Project Name: All Electronic Tolling (AET) Design Services. Consultant s Name: The Heimburg Group, Inc.
|
|
|
- Kory Kelly
- 10 years ago
- Views:
Transcription
1 Page 1 Advertisement No.: DOT FM Number: Project Name: All Electronic Tolling (AET) Design Services Consultant s Name: The Heimburg Group, Inc. Street Address: 5461 W Waters Avenue, Suite 910 City: Tampa State: FL Zip: Office Location: Tampa Contact person: Stephan Heimburg, PE Phone: Contact [email protected] By submittal of this letter the Consultant certifies that all information provided in the letter is true and accurate. The Consultant further affirms that staff proposed are currently employed by the firm(s) identified, or the Consultant has provided a statement of when staff will become employed by the identified firm(s). Please provide the following information: Proposed approach and understanding of critical issues. Relevant project experience Similar type of work experience. Other content provided by firm. Proposed key personnel and their proposed roles (do not include resumes). Consultants: Please be aware that all font (including in graphics, tables, and captions on photos) must be standard Arial Narrow, 11 point, single line spacing with no modification of font or spacing allowed. ½ clear margin on all sides must be maintained on all pages. It is the Consultant s responsibility, due to font and format restrictions within this form, to work within the constraints of the form and its format. Character styling such as use of color, bold, and italics is allowed. Use of a table is recommended for text boxes. The page layout may be modified to add columns, tables, graphics, and photos. All graphics and photos must be created in a clean, blank word document and the text wrapping square option applied before cutting and pasting into this form. Consultants may add their logo at the top of the first page (directly underneath the header), however, the Consultant shall not extend the form beyond the pages allocated for the Letter to accommodate insertion of the logo. Consultants are not permitted to insert any other information in the header other than the logo. After pasting your letter into this form, highlight all text and ensure the font size of Arial Narrow, 11 point was retained. Once your content is inserted, delete any additional blank pages that are generated by pressing your delete key after the last word in the Letter of Response. Recreation of the form in another software application to modify the form format is not permitted. This form works best when saved with a.docx extension. *Please retain the source document as it may be requested at a later date in the procurement, to verify adherence with aforementioned restrictions. Note: You may begin typing on this page. PROJECT AWARENESS For over 20 years, the FTE has been at the forefront of the evolution to AET. It began with the development of the SunPass system and implementation of low speed, dedicated lanes under SunPass Challenge (SPC). The evolution continued with: Open Road Tolling (ORT) with expansion and capacity projects, SunPass Only interchanges, Expedited design speed tolling, at selected mainline toll plazas, while maintaining cash collection under ORT Lite, and AET conversion with Toll-by-Plate at the most utilized corridors in South Florida and Tampa. The goal of the AET contract is the expedited, economical AET conversion of the remaining mixed-use toll sites operated and owned by FTE. The scope includes existing conditions analysis, conceptual design, and final design. Through our discussions with the Technical Review Committee and our vast experience, we understand the design must address the following objectives: The Safety of Patrons and Tolls staff with a consistent and criteria based design, and a common sense approach. Protection of Revenue through a robust, maintainable infrastructure, and a design that eliminates potential toll evasion. A constructible design that addresses TCP, toll collection, driver inconvenience and reduces construction schedule. Adherence to stakeholder requirements and constraints, such as Toll Operations and critical utilities including FGT. Comparing Best Value Options, based on benefits, costs (infrastructure & equipment), safety, and operations. Development of an implementation plan that addresses the objectives for a plaza, project, corridor and system-wide basis. Congestion-free traffic operations, through analysis of signalization, weaving and merging conditions, as the toll impedance is removed from the system. Expedited customer driven delivery of designs and plans, like the SPC and ORT Lite Programs.
