IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS

Size: px
Start display at page:

Download "IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS"

Transcription

1 NOTTINGHAM CITY HOMES IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS Report issued: February 2011 Audit Plan: The matters raised in this report are only those that came to the attention of the auditor during the course of the internal audit review and are not necessarily a comprehensive statement of all the weaknesses that exist or all the improvements that might be made. This report has been prepared solely for management's use and must not be recited or referred to in whole or in part to third parties without our prior written consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended, for any other purpose. TIAA neither owes nor accepts any duty of care to any other party who may receive this report and specifically disclaims any liability for loss, damage or expense of whatsoever nature, which is caused by their reliance on our report.

2 INTRODUCTION - EXECUTIVE SUMMARY - 1. We have reviewed the Disaster Recovery arrangements at Nottingham City Homes. The review was carried out in July 2010 as part of the planned internal audit work for. SUMMARY 2. One Key Risk Control Objective was identified and based on the findings from this work an overall evaluation of the overall adequacy of the internal controls was established (figure 1). Figure 1 - Evaluation of the Effectiveness of the Internal Controls Evaluation Limited Assurance KEY FINDINGS 3. The key control and operational practice findings that need to be addressed in order to strengthen the control environment are set out in the Management and Operational Effectiveness Action Plans. The prioritisation of the recommendations are summarised below (figure 2). Figure 2 - Summary of Priorities of Recommendations Urgent Important Routine Operational MANAGEMENT RESPONSES 4. Recommendations for improvements should be assessed by the Company for their full impact before they are implemented. RELEASE OF REPORT 5. The table below sets out the history of this report. Date draft report issued: 1 st September 2010 Date management responses recd: 23 rd February 2011 Date final report issued: 23 rd February 2011 Page 1

3 MANAGEMENT ACTION PLAN PRIORITY 1, 2 AND 3 RECOMMENDATIONS Risk Finding Recommendation Priority Management Comments Implementation Timetable Responsible Officer Failure to direct the process through approved policy & procedures. It was ascertained that key IT systems and services had been identified and prioritised for recovery in a disaster situation, however, no evidence was provided to substantiate this. Recommendation 2: The prioritisation of IT systems and services be undertaken to identify the critical recovery path should such a disaster occur. 1 The information on key systems and services will be consolidated, allowing a critical recovery path to be identified and agreed with the NCH Business Continuity lead officer End of May 2011 Robert Allen Head of ICT Failure to direct the process through approved policy & procedures. There is no evidence to support the identification of risks associated with IT systems. Significant risks to systems must first be identified before a comprehensive recovery plan can be developed, tested and implemented. Recommendation 1: A risk assessment be undertaken to identify significant risks relating to the loss of IT systems and services. 2 A risk assessment will be carried out for all key systems/services identified in the response to Recommendation 2 to identify risks to system/service availability End of May 2011 Robert Allen Head of ICT PRIORITY GRADINGS 1 URGENT Fundamental control issue on which action should be taken immediately. 2 IMPORTANT Control issue on which action should be taken at the earliest opportunity. 3 ROUTINE Control issue on which action should be taken. Page 2

4 Risk Finding Recommendation Priority Management Comments Implementation Timetable Responsible Officer There is no procedure for restoring critical business systems following an incident. Backup and recovery of IT systems is undertaken by the Local Authority, who provide IT services to NCH under contract. It is understood that a comprehensive SLA has been sought with the Local Authority for some time and that a recent draft has been written. No evidence of the draft SLA was provided during the review. Recommendation 3: A comprehensive SLA with the Local Authority be sought to ensure that NCH is receiving acceptable levels of service and that value for money from the service provided can be demonstrated. 2 Formalisation of the backup and recovery arrangements for our systems is one of the reasons that NCH has been attempting to develop a comprehensive ICT SLA with NCC and progress against this recommendation is tied to the progress on the SLA. A deadline of March 2011 has been set to agree with NCC a new ICT SLA Action Plan. Once this is in place, timings for progress against this recommendation may be available. TBC Robert Allen Head of ICT PRIORITY GRADINGS 1 URGENT Fundamental control issue on which action should be taken immediately. 2 IMPORTANT Control issue on which action should be taken at the earliest opportunity. 3 ROUTINE Control issue on which action should be taken. Page 3

5 Risk Finding Recommendation Priority Management Comments Implementation Timetable Responsible Officer There is no procedure for restoring critical business systems following an incident. A backup schedule was provided to Internal Audit. A review of the schedule identified several servers that were not backed up, although it should be noted that there were some that had a legitimate reason for not being backed up. However, there were still servers that were not backed up and therefore information may not be recoverable should a disaster occur Recommendation 4: The current backup arrangements be reviewed to ensure that critical systems are effectively backed up and the schedule is sufficiently documented to reflect the actual arrangements. 2 COMPLETE All of NCH s critical business systems are backed up appropriately. Further checks have ensured that the missing information leading to the audit finding has been added to the backup schedule document. N/A Robert Allen Head of ICT PRIORITY GRADINGS 1 URGENT Fundamental control issue on which action should be taken immediately. 2 IMPORTANT Control issue on which action should be taken at the earliest opportunity. 3 ROUTINE Control issue on which action should be taken. Page 4

