DRAFT Addendum to IVM Best Management Practices
|
|
|
- Fay Sparks
- 10 years ago
- Views:
Transcription
1 Integrated Vegetation Management on Pipeline Rights-of-Way Addendum to Best Management Practices: Integrated Vegetation Management Ryan Brockbank, Western Environmental Consultants, Inc. The intent of this document is to serve as an addendum to the Best Management Practices: Integrated Vegetation Management for Electric Utility Rights-of-Way published by the International Society of Arboriculture. The aforementioned publication and this addendum are designed to provide managers and field technicians with what industry experts consider to be the most appropriate Integrated Vegetation Management (IVM) techniques that can be utilized on pipeline right-of-way (ROW) projects. It is recommended that all site-specific safety, environmental, and facilities conditions and constraints be evaluated prior to implementing any best management practices (BMPs) described. This publication is not intended to replace the reader s organization policies and procedures nor does it supersede applicable laws and regulations. Introduction Pipelines carrying natural gas, oil, water, and other liquids and gases traverse North America above ground and underground along rights-of-way (ROW). Vegetation growing on pipeline ROW can compromise the integrity of pipeline facilities and cause problems with public safety, energy supply, security, emergency service restoration, ROW and facility access, and lines-of-sight (Miller, 2007). Vegetation that is not maintained can also compromise compliance with applicable regulatory requirements. A properly maintained pipeline ROW is typically kept clear of trees and large shrubs that can interfere with above-ground pipelines and underground pipelines via plant root systems. Vegetation on ROW growing near pipelines can be systematically managed to: 1. Facilitate safe, reliable, and cost-efficient service and transport; 2. Facilitate routine ground access to the ROW for inspection, maintenance, and testing of the pipeline; 3. Facilitate aerial patrol of the ROW to identify maintenance needs and encroachment issues; 4. Facilitate compliance with applicable laws and regulations; and 5. Potentially provide natural resource values (e.g., wildlife habitat, grazing, recreation, etc.). Vegetation on pipeline ROW is most commonly managed by manual and mechanical methods (i.e., mowing, chainsaw use and other physical means of cutting vegetation). Mechanical cutting can be an effective method to initially clear vegetation on ROW, but potential safety, economic, and environmental issues indicate that more progressive vegetation control methods may be necessary to effectively manage pipeline ROW vegetation over the long-term. The use of IVM can reduce maintenance costs and improve access to and security of pipeline ROW. IVM has proven cost-effective in controlling unwanted vegetation in other ROW corridors with similar objectives, such as electric transmission ROW and along roadsides. The potential exists to manage vegetation on pipeline ROW in a similar manner as electric transmission ROW because both experience similar vegetation management challenges (Nowak et al., 2002). Page 1
2 Integrated Vegetation Management IVM is a system of managing vegetation by implementing different control options, which are based on anticipated effectiveness, environmental impact, site characteristics, economic considerations, and public and worker health and safety. IVM principles and practices can be utilized to 1.) manage vegetation so that it is compatible with the intended use of the ROW and 2.) control vegetation that can present safety and service reliability challenges. The various phases of IVM have been described as follows (ANSI A300 Part 7, 2011 and Miller, 2007): 1. Define and document objectives; 2. Assess field conditions to evaluate the site for planning purpose; 3. Set ecological and economic thresholds for incompatible vegetation that indicate a need for treatment; 4. Prescribe site-specific treatments based on inventory of the site condition and knowledge of the compatible and incompatible organisms; 5. Utilize a diverse array of treatment modes and methods implement IVM; and 6. Monitor treatment effects on target and non-target organisms. Vegetation is managed to sustainably produce desired conditions (plant community density, structure and composition) and associated values consistent with management objectives. The choice of control methods is based on the environmental impact and the anticipated effectiveness of the control method, along with site characteristics, safety, current land use and other factors (Miller, 2007). IVM is a process that balances the use of physical (manual and mechanical cutting), chemical (herbicides), cultural (tillage) and biological (allelopathy, herbivory) treatments for managing plant populations to tolerable levels (McLoughlin, 1997). The method used at one point in time can establish the future trajectory of vegetation development on the site, influencing the frequency, extent, and type of future treatment needs. When selecting vegetation control methods, effectiveness should be a dominant factor, but the choice of method can be equally influenced by site characteristics, applicable regulations, environmental effects, cost, and public sentiment. In IVM, no one treatment is consistently utilized; rather, each management decision is made with full consideration of all treatment options (Nowak et al., 2002). Chemical treatment methods (e.g., herbicides) can be an effective IVM tool for controlling plant populations when used properly (Figure 1). Herbicides are widely recognized as an effective way of directly controlling incompatible plants. In some cases, the use herbicides in a ROW segment may be the only viable IVM prescription, particularly when desired management objectives cannot be achieved over the same ROW segment through utilization of physical, biological, or cultural control methods. Numerous scientific studies conclude that the use of stable, low-growing, less intrusive plant communities that compete with and resist invasion of incompatible vegetation can be one of the most effective long-term vegetation management tools on overhead electric transmission ROW (Bramble and Byrnes, 1983; Nesmith et al., 2004). Documented benefits of this vegetation management approach include improved cost effectiveness, service reliability, safety, aesthetics, wildlife habitat enhancement, and decreased fire risk. This success can be translated to vegetation management challenges on pipeline ROW. Page 2
3 DRAFT Addendum to IVM Best Management Practices Figure 1. A distribution gas pipeline ROW managed with IVM principles and techniques (ROW was treated with herbicide two years prior). Utilizing IVM principles and practices to manage vegetation on pipeline ROW can lead to significant cost savings and enhance plant and wildlife habitat conditions on the pipeline ROW. Similar benefits have been realized by electric utilities with power line corridors. In general, IVM has not been widely used on pipeline ROW. Many vegetation management objectives and challenges are similar, regardless of ROW function, and much can be learned by reviewing vegetation control practices in other disciplines and industries (Nowak et al., 2002). Field research on pipeline ROW is valuable to further understand how IVM can be adapted to pipeline vegetation management programs. Reasons and Benefits for Pipeline ROW Vegetation Management The following section details the reasons for managing vegetation and the benefits of utilizing IVM principles and practices on pipeline ROW. Safety and Reliability Urban and rural development as well as the natural growth of plants has resulted in encroachments near to or within pipeline ROW. Vegetation and other obstructions may interfere with safe and effective access, inspection, maintenance and operation of pipeline facilities. Pipeline operators may also control vegetation to mitigate potential fire risk and hazards (e.g., near gas and oil wells and Page 3
4 pipelines). To ensure safety and reliability, pipeline operators require direct and immediate access to facilities and buried pipelines in order to conduct testing on the pipeline to monitor its integrity and to perform general maintenance and repairs. In the event of an emergency, a clear ROW is necessary for pipeline operators and emergency response officials. Obstructions on the right of way can prohibit safe and timely access in case of emergency. Third-party damages are a leading cause of incidents to natural gas pipelines. Third-party incidents can occur when, for example, digging, blasting, boring, excavating or other construction occurs near the pipeline and the buried pipe is accidentally hit. This can cause damage to the underground pipeline, nearby property and even personal injury. It is recommended that any person contact the local utility locating services prior to digging or excavating near underground utilities and have all underground utilities located and marked. A well- managed pipeline ROW helps identify the presence of underground facilities by clearly delineating the presence of the ROW, and improving visibility of markers. Pipeline Inspection, Maintenance, and Testing A clear ROW can make inspection efforts more safe and effective. The U.S. Department of Transportation requires that many pipeline ROW be routinely patrolled 1. Inspections may identify signs of a leak or damage and spot activities occurring near the pipeline that may threaten its safety or integrity. Excessive vegetation such as trees, brush, landscaping or other obstructions can block the view of and impede access to the pipeline. In addition, tree roots can damage pipeline coating or the pipe itself. Pipeline coating can be an important safety measure as it helps prevent corrosion of the pipeline. A ROW clear of obstructions is important because it helps identify the location of pipeline facilities to those who are performing construction, inspection, testing or routine maintenance work and for responding to emergencies near the buried pipeline. Pipeline markers, unobstructed by vegetation, placed along a ROW are a visible indicator that an underground pipeline is in the area. Pipeline markers are important for public safety as well. It is a federal crime to willfully deface, damage, remove or destroy any pipeline sign or ROW marker. While the markers are very helpful to indicate the presence of pipelines in the area, they do not show the exact location, depth, or how many pipelines are in the ROW. These pipeline markers can provide valuable information about the type of underground facilities and important contact information. Aerial Patrol of Pipeline ROW In portions of the United States where higher densities of woody vegetation are present, vegetation clearing and maintenance can be performed to allow for and facilitate effective aerial reconnaissance (Figure 2). Dense, low-growing, green vegetation cover is desired to monitor the pipeline ROW from the air to identify below ground leaks. Herbs, grasses, and forbs have smaller, more localized roots as compared to trees having more extensive and established root systems. Smaller, lower-growing plants can experience root death and exhibit plant necrosis sooner and more noticeably than trees as a result of the soil oxygen depletion that occurs with gas pipeline leaks. 1 Code of Federal Regulations, Title 49, Page 4
5 Aerial reconnaissance of the ROW utilizing photo imagery and lasers to capture field information can help the ROW manager to make maintenance decisions. Ground verification of the aerial imagery and data may be required depending upon field conditions and vegetation density on the pipeline ROW. The ROW owner can make more informed decisions with appropriate analytical and delivery tools that can be utilized as part of the long-term management of the pipeline ROW. Figure 2. Aerial reconnaissance of a natural gas pipeline ROW with vegetation impacts caused by pipeline-associated ambient soil temperature increases. FERC Compliance The Federal Energy Regulatory Commission (FERC) has various compliance requirements for pipeline ROW. FERC requirements concerning revegetation and maintenance of the pipeline ROW can be found in Upland Erosion Control, Revegetation, and Maintenance Plan (2003). The FERC policy concerning pipeline ROW vegetation states that: "Routine vegetation maintenance clearing shall not be done more frequently than every three years. However, to facilitate periodic corrosion and leak surveys, a corridor not exceeding 10 feet in width centered on the pipeline may be maintained annually in a herbaceous state. In no case shall routine vegetation maintenance occur between April 15 and August 1 of any year." The intent is to protect wildlife (e.g., nesting birds) and habitat from mechanical vegetation control methods. Clearing, as described above, refers to the physical removal of vegetation from the ROW. Page 5
6 Removed vegetation can be detrimental to wildlife, especially ground-nesting birds utilizing the ROW plant communities. IVM can offer alternative control measures that are compliant with FERC constraints and can still be applied between April 15 and August 1 to manage incompatible vegetation on pipeline ROW. Natural Resources Impacts and Enhancements Natural resources typically impacted or enhanced by ROW management activities include 1.) biological resources (e.g., plants and wildlife), 2.) soil and land use resources, 3.) water resources (e.g., wetlands, streams, groundwater), 4.) air resources, and 5.) cultural resources (e.g., archaeological sites). For purposes of this addendum, biological resource impacts and enhancements are covered in more detail. Impacts to wildlife resources from pipeline ROW activities can result in habitat loss, habitat and population fragmentation, introduction of invasive plant species, wildlife displacement, and disruption of rare, threatened, and endangered species. However, numerous studies have demonstrated that properly managed ROW can provide valuable habitat for many species of wildlife, including game and non-game species, as well as threatened and endangered species. As part of IVM, establishing goals for what type of wildlife or natural community is desired to benefit from ROW management activities is necessary to determine what vegetation control method may best be utilized. Vegetation within a ROW is typically maintained free of large shrubs and trees and as such, an early successional plant habitat is created. A positive effect of an early successional habitat in the ROW is the potential for an overall increase in plant species diversity. The ROW creates an open space that when surrounded by trees, provides a habitat for meadow-type plants to thrive (Bramble and Byrnes, 1983). Additionally, the creation of early successional plant habitats in a ROW is detrimental to some species and beneficial to others. For example, bird species that nest in brush or grass plant communities facilitated by the Wire Zone-Border Zone method are particularly prevalent on ROW. On the State Game Lands 33 Research and Demonstration Project in central Pennsylvania, the abundance of birds along a transmission ROW was about seven times higher than in the adjacent forest and nearly four times as many birds were observed in the shrubby border zones than in the wire zones (Yahner et al., 2002). With its combination of trees and shrubs, the border zone is important habitat for bird species. There are many opportunities for pipeline companies to work with public and private organizations to demonstrate that their ROW can be compatible with wildlife enhancement programs. Pipeline companies also have a vested interest in maintaining stable and compatible vegetation on their ROW in order to prevent erosion and cost-effectively manage ROW operations (Nowak et al., 2002). The pipeline industry can work collaboratively with wildlife, land conservation and environmental groups to effectively manage vegetation, adequately protect the environment, and provide multiple land use values on pipeline ROW (Figure 3). Examples of environmental benefits and impacts associated with vegetation management and wildlife compatibility with ROW and their vegetative communities may be found in the series of symposia proceedings titled Environmental Concerns in Rights-of-Way Management. Page 6
7 Figure 3. Example of multiple land uses on a natural gas pipeline ROW. Pipe Zone Border Zone Many pipeline ROW are relatively wide which can allow for varied vegetation management techniques and methods. There is the potential for the pipeline zone to be managed one way, while the offpipeline zones, or border zones, be alternatively managed. Electric transmission ROW and pipeline ROW can both be managed using distinct zones. Electric transmission ROW have been successfully managed using the Wire Zone Border Zone method (Figure 4). Low-growing vegetation is typically encouraged in the Wire Zone (i.e., under the overhead wires and in the immediate adjacent area). The Border Zone is a transition zone extending toward the edge of the ROW and is managed for taller vegetation. The zone designation used for electric transmission ROW can be applied to pipeline ROW (Figure 5). On pipeline ROW, vegetation can be managed according to where the plant is located on the ROW in relation to the pipeline. Over the pipe zone, forbs and grasses may be encouraged. Taller growing vegetation species with more extensive root systems can be managed on the edges of a pipeline ROW. A more comprehensive approach utilizing pipeline zone border zone vegetation management concepts and various vegetation control methods can be realized through utilization of IVM principles and practices (Nowak et al., 2002). Page 7
8 Figure 4. Wire Zone-Border Zone concept for integrated vegetation management on electric transmission ROW. Figure 5. Pipe Zone-Border Zone concept for integrated vegetation management on pipeline ROW (Adapted from Yahner et al., 2001). Page 8
9 Summary Pipeline and electric utility ROW have many similarities with regard to siting, planning, construction methods, operational procedures, and maintenance practices. Vegetation growing on ROW can interfere with pipeline and electric facility safety and reliability. A commitment to safety and sound economic and environmental management of natural resources indicates that more progressive vegetation control methods may be necessary to effectively manage pipeline ROW vegetation over the long-term. IVM offers a systematic way of planning and implementing a pipeline vegetation management program. The various phases of IVM have been described as: 1) define and document objectives; 2) assess field conditions to evaluate the site for planning purpose; 3) set ecological and economic thresholds for incompatible vegetation that indicate a need for treatment; 4) prescribe site-specific treatments based on inventory of the site condition and knowledge of the compatible and incompatible organisms; 5) utilize a diverse array of treatment modes and methods implement IVM; and 6) monitor treatment effects on target and non-target organisms. Managers can select control options that best promote management objectives as well as address safety, environmental, and economic factors. When effectively implemented, IVM is a systematic, preventive strategy that results in site-specific treatments to meet management objectives. A sound program includes documented processes to evaluate results, which should involve both monitoring for quality assurance while work is underway and after it is completed (Miller, 2007). Utilizing IVM principles and practices to manage vegetation on pipeline ROW can 1) facilitate safe and reliable service and transport; 2) enable routine ground access to the ROW for inspection, maintenance, and testing of the pipeline; 3) facilitate aerial patrol of the ROW enabling inspectors to identify maintenance needs and encroachment concerns; 4) increase regulatory compliance; and 5) potentially provide other natural resource values (e.g., wildlife habitat, multiple land use, recreation, etc.). Documented benefits of IVM applied on electric transmission ROW include improved safety, cost effectiveness, service reliability, aesthetics, wildlife habitat enhancement, community relations opportunities, and decreased fire risk. There are significant opportunities to expand the application of IVM principles and practices developed for electric transmission ROW to the management of vegetation on pipeline ROW. Page 9
10 References Bramble, W.C., and W.R. Byrnes, Thirty Years of Research on Development of Plan Cover on an Electric Transmission Right-of-Way. Journal of Arboriculture 9 (3). International Society of Arboriculture, Champaign, IL. McLoughlin, Kevin T Application of Integrated Pest Management to Electric Utility Rights-of-Way Vegetation Management in New York State. The Sixth International Symposium on Environmental Concern in Rights-of-Way Management. Elsevier Science, Ltd., Oxford, UK. Miller, Randall H Best Management Practices: Integrated Vegetation Management. International Society of Arboriculture, Champaign, IL. Nesmith, J.C.B., J.P. Shatford, and D.E. Hibbs Stable Plant Communities in the Pacific Northwest. Proceedings of the Eighth International Symposium on Environmental Concerns in Rights-of-Way Management. Elsevier Science, Ltd., Oxford, UK. Nowak, Christopher A., Benjamin D. Ballard, Paul J. Appelt, and Donald K. Gartman Integrated Vegetation Management on Gas Pipeline Rights-of-Way. Gas Research Institute, Des Plaines, IL. Yahner, Richard L., Bramble, W.C., and W.R.Byrnes, Effect of Vegetation Maintenance of an Electric Transmission Right-of-Way on Reptile and Amphibian Populations. Journal of Arboriculture 27 (1). International Society of Arboriculture, Champaign, IL. Yahner, Richard H., Russel J. Hutnik, Stephen A. Liscinsky Bird Populations Associated with an Electric Transmission Right-of-Way. Journal of Arboriculture 28(3). International Society of Arboriculture, Champaign, IL. Page 10
How To Manage Vegetation
Introduction Utilities manage vegetation for several performance reasons: safety, service reliability, and accessibility being among the key factors. Managing vegetation is critical because it can be the
Vegetation Management. for Distribution Lines
Vegetation Management for Distribution Lines Working Hand in Hand with Nature Trees contacting power lines and other electric facilities are the major cause of electric service interruptions, especially
Part of Your Community Important Safety Information. TransCanada - Bison Pipeline
Part of Your Community Important Safety Information TransCanada - Bison Pipeline Public Safety Information Pipeline Safety is Everybody s Business This brochure contains important safety information about
Frequently Asked Transmission Pipeline Questions
Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).
FORESTED VEGETATION. forests by restoring forests at lower. Prevent invasive plants from establishing after disturbances
FORESTED VEGETATION Type of strategy Protect General cold adaptation upland and approach subalpine forests by restoring forests at lower Specific adaptation action Thin dry forests to densities low enough
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA A. LAND USE ELEMENT INTERPRETIVE GUIDELINES B. COMMUNITY BENEFITS C. COUNTY ACTION ITEMS Adopted by the Board of Supervisors November 9, 1999 A. Santa
S Y S T E M M O D E R N I Z A T I O N
S Y S T E M M O D E R N I Z A T I O N T H E L I N E M B E X T E N S I O N P R O J E C T B A L T I M O R E A N D H A R F O R D C O U N T I E S, M A R Y L A N D Project Overview Columbia Gas Transmission
Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan
Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how
How To Preserve Trees
San Diego County Water Authority Vic Bianes, PE - Engineering Manager Tad Brierton, SR/WA - Right of Way Supervisor APWA National Congress 2013 Chicago, IL 2 1 Background - San Diego County Water Authority
Experienced Planning and Design
www.pizzo.info Consistently Better Natural Restoration Everyone should have a passion in life, and for me it s been to protect and restore our lands to their original native beauty. That s why in 1988
American Forest Foundation (AFF) 2010-2015 Standards of Sustainability for Forest Certification
American Forest Foundation (AFF) 2010-2015 Standards of Sustainability for Forest Certification Standards Prologue The American Forest Foundation s (AFF) 2010-2015 Standards of Sustainability for Forest
Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices
Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Purpose The purpose of this document is to provide guidance and recommendations for minimizing potential impacts to
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
Addendum D. Nomination of Moody Wash ACEC
Addendum D Nomination of Moody Wash ACEC Moody Wash ACEC is hereby nominated by Citizens for Dixie s Future to: BLM St. George Field Office 345 East Riverside Drive St. George, UT 84790 Moody Wash is a
March 17, 2015. Dear Mr. Sullins:
Tony Sullins Endangered Species Chief, Midwest Regional Office Public Comment Process Attn: FWS-R5-ES-2011-0024 Division of Policy and Directives Management U.S. Fish and Wildlife Service 4401 N. Fairfax
How To Plan A Buffer Zone
Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other
Natural Gas Pipelines
Natural Gas Pipelines Excerpt from Report 2 of the Pennsylvania Energy Impacts Assessment December 16, 2011 Authors: Nels Johnson, Tamara Gagnolet, Rachel Ralls, and Jessica Stevens The Nature Conservancy
Broadmoor Public Golf Course TREE MANAGEMENT GUIDE
Broadmoor Public Golf Course TREE MANAGEMENT GUIDE Conservation of the trees at the Broadmoor Public Golf Course is a priority for environmental, economic and human health reasons. Trees make a difference
Understanding Line Clearing Efforts. Improving service reliability and promoting the health of your trees.
Understanding Line Clearing Efforts Improving service reliability and promoting the health of your trees. Trees are an important part of our environment. That s why American Electric Power (AEP) is committed
Appendix C. Municipal Planning and Site Restoration Considerations
Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning
A. In this chapter, the following terms have the meanings indicated.
08.07.02.01 Title 08 DEPARTMENT OF NATURAL RESOURCES Subtitle 07 FORESTS AND PARKS Chapter 02 Roadside Tree Care Authority: Natural Resources Article, 5-209 and 5-406, Annotated Code of Maryland.01 Purpose.
Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program
Angora Fire Restoration Activities June 24, 2007 Presented by: Judy Clot Forest Health Enhancement Program California Tahoe Conservancy Independent California State Agency within the Resources Agency Governed
For additional information on qualifications and experience of representative EDGE senior staff members, please contact us.
About Us Edge Engineering & Science, LLC (EDGE) is a privately owned professional services firm headquartered in Houston, Texas. EDGE was established with the primary goal of providing high quality environmental
Frequently Asked Questions About PennEast Pipeline Project
Frequently Asked Questions About PennEast Pipeline Project Who is PennEast Pipeline Company, LLC? AGL Resources, NJR Pipeline Company, South Jersey Industries, PSEG Power LLC and UGI Energy Services (UGIES)
Tree Trimming Practices. For transmission and distribution power lines. TREE TRIMMING PRACTICES h 1
Tree Trimming Practices For transmission and distribution power lines TREE TRIMMING PRACTICES h 1 RiGht Tree. RiGht Place. CenterPoint Energy encourages you to plant the Right Tree in the Right Place by
Recommended Resources: The following resources may be useful in teaching
Unit D: Controlling Pests and Diseases in the Orchard Lesson 1: Managing and Controlling Pests of Fruit and Nut Crops Student Learning Objectives: Instruction in this lesson should result in students achieving
Proposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.
Q. Why does OG&E clear vegetation away from power lines? A. Trees that grow into power lines can cause problems in multiple ways:
Q. Why does OG&E clear vegetation away from power lines? A. Trees that grow into power lines can cause problems in multiple ways: Outages Tree limbs contacting power lines are one of the most common causes
Backyard Buffers that Work for People and Nature by Restoring Ecological Function
Backyard Buffers that Work for People and Nature by Restoring Ecological Function What is a Wetland Buffer? A wetland buffer is a simple land management practice that is employed by municipalities to protect
High Conservation Value Forests 3.1. Old Growth Forests. Management & Monitoring Framework
High Conservation Value Forests 3.1 Old Growth Forests Management & Monitoring Framework HCV 3: Forest areas that are in or contain rare, threatened or endangered ecosystems. HCVF 3.1 Old Growth Areas
School pipeline safety information WHAT S INSIDE
School pipeline safety information WHAT S INSIDE Emergency Response Plan/Management Guide Call Before You Dig How To Recognize The Location Of A Pipeline Recognizing A Pipeline Leak Pipelines are near
Chapter 162 SHADE TREE COMMISSION
Chapter 162 SHADE TREE COMMISSION 162-1. Purpose. 162-2. Definitions. 162-3. Shade Tree Commission. 162-4. Powers and duties of Commission. 162-5. Approval required. 162-6. Duties and responsibilities.
US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing
US 281 AT PREMONT PUBLIC HEARING Hearing Purpose The purpose of tonight s Public Hearing is for the public to: Learn about the status of the proposed project Review the purpose and need for the project
HAILEY ORDINANCE NO. 1013
HAILEY ORDINANCE NO. 1013 AN ORDINANCE OF THE CITY OF HAILEY, IDAHO, AMENDING THE HAILEY MUNICIPAL CODE, ADDING A NEW CHAPTER 2.36 TO ESTABLISH A HAILEY TREE COMMITTEE AND POLICIES, REGULATIONS AND STANDARDS
Transmission/Distribution Vegetation Management Program. Flathead Electric Cooperative,Inc. Powerful Solutions. for our communities
Transmission/Distribution Vegetation Management Program Flathead Electric Cooperative,Inc. Powerful Solutions for our communities Table of Contents Page 3 Vegetation Management Plan Flathead Electric
KUB Tree Pruning: A Customer Guide
KUB Tree Pruning: A Customer Guide . KUB Tree Pruning: A Customer Guide Table of Contents Introduction....2 Plant Smart....4 Why Prune?....6 Before We Prune....8 Meet the Crew... 10 How We Prune... 12
REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:
EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,
CITY OF UKIAH TREE MANAGEMENT GUIDELINES TREE MANAGEMENT POLICIES FOR THE PROTECTION, OPERATION AND MAINTENANCE OF CITY PROPERTY
CITY OF UKIAH TREE MANAGEMENT GUIDELINES TREE MANAGEMENT POLICIES FOR THE PROTECTION, OPERATION AND MAINTENANCE OF CITY PROPERTY FINAL DRAFT November 2010 1.0 PURPOSE STATEMENT The purpose of this document
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)
Forest Management Guidelines for the Protection of Four-toed and Spotted Salamander Populations Carol Hall & Bruce Carlson May 2004
Forest Management Guidelines for the Protection of Four-toed and Spotted Salamander Populations Carol Hall & Bruce Carlson May 2004 Salamander Natural History Four-toed Salamanders: The Four-toed Salamander,
Integration of Forestry & Wildlife Management
Integration of Forestry & Wildlife Management By Ken Negray Regional Certification Manager, NewPage Corp & member of the KY SIC Committee Abstract: Kentucky SIC (Sustainable Forestry Initiative Implementation
Wildlife Habitat Conservation and Management Plan
Wildlife Habitat Conservation and Management Plan For [Applicant Name] [Insert photo of property] Developed in Cooperation with Jane Doe Habitat Conservation Biologist Oregon Department of Fish and Wildlife
MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1
MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1 Mitigation Goals and Objectives o Describe functions lost at impact site o Describe functions to be gained at mitigation site o Describe overall watershed
NW Natural & Pipeline Safety
NW Natural & Pipeline Safety We Grew Up Here NW Natural is an Oregon-based utility company founded in 1859. The company purchases natural gas for its core market in western Oregon and southwestern Washington,
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment Water Protection Bureau Name of Project: Applicant: Ueland Land Development LLC Type of Project: Proposed discharge of treated domestic wastewater
INTEGRATED PEST MANAGEMENT SYSTEM FOR KENNESAW STATE UNIVERSITY
INTEGRATED PEST MANAGEMENT SYSTEM FOR KENNESAW STATE UNIVERSITY KENNESAW, GEORGIA PREPARED JANUARY 1997 REVISED NOVEMBER 2006 TABLE OF CONTENTS Introduction and Principles of Integrated Pest Management
WEED MANAGEMENT PLAN FOR. (NAME of PROPERTY or MANAGED AREA) (TOWN or COUNTY, STATE) (TIME PERIOD; e.g. 1996-2000)
(WEED MANAGEMENT PLAN OUTLINE FOR PUBLIC LAND MANAGERS) (Note: This outline is a modification of a weed management plan template produced by The Nature Conservancy) WEED MANAGEMENT PLAN FOR (NAME of PROPERTY
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein
FWRC. Cooperators: Delta Wildlife, Inc. Forest and Wildlife Research Center, Mississippi State University
Cooperators: Delta Wildlife, Inc. Forest and Wildlife Research Center, Mississippi State University Mississippi Department of Wildlife, Fisheries and Parks Mississippi Fish and Wildlife Foundation Mississippi
Background research on the topic of urban forestry is intended to
overview urban forestry Urban Forestry Background research on the topic of urban forestry is intended to help guide the task of integrating trees and urban forestry goals and aspirations into the Portland
Restoration Planning and Development of a Restoration Bank
Restoration Planning and Development of a Restoration Bank Black Creek Pioneer Village, South Theatre 8:30 a.m. to 3:30 p.m. Habitat Restoration and Environmental Monitoring Projects Section Restoration
EFB 496.10/696.03 Online Wetland Restoration Techniques Class Syllabus
EFB 496.10/696.03 Wetland Restoration Techniques Online Class Syllabus SUNY-ESF College of Environmental Science and Forestry Summer Session II 2015 Wetland Restoration Techniques is a graduate and undergraduate
Ecosystem Services in the Greater Houston Region. A case study analysis and recommendations for policy initiatives
Ecosystem Services in the Greater Houston Region A case study analysis and recommendations for policy initiatives Ecosystem Services Ecosystems provide services through their natural processes that we
Vegetation Management Frequently Asked Questions
Vegetation Management Frequently Asked Questions Q. Why does AEP Ohio clear vegetation away from power lines? A. AEP Ohio s goal is to provide safe, dependable electric service to its customers. Line clearance
RESTORATION & REVITALIZATION
RESTORATION & REVITALIZATION Legal preservation has not proved to be sufficient to preserve natural communities. Restoration activities are diverse and includes revitalization of natural communities which
CRP Mid-Contract Management Option: Integrated Wildlife Management (645)
CRP Mid-Contract Management Option: Integrated Wildlife Management (645) Conservation Practice Job Sheet ID - CRP, JS-20 Revised August 2013 The purpose of mid-contract management activities is to enhance
Regulation of Natural Gas Pipelines. June 23, 2008
Regulation of Natural Gas Pipelines June 23, 2008 Federal and State Regulations Federal: 49 United States Code 60101. et. seq. Title 49 Code of Federal Regulations The Office of Pipeline Safety (OPS),
NASA Stennis Space Center Environmental Resources Document
16.0 Major Environmental Considerations for Proposed Actions All construction, rocket testing, and operations that may potentially impact environmental media, such as air, water, land, aquatic and biotic
B. Reduce the use of broad spectrum pesticides when feasible. C. Create awareness among City staff of less-toxic pest management techniques.
City of Newark MAINTENANCE POLICY: INTEGRATED PEST MANAGEMENT POLICY ORIGINAL DATE: January 11, 2010; revised May 24, 2012 PURPOSE: The purpose of the City of Newark s Integrated Pest Management (IPM)
RECORD OF PLAN CONFORMANCE AND CATEGORICAL EXCLUSION (CX) DETERMINATION
RECORD OF PLAN CONFORMANCE AND CATEGORICAL EXCLUSION (CX) DETERMINATION CX Log #: DOI-BLM-OR-V060-2015-032-CX CE Exemption category: 516 DM 11.9, E.12: Grants of right-of-way wholly within the boundaries
Portland State University. Campus Tree Care Plan
Portland State University Campus Tree Care Plan 1. Purpose Portland State University (PSU) resides in a densely populated urban setting in downtown Portland, Oregon. With green space in short supply, maintaining
1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
SITE WEED MANAGEMENT PLAN FOR. (NAME of PRESERVE or CONSERVATION AREA) (TOWN, STATE) (PERIOD; e.g. 2001-2005)
Site Weed Management Plan Template TNC s Wildland Invasive Species Program Revised: Mandy Tu & Barry Meyers-Rice/WISP SITE WEED MANAGEMENT PLAN FOR (NAME of PRESERVE or CONSERVATION AREA) (TOWN, STATE)
3. The submittal shall include a proposed scope of work to confirm the provided project description;
QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding
Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.
Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource
Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria
Memorandum TO: FROM: Michael Bergstrom and Robin Cole City of Bellevue Nancy Bird, AICP EDAW, Inc. DATE: July 23, 2008 RE: Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria
Tree Work on District of West Vancouver Property
CORPORATE POLICY Parks & Community Services File #2190-01-01 West Vancouver Property 1.0 Purpose This policy has three sections: 1.1 Section 1 ensures the safety of the residents of West Vancouver through
Wildlifer 2013 Managing Wildlife on Private Lands
Master Wildlifer 2013 Managing Wildlife on Private Lands Greg Yarrow, Chair and Professor Natural Resources School of Agricultural, Forest, & Environmental Sciences Clemson University Clemson, South Carolina,
King Fire Restoration Project, Eldorado National Forest, Placer and El Dorado Counties, Notice of intent to prepare an environmental impact statement.
This document is scheduled to be published in the Federal Register on 12/24/2014 and available online at http://federalregister.gov/a/2014-30158, and on FDsys.gov [3410-11- P] DEPARTMENT OF AGRICULTURE
Trenching and Excavation Safety
1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking
FEDERAL GOVERNMENT OVERSIGHT OF PIPELINE SAFETY
Operational Safety INTRODUCTION The Millennium Pipeline Company (Millennium) is proud of the key role it plays in New York s energy infrastructure. The Millennium Pipeline is a vital link in a system that
NATURAL GAS PIPELINE SAFETY
NATURAL GAS PIPELINE SAFETY INFORMATION FOR EMERGENCY OFFICIALS Pipeline Safety in Your Community We WANT TO MAKE sure you are aware of our continuing efforts to keep your community safe and how you can
Environmental guidelines for preparation of an Environment Management Plan
Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use
Fire Management needs assessment and priority actions
Needs Assessment Questionnaire Fire Management needs assessment and priority actions In the introduction of the guidelines it is said that the Principles and Strategic Actions can serve as a checklist
APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES
Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan
Natural Gas Summit 11/14/12
Natural Gas Summit 11/14/12 1 Natural Gas Summit 11/14/12 Maureen Ball Joined Central New York Oil and Gas (Inergy) in 1999. Participated in the development and construction of various storage, compression,
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the
Revision of Land and Resource Management Plan for the Santa Fe National Forest;
This document is scheduled to be published in the Federal Register on 06/30/2016 and available online at http://federalregister.gov/a/2016-15525, and on FDsys.gov [3410-11- P] DEPARTMENT OF AGRICULTURE
TREE CUTTING & TRIMMING INFORMATION As of 8-20-2009
TREE CUTTING & TRIMMING INFORMATION As of 8-20-2009 Many people are unaware that Electric Utilities have the legal right and authority to maintain its electrical transmission and distribution facilities
Flood Plain Reclamation to Enhance Resiliency Conserving Land in Urban New Jersey
Flood Plain Reclamation to Enhance Resiliency Conserving Land in Urban New Jersey Rutgers Cooperative Extension Water Resources Program Christopher C. Obropta, Ph.D., P.E. Email: [email protected]
Corridor Goals and Objectives
Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty
Program Design and Engineering Key to Infrastructure Replacement and Cost Containment
Program Design and Engineering Key to Infrastructure Replacement and Cost Containment By: Tom Ziegenfuss, COO Les Goodman VP/Distribution Dave Klimas, VP/Distribution Glen Armstrong, Senior Codes Specialist
Oregon. Climate Change Adaptation Framework
Oregon Climate Change Adaptation Framework Oregon Environmental Quality Commission Climate Change Adaptation Framework Presentation at a glance: Purposes of the framework Participating agencies Climate
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES April 20, 2010 EXHIBIT 1 ELEMENT 4 WATER RESOURCES TABLE OF CONTENTS 4.1 INTRODUCTION 4.2 GOALS AND POLICIES 4.2.A General Goals and Policies 1 4.2.B
MBJ Environmental Programmes
MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,
Developing a Prescribed Fire Burn Plan: ELEMENTS & CONSIDERATIONS
Developing a Prescribed Fire Burn Plan: ELEMENTS & CONSIDERATIONS What s Inside PURPOSE OF A BURN PLAN Goals and Objectives 3 Burn Site Information 3 Site Preparation 3 Prescription 3 Ignition and Holding