1 NYISO Demand Response Programs: Enrollment Donna Pratt Demand Response Market Product Specialist New York Independent System Operator DR-Expo Chicago, Illinois October 16-17, 2007
2 New York Independent System Operator Manages New York s bulk electricity grid a 10,775 mile network of high-voltage transmission lines that carry electricity throughout the state. Administers the Empire State s wholesale electricity markets, where more than $50 billion has been transacted since Interconnects to all major areas of the Northeast: North: Hydro-Québec South: PJM East: ISO New England West: Independent Electricity System Operator of Ontario Has included demand response resources in its capacity market since beginning operations in December
3 NYISO Markets Two-settlement, Day-ahead and Real-time, cooptimized markets for: Energy Sufficient generation to supply electricity demands Regulation Balancing of load and generation every 6 seconds Operating Reserve Supply ready to respond immediately to unexpected generation or transmission failures Installed Capacity Market Loads required to secure sufficient generating capacity equal to forecasted peak load plus a margin ISO-run auction or bilaterals Transmission Congestion Cost Market Auction-based market to hedge day-ahead congestion costs 3
4 NYISO DR Programs Reliability-based programs NYISO controls activation Purpose: provide load reductions to supplement generation when operating reserves are forecast to be short Emergency Demand Response Program (EDRP) ICAP-Special Case Resources (ICAP SCR) Economic-based programs Resource determines when to participate through bidding Purpose: load reduction acting as and competing with generation Day-Ahead Demand Response Program (DADRP) Demand-Side Ancillary Service Program (DSASP) implementation 4
5 DR Program Comparison EDRP Low Risk Low-Moderate Return Activation not guaranteed No payment if no activation DADRP Moderate Risk Moderate Return Scheduling based on bids ICAP SCR Moderate Risk Moderate-High Return Payment regardless of activation Activation not guaranteed DSASP High Risk High Return Scheduling base on bids Return EDRP Activation Frequency DSASP Real-Time DSASP ICAP SCR DADRP Risk DADRP ICAP SCR EDRP 2-hour Day-Ahead advance Notification Time 5
6 Who Can Participate? If you have interruptible load: The Emergency Demand Response (EDRP) program ICAP Special Case Resources (SCR) program The Day-Ahead Demand Response (DADRP) program If you have standby generators: The EDRP program The SCR program If you have very flexible operations and automated controls, beginning in spring 2008: Demand-Side Ancillary Service Program (DSASP) Real-time reserve (5-minute response) Real-time regulation (6-second response) Standby generators may participate in non-synchronized reserve markets 6
7 How to Enroll End-use (retail) customers enroll in NYISO programs through a NYISO (wholesale market) Customer NYISO (wholesale market) Customers include: Transmission Operator local distribution utility Load-Serving Entity competitive energy supplier Aggregator companies who transact with NYISO on behalf of end-use customers Also known as Curtailment Service Providers Direct Customer buys and sells in NYISO market 7
8 May-01 Aug-01 Nov-01 Feb-02 May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Nov-03 Feb-04 May-04 Aug-04 Nov-04 Feb-05 May-05 Aug-05 Nov-05 Feb-06 May-06 Aug-06 Nov-06 Feb-07 May-07 Aug-07 Date MWs Customers Total MWs Total Customers Program Growth
9 The New York Independent System Operator (NYISO) is a nonprofit corporation that began operations in 1999 to facilitate the restructuring of New York s s electric industry. The NYISO operates the state s s bulk electricity grid and administers New York s s wholesale electricity markets.
Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England
Business Models for Transactive Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England About ISO New England (ISO) Not-for-profit
Demand Response Programs: Lessons from the Northeast
Demand Response Programs: Lessons from the Northeast Charles Goldman E. O. Lawrence Berkeley National Laboratory [email protected] Mid Atlantic Demand Response Initiative Meeting Baltimore MD December
Presentation for The National Commission for Energy State Regulation of Ukraine
Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection
Emergency Demand Response Program Manual
MANUAL 7 Emergency Demand Response Program Manual June 2016 Version: 7.2 Effective Date: 06/03/2016 Committee Acceptance: 05/18/2016 BIC This document was prepared by: NYISO Demand Response Operations
PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations
PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region
PJM LMP Market Overview
PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people
Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public
Overview of the IESO-Administered Markets IESO Training Updated: January, 2014 Public Overview of the IESO-Administered Markets AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the
A Guide to Inform Institutions about Participation in PJM s Demand Response Programs
A Guide to Inform Institutions about Participation in PJM s Demand Response Programs John Soden & Robin Aldina Dr. Dalia Patiño-Echeverri, Advisor May 2013 Masters Project submitted in partial fulfillment
PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013
PJM Overview of Markets Georgian Delegation PUCO Office April 11, 2013 1 Agenda Introduction Energy Markets Locational Marginal Pricing - LMP Two Settlement - Day Ahead / Real time Ancillary Services Capacity
Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets
Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets Robert H. Patrick Frank A. Wolak Graduate School of Management Department of Economics Rutgers University Stanford University
ICAP/UCAP Overview. Aaron Westcott [email protected] 518 356 7657. If possible, Please mute your phones Please do not use the hold button.
ICAP/UCAP Overview Aaron Westcott [email protected] 518 356 7657 If possible, Please mute your phones Please do not use the hold button. Agenda What is ICAP/UCAP? How are ICAP and UCAP calculated? How
Comparison of Market Designs
Public Utility Commission of Texas Comparison of Market Designs Market Oversight Division Report Project 26376, Rulemaking Proceeding on Wholesale Market Design Issues in the Electric Reliability Council
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional
Virtual Transactions in the PJM Energy Markets
PJM Interconnection October 12, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com i P age Table of Contents Executive Summary... 1 Background... 3 Synopsis of the Virtual Transactions...
PJM Electric Market. PJM Electric Market: Overview and Focal Points. Federal Energy Regulatory Commission Market Oversight www.ferc.
PJM Electric Market: Overview and Focal Points Page 1 of 14 PJM Electric Market Source: Velocity Suite Intelligent Map Updated August 23, 21 145 PJM Electric Market: Overview and Focal Points Page 2 of
New York Independent System Operator (NYISO)
New York Independent System Operator (NYISO) 2010 ISO/RTO Metrics Report 196 Section 5 NYISO Performance Metrics and Other Information The New York Independent System Operator ( NYISO ) is a not-for-profit
Section 4: Scheduling Philosophy & Tools
Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy
Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers
Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers Presented to ISO/RTO Council by Edward G. Cazalet, PhD The Cazalet Group [email protected] www.cazalet.com 650-949-0560
International Review of Demand Response Mechanisms
International Review of Demand Response Mechanisms PREPARED FOR Australian Energy Market Commission PREPARED BY Toby Brown Samuel A. Newell David Luke Oates Kathleen Spees October 2015 This report was
Transmission Pricing. Donald Hertzmark July 2008
Transmission Pricing Donald Hertzmark July 2008 Topics 1. Key Issues in Transmission Pricing 2. Experiences in Other Systems 3. Pricing Alternatives 4. Electricity Market Structure and Transmission Services
How To Manage The Ercot Grid
US MEXICO Cross-border trade Joel Mickey Director, Market Design & Development NARUC Summer Meeting Dallas, Texas North American ISOs and RTOs Independent System Operators and Regional Transmission Organizations
Market Solutions to Loop Flow
Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution
Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play?
Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play? Professor Joel B. Eisen Austin Owen Research Fellow University of Richmond School of Law Austin Electricity Conference
Texas transformed. Achieving significant savings through a new electricity market management system
Texas transformed Achieving significant savings through a new electricity market management system KHOSROW MOSLEHI The state of Texas has long been the center of energy activities in the United States,
Update on Northeast Seams Issues. January 9, 2008 NYISO Management Committee Meeting
Update on Northeast Seams Issues January 9, 2008 NYISO Management Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have documented
Energy Efficiency and Demand Response Programs in the United States
Energy Efficiency and Demand Response Programs in the United States Structure, Operations, Accomplishments, Lessons Learned Claude Godin Director Energy Data Analytics Overview Introduction - Definitions
The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.