2 Page 2 PROJECT TEAM AND EXPERIENCE Achieving these objectives will require an understanding that each site has unique geometric, toll, and traffic conditions. It will also require the collaborative efforts of the design team and all FTE internal stakeholders, including Planning, Design, Traffic & Toll Operations and Construction. The range of challenges mandates innovation, experience and knowledge in concept development and final design to achieve success. THG s Team is proud to have provided unique concepts and final designs that meet operational, design and tolling requirements for the FTE. Our collective experience and our reputation for developing innovative solutions makes us uniquely qualified for these assignments. THG selected Team members based on project needs, as well as shared values of accountability, quality, on-time delivery and reputation for superior service to the FTE. The Team will be led by Stephan Heimburg, PE, who has led numerous multidiscipline projects, with an eye toward the big picture and attention to details. Key subconsultants are Bentley Architects (Bentley) for architecture and Kimley-Horn & Associates for support disciplines and final design, as needed. The depth of our recent toll experience includes: THG provided concepts for AET 5A, 6B & 6C, TCP for AET 5B & 6B, and final site designs for AET 6C. Wantman Group is certified to perform SUE on FGT facilities, eliminating the need for FGT supervision. Bentley has designed and obtained building and State Fire Marshal permits for numerous FTE facilities. PROJECT APPROACH MANAGEMENT APPROACH: Our approach is based on coordination, planning, and quality. Coordination: We recommend regularly scheduled coordination meetings with the two teams selected and the FTE stakeholders to ensure consistency in methodology and concurrence with the potential alternatives. This approach will allow the FTE to fairly evaluate options and prioritize improvements. This effort also includes supporting PIO inquiries from stakeholders with meetings, graphics and narratives. Planning: This task driven contract provides flexibility for the range of activities. It also provides the opportunity to adjust approaches as decisions are made based on data collection and analysis. Corridor segments, as identified in the scope, should be assigned to a specific team. This approach aids creation of an implementation plan on small and large scales, as well as construction packaging. Tasks may include: Task 1: Existing Conditions This task includes data collection, review and analysis of record drawings, inventories of toll lane type, traffic data, and programmed improvements. The AET 8 Concept Report for the ticket system will facilitate the effort for this segment. Deliverable documents include an ERCAR, lane line concepts, evaluation of buildings to be repurposed and if needed, a traffic analysis. Task 2: Concept Development This task includes the application of toll and traffic operations concepts to individual sites, similar to the approach we used on the AET 5A Concept Memoranda. Concepts will be developed to ensure constructability, as well as continued traffic and toll operations. Viable concepts will be evaluated based on infrastructure and equipment costs, design deviations required, acceptable toll operations and compatibility with future plans. For example, AET deployment on the eastern mainline site of the Polk Parkway could include considering future widening from two to four lanes. Task 3: Final Design This task includes field surveys and geotechnical work. It relies on a multidiscipline team and comprehensive completion of Task 2 to efficiently complete design. Our Team is built for consistency of staffing, as sites evolve from concepts to design, minimizing coordination. Quality: THG is responsible to FTE for quality delivery of all deliverables. Team members are responsible to THG for the quality of their deliverables. Each discipline will have a designated QC reviewer. As Principal, Lisa Heimburg, PE will be responsible for Quality Assurance. Key tenets of our QA/QC Plan include: 1) A project specific QC Plan that outlines procedures (including the 5-step process), responsibilities and schedule, 2) Review of Lessons Learned on previous projects, 3) Senior staff with discipline specific and toll experience, 4) Maintaining production schedules so that there is sufficient time for pre-delivery QC and implementation of necessary changes, and 5) QA of subconsultant deliverables. TECHNICAL APPROACH: We have formed the following strategies as part of our approach: Design Standards: Concepts will conform to AASHTO, FDOT, and TPPPH criteria & processes, including the General Tolling Requirements (GTR). When these requirements conflict, innovation is required. Our design will meet the intent (safety, operations, tolling) of the requirements. Our approach emphasizes: Avoidance of design exceptions, but consideration of variations with the reuse of existing infrastructure. Full design speed improvements and ORT equipment for conversion of mainline sites. Consultation with the Tolls Office on possible refinement of requirements for unique site conditions. KEY PROJECTS THG THG Staff KHA BAE AET 1-3 AET 5A AET 5B AET 6A/B/C SPC ORT Lite KEY STAFF Project Manager (THG) Stephan Heimburg, PE Roadway/TCP (THG) J. Webb Jones III, PE Robb Hideck, PE Lindsey Skourellos, PE Gerald Sudimick, PE Traffic Anal. (THG/KHA) Patricia Sikowski, AICP Ian Rairden, PE S&PM(THG) J. Webb Jones III, PE Signals(KHA) Ron Hildebrand, PE Drainage (THG) John Westgate, PE Permitting (KHA) Lynn Kiefer Structures (KHA) Jamea Long, PE Landscape (KHA) Bill Waddill, RLA ITS (KHA) Sam Trotman, PE Lighting (KHA) Matthew Fursetzer, PE Utility Coord. (WGI) Kristen Youcis, PE Survey (WGI) Sam Hall, PSM Joe Shatto, PSM SUE (WGI) Erik Brueningsen, PE Tolling (BAE/SWC) Gary Kranston, AIA Molly devivero, PE Brian Mullin, PE Malcolm Watkins, PE Geotechnical (TI) Jeremy Sewell, PE
3 Page 3 Interchange Operations: AET operations will unmeter traffic that can impact interchange traffic operations. We will identify low cost improvements, including the addition of turn lanes and signal timing modifications. A diamond ramp could be considered for trumpet interchanges (like the Hollywood Blvd. interchange) to reduce left turn volumes but would add cost to the project. This approach extends the life of the interchange without constructing cross street improvements. Overhead destination signing on cross street turn lanes will minimize weaving at trumpet entrance ramps. Toll Alternatives: We understand that most toll plazas within the project limits have newer toll equipment with Toll-by-Plate capabilities for both dedicated and ORT lanes. This condition allows for consideration of a variety of AET design options: Full AET: Reconstruction of toll infrastructure and approaches to meet higher design speeds, mostly applicable to mainline sites. AET Lite: Use of dedicated lanes with closure of cash lanes and signing modifications, applicable to low speed ramps, based on the limited benefit of a higher ramp design speed near a signal. AET Hybrid: Reconfiguration of existing infrastructure elements (canopy, building, pavement) for AET. This approach was used for the clear span canopy at HEFT/SW 8 th St. toll site. The full AET and AET Lite alternatives represent extremes in cost and operation. Hybrid concepts will be developed to provide a higher design speed than AET Lite, an interim mainline condition or other needs. Like the ORT Lite program, Hybrid and Lite concepts may require design variations for a limited design life. Toll Siting: The GTR outlines primary considerations, including geometry, availability of utilities and access. Full AET ramp options will be the most challenging to design, based on geometric limitations and the need to maintain tolls. For full AET mainline sites, consistent siting of the Toll Equipment Building on one side of the route is preferred. Some toll plazas on the northern coin system have off-site access due to remote locations. During Task 2, we will review the disposition of these access roads. TCP/Constructability/Implementation: These interrelated issues must be addressed during Task 2, due to impacts to siting and configuration. Our strategy to address these issues includes: Construction packaging and implementation by segment will eliminate the need for coordination of contractor schedules. Construction documents will provide testing requirements. Phasing within segments: Construction of mainline AET sites for plazas without ORT lanes; a soft AET conversion with closure of all cash lanes; followed by completion of all AET sites. o Soft conversion is supported by existing toll equipment and will facilitate operations by providing consistent toll collection. o Soft conversion will aid TCP by reducing the number of lanes to be maintained. Without a soft conversion, there will be more TCP phases and extended construction duration. Ramp closures are not desirable for the Orlando area, based on potential concurrent I-4 construction and tourist traffic; or the Turnpike beyond Orlando, based on extended detour lengths. We will also look for opportunities to use the Mobile Emergency Gantry, previously developed by Bentley, for temporary tolling. OTHER ISSUES AND OPPORTUNITIES Implementation: Segment interfaces with mixed-use toll routes are unique areas, requiring the following considerations: Public notice and toll operations will be simplified with segment packaging and a complete soft conversion of a segment. Signing for last chance exits must be included beyond the limits of each converted segment for cash customers. The schedule of AET conversion on the Turnpike may impact configurations at segment interfaces, if there is schedule lag: o Three Lakes Plaza could have an ORT Lite configuration with the initial conversion of the northern coin or ticket segment. o Lantana Plaza must maintain cash collection until both AET 5A (I-595 to Lantana) and ticket segments are converted. Interfaces with Orlando toll routes (SR 429, SR 417, and SR 528) have unique considerations, if CFX maintains cash tolls: o CFX has both cash and ORT lanes. Sporadic cash collection may lead to driver confusion, requiring more signing for AET. o The SR 417 Celebration site will be the only mainline non- ORT site in Orlando. FTE may elect to provide an interim ORT Lite configuration (with cash tolls), in advance of AET. Consistency in Toll Collection: We understand the current FTE approach of maintaining the current toll system to avoid shifting of toll burden between users. However, the ticket system is a legacy toll system that could be changed to a barrier system, with minimal toll changes to maintain consistency along the Turnpike. AET conversion provides an opportunity to change seamlessly. Starnet Gantries: This legacy toll infrastructure is subject to fatigue cracking. AET conversion provides the opportunity to replace these structures, as needed. Express Lanes: FTE is implementing Express Lanes on selected routes. The Team will review opportunities for consolidating express tolling and AET sites, such as the Beachline West. We are utilizing a similar approach at the HEFT/Kendall interchange. Toll Leaks: AET conversion also provides the opportunity to close access to the system without paying tolls by adding toll sites at locations, such as the Turnpike/US 301 ramps to/from the north. Environmental Permitting: Siting will be developed to minimize environmental impacts. In addition, AET will result in a reduction in pavement, which must be documented in the permit modification so that pond volumes are available for future improvements. FGT and AT&T: These stakeholders require considerations based on established agreements. The Team is well versed in their requirements, having provided unique solutions for the development of both ramp and mainline concepts for AET 5A. Commitment: Quality staff is not relevant without staff availability. THG commits to providing the project staff for the AET Contract project for planning, design and post-design phases. Close: At THG, we are proud that this Team has the experience, innovation, knowledge and enthusiasm for this project and we look forward to demonstrating these qualities to FTE. We thank you for your consideration and look forward to your favorable review. The Heimburg Group, Inc. Stephan Heimburg, PE, Project Manager
4 Page 4 Prequalification of Prime Consultant and any proposed Subconsultants by advertised type(s) of work: Project Advertised Major & Minor Work Types Consultant Name DBE SB UU Prime The Heimburg Group, Inc. (THG) Kimley-Horn & Associates, Inc. (KHA) Bentley Architects & Engineers, Inc. (BAE) Wantman Group, Inc. (WGI) Tierra, Inc. (TI) Sims Wilkerson Cartier Engineering, Inc. (SWC) Subconsultants SB = Small Business UU = Under-utilized work type; subconsultant is fulfilling an under-utilized work type My firm has submitted a Bid Opportunity List through the Equal Opportunity Compliance System for this project.
5 Page 5 Prequalification of Prime Consultant and any proposed Subconsultants by advertised type(s) of work: Project Advertised Major & Minor Work Types Consultant Name DBE SB UU Prime The Heimburg Group, Inc. (THG) Kimley-Horn & Associates, Inc. (KHA) Bentley Architects & Engineers, Inc. (BAE) Wantman Group, Inc. (WGI) Tierra, Inc. (TI) Sims Wilkerson Cartier Engineering, Inc. (SWC) Subconsultants SB = Small Business UU = Under-utilized work type; subconsultant is fulfilling an under-utilized work type My firm has submitted a Bid Opportunity List through the Equal Opportunity Compliance System for this project.
DOT FM Number: 40906144201 & 42427144B01
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 15465 DOT FM Number: 40906144201 & 42427144B01 Project Name: District Four Right
City: Orlando State: Florida Zip: 32804
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 11/14 Page 1 Advertisement No.: 15820 DOT FM Number: TBD Project Name: Turnpike-Wide Miscellaneous Design
Consultant s Name: HSQ GROUP INC. Street Address: 1489 W. Palmetto Park Road, Suite 340. City: Boca Raton State: FL Zip: 33486
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 16444 DOT FM Number: 43165713201 Project Name: SR-811 DIXIE HWY./NE 4 th AVE.
City: Fort Lauderdale State: FL Zip: 33309
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 16427 DOT FM Number: 431513-2-1201 Project Name: Districtwide Planning & Environmental
Consultant s Name: F.R. Aleman & Associates, Inc. Street Address: 10305 NW 41 Street, Suite 200. City: Miami State: FL Zip: 33178
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 16118 DOT FM Number: 20201511208 Project Name: Districtwide Statistics - Data
City: Tampa State: Florida Zip: 33619
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 16107 DOT FM Number: 43719412201, 43719412202 Project Name: Environmental Management
Industry Forum Road to Success This Exit. Centralized Customer Service System (CCSS)
Industry Forum Road to Success This Exit Centralized Customer Service System (CCSS) Welcome to the Centralized Customer Service System Industry Forum Welcome to the Centralized Customer Service System
Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1
Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important
Project Name: Natural Disaster Monitoring/Construction Engineering & Inspection. Consultant s Name: Target Engineering Group, Inc.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES EXPANDED LETTER OF RESPONSE 375-030-23 Page 1 Advertisement No.: 16546 DOT FM Number: TBD Project Name: Natural Disaster Monitoring/Construction
FDOT DISTRICT 5 ITS DECISION SUPPORT SYSTEM & ATMS SOFTWARE DEVELOPMENT (CONCEPT STUDY)
December 11, 2014 EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). 436328-1-22-01 FDOT DISTRICT 5 ITS DECISION SUPPORT SYSTEM & ATMS SOFTWARE DEVELOPMENT (CONCEPT STUDY) TABLE OF CONTENTS TABLE
Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital
Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering
Advertisement No.: 15554 DOT FM Number: 43067813201 (Submitted 7/17/14) Project Name: SR 5 (US 1) from South Street to Magnolia
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 15554 DOT FM Number: 43067813201 (Submitted 7/17/14) Project Name: SR 5 (US 1)
Multi Modal Roadway Transportation Impact Fees and Asset Value
January 2010 SB 360 Article Series: Factors to be Considered in Transitioning from a Road Impact Fee to a Mobility Fee Contributing Authors: Steven A. Tindale, P.E., AICP Robert P. Wallace, P.E., AICP
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...
All Electronic Tolling System (AETS) Implementation Project
All Electronic Tolling System (AETS) Implementation Project I-90 (Western Turnpike / Boston Extension) & Harbor Crossings Stephen M. Collins MassDOT Director of Statewide Tolling Presented by: Donald Bell
IH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
Incremental Changes and Disruptive Impacts in Tolling. By Philip Miller, P.E., AECOM
Incremental Changes and Disruptive Impacts in Tolling By Philip Miller, P.E., AECOM Incremental Changes and Disruptive Impacts in Tolling Outline Incremental Changes From 1990 to Today, The Way It Was
The Need for Traffic Incident Management
The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity
3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
FTP/SIS/FMTP Regional Workshop - Tampa
Meeting Highlights Welcome and Introductions FTP/SIS/FMTP Regional Workshop - Tampa September 2, 2015 FDOT District 7 Auditorium 11201 N. Malcolm McKinley Drive Tampa, FL 32612 Debbie Hunt, FDOT District
DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST
State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage
Background and Goals for the Project
City of Asheville, NC REQUEST FOR PROPOSALS Wilma Dykeman Riverway Environmental Analysis, Project Development, and Preliminary Design Submittal Address: Dan Baechtold, AICP City of Asheville Engineering
Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects
General: Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects The information outlined within this document, depicts a portion of Florida s Turnpike
University of Northern Iowa Design Documents Standards. October 2014
University of Northern Iowa Design Documents Standards October 2014 2014 UNI BUILDING AND DESIGN STANDARDS 1.1 CONTRACT DOCUMENT FORMAT 1.1.1 The Electronic Word Programs used for the Project manual shall
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST
FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST August 2003 Background: The Federal Highway Administration (FHWA) has retained all approval rights to the control
HRTAC Regional Financial Planning. October 29, 2015
HRTAC Regional Financial Planning October 29, 2015 PFM s Transportation Experience For 29 years PFM has been ranked the leading financial advisor, including investment and commercial banks, to transportation
SCOTTSDALE TRANSPORTATION COMMISSION REPORT
SCOTTSDALE TRANSPORTATION COMMISSION REPORT To: Transportation Commission From: Paul Basha, Transportation Director Meeting Date: September 19, 2013 Subject: SR-101 Pima Freeway Improvements ITEM IN BRIEF
Ocoee, FL May 13, 2016 Advertisement No. 1
BID SOLICITATION NOTICE Turnpike FLORIDA DEPARTMENT OF TRANSPORTATION CONSTRUCTION AND MAINTENANCE PROGRAMS Ocoee, FL May 13, 2016 Advertisement No. 1 All bids must be completed using Expedite Bid software
Bay. Region Design- US-10. June 13, 2014
REQUEST FOR QUALIFICATIONS MICHIGAN DEPARTMENT OF TRANSPORTATION Bay Region Design- Build Project US-10 over I-75 Job Numbers: 122868 Control Section: 09034 Original Issue June 13, 2014 TABLE OF CONTENTS
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of
Illinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015
Illinois Tollway and Chicago Department of Transportation Construction Networking Event March 13, 2015 Today s Agenda Welcome Illinois Tollway projects Chicago Department of Transportation (CDOT) projects
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program SECTION 1 - GENERAL INFORMATION The Greenville-Spartanburg
REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES. The Battery Conservancy
REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES The Battery Conservancy Issue Date: March 23, 2012 Responses Due: April 20, 2012 Introduction The Battery Conservancy ( TBC ) is a 501(c)(3) not-for-profit
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION TRANSPORTATION IMPROVEMENT PROGRAM MIAMI-DADE EXPRESSWAY AUTHORITY (MDX)
XA10016 10016 SR 112 Toll System Conversion LeJeune Road I-95 4.1 Toll System Conversion 4,811 1,723 Activity - - DSB MDX 3,088 0 0 0 0 XA10017 10017 SR 836 Toll System Conversion NW 137th Avenue I-95
MIAMI-DADE EXPRESSWAY AUTHORITY (MDX) OPERATIONS COMMITTEE MEETING TUESDAY, AUGUST 27, 2013 12:00 PM
MIAMI-DADE EXPRESSWAY AUTHORITY (MDX) Attendees: Present Committee Members: Louis V. Martinez, Esq., Chair Gus Pego, P.E., Vice Chair via phone Alfredo L. Gonzalez, Esq. Jose M. Hevia Luz Weinberg Present
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
City of Mercer Island
City of Mercer Island MOBILE ASSET DATA COLLECTION: Pavement Condition Index Deflection Testing Sign Inventory Sign Retroreflectivity Contact Information: Leah Llamas, GIS Coordinator The City of Mercer
How To Develop An Enterprise Architecture
OSI Solution Architecture Framework Enterprise Service Center April 2008 California Health and Human Services Agency Revision History REVISION HISTORY REVISION/WORKSITE # DATE OF RELEASE OWNER SUMMARY
PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...
CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........
Executive Summary. Literature/Community Review. Traffic Flows and Projections. Final Report Truck Route System for Miami-Dade County CORRADINO
Executive Summary The Miami-Dade County Metropolitan Planning Organization (MPO) has prepared a Truck Route System Plan for Miami-Dade County. The MPO and its consultants have worked closely with the MPO
Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management
Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management Wisconsin Department of Transportation FDM 2-15-1 Project Integration Management December 11, 2014 1.1
Introduction to Public-Private Partnerships (P3s)
Introduction to Public-Private Partnerships (P3s) Today s Instructor Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Program Development Team Course Outline Slide 2 Lesson
EDUCATION AND PROFESSIONAL DEVELOPMENT PROFESSIONAL EXPERIENCE
JESSICA C. MILES, P.E. Curriculum Vitae September 19, 2003 SJB Group, Incorporated 225-769-3400 P.O. Box 1751 [email protected] Baton Rouge, La. 70821-1751 EDUCATION AND PROFESSIONAL DEVELOPMENT Florida
MOHAMMAD I CHAUDHRY, P.E. A CONSTRUCTION PROJECT MANAGER Specialized in Highways, Bridges and Infrastructures construction & Maintenance
MOHAMMAD I CHAUDHRY, P.E. A CONSTRUCTION PROJECT MANAGER Specialized in Highways, Bridges and Infrastructures construction & Maintenance SUMMARY: Mr. Chaudhry, a decisive, innovative leader with a demonstrated
CONNECTICUT DEPARTMENT OF TRANSPORTATION
CONNECTICUT DEPARTMENT OF TRANSPORTATION DIGITAL PROJECT DEVELOPMENT MANUAL Version 3.11 Issued 01-2016 1 Version 3.11 INTRODUCTION This document is for Consultant and State Employees responsible for the
EPA Technical Assistance for Sustainable Communities Building Blocks
EPA Technical Assistance for Sustainable Communities Technical Assistance Tool: Complete Streets Deerfield Beach, Florida February 16, 2012 To: CC: Amanda Martinez, City of Deerfield Beach Roger Millar,
MODULE 2: SMARTLIST, REPORTS AND INQUIRIES
MODULE 2: SMARTLIST, REPORTS AND INQUIRIES Module Overview SmartLists are used to access accounting data. Information, such as customer and vendor records can be accessed from key tables. The SmartList
Transportation Management Plan Template
DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County
QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS
QUALITY ASSURANCE and QUALITY CONTROL PROCESS GUIDE for PROJECT MANAGERS MDOT Trunkline Projects January 2005 TABLE OF CONTENTS Discussion.. 2 Scope Verification Meeting..... 3 Overview 3 Procedure...
Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
AIR QUALITY TECHNICAL MEMORANDUM
AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision
LBJ Express Project (LBJ Managed Lanes Project)
(LBJ Managed Lanes Project) LBJ Through the Years LBJ Through the Years LBJ Through the Years History 1987 LBJ Corridor Study Begins 1987 2004 Extensive Planning - 200+ Public Meetings June 2004 LBJ Coalition
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
Scope of Work Construction Inspection and Materials Testing Services
Glenwood Resident Engineer 202 Centennial Drive Glenwood Springs, CO 81601 Scope of Work Construction Inspection and Materials Testing Services Estimated Start Date: November 1, 2015 Region 3 Project:
Ne w J e r s e y Tr a f f i c Co n g e s t i o n :
Ne w J e r s e y Tr a f f i c Co n g e s t i o n : A Growing Crisis January 2008 Cover photo : Route 3, Passaic County introduction A rising tide of traffic congestion threatens to increase roadway gridlock,
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
Airport Safety and Construction Management Under The FAA
U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Quality Management for Federally Funded Airport Construction Projects Date: DRAFT Initiated by: AAS-100 AC No.:
Interchange Access Request. User s Guide. User Guide
Interchange Access Request User s Guide User Guide 2013 2013 TABLE OF CONTENTS Table of Contents Preface... 1 Purpose... 1 Scope... 1 Organization... 2 Distribution, Updates and Contact... 3 Chapter 1
WFT - SAP Disaster Recovery Solution Brief Planning and Automating an SAP Landscape Remote Recovery Procedure
WFT - SAP Disaster Recovery Solution Brief Planning and Automating an SAP Landscape Remote Recovery Procedure Abstract This Solution Brief discusses how WFT Disaster Recovery Services helps a customer
Polk Commerce Centre CRA Spine Road Alignment Study
Polk Commerce Centre CRA Spine Road Alignment Study Florida Polytech Pace Road (LIMIT) Berkley Road Williams DRI Proposed Alignment Polk Commerce Centre CRA Boundary Braddock Road (LIMIT) Lake Myrtle Sports
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Accenture Mobility Services Mobility for Better Business Outcomes. IBTTA 80 th Annual Meeting & Exhibition
Accenture Mobility Services Mobility for Better Business Outcomes IBTTA 80 th Annual Meeting & Exhibition Mobile Tolling Solution & Demonstration September, 2012 Orlando Accenture, its logo, and High Performance
CAD Standards Guideline For Facility Documentation and Construction Projects
CAD Standards Guideline For Facility Documentation and Construction Projects Page 1 of 12 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4. External References 5.
VDOT GOVERNANCE DOCUMENT
VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery
PROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
STAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Scarborough Subway Extension Project Management Services Contract FE85-3 Date: February 25, 2015 To: From: TTC Board Chief Executive Officer Summary
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
CHAPTER 5 - Construction Project Management Contents Introduction... 2 Construction Contract Management... 2 CEI Contracts... 3 Community Awareness Plan... 7 Alternative Contracting Methods... 8 Warranty
Traffic Forecasting. Resource Guidebook. Florida Department of Transportation District Five
Traffic Forecasting Resource Guidebook Florida Department of Transportation District Five Florida Department of Transportation District Five November November 2006 2006 Traffic Forecasting Resource Guidebook
State of the Practice and Recommendations on Traffic Control Strategies at Toll Plazas
State of the Practice and Recommendations on Traffic Control Strategies at Toll Plazas State of the Practice and Traffic Control Strategies at Toll Plazas: Best Practices BY: IN PARTNERSHIP WITH: With
Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.
Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
MAP 21 themes. Strengthens America s highway and public transportation systems. Supports the Department s aggressive safety agenda
MAP 21 themes Strengthens America s highway and public transportation systems Creates jobs and supports economic growth Supports the Department s aggressive safety agenda Simplifies and focuses the Federal
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems
Fire Alarm Systems Level IV Content Outline Standard Model/CBT The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive
The Lancaster Medical District Master Plan. The Lancaster Campus District 1
The Lancaster Medical District Master Plan The Lancaster Campus District 1 Table of Contents 1 INTRODUCTION 3 2 THE PLANNING PROCESS 4 Assumptions 6 3 PLANNING CONTEXT AND ECONOMIC OUTLOOK 7 Site Analysis
Telecommunications Systems Manager I (Supervisor) Essential Task Rating Results
Telecommunications Systems Manager I (Supervisor) Essential Task Rating Results 1 2 3 4 5 6 7 8 9 10 11 12 13 Supervise activities and direct personnel in the implementation of various departmental programs
Traffic Incident Management Enhancement (TIME) Blueprint Version 2.0 Executive Summary
Blueprint Version 2.0 Executive Summary Strategic Background The Southeastern Wisconsin region, which encompasses the following eight counties: Fond du Lac, Kenosha, Milwaukee, Ozaukee, Racine, Walworth,
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
Proposed Service Design Guidelines
Proposed Service Design Guidelines July 2015 I. Introduction During Phase II of the Reimagining CityBus project, feedback from public outreach and data analysis conducted during Phase I of the project
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF