatting toolbar by choosing View > Toolbars > Formatting. ITPMMSProjectDependencies.doc Page 3 of 5 Last revised: 10/13/2008 10:14 AM

5. From the Filter drop down menu near the right side of the Formatting toolbar choose Dependencies. (Dependencies is a custom filter that must be added to the project plan.) 6. Only external Predecessors and Successors (plus their associated summary tasks) are displayed using this filter. 7. If the graphical Gantt bar chart (with the horizontal bar graphs) is not visible on the right side of the project window then: 7.1. Move the slider for the Gnatt bar chart window to the left or right to correspond with the start or finish date of the desired task until the bar graphs are visible. 7.2. If the slider is not visible, move your cursor to the left edge of the vertical scroll bar until the pointer becomes a double arrowed, double vertical line. Click and drag to the left to display the Gantt bar graphs. 8. Hover the mouse pointer over any of the link lines between dependent tasks to view detailed information about that link. Notice that in the information displayed is the ID (or Task) number of both the From: and To:, linked tasks. This tells you which task is linked to which. 8.1. If you double click a link line the Task Dependency popup displays similar, but not as detailed information. 9. When finished choose All Tasks from the Filter drop down menu on the Formatting toolbar. tasks (because they re hidden by the filter). Method 2, using Predecessors and Successors 4. Click the Predecessors or Successors column of the task in your plan that begins with a backslash (\). 5. Look at the edit bar (towards the top just below the toolbars). The information displayed is the path to the location of the dependent project that this task is linked to. 6. The last two pieces of information in this path are: 6.1. Second to last: name of the dependent project file. 6.2. Last: the task number of the specific, linked, dependent task in the dependent project. If the type of dependency is anything other than the default finish to start, the abbreviated type of dependency (Start to start [SS], Finish to finish [FF], and Start to finish [SF]) appends the task number. 7. Immediately above (if a Predecessor) or below (if a Successor) the dependent task in your plan is the grayed out dependent task in the other plan. You should see a Yes in the External Task column of this grayed out task indicating it is an external, dependent task. 7.1. In the Predecessors or Successors column of the grayed out task is a number that corresponds to the task in your plan that this dependent task is linked to. If appropriate, the type of dependency appends the task number. ITPMMSProjectDependencies.doc Page 4 of 5 Last revised: 10/13/2008 10:14 AM

a. An advantage of this view is to use the number in the Predecessors or Successors column to tell which specific task (ID number or Task number) in your project is linked to which specific task in the dependent project. b. Externally linked tasks appear dimmed in the task list. Double clicking a task with an external successor or an external predecessor opens the project that contains the external task, if the project is available. Method 3, using Links Between Projects tool 4. Choose Tools > Links Between Projects 5. In the Links Between Projects popup click the External Predecessors or External Successors tab to see all, of that type of linked tasks, in your project. tasks (only the dependent tasks are displayed). b. Another possible limitation of this view is, not knowing the specific task ID number in the dependent project that your task is linked to. (: You can see the name of the dependent project in the Path: information at the bottom of the Links Between Projects popup window.) c. An advantage of this view is the ability to get a quick look at dependent tasks without using filters or displaying additional columns. ITPMMSProjectDependencies.doc Page 5 of 5 Last revised: 10/13/2008 10:14 AM