The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Coordination between Natural Gas and Electricity Markets Docket No. AD12-12-000 Prepared Statement of Brad Bouillon on behalf of
Load Participation in Ancillary Services
Load Participation in Ancillary Services DOE Framing Workshop October 25-26, 2011 EnerNOC Inc. Proposed Agenda EnerNOC Overview Who, Where, How and What we do Demand Response for Ancillary Services Wholesale
Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT
Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT FERC Conference on Increasing Real-Time and Day-Ahead Market Efficiency through Improved
PI.'s"'1-SlttlllIl. bstili
PI.'s"'1-SlttlllIl. bstili Market Implementation linda J. Clarke Strategist PJM Market Design y Supports many options for energy traders. balanced bilateral transactions (Le. scheduling coordinator) with
Demand Response Policy and Programs
Demand Response Policy and Programs Dr David Crossley Managing Director Energy Futures Australia Pty Ltd Metering, Billing and CRM/CIS Australia and New Zealand Conference 2005 Melbourne, 16 March 2005
Preliminary Project Description
Auxiliary Market Products Additional Capacity Zones The NYISO and stakeholders are developing the rationale in 2010 for creating additional capacity zones, identified as a recommendation in the 2009 State
Grid Operations and Planning
Grid Operations and Planning Report Kent Saathoff ERCOT Board of Directors April 20, 2010 Kent Content Summary March 2010 Operations Peak Demand: Actual vs. Forecast On-line Resources: Total at Peak and
Convergence Bidding Tutorial & Panel Discussion
Convergence Bidding Tutorial & Panel Discussion CAISO June 13, 2006 Joe Bowring PJM Market Monitor www.pjm.com Convergence Basics Day-Ahead Market basics Day-Ahead and Real-Time Market interactions Increment
Demand Response Management System Smart systems for Consumer engagement By Vikram Gandotra Siemens Smart Grid
Demand Response Demand Response Management System Smart systems for Consumer engagement By Vikram Gandotra Siemens Smart Grid siemens.com/answers The Siemens Smart Grid Suite DRMS part of Grid Application
Two Settlement - Virtual Bidding and Transactions
Two Settlement - Virtual Bidding and Transactions (Fall 2009) PJM 2009 2009 PJM 1 Agenda Two-Settlement Overview Two-Settlement Features & System Two-Settlement Business Rules Two-Settlement Data Requirements
Outage Scheduling Manual
MANUAL 29 Outage Scheduling Manual July 2015 Version: 4.3.1 Effective Date: 07/29/2015 Committee Acceptance: 6/11/2015 OC This document was prepared by: NYISO Energy Market Operations New York Independent
electricity restructuring compromise between competition and stability
the business scene Mohammad S. Ghazizadeh, Mohammad K. Sheikh-El-Eslami, and Hossein Seifi electricity restructuring compromise between competition and stability THE ISLAMIC REPUBLIC OF IRAN currently
THE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 20
TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 20 1. Applicability 1A. The following Terms and Conditions shall apply to every registered Electric Supplier authorized to do business within Connecticut
Wind Power and Electricity Markets
PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: [email protected] Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy
Administrative Services for the PJM Interconnection Operating Agreement
PJM Manual 33: Administrative Services for the PJM Interconnection Operating Agreement Revision: 12 Effective Date: March 31, 2016 Prepared by Member Relations PJM 2016 PAGE iii lviii PJM 2008 Revision
The Market Guide. An introductory guide to how the Electric Reliability Council of Texas (ERCOT) facilitates the competitive power market
The Market Guide An introductory guide to how the Electric Reliability Council of Texas (ERCOT) facilitates the competitive power market This version is based on operations of the ERCOT market on January
THE COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING
THE COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING 2014-2015 COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING CONTENTS ComEd Residential Real-Time Pricing
Electric Energy Storage. Opportunities and Challenges in New York
EESAT 2005 Electric Energy Storage Opportunities and Challenges in New York Presented by Rahul Walawalkar CEM, CDSM Authors Customized Energy Solutions Rahul Walawalkar Rick Mancini Stephen Fernands Raj
The Hidden Daytime Price Of Electricity BY EVAN BERGER
The Hidden Daytime Price Of Electricity BY EVAN BERGER Whether or not you know it, if you manage an office building, school, university, mall, or hospital and are in a region that has a demand charge over
THE CONNECTICUT LIGHT AND POWER COMPANY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 18
TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 18 1. Applicability 1A. The following Terms and Conditions shall apply to every registered Electric Supplier authorized to do business within Connecticut
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION
Increasing Demand Response in Maine
Increasing Demand Response in Maine January 4, 2008 AUTHORS Rick Hornby, Chris James, Kenji Takahashi, Dr. David White Prepared for Staff of the Maine Public Utilities Commission Table of Contents 1. EXECUTIVE
Demand Response as a Power System Resource Program Designs, Performance, and Lessons Learned in the United States
Demand Response as a Power System Resource Program Designs, Performance, and Lessons Learned in the United States Authors Doug Hurley Paul Peterson Melissa Whited May 2013 The Regulatory Assistance Project
Using Demand Response Programs to Benefit the. PtikJ Patrick J. Oshie, Ohi Commissioner Washington Utilities & Transportation Commission
Using Demand Response Programs to Benefit the Customer and the Utility PtikJ Patrick J. Oshie, Ohi Commissioner i Washington Utilities & Transportation Commission i 1 What is Demand Response? Changes in
103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. Ontario Energy Trading International
Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market?
Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Regulation and Operating Reserves 33 rd Eastern Conference Center for Research in Regulated Industry Romkaew P.
THE STRUCTURE OF AN ELECTRICITY MARKET
THE STRUCTURE OF AN ELECTRICITY MARKET Lectures 1-2 in EG2200 Power Generation Operation and Planning Mikael Amelin 1 COURSE OBJECTIVE To pass the course, the students should show that they are able to
Governance. What s a Governance?
Governance What s a Governance? Governance FERC - Federal Energy Regulatory Commission NERC - North American Electric Reliability Council. NPCC - Northeast Power Coordinating Council NYSRC - New York State
Workshop B. 11:15 a.m. to 12:30 p.m.
Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30
2010 STATE OF THE MARKET REPORT
2010 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market August 2011 TABLE OF CONTENTS Executive Summary...
Performance Metrics. For Independent System Operators And Regional Transmission Organizations
Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April
UNDERSTANDING YOUR UTILITY BILL A GUIDE FOR BUSINESSES IN OHIO
UNDERSTANDING YOUR UTILITY BILL A GUIDE FOR BUSINESSES IN OHIO TABLE OF CONTENTS INTRODUCTION Introduction... 3 Basic Billing Concepts... 4 Customer Choice Programs... 4 Gas Consumption and Charges...
Demand Response Review
Demand Response Review Presented to: AESO Presented by: Johannes Pfeifenberger and Attila Hajos March 2011 Copyright 2011 The Brattle Group, Inc. www.brattle.com Antitrust/Competition Commercial Damages
2013 Ventyx, an ABB company
Co-optimization of Congestion Revenue Rights in ERCOT Day-Ahead Market Chien-Ning Yu, Vladimir Brandwajn, Show Chang ABB/Ventyx Sainath M. Moorty ERCOT FERC Conference on increasing real-time and day-ahead
PJM Interconnection LLC Regional Transmission Organization (RTO)
PJM Interconnection LLC Regional Transmission Organization (RTO) ComEd Generator Interconnection Meeting October 2015 William Patzin PJM Infrastructure Coordination October 2015 PJM 2013 Nine Major North
Measurement and Mitigation of Market Power in Wholesale Electricity Markets
Measurement and Mitigation of Market Power in Wholesale Electricity Markets Frank A. Wolak Department of Economics Stanford University Stanford, CA 94305-6072 [email protected] http://www.stanford.edu/~wolak
Convergence of Wholesale And Retail Markets: The Texas Experience
Convergence of Wholesale And Retail Markets: The Texas Experience 1 COMMISSIONER KENNETH W. ANDERSON, JR. PUBLIC UTILITY COMMISSION OF TEXAS PRESENTATION FOR HARVARD ELECTRICITY POLICY GROUP JUNE 12, 2014
Transmission Planning in the ERCOT Interconnection
Transmission Planning in the ERCOT Interconnection Warren Lasher Manager, Long-Term Planning and Policy Department of Energy Electricity Advisory Committee The ERCOT Interconnection The ERCOT Region is
2014 Retail Electric Rates. in Deregulated and Regulated States
2014 Retail Electric Rates in Deregulated and Regulated States Published April 2015 2014 Retail Electric Rates in Deregulated and Regulated States Prepared by Paul Zummo, Manager, Policy Research and Analysis
Operator Initiated Commitments in RTO and ISO Markets
Price Formation in Organized Wholesale Electricity Markets Docket No. AD14-14-000 Staff Analysis of Operator Initiated Commitments in RTO and ISO Markets December 2014 For further information, please contact: