1 Contract for Difference for non-uk Renewable Electricity Projects August 2014
2 Crown copyright 2014 URN 14D/291 You may re-use this information (not including logos) free of charge in any format or medium, under the terms of the Open Government Licence. To view this licence, visit or write to the Information Policy Team, The National Archives, Kew, London TW9 4DU, or Any enquiries regarding this publication should be sent to us at 2
3 Contents Background... 4 Purpose... 5 Transmission asset regime... 5 Non-UK CfDs Programme of Work... 6 CfD Allocation... 6 Eligibility... 6 The Budget for CfDs (the Levy Control Framework)... 6 CfD Contract... 7 CfD Institutional Framework... 7 Indicative Timings
4 Background Background 1. The Government has been considering the benefits of supporting renewable electricity projects located outside the United Kingdom ( UK ) for a number of reasons, including: to use the cooperation mechanisms created under the EU Renewable Energy Directive 1 (particularly joint projects) as a contingency option to help the UK meet its renewables target; to improve the security of electricity supply in the UK and to support the creation of the European internal market through greater interconnectivity with neighbouring countries; to reduce the cost of investment in low-carbon technologies through greater competition; and more generally, to support the UK in achieving its longer term carbon reduction objectives in a cost-effective way. 2. In 2013 a Memorandum of Understanding was signed between the UK and the Republic of Ireland 2 to explore the benefits of renewable trading 3 for the two countries. This was a first step in understanding the issues that need to be resolved to establish a framework to govern renewable trading with non-uk projects generally. In June 2013, the UK Government published its response to the Call for Evidence on Renewables Trading 4. It indicated that there was potential for the physical trade in renewable energy and that more work should be undertaken to understand the issues associated with this area of work. 3. Progress has been made in assessing feasibility of renewable trading and there are a number of challenges in considering renewable trading as a realistic contingency option for meeting the UK s renewable target. 4. The strong pipeline of investment in renewable electricity projects in the UK that contribute towards the 2020 target constrains the available resources under the Levy 1 The Renewable Energy Directive created cooperation mechanisms" (statistical transfers, joint projects, and joint support schemes) to give Member States flexibility to jointly exploit renewable energy sources and to facilitate cross-border support of renewable energy. Joint projects are where a new renewable energy project in one country can be co-financed by another, and the renewable value of the energy (i.e. renewable credits) can be shared, accompanying the physical flow of energy. LEX:32009L Renewable trading refers to physical export of renewable electricity generated in one country (e.g. Ireland) to another country (e.g. the UK). 4 _for_evidence_on_renewable_energy_trading_final.pdf 4
5 Purpose Control Framework (LCF). And the long lead times for renewable trading projects suggests they should not be considered as a contingency for Over the longer term increasing investments into low carbon technologies in a way that is cost effective while improving the UK s electricity supply and moving towards an integrated internal market are key objectives for this Government to continue exploring the benefits of renewable trading in the future. 5. This document outlines the existing high level issues regarding the use of Contracts for Difference ( CfDs ) to incentivise the development of new renewable electricity projects connected to the electricity systems of Great-Britain ( GB ) but located outside the UK. It sets out indicative areas of work that would need to be addressed to open the UK CfD scheme to eligible non-uk renewable electricity projects. 6. The Electricity Market Reform ( EMR ) programme will increase investment in low-carbon technologies, ensure the UK s security of supply in the short, medium and long term, at least cost to consumers. The government s long-term vision is for intervention in the electricity market to decrease over time, achieving transition to a market where low carbon electricity generation can compete on price. Therefore the design of the CfD scheme includes competition between technologies to meet the EMR objectives in the most cost-effective way. Opening the EMR CfD scheme to projects from outside the UK in due course is an aspect of EMR originally announced in This type of support would be the first of a kind in Europe and, reflecting this, we need to find ways of addressing a number of complex issues set out in this document. 7. For the purposes of this document and the scope of future development of non-uk CfDs policy, the definition of non-uk renewable generator is that: the generator operates an eligible renewable electricity generation facility; is located outside the UK territory; and exports its generation to the GB electricity system This paper sets out initial areas of work to explore and, over time, address in order to open up the UK CfD scheme up to non-uk projects. At this stage, all timings and suggested areas of work are indicative. Transmission asset regime 9. It should be noted that another major issue that needs to be resolved is the regulatory approach to the transmission asset connecting non-uk generation to the electricity system in Great Britain ( GB ). 10. Progress on the possible regulatory approach had been set out in more detail separate to this document. Ofgem provided an update 7 on the regulation of transmission connecting non-uk generation to the GB transmission system earlier this year. In this update it confirmed that future non-gb connections regulation would be captured within the Integrated Transmission Planning and Regulation (ITPR) project and timelines The intention would be to explore if and how exports to the Northern Irish electricity system could work once the CfD is implemented in Northern Ireland
6 Non-UK CfDs Programme of Work 11. The ITPR project will help to establish a regime for non-gb connections which best reflects the use of the assets, coordinated system planning and arrangements for revenue regulation. Further updates on ITPR are likely to follow in September this year. Additional work has also been undertaken by The Crown Estate to establish how they will grant seabed rights to developers bringing forward renewable energy import projects with cables on seabed 8, which The Crown Estate manages. This work will progress in tandem with the work programme set out in this document. Non-UK CfDs Programme of Work 12. The purpose of the CfD is to increase revenue certainty for low-carbon generators over the duration of the contract. This reduces the commercial risks faced by the projects thereby lowering the cost of raising finance and ultimately supporting low-carbon generation at least cost to UK consumers. CfDs can be allocated to a range of lowcarbon technologies, including renewables, and relies on a dedicated institutional framework for the allocation, signature and management of the contracts. 13. To date the CfD policy, processes, systems and institutional arrangements have been designed for projects located in GB (which will be extended to cover Northern Ireland from 2017). Opening the CfD scheme to projects located outside the UK, with the challenges and complexities that this carries, will require most aspects of the EMR policy design to be reviewed, notably the allocation of CfDs, the CfD contract itself, and the supporting institutional framework. CfD Allocation 14. There are two main aspects of the process for allocating CfDs: eligibility for CfDs and the process of managing the budget for CfDs, including how CfDs are awarded when demand for contracts exceeds the available budget. Eligibility 15. The legislative framework for CfDs defines eligible projects by reference to their renewable electricity technology, rather than their geographic location. However the current allocation system relies on the generator demonstrating that they meet certain qualification requirements, which ensure that the project is of an appropriate technology and that the project is sufficiently advanced to warrant the award of a CfD. 9 We will need to ensure and if necessary develop eligibility criteria that have a similar policy effect as they do for GB and NI projects without treating non-uk generators unfairly. The Budget for CfDs (the Levy Control Framework) 16. CfDs are funded through the Levy Control Framework (LCF) which allows the UK Government to manage public expenditure paid for through UK consumers energy bills. Budget control through the LCF reflects the importance the Government places on
7 monitoring and controlling spending on levy schemes that are funded in this way. The LCF sets annual limits on the overall costs of all DECC s low carbon electricity levyfunded policies. These comprise the Renewables Obligation (RO), small scale Feed-in Tariffs and CfDs (including Investment Contracts). 17. Government is committed to achieving value for money for UK consumers, and ensuring that the award of CfDs allows it to remain within the LCF constraints. The use of auctions is an important aspect of the CfD allocation process, which supports value for money and allows for orderly management of the LCF budget. The Government is minded that non-uk renewables applicants would apply for CfDs in competition with UK projects participating in auctions when applications exceed the available budget and be subject to the same budget management requirements as for GB/NI CfDs. Ofgem is establishing the regulatory regime for transmission connecting non-uk generation to GB. We intend competition to apply regardless of the regulatory regime for transmission assets. CfD Contract 18. The CfD takes the form of a private law contract, providing generators with a clear set of rights and obligations. This structure supports investor confidence in the arrangements, not least through providing certainty that the CfD payments are reliable; further reducing revenue risk to investors and therefore costs to consumers. A non-uk CfD would seek to maintain similar policy principles, contract structure and risk profiles as under the UK contract while ensuring value for money for UK consumers. It would be based on the UK CfD Terms and Conditions, although several terms would need amendment. CfD Institutional Framework 19. The Government is keen to avoid duplication of institutions, and so will look to use the existing UK CfD s institutional arrangements when developing a position for non-uk CfDs. However, the challenges of non-uk projects might require the creation of new and/or complementary arrangements and cooperation with institutions in other countries (e.g. transmission system operators and regulators). 20. To date the CfD Institutional Framework defines clear roles for the institutions that govern the scheme in GB. The Low Carbon Contracts Company (LCCC) acts as the CfD Counterparty to all CfDs and administers the supplier obligation. National Grid, acting as the Delivery Body, administers CfD allocation and provides analysis to Government to underpin the setting of (maximum) strike prices. Ofgem, as regulator of the electricity market in GB oversees National Grid s delivery and enforces the supplier obligation. A subsidiary of Elexon carries out the settlement for CfDs on behalf of the LCCC. The Government will work closely with these institutions when developing a position for the non-uk CfD institutional framework. 7
8 Indicative Timings Indicative Timings 21. The Government understands that giving greater visibility on when non-uk renewable electricity projects can expect to have access to CfDs is a key question for interested parties. At this early stage of the CfD implementation and given the number of challenges and complexities that setting up a non-uk CfD policy will raise, the Government cannot commit to specific timelines. However to start managing the interested parties expectations we can outline a couple of timing constraints that will determine the timelines for non-uk CfDs. 22. As set out in the CfD Implementation Plan 10 it is anticipated that the application process for CfDs will open and allocation is expected to begin in autumn 2014, with first contracts awarded in late 2014 or early 2015 for projects located in GB. The Government s priority is to implement the CfD across the UK before opening it to non-uk projects. Because the electricity market is under reform in Northern Ireland with the new market arrangements under the Integrated Single Electricity Market due to be operational from December 2016, we currently expect the CfD regime to start in Northern Ireland from April The dependency on the CfD implementation across the UK and the complexity of the issues that need to be resolved to open the CfD to non-uk generators means that under our current planning assumptions the non-uk projects would be likely to have access to CfDs from 2018 at the earliest. 23. Another constraint to the timing for opening of the CfD scheme to non-uk renewable electricity projects is the availability of budget within the LCF. More details on the CfD budget were published in July Further updates on indicative timing will be communicated in the future as the CfD implementation across the UK and the areas of work progress 10 df
9 9
10 Crown copyright 2014 Department of Energy & Climate Change 3 Whitehall Place London SW1A 2AW URN 14D/291
Investing in renewable technologies CfD contract terms and strike prices
Investing in renewable technologies CfD contract terms and strike prices December 2013 Crown copyright 2013 You may re-use this information (not including logos) free of charge in any format or medium,
Electricity Market Reform:
Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001
EMR: Consultation on Balancing and Settlement Code subsidiary documents
EMR: Consultation on Balancing and Settlement Code subsidiary documents URN: 14D/108 April 2014 Department of Energy and Climate Change 3 Whitehall Place London SW1A 2AW Telephone: 0300 068 4000 Website:
Government response: EMR consultation on industry code and licence modifications
Government response: EMR consultation on industry code and licence modifications June 2014 Crown copyright 2014 Copyright in the typographical arrangement and design rests with the Crown. This publication
Annex A Feed-in Tariff with Contracts for Difference: Operational Framework
Annex A Feed-in Tariff with Contracts for Difference: Operational Framework November 2012 Contents Executive Summary... 5 Document Overview... 9 1. Introduction... 10 The Energy Bill: The Legal Framework
Opening the CfD support scheme to non-uk renewables projects
Opening the CfD support scheme to non-uk renewables projects European Commission workshop, Brussels, 5 November 2014 Agenda 1. What is the CfD support scheme? 2. What may be the benefits of opening the
EMR: Consultation on industry code and licence modifications
EMR: Consultation on industry code and licence modifications January 2014 Department of Energy and Climate Change 3 Whitehall Place London SW1A 2AW Telephone: 0300 068 4000 Website: https://www.gov.uk/government/organisations/department-of-energy-climate-change
Eligibility for an exemption from the costs of Contracts for Difference updated cost estimates
Electricity Market Reform Eligibility for an exemption from the costs of Contracts for Difference updated cost estimates AUGUST 2013 1. In examining the consultation currently open on eligibility for an
Electricity Market Reform: Consultation on Proposals for Implementation
Electricity Market Reform: Consultation on Proposals for Implementation October 2013 2 Electricity Market Reform: Consultation on Proposals for Implementation Presented to Parliament by the Secretary of
Low Carbon Contracts Company and Electricity Settlements Company operational costs 2016/17
Low Carbon Contracts Company and Electricity Settlements Company operational costs 2016/17 Consultation on the operational cost levies November 2015 Department of Energy and Climate Change 3 Whitehall
Government response: EMR consultation on BSC subsidiary documents
Government response: EMR consultation on BSC subsidiary documents June 2014 Crown copyright 2014 Copyright in the typographical arrangement and design rests with the Crown. This publication (excluding
Heat Networks Delivery Unit
Heat Networks Delivery Unit HNDU Round 6: Overview April 2016 Crown copyright 2016 URN 16D/056 You may re-use this information (not including logos) free of charge in any format or medium, under the terms
How To Write The Energy Bill
Implementing Electricity Market Reform (EMR) Finalised policy positions for implementation of EMR June 2014 Crown copyright 2014 URN 14D/221 You may re-use this information (not including logos) free of
Annex B: Strike price methodology July 2013
July 2013 URN 13D/189 Contents Introduction... 3 Overview of methodology for deriving a CfD strike price... 3 Strike Prices during the cross-over period with the RO (2014/15 2016/17)... 4 Comparison of
Regulatory Briefing. Capital Markets Day. 17 October 2013
Regulatory Briefing Capital Markets Day 17 October 2013 Agenda Andrew Koss Director of Strategy Damien Speight Head Trader Renewables Obligation Contracts for Difference Levy Control Framework Capacity
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy
Electricity market reform: policy overview
Electricity market reform: policy overview May 2012 Contents Introduction... 3 Electricity Market Reform... 6 The Move to EMR... 21 Costs and Benefits of EMR... 24 EMR in the Devolved Administrations...
This seeks to define Contracts for Difference (CfDs) and their relevance to energy related development in Copeland.
Contracts for Difference and Electricity Market Reform LEAD OFFICER: REPORT AUTHOR: John Groves Denice Gallen Summary and Recommendation: This seeks to define Contracts for Difference (CfDs) and their
Mass Balance Guidance
Mass Balance Guidance 9 September 2014 Crown copyright 2014 URN 14D/337 You may re-use this information (not including logos) free of charge in any format or medium, under the terms of the Open Government
The levy control framework (LCF) & contracts for difference (CfD) allocation what it means for the low-carbon generation mix
The levy control framework (LCF) & contracts for difference (CfD) allocation what it means for the low-carbon generation mix Gareth Redmond 24 th September, 2014 Paid for through energy bills costs passed
ANNEX B FEED-IN TARIFF WITH CONTRACTS FOR DIFFERENCE: DRAFT OPERATIONAL FRAMEWORK
ANNEX B FEED-IN TARIFF WITH CONTRACTS FOR DIFFERENCE: DRAFT OPERATIONAL FRAMEWORK 1 CONTENTS Introduction...3 Section A Price Setting...8 Section B CfD Allocation... 18 Section C CfD Terms Pre Commissioning...
The Gas and Electricity Regulated Providers (Redress Scheme) Order 2008. Consultation Document
The Gas and Electricity Regulated Providers (Redress Scheme) Order 2008 Consultation Document URN 13D/305 07 January 2014 2 The Gas and Electricity Regulated Providers (redress scheme) Order 2008 Department
www.gov.uk/government/consultations/ship-recycling-authorising-uk-facilities-to-work-oneu-flagged-ships
www.gov.uk/defra Consultation on proposed measures to implement elements of EU regulation 1257/2013 on ship recycling relating to the authorisation of UK ship recycling facilities Summary of response and
Electricity Market Reform: policy overview
Electricity Market Reform: policy overview November 2012 2 ELECTRICITY MARKET REFORM: POLICY OVERVIEW Presented to Parliament by the Secretary of State for Energy and Climate Change by Command of Her Majesty
The Levy Control Framework
Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn
Special administration regime for payment and settlement systems: summary of responses
Special administration regime for payment and settlement systems: summary of responses November 2013 Special administration regime for payment and settlement systems: summary of responses November 2013
Energy Act 2013 CHAPTER 32. Explanatory Notes have been produced to assist in the understanding of this Act and are available separately
Energy Act 2013 CHAPTER 32 Explanatory Notes have been produced to assist in the understanding of this Act and are available separately Energy Act 2013 CHAPTER 32 CONTENTS PART 1 DECARBONISATION 1 Decarbonisation
UK renewable energy an update
UK renewable energy an update 30 October 2014 Robert Hull, Managing Director Renewable energy key challenges 1 2 3 Costs to Climate change: Risks to security consumers: decarbonising of supply: short affordability
UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT NOTICE. Services
1/6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:273114-2011:text:en:html UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT
2014 No. 0000 ELECTRICITY. The Contracts for Difference (Standard Terms) Regulations 2014
Draft Regulations laid before Parliament under section 6(8) of the Energy Act 2013, for approval by resolution of each House of Parliament. D R A F T S T A T U T O R Y I N S T R U M E N T S 2014 No. 0000
Dear Colleague, Summary
System Operators, Transmission and Transportation System Owners, Generators, Shippers, Suppliers, Customers, Investors and other interested parties Date: 20 December 2013 Dear Colleague, Consultation on
Disclaimer: All costs contained within this report are indicative and based on latest market information. 16 th March 2015
Disclaimer: All costs contained within this report are indicative and based on latest market information 16 th March 2015 FD SUMMARY The make up of the electricity bill is changing, with non-commodity
Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE
National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE 16 June 2015 Duncan Burt Head of Commercial Operation National
Synergies and Conflicts of Interest arising from the Great Britain System Operator delivering Electricity Market Reform
Synergies and Conflicts of Interest arising from the Great Britain System Operator delivering Electricity Market Reform Final report URN: 13D/088 Department of Energy and Climate Change 3 Whitehall Place
Treaty Series No. 12 (2013)
Treaty Series No. 12 (2013) Exchange of Letters between the Government of the United Kingdom of Great Britain and Northern Ireland and the Government of the French Republic Amending the Agreement between
POLICY FEEDING RENEWABLE. How the Energy Bill might affect green electricity suppliers and also renewable generators
FEEDING RENEWABLE POLICY How the Energy Bill might affect green electricity suppliers and also renewable generators Holly Tomlinson Regulation and Compliance Analyst for Ecotricity 18 th January 2013 Contents
Fixed + Protect Electricity supply contracts explained for large business customers
Fixed + Protect Electricity supply contracts explained for large business customers 2/7 Fixed + Protect explained We fix your unit price, with a generous tolerance on how much your electricity use can
The Draft Consumer Credit (Total Charge For Credit) (Amendment) Regulations 2012
NOTES ON : The Draft Consumer Credit (Total Charge For Credit) (Amendment) Regulations 2012 MAY 2012 Department for Business, Innovation and Skills Notes on: THE DRAFT CONSUMER CREDIT (TOTAL CHARGE FOR
A Users Guide to the recast Late Payment Directive
DIRECTIVE 2011/7/EU ON COMBATING LATE PAYMENT IN COMMERCIAL TRANSACTIONS A Users Guide to the recast Late Payment Directive OCTOBER 2014) Contents Contents.2 Summary...3 Summary of new measures 4 What
Fixed + Protect Electricity supply contracts explained for large business customers
Fixed + Protect Electricity supply contracts explained for large business customers 2/7 Fixed + Protect explained We fix your unit price, with a generous tolerance on how much your electricity use can
Next steps to zero carbon homes
Next steps to zero carbon homes Small sites exemption November 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown.
npower EMR Explained Session The Energy Event 10 th & 11 th September 2013
npower EMR Explained Session The Energy Event 10 th & 11 th September 2013 Welcome Chris Billing, Head of Indirect Sales, npower Agenda > 13.30 Welcome & introduction Chris Billing EMR Pulse Survey Results
ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW
ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW February 2014 ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL The Energy Bill is the government s flagship energy policy. There have
Recruitment Sector. Consultation on prohibiting employment agencies and employment businesses from advertising jobs exclusively in other EEA countries
Recruitment Sector Consultation on prohibiting employment agencies and employment businesses from advertising jobs exclusively in other EEA countries JULY 2014 Contents Contents... 2 Prohibiting employment
Fixed + Peace of Mind Electricity supply contracts explained for large business customers
Fixed + Peace of Mind Electricity supply contracts explained for large business customers 2/7 Fixed + Peace of Mind explained This contract guarantees your unit price will stay fixed in all but exceptional
The UK Offshore Wind Experience
The UK Offshore Wind Experience Tom Simchak Policy Advisor, Energy British Embassy, Washington EESI Briefing, 28 September 2015 UNCLASSIFIED The United Kingdom is The global market leader in offshore wind:
Firefighter fitness standards and assessment
Firefighter fitness standards and assessment Consultation response December 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with
A GUIDE TO LEGAL FORMS FOR BUSINESS NOVEMBER 2011
A GUIDE TO LEGAL FORMS FOR BUSINESS NOVEMBER 2011 Guide to Legal Forms Unincorporated legal forms: The distinguishing feature of unincorporated forms is that they have no separate legal personality. There
Why do we need new arrangements for flood insurance?... 1. What is the Government s proposed approach?... 1. Flood Re... 1
Department for Environment, Food and Rural Affairs Water Bill Flood Insurance November 2013 This is one of a series of briefing notes on the Water Bill. This note explains in detail what the Government
Company Investigations What we do.
Company Investigations What we do. What we do Company Investigations has the power to investigate limited companies where information we receive suggests corporate abuse; this may include serious misconduct,
Cyber Essentials Scheme
Cyber Essentials Scheme Assurance Framework January 2015 December 2013 Contents Introduction... 3 Change from June 2014 version... 3 Overview... 4 Stage Definitions... 5 Stage 1 Cyber Essentials: verified
Electricity Market Reform: Proposals for Implementation
EMR Programme Team Department of Energy & Climate Change 4 th Floor Area D 3 Whitehall Place London SW1A 2AW 23 rd December 2013 Dear Sirs, Electricity Market Reform: Proposals for Implementation I am
Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth
Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth January 2014 Purpose of this document The duty to have regard to the desirability of promoting economic growth (the growth duty )
Basis for setting the discount rate for calculating cash equivalent transfer values payable by public service pension schemes
Basis for setting the discount rate for calculating cash equivalent transfer values payable by public service pension schemes updated guidance issued by HM Treasury March 2011 Official versions of this
Contracts for Difference Round Guidance
30th June 2014 Contracts for Difference Round Guidance Contracts for Difference Allocation Round 1 2014 CFD Round Guidance 3 rd October 2014 National Grid Delivery Body Page 1 CFD Allocation Round Guidance
Gaelectric Holdings Plc
Gaelectric Holdings Plc Response Paper to: Consultation on Transition from the NIRO to CfDs and Grace Periods 14/04/2015 Public 1 INTRODUCTION Gaelectric Holdings Plc (Gaelectric) welcomes the opportunity
Guidance for Mobile Air Conditioning (MAC) Sectors. Guidance: F Gas and Ozone Regulations Information Sheet MAC 3: Key Obligations
Department for Environment, Food and Rural Affairs Guidance for Mobile Air Conditioning (MAC) Sectors Guidance: F Gas and Ozone Regulations Information Sheet MAC 3: Key Obligations April 2012 Contents
Reforming the business energy efficiency tax landscape
Reforming the business energy efficiency tax landscape September 2015 Reforming the business energy efficiency tax landscape September 2015 Crown copyright 2015 This publication is licensed under the
Environmental damage: extending the Environmental Liability Directive into marine waters
www.gov.uk/defra Environmental damage: extending the Environmental Liability Directive into marine waters Consultation on amending the Environmental Damage (Prevention and Remediation) Regulations 2009
Response to direct consultation questions
Consultation on proposals for the levels of banded support under the Renewables Obligation for the period 2013-17 and the Renewables Obligation (Scotland) Order 2011 Response by RenewableUK RenewableUK