Project Management System Based on Work-Breakdown-Structure Process Model
|
|
|
- Lora O’Brien’
- 10 years ago
- Views:
Transcription
1 Project Management System Based on Work-Breakdown-Structure Process Model Akira Harada 1, Satoshi Awane 1, Yuji Inoya 1, Osamu Ohno 1, Makoto Matsushita 2, Shinji Kusumoto 2, and Katsuro Inoue 2 1 Engineering Support Management Division, Solution Systems, Hitachi Ltd. 890 Kashimada Kawasaki, Kanagawa, , Japan {aharada, awane, yinoya, ohno }@itg.hitachi.co.jp 2 Department of Computer Science Graduate School of Information Science and Technology Osaka University 1-3, Machikaneyama, Toyonaka, Osaka ,Japan {matusita, kusumoto, inoue}@ist.osaka-u.ac.jp Abstract: We have developed a WBS(Work Breakdown Structure) process model for a business application software development project. We have also developed a project management system called PRO-NAVI which works on the WBS process model. This WBS process model provides (1) mutual mapping between the software development processes, activities, products, know-how, rules, and standards, and provides (2) comprehensive control. The role of project management in a business application software development project is recognized to be of more importance. These projects generally involve huge efforts, and cost heavy payloads to their project management. Thus, an efficient project management system is needed. We have developed PRO-NAVI. We have applied and evaluated PRO-NAVI with a number of projects and confirmed that it is effective for efficient project fulfillment. 1 INTRODUCTION Digitization and networking of the society is accelerated, such as seen in diffusion ofthe Internet and the World Wide Web, and in business application software development, requirements for larger scale, higher function, shorter delivery schedule, and lower cost are urged. Accordingly, role of project management is becoming more important to carry out business application software development projects as planned: [1],[2],[3],[4]. Generally in a project management, repetition of so called Plan-Do-Check-Action process, make plan, execute it, check progress situation, and take action if necessary is said to be fundamental. A project is a set of multiple works and their consequential products, and a project management is a facilitation to make these works done with efficiency and to manage works and products. Therefore, a system to support a project management is required.
2 This paper is a proposal of a management method of works and products and a project management support method based on WBS(Work Breakdown Structure) process model: [5],[6],[7],[8] We also show our actual development of PRO-NAVI, which is a WBS-based project management system. As project management systems, MS-Project [9], ProcessDirector [10], and KnowledgePLAN [11] are well known products. As Product document management systems, DocumentBroker [12] and documentum [13] are well known products. We thought a new point of view is required, to relate and use with efficiency, of project process information, work information, product information, know-how information, which both of above have. PRO-NAVI provides [a] clear definition of software development process, work, and products of the project at the project planning phase, [b] grasp of project progress status, [c] standardization of software project development process and navigation, [d] sharing of project knowledge such as project products and know-how. These improve efficiency of project promotion. PRO-NAVI is used by more than 1,000 projects by now and will be used more. In this paper, we will show modeling of a business application software project by WBS in chapter 2, realization of PRO-NAVI in chapter 3, we will also show an application example, evaluation and consideration in chapter 4, and we will show a summary and address future issues in chapter WBS WBS is a hierarchy chart to describe project goals in detail. 2.1 WBS process model Department of Defense handbook Work Breakdown Structure defines WBS as below: [5] (1) A product-oriented family tree composed of hardware, software, services, data, and facilities. The family tree results from systems engineering efforts during the acquisition of a defense material item. (2) A WBS displays and defines the product, or products, to be developed and/or produced. It relates the elements of work to be accomplished to each other and to the end product. (3) A WBS can be expressed down to any level of interest. However the top three levels are as far as any program or contract need go unless the items identified are high cost or high risk. Then, and only then, is it important to take the work breakdown structure to a lower level of definition. PMBOK defines WBS as, A deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Each descending level represents an increasingly detailed definition of the project work,: [6] In this paper, we will explain according to the definition of [6]. We will also call each element of WBS as work.
3 2.2 Project planning based on WBS (1) Standard PRO-NAVI WBS We propose a five layer WBS process model for a software development project and name it Standard PRO-NAVI WBS. [a] first layer: project [b]second layer: sub-project [c]third layer: phase [d]fourth layer: work step [e]fifth layer: product Fig.1. Standard PRO-NAVI WBS Figure 1 shows an example of Standard PRO-NAVI WBS. First layer is the project itself. We divide the whole software to be developed by a project to several loosely related sub systems and name each project to develop one of these sub systems as sub-project. We define this sub-project as the second layer. For example, for a project to develop a management administration system for an enterprise, first layer will be management administration system, second layer will be sub systems of the management administration system such as employee management system, account management system, merchandise management system, and so on. Standard PRO-NAVI WBS defines names of works in 3 rd, 4 th, and 5 th layer as shown in Figure 1. Third layer, that is, phase, is equivalent to waterfall model development phase: [14],[15], and it divides the project lifecycle into 7 phases, namely, requirement analysis, business requirement design, software design, software detailed design, programming and unit test, combination test, and integrated or system test. These phases proceed with time by the above order.
4 The fourth layer, or work step, divides the work of each phase into multiple concrete works. Software design for example, will be divided into following 7 work steps: architecture design, test planning, business process design, database layer class design, function layer class design, presentation layer event design, and physical database design. Fifth layer, or product, includes process design document, system component definition, business flow diagram, display transition diagrams and so on. Product entities are managed by files