6 Risk Finding Recommendation Priority Management Comments Implementation Timetable Responsible Officer There is no procedure for restoring critical business systems following an incident. There is no formal documented Disaster Recovery plan in place with reliance placed upon the Nottingham City Council (NCC) to provide a recovery service. Whilst this process is appropriate for NCH, there was no evidence to suggest that NCC has a detailed disaster recovery plan which has been tested to ensure that NCH s IT systems can be fully and accurately recovered should a disaster occur. Recommendation 5: Confirmation be sought from NCC that they have a fully tested and detailed Disaster Recovery plan that identifies NCH s critical systems and that these can be effectively recovered should a disaster occur. 3 Confirmation has been sought and NCH are awaiting a response from NCC. End of March 2011 Robert Allen Head of ICT PRIORITY GRADINGS 1 URGENT Fundamental control issue on which action should be taken immediately. 2 IMPORTANT Control issue on which action should be taken at the earliest opportunity. 3 ROUTINE Control issue on which action should be taken. Page 5

7 OPERATIONAL EFFECTIVENESS MATTERS Item Management Comments No Operational Effectiveness Matters were identified. ADVISORY NOTE Operational Effectiveness Matters need to be considered as part of management review of the procedures, rather than on a one-by-one basis Page 6

8 SCOPE AND LIMITATIONS OF THE REVIEW 6. The review considered the extent to which the organisation has put into place arrangements which provides reasonable but not absolute assurance that the impact on the organisation of any major incident will be minimised. The scope of the review did not include providing assurance that the actual testing of hardware/software etc has been carried out effectively. 7. The limitations and the responsibilities of management in regard to this review are set out in the Annual Plan. ASSESSMENTS OF THE KEY RISK CONTROL OBJECTIVES 8. This review identified and tested the controls that are being operated by the Organisation and an assessment of the combined effectiveness of the controls in mitigating the key probity risks is provided. The assessments are: Substantial Assurance robust series of internal controls in place which should ensure continuous and effective achievement of the control objective. Reasonable Assurance reasonable number of internal controls in place, however may not be operated all the time. Limited Assurance the controls in place are not sufficient to ensure the continuous and effective achievement of the control objective. No Assurance fundamental breakdown or absence of core internal controls. MATERIALITY 9. NCH places reliance of the Local Authority to provide ICT services. These services included the recovery of IT systems in the event of a disaster scenario. Page 7

9 Risk Failure to direct the process through approved policy & procedures. Risk Control Objective Arrangements in place provide for compliance with established policies, procedures, laws and regulations. Evaluation Limited Assurance 10. The following matters were identified in reviewing the Key Risk Control Objective: Risk: Critical business systems are not identified and as a consequence are not considered a priority for restore and recovery There is no evidence to support the identification of risks associated with IT systems. Significant risks to systems must first be identified before a comprehensive recovery plan can be developed, tested and implemented. Recommendation 1: A risk assessment be undertaken to identify significant risks relating to the loss of IT systems and services It was ascertained that key IT systems and services had been identified and prioritised for recovery in a disaster situation, however, no evidence was provided to substantiate this. Recommendation 2: The prioritisation of IT systems and services be undertaken to identify the critical recovery path should such a disaster occur It was demonstrated that, for new systems and projects, the requirements for resilience and recovery were addressed at the time of inception. Risk: There is no procedure for restoring critical business systems following an incident Backup and recovery of IT systems is undertaken by the Local Authority, who provide IT services to NCH under contract. It is understood that a comprehensive SLA has been sought with the Local Authority for some time and that a recent draft has been written. No evidence of the draft SLA was provided during the review. Recommendation 3: A comprehensive SLA with the Local Authority be sought to ensure that NCH is receiving acceptable levels of service and that value for money from the service provided can be demonstrated A backup schedule was provided to Internal Audit. A review of the schedule identified several servers that were not backed up, although it should be noted that there were some that had a legitimate reason for not being backed up. However, there were still servers that were not backed up and therefore information may not be recoverable should a disaster occur. Recommendation 4: The current backup arrangements be reviewed to ensure that critical systems are effectively backed up and the schedule is sufficiently documented to reflect the actual arrangements. Page 9

10 10.6 There is no formal documented Disaster Recovery plan in place with reliance placed upon the Nottingham City Council (NCC) to provide a recovery service. Whilst this process is appropriate for NCH, there was no evidence to suggest that NCC has a detailed disaster recovery plan which has been tested to ensure that NCH s IT systems can be fully and accurately recovered should a disaster occur. Recommendation 5: Confirmation be sought from NCC that they have a fully tested and detailed Disaster Recovery plan that identifies NCH s critical systems and that these can be effectively recovered should a disaster occur. Risk: Data is lost and/or is irrecoverable The current data centre contains a mixture of physical and virtual servers. Plans are underway to move the data centre from its current location with a separate recovery location being available. During this migration it is understood that more systems will be virtualised, where possible, and a storage area network will also be implemented. It is anticipated that data will be replicated across sites and therefore provide online resilience for network systems and services. Regular backups should still be taken for archive purposes Page 9

REVIEW OF THE FIREWALL ARRANGEMENTS

REVIEW OF THE FIREWALL ARRANGEMENTS WEST DORSET DISTRICT COUNCIL REVIEW OF THE FIREWALL ARRANGEMENTS Report issued: December 2007 The matters raised in this report are only those, which came to the attention of the auditor during the course

More information

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY INFORMATION GOVERNANCE TOOLKIT REPORT

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY INFORMATION GOVERNANCE TOOLKIT REPORT NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY INFORMATION GOVERNANCE TOOLKIT REPORT 9.7 Date of the meeting 15/07/2015 Author Sponsoring Clinician Purpose of Report Recommendation J Green - Head

More information

Dacorum Borough Council Final Internal Audit Report. IT Business Continuity and Disaster Recovery

Dacorum Borough Council Final Internal Audit Report. IT Business Continuity and Disaster Recovery Dacorum Borough Council Final Internal Audit Report IT Business Continuity and Disaster Recovery Distribution list: Chris Gordon Group Manager Performance, Policy and Projects John Worts ICT Team Leader

More information

Internal Audit Report Disaster Recovery / Business Continuity Planning

Internal Audit Report Disaster Recovery / Business Continuity Planning Audit Committee, 28 November 2013 Internal Audit Report Disaster Recovery / Business Continuity Planning Executive summary and recommendations Introduction As part of the Internal Audit Plan for 2013-14,

More information

Comhairle nan Eilean Siar Internal Audit Review DISASTER RECOVERY ARRANGEMENTS Information Technology. Final Report 2014/15-06

Comhairle nan Eilean Siar Internal Audit Review DISASTER RECOVERY ARRANGEMENTS Information Technology. Final Report 2014/15-06 Comhairle nan Eilean Siar Internal Audit Review Information Technology Final Report 2014/15-06 3 rd November 2014 CONTENTS Page SECTION 1 - EXECUTIVE SUMMARY 1-6 SECTION 2 - DETAILED FINDINGS AND RECOMMENDATIONS

More information

Dacorum Borough Council Final Internal Audit Report

Dacorum Borough Council Final Internal Audit Report Dacorum Borough Council Final Internal Audit Report ICT Change Management Distribution list: Chris Gordon Group Manager Neil Telkman - Information, Security and Standards Officer Gary Osler ICT Service

More information

Comhairle nan Eilean Siar Internal Audit Follow Up Review Disaster Recovery. Final Report FU18 14/15

Comhairle nan Eilean Siar Internal Audit Follow Up Review Disaster Recovery. Final Report FU18 14/15 Comhairle nan Eilean Siar Internal Audit Follow Up Review Disaster Recovery Final Report FU18 14/15 27 th May 2015 CONTENTS Page SECTION 1 - EXECUTIVE SUMMARY 1 3 SECTION 2 - DETAILED FINDINGS AND RECOMMENDATIONS

More information

Disaster Recovery and Contingency Planning

Disaster Recovery and Contingency Planning ITEM: 7(ii) AUDIT COMMITTEE 2 NOVEMBER Nottingham City Homes Disaster Recovery and Contingency Planning June Final Report Executive Summary & Action Plan Assurance Level: Partly meets expectations Audit

More information

Business Continuity Business Impact Analysis arrangements

Business Continuity Business Impact Analysis arrangements Aberdeen City Council Internal Audit Report 2012/2013 for Aberdeen City Council May 2013 Business Continuity Business Impact Analysis arrangements Final Report Contents Section Page 1. Executive Summary

More information

Aberdeen City Council IT Disaster Recovery

Aberdeen City Council IT Disaster Recovery Aberdeen City Council IT Disaster Recovery Internal Audit Report 2014/2015 for Aberdeen City Council January 2015 Terms or reference agreed 4 weeks prior to fieldwork Target Dates per agreed Actual Dates

More information

How To Audit Health And Care Professions Council Security Arrangements

How To Audit Health And Care Professions Council Security Arrangements Audit Committee 28 Internal audit report ICT Security Executive summary and recommendations Introduction Mazars has undertaken a review of ICT Security controls, in accordance with the internal audit plan

More information

IT Assurance - Business Continuity and Disaster Recovery

IT Assurance - Business Continuity and Disaster Recovery Audit Summary Report October 2006 PAPER D IT Assurance - Business Continuity and Disaster Recovery Audit 2006/2007 Paper D - 1 External audit is an essential element in the process of accountability for

More information

FINAL. Internal Audit Report. Data Centre Operations and Security

FINAL. Internal Audit Report. Data Centre Operations and Security FINAL Internal Audit Report Data Centre Operations and Security Document Details: Reference: Report nos from monitoring spreadsheet/2013.14 Senior Manager, Internal Audit & Assurance: ext. 6567 Engagement

More information

NHS Dorset Clinical Commissioning Group. Internal Audit Annual Report 2014/15. May 2015

NHS Dorset Clinical Commissioning Group. Internal Audit Annual Report 2014/15. May 2015 Internal Audit Annual Report 2014/15 May 2015 Internal Audit Annual Report INTRODUCTION This is the 2014/15 Annual Report by TIAA on the internal control environment at Dorset Clinical Commissioning Group.

More information

Appendix 6c. Final Internal Audit Report Disaster Recovery Planning. June 2007. Report 6c Page 1 of 15

Appendix 6c. Final Internal Audit Report Disaster Recovery Planning. June 2007. Report 6c Page 1 of 15 Appendix 6c Final Internal Audit Report Disaster Recovery Planning June 2007 Report 6c Page 1 of 15 Contents Page Executive Summary 3 Observations and Recommendations 8 Appendix 1 - Audit Framework 13

More information

Summary of Information Technology General Control Environment Findings for the year ended 30 June 2015

Summary of Information Technology General Control Environment Findings for the year ended 30 June 2015 Summary of Inmation Technology General Control Environment Findings the year ended 30 June 2015 1 Change management Complete Revisiting the Change Management control process documentation and updating

More information

Audit of Business Continuity Planning

Audit of Business Continuity Planning Cumbria Office of the Police & Crime Commissioner Audit of Business Continuity Planning 0 Cumbria Shared Internal Audit Service Images courtesy of Carlisle City Council except: Parks (Chinese Gardens),

More information

Information Security Policies. Version 6.1

Information Security Policies. Version 6.1 Information Security Policies Version 6.1 Information Security Policies Contents: 1. Information Security page 3 2. Business Continuity page 5 3. Compliance page 6 4. Outsourcing and Third Party Access

More information

Coleg Gwent. Business Continuity Plan Test - Post Implementation Review (PIR) Internal Audit Report (12.09/10)

Coleg Gwent. Business Continuity Plan Test - Post Implementation Review (PIR) Internal Audit Report (12.09/10) Internal Audit Report 1 June 2010 Business Continuity Plan Test Post Implementation Review (PIR) CONTENTS Section Page Executive Summary 1 Action Plan 4 Findings and Recommendations 5 Debrief meeting 28

More information

Audit Committee, 13 March 2013. Internal Audit Report Project Management. Executive summary and recommendations. Introduction

Audit Committee, 13 March 2013. Internal Audit Report Project Management. Executive summary and recommendations. Introduction Audit Committee, 13 March 2013 Internal Audit Report Project Management Executive summary and recommendations Introduction Mazars has undertaken a review of the arrangements for project management in accordance

More information

Comhairle nan Eilean Siar Internal Audit Review DISASTER RECOVERY. Final Report 12/13-20

Comhairle nan Eilean Siar Internal Audit Review DISASTER RECOVERY. Final Report 12/13-20 Comhairle nan Eilean Siar Internal Audit Review Final Report 12/13-20 8 th January 2013 CONTENTS Page SECTION 1 - EXECUTIVE SUMMARY 1-3 SECTION 2 - DETAILED FINDINGS AND RECOMMENDATIONS 4-9 SECTION 3 -

More information

SUBJECT: REPLACEMENT OF CORPORATE ELECTRONIC DATA STORAGE, BACKUP AND DISASTER RECOVERY SOLUTIONS

SUBJECT: REPLACEMENT OF CORPORATE ELECTRONIC DATA STORAGE, BACKUP AND DISASTER RECOVERY SOLUTIONS REPORT TO CABINET TO BE HELD ON 15 SEPTEMBER 2015 Key Decision No Forward Plan Ref No 23K Corporate Priority The proposals in this report contribute to the delivery of all the Council s priorities Cabinet

More information

SOUTH LAKELAND DISTRICT COUNCIL INTERNAL AUDIT FINAL REPORT IT 11-02. IT Backup, Recovery and Disaster Recovery Planning

SOUTH LAKELAND DISTRICT COUNCIL INTERNAL AUDIT FINAL REPORT IT 11-02. IT Backup, Recovery and Disaster Recovery Planning SOUTH LAKELAND DISTRICT COUNCIL INTERNAL AUDIT FINAL REPORT IT 11-02 IT Backup, Recovery and Disaster Recovery Planning Executive Summary Introduction As part of the 2011/12 Audit Plan and following discussions

More information

Glasgow Life Risk Management & Business Continuity Planning. Final Report

Glasgow Life Risk Management & Business Continuity Planning. Final Report Glasgow Life Risk Management & Business Continuity Planning Final Report INTERNAL AUDIT October 2014 Glasgow City Council Internal Audit 1 Glasgow Life Risk Management & Business Continuity Planning Table

More information

Gravesham Borough Council

Gravesham Borough Council Gravesham Borough Council Report to: Finance & Audit Committee Date: 21 February 2008 Reporting officer: Subject: Senior Auditor Audit Opinion of Unsatisfactory Council Tax Purpose and summary of report:

More information

Joint Audit Report for South Lakeland District Council. & Eden District Council

Joint Audit Report for South Lakeland District Council. & Eden District Council Joint Audit Report for South Lakeland District Council & Eden District Council Audit of IT Data Backup and Recovery Arrangements Audit of Development Management 22nd May 2015 11 th June 2015 0 Page 0 Audit

More information

Internal audit report Information Security / Data Protection review

Internal audit report Information Security / Data Protection review Audit Committee 29 September 2011 Internal audit report Information Security / Data Protection review Executive summary and recommendations Introduction Mazars have undertaken a review of Information Security

More information

Review of Information Technology s Data System Backup and Disaster Recovery Process Page 2 of 10 September 30, 2013

Review of Information Technology s Data System Backup and Disaster Recovery Process Page 2 of 10 September 30, 2013 Page 2 of 10 Scope and Objectives We reviewed the backup and disaster recovery processes utilized by DOH for information applications/systems managed by IT over the last three years. This review included

More information

A Review of the Disaster Recovery Testing Process

A Review of the Disaster Recovery Testing Process To: LASERS Audit Committee; Cindy Rougeou, Executive Director Cc: Maris LeBlanc, Deputy Director; Lance Armstrong, IT Director; Dan Bowden, IT Deputy Director From: Ryan Babin, Audit Director; Blake Lee,

More information

Avon & Somerset Police Authority

Avon & Somerset Police Authority Avon & Somerset Police Authority Internal Audit Report IT Service Desk FINAL REPORT Report Version: Date: Draft to Management: 19 February 2010 Management Response: 12 May 2010 Final: 13 May 2010 Distribution:

More information

IT Services. Service Level Agreement

IT Services. Service Level Agreement IT Services Service Level Agreement Contents 1 Purpose... 3 2 IT Services Objectives... 3 3 IT Helpdesk... 3 3.1 Issues... 3 3.2 Service Requests... 4 3.3 Development Requests... 4 4 Priorities... 4 5

More information

SOUTH NORTHAMPTONSHIRE COUNCIL. 11/31 ICT Capacity Management FINAL REPORT. June 2011

SOUTH NORTHAMPTONSHIRE COUNCIL. 11/31 ICT Capacity Management FINAL REPORT. June 2011 SOUTH NORTHAMPTONSHIRE COUNCIL 11/31 ICT Capacity Management FINAL REPORT June 2011 This report and the work connected therewith are subject to the Terms and Conditions of the contract dated 18/06/07,

More information

Internal Audit Progress Report Performance and Overview Committee (19 th August 2015) Cheshire Fire Authority

Internal Audit Progress Report Performance and Overview Committee (19 th August 2015) Cheshire Fire Authority Internal Audit Progress Report (19 th August 2015) Contents 1. Introduction 2. Key Messages for Committee Attention 3. Work in progress Appendix A: Risk Classification and Assurance Levels Appendix B:

More information

INTERNAL AUDIT 2008/09 INFORMATION TECHNOLOGY (BUSINESS CONTINUITY)

INTERNAL AUDIT 2008/09 INFORMATION TECHNOLOGY (BUSINESS CONTINUITY) 2008/09 SUMMARY Location Subject Business Sponsor Staff engaged Coleg Gwent Information Technology (Business Continuity) Lynda Roberts Sue Harris Head of Internal Audit Gaynor Rains Manager David Bratt

More information

Information Commissioner's Office

Information Commissioner's Office Phil Keown Engagement Lead T: 020 7728 2394 E: philip.r.keown@uk.gt.com Will Simpson Associate Director T: 0161 953 6486 E: will.g.simpson@uk.gt.com Information Commissioner's Office Internal Audit 2015-16:

More information

Aberdeen City Council

Aberdeen City Council Aberdeen City Council Internal Audit Report Final Contract management arrangements within Social Care & Wellbeing 2013/2014 for Aberdeen City Council January 2014 Internal Audit KPI Targets Target Dates

More information

Internal Audit Strategic and Annual Plans 2015/16

Internal Audit Strategic and Annual Plans 2015/16 Internal Audit Strategic and Annual Plans 2015/16 Financial Scrutiny and Audit Committee 10 February 2015 Agenda Item No 8 Summary: This report provides an overview of the stages followed prior to the

More information

Essex Fire Authority

Essex Fire Authority Internal Audit Report (2.13/.14) FINAL with the Civil Contingencies Act 1 October 2013 Contents Section Page Executive Summary 1 Action Plan 5 Findings and Recommendations 6 Debrief meeting 15 August 2013

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com

More information

Balancing and Settlement Code BSC PROCEDURE BSCP537. QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs

Balancing and Settlement Code BSC PROCEDURE BSCP537. QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs Balancing and Settlement Code BSC PROCEDURE BSCP537 QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs APPENDIX 3 GUIDANCE NOTES ON COMPLETING THE SAD Version 2.0 Date: 10 September 2007

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Internal Audit 2011-12: Business Continuity Review Last updated 6 February 2012 Will Simpson Senior Manager

More information

ESSEX FIRE AUTHORITY. Internal Audit Progress Report. Audit Sub-Committee Meeting: April 2012

ESSEX FIRE AUTHORITY. Internal Audit Progress Report. Audit Sub-Committee Meeting: April 2012 ESSEX FIRE AUTHORITY Internal Audit Progress Report Audit Sub-Committee Meeting: April Essex Fire Authority CONTENTS Section Page 1 Introduction 1 2 Final reports 1 3 Key Findings from Internal Audit Work

More information

Interim Audit Report. Borough of Broxbourne Audit 2010/11

Interim Audit Report. Borough of Broxbourne Audit 2010/11 Interim Audit Report Borough of Broxbourne Audit 2010/11 The Audit Commission is an independent watchdog, driving economy, efficiency and effectiveness in local public services to deliver better outcomes

More information

Internal Audit Monitoring Report. Audit Report status Assurance. Payroll Final Limited

Internal Audit Monitoring Report. Audit Report status Assurance. Payroll Final Limited Appendix 1 Internal Audit Monitoring Report Audit Report status Assurance Payroll Final Limited The Payroll system was reviewed to seek assurance that processes and procedures are operating effectively

More information

How To Write An Audit And Governance Committee Report On An Itd Plan

How To Write An Audit And Governance Committee Report On An Itd Plan Public Document Pack Worcestershire County Council Agenda Audit and Governance Committee Friday, 12 September 2014, 10.00 am County Hall, Worcester This document can be made available in other formats

More information

Internal Audit Report Project Management

Internal Audit Report Project Management Audit Committee, 20 Internal Audit Report Project Management Executive summary and recommendations Introduction As part of the Internal Audit Plan for 2013-14 Mazars have undertaken a review of arrangements

More information

Cumbria Constabulary. Business Continuity Planning

Cumbria Constabulary. Business Continuity Planning Cumbria Constabulary Business Continuity Planning 0 Cumbria Shared Internal Audit Service Images courtesy of Carlisle City Council except: Parks (Chinese Gardens), www.sjstudios.co.uk, Monument (Market

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

How To Audit World Health Organisation (Whoa)

How To Audit World Health Organisation (Whoa) WORLD HEALTH ORGANIZATION FIFTY-SIXTH WORLD HEALTH ASSEMBLY A56/29 Provisional agenda item 16.1 10 April 2003 Interim report of the External Auditor The Director-General has the honour to transmit herewith

More information

Coleg Gwent Internal Audit Report 2012/13 Assets and Inventory. Assurance Rating:

Coleg Gwent Internal Audit Report 2012/13 Assets and Inventory. Assurance Rating: Coleg Gwent Internal Audit Report 2012/13 Assets and Inventory Assurance Rating: Distribution List: Draft Report: Principal Vice Principal, (Finance, Estates and Information Services) Clerk to the Corporation

More information

West Dunbartonshire Council. Follow-up data protection audit report

West Dunbartonshire Council. Follow-up data protection audit report West Dunbartonshire Council Follow-up data protection audit report Auditors: Lee Taylor (Audit Team Manager) Jonathan Kay (Engagement Lead Auditor) Data controller contacts: Michael Butler (Data Protection/Information

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office Internal Audit 2013-14: Follow up Last updated 4 July 2014 Distribution For action Senior Corporate Governance Manager Timetable Fieldwork completed 21 May 2014 Draft

More information

Internal Audit Report Business Continuity Planning Arrangements

Internal Audit Report Business Continuity Planning Arrangements The Highland Council Community Services Committee 6 November 2014 Agenda Item Report No 19 COM 45/14 Internal Audit Report Planning Arrangements Report by Director of Community Services Summary This report

More information

The Scrutiny Panel heard from Fiona Kordiak, Audit Scotland, the Council s auditors and the Director of Finance.

The Scrutiny Panel heard from Fiona Kordiak, Audit Scotland, the Council s auditors and the Director of Finance. + ED I N BVRG H + THE CITY OF EDINBURGH COUNCIL Item no \8 External Audit Reports Received Executive of the Council 16 December 2003 Purpose of report 1 To refer a recommendation arising from consideration

More information

Code Subsidiary Document No. 0007: Business Continuity Management. September 2015

Code Subsidiary Document No. 0007: Business Continuity Management. September 2015 Code Subsidiary Document No. 0007: September 2015 Change History Version Number Date of Issue Reason For Change Change Control Reference Sections Affected 20150511 11 May 2015 For industry consultation

More information

Business Continuity Management Policy

Business Continuity Management Policy Business Continuity Management Policy Business Continuity Policy Version 1.0 1 Version control Version Date Changes Author 0.1 April 13 1 st draft PH 0.2 June 13 Amendments in line with guidance PH 0.3

More information

Cleveland Police. Data protection audit report. Executive summary November 2014

Cleveland Police. Data protection audit report. Executive summary November 2014 Cleveland Police Data protection audit report Executive summary November 2014 1. Background The Information Commissioner is responsible for enforcing and promoting compliance with the Data Protection Act

More information

Joint ICT Service ICT Strategy 2014-17

Joint ICT Service ICT Strategy 2014-17 Document History Document Location This document is only valid on the day it was printed. The source of the document will be found in (see footer) Revision History Date of this revision: 19 th May 2014

More information

Business Continuity Plan Template

Business Continuity Plan Template Business Continuity Plan Template Disclaimer This publication has been produced to provide a guide for people anticipating going into business and for business owners. It should not be regarded as an

More information

BACKUP STRATEGY AND DISASTER RECOVERY POLICY STATEMENT

BACKUP STRATEGY AND DISASTER RECOVERY POLICY STATEMENT TADCASTER GRAMMAR SCHOOL Toulston, Tadcaster, North Yorkshire. LS24 9NB BACKUP STRATEGY AND DISASTER RECOVERY POLICY STATEMENT Written by Steve South November 2003 Discussed with ICT Strategy Group January

More information

White Paper: Cloud Solutions for Continuity

White Paper: Cloud Solutions for Continuity White Paper: Cloud Solutions for Continuity 2014, igroup ltd. All rights reserved. INTELLECTUAL PROPERTY DISCLAIMER This white paper is for informational purposes only and is provided as is with no warranties

More information

Information Governance Policy

Information Governance Policy Information Governance Policy Document Number 01 Version Number 2.0 Approved by / Date approved Effective Authority Customer Services & ICT Authorised by Assistant Director Customer Services & ICT Contact

More information

Information and Communications Technology Controls Report 2013 14

Information and Communications Technology Controls Report 2013 14 Information and Communications Technology Controls Report 2013 14 Victorian Auditor-General s Report October 2014 2014 15:12 V I C T O R I A Victorian Auditor-General Information and Communications Technology

More information

House of Commons Corporate Governance Framework

House of Commons Corporate Governance Framework House of Commons Corporate Governance Framework What is Corporate Governance? 1. Good corporate governance is fundamental to any effective organisation and is the hallmark of any well-managed corporate

More information

OUTSOURCING INVOLVING SHARED COMPUTING SERVICES (INCLUDING CLOUD) 6 July 2015

OUTSOURCING INVOLVING SHARED COMPUTING SERVICES (INCLUDING CLOUD) 6 July 2015 OUTSOURCING INVOLVING SHARED COMPUTING SERVICES (INCLUDING CLOUD) 6 July 2015 Disclaimer and Copyright While APRA endeavours to ensure the quality of this publication, it does not accept any responsibility

More information

Insurance Commission of Western Australia

Insurance Commission of Western Australia Summarised Version March 2014 1. Executive summary 1.1 Background As part of the routine internal audit program, ICWA has requested Ernst & Young (EY) to undertake a claims management review of RiskCover

More information

Internal Audit at the University of Cambridge.

Internal Audit at the University of Cambridge. Internal Audit at the University of Cambridge. Contents Introduction to Deloitte 1 Our team 2 What is Internal Audit? 4 Our approach to Internal Audit 5 Authority and reporting lines 7 Planning 8 Ad Hoc

More information

Report to Parliament No. 4 for 2011 Information systems governance and security. Financial and Assurance audit. Enhancing public sector accountability

Report to Parliament No. 4 for 2011 Information systems governance and security. Financial and Assurance audit. Enhancing public sector accountability Financial and Assurance audit Report to Parliament No. 4 for 2011 Information systems governance and security ISSN 1834-1128 Enhancing public sector accountability RTP No. 4 cover.indd 1 15/06/2011 3:19:31

More information

NHS TRUST DEVELOPMENT AUTHORITY PUBLIC BOARD MEETING, 24 JANUARY 2013 PAPER F: TRANSITION ARRANGEMENTS - TRANSFER ORDER AND TRANSFER SCHEMES

NHS TRUST DEVELOPMENT AUTHORITY PUBLIC BOARD MEETING, 24 JANUARY 2013 PAPER F: TRANSITION ARRANGEMENTS - TRANSFER ORDER AND TRANSFER SCHEMES NHS TRUST DEVELOPMENT AUTHORITY PUBLIC BOARD MEETING, 24 JANUARY 2013 PAPER F: TRANSITION ARRANGEMENTS - TRANSFER ORDER AND TRANSFER SCHEMES Board Meeting 24 January 2013 Agenda Item 6 Paper F Title: Transition

More information

Smart Meters Programme Schedule 8.6. (Business Continuity and Disaster Recovery Plan) (CSP North version)

Smart Meters Programme Schedule 8.6. (Business Continuity and Disaster Recovery Plan) (CSP North version) Smart Meters Programme Schedule 8.6 (Business Continuity and Disaster Recovery Plan) (CSP North version) Schedule 8.6 (Business Continuity and Disaster Recovery Plan) (CSP North version) Amendment History

More information

Disaster Recovery Policy

Disaster Recovery Policy Disaster Recovery Policy INTRODUCTION This policy provides a framework for the ongoing process of planning, developing and implementing disaster recovery management for IT Services at UCD. A disaster is

More information

Advisory Guidelines of the Financial Supervision Authority. Requirements for Organising the Business Continuity Process of Supervised Entities

Advisory Guidelines of the Financial Supervision Authority. Requirements for Organising the Business Continuity Process of Supervised Entities Advisory Guidelines of the Financial Supervision Authority Requirements for Organising the Business Continuity Process of Supervised Entities These advisory guidelines were established by Resolution No

More information

Business Continuity Plans

Business Continuity Plans Version Number Issue 2 Business Continuity Policy Date Revision Complete Policy Owner Author Reason for Revision Proof Read April 2016 Business Improvement Manager Emma Earle, Business Services Officer

More information

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit Page 1 Walton Centre Monitoring & Audit Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt Page 2 Table of Contents Section Contents 1 Introduction 2 Responsibilities Within This

More information

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Internal Audit Report () FINAL Risk Management: Follow Up of Previous Internal Audit Recommendations

More information

Governance and Audit Committee 23 November 2015

Governance and Audit Committee 23 November 2015 Agenda Item 7 Governance and Audit Committee 23 November 2015 Welland Internal Audit Consortium Internal Audit Plan & Performance Update 2015/16 Purpose of report: To provide Members with information on

More information

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19 Aberdeen City Council Performance Management Process External Audit Report o: 2008/19 Draft Issued: 11 February 2009 Final Issued: 6 April 2009 Contents Pages Pages Management Summary Introduction 1 Background

More information

Webnet2000 DataCentre

Webnet2000 DataCentre Webnet2000 DataCentre WEBNET2000 have been enabling organisations develop their Internet presence for over 10 Years. The Webnet2000 Datacentre features the very latest world class resilient infrastructure,

More information

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11 For Publication REPORT AUTHOR(S): Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11 ASSISTANT CHIEF OFFICER (HUMAN RESOURCES AND ORGANISATIONAL

More information

POLICY. 1) Business Continuity Management 2) Disaster Recovery 3) Critical Incident Management 4) Risk Management

POLICY. 1) Business Continuity Management 2) Disaster Recovery 3) Critical Incident Management 4) Risk Management POLICY Policy Title: Management Descriptors: 1) Management 2) Disaster Recovery 3) Critical Incident Management 4) Risk Management Category: Risk Management Intent Organisational Scope Definitions Policy

More information

Big Data Analytics Service Definition G-Cloud 7

Big Data Analytics Service Definition G-Cloud 7 Big Data Analytics Service Definition G-Cloud 7 Big Data Analytics Service Service Overview ThinkingSafe s Big Data Analytics Service allows information to be collected from multiple locations, consolidated

More information

Report 7 Appendix 1d Final Internal Audit Report Sundry Income and Debtors (inc. Fees and Charges) Greater London Authority February 2010

Report 7 Appendix 1d Final Internal Audit Report Sundry Income and Debtors (inc. Fees and Charges) Greater London Authority February 2010 Report 7 Appendix 1d Final Internal Audit Report Sundry Income and Debtors (inc. Fees and Charges) Greater London Authority February 2010 This report has been prepared on the basis of the limitations set

More information

Nottinghamshire County Council. Data protection audit report

Nottinghamshire County Council. Data protection audit report Nottinghamshire County Council Data protection audit report Executive summary October 2015 1. Background The Information Commissioner is responsible for enforcing and promoting compliance with the Data

More information

How To Ensure Information Security In Nhs.Org.Uk

How To Ensure Information Security In Nhs.Org.Uk Proforma: Information Policy Security & Corporate Policy Procedures Status: Approved Next Review Date: April 2017 Page 1 of 17 Issue Date: June 2014 Prepared by: Information Governance Senior Manager Status:

More information

FINAL Internal Audit Report. IT Disaster Recovery

FINAL Internal Audit Report. IT Disaster Recovery FINAL Internal Audit Report IT Disaster Recovery Document Details: Reference: 2.5c/2014.15 Senior Manager, Internal Audit & Assurance: David Jenkins ext. 6567 Engagement Manager: Auditor: Date: 07 August

More information

ICT Internal Audit Strategy 2009-10 to 2011-12. Report by the Head of Finance

ICT Internal Audit Strategy 2009-10 to 2011-12. Report by the Head of Finance Audit Committee 24 September 2009 Item No. 12 ICT Internal Audit Strategy 2009-10 to 2011-12 Report by the Head of Finance This report introduces the ICT Internal Audit Strategy and asks the Audit Committee

More information

I will cover. Cyber Security and other recent performance audits. Report # 8 Why this audit? Background. Audit objective.

I will cover. Cyber Security and other recent performance audits. Report # 8 Why this audit? Background. Audit objective. I will cover. Report # 8 Security of information communications technology infrastructure Cyber Security and other recent performance audits Report # 9 TMAG: compliance with the National Standards for

More information

IT Service Continuity Management PinkVERIFY

IT Service Continuity Management PinkVERIFY -11-G-001 General Criteria Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 Edition workflows and process integrations? -11-G-002 Does the tool have security controls in place to

More information

Financial Services Guidance Note Outsourcing

Financial Services Guidance Note Outsourcing Financial Services Guidance Note Issued: April 2005 Revised: August 2007 Table of Contents 1. Introduction... 3 1.1 Background... 3 1.2 Definitions... 3 2. Guiding Principles... 5 3. Key Risks of... 14

More information

Performance Management 2012/ 13: Quarter 4

Performance Management 2012/ 13: Quarter 4 Performance Management 2012/ 13: Quarter 4 Policy and Resources Committee Chief Executive Director of Finance and Corporate Resources Director of Social and Community Services Director of Technical Services

More information

Data Storage And Backup

Data Storage And Backup Data Storage And Backup The availability of Superfast Broadband enables you to take advantage of a range of cloud-based storage and backup solutions capable of handling vast volumes of digital data. Data

More information

ICT Strategy 2010-2013

ICT Strategy 2010-2013 ICT Strategy 2010-2013 If you would like to receive this publication in an alternative format (large print, tape format or other languages) please contact us on 01832 742000. East Northamptonshire Council

More information

APPENDIX 4 GREATER LONDON AUTHORITY SUN ACCOUNTS UNIX REVIEW FINAL AUDIT REPORT. Auditor: Chris Power & Michael Lacey Date: April 2003 Reference: 320

APPENDIX 4 GREATER LONDON AUTHORITY SUN ACCOUNTS UNIX REVIEW FINAL AUDIT REPORT. Auditor: Chris Power & Michael Lacey Date: April 2003 Reference: 320 APPENDIX 4 GREATER LONDON AUTHORITY SUN ACCOUNTS UNIX REVIEW FINAL AUDIT REPORT Auditor: Chris Power & Michael Lacey Date: April Reference: 320 Table of Contents 1 INTRODUCTION 2 Page 2 OBJECTIVES AND

More information

Audit Report for South Lakeland District Council. People and Places Directorate Neighbourhood Services. Audit of Grounds Maintenance

Audit Report for South Lakeland District Council. People and Places Directorate Neighbourhood Services. Audit of Grounds Maintenance Audit Report for South Lakeland District Council People and Places Directorate Neighbourhood Services Audit of Grounds Maintenance Cumbria Shared Internal Audit Service: Internal Audit Report 7 th November

More information

Introduction UNDERSTANDING BUSINESS CONTINUITY MANAGEMENT

Introduction UNDERSTANDING BUSINESS CONTINUITY MANAGEMENT INFORMATION SECURITY: UNDERSTANDING BUSINESS CONTINUITY MANAGEMENT FACTSHEET This factsheet will introduce you to Business Continuity Management (BCM), which is a process developed to counteract systems

More information

Cambridgeshire and Peterborough Fire Authority. Internal Audit Progress Report Overview & Scrutiny Committee meeting 16 October 2014

Cambridgeshire and Peterborough Fire Authority. Internal Audit Progress Report Overview & Scrutiny Committee meeting 16 October 2014 Cambridgeshire and Peterborough Fire Authority Internal Audit Progress Report Overview & Scrutiny Committee meeting 16 October 2014 Cambridgeshire & Peterborough Fire Authority 1 Introduction This report

More information

LFRS Business Continuity Planning

LFRS Business Continuity Planning LFRS Business Continuity Planning 1.1 INTRODUCTION The LFRS Business Continuity Plan provides a framework for the activation, allocation and deployment of Lancashire Fire and Rescue Services resources

More information

ANNEXURE D 2. OBJECTIVE

ANNEXURE D 2. OBJECTIVE OVERSIGHT REPORT OF THE CITY OF JOHANNESBURG GROUP AUDIT COMMITTEE ON THE MONITORING OF THE 30 JUNE 2014 STATUTORY YEAR END AUDIT, THE EVALUATION OF THE FINAL AUDITED ANNUAL FINANCIAL STATEMENTS, THE AUDITOR

More information

The Learning Zone - Project Management Arrangements

The Learning Zone - Project Management Arrangements Coleg Gwent Internal Audit Report () 6 June 2012 Overall Opinion The Learning Zone - Project Management Arrangements CONTENTS Section Page Executive Summary 1 Action Plan 4 Findings and Recommendations

More information

CONTINUITY OF OPERATIONS AUDIT PROGRAM EVALUATION AND AUDIT

CONTINUITY OF OPERATIONS AUDIT PROGRAM EVALUATION AND AUDIT CONTINUITY OF OPERATIONS AUDIT PROGRAM EVALUATION AND AUDIT April 16, 2014 INTRODUCTION Purpose The purpose of the audit is to give assurance that the development of the Metropolitan Council s Continuity

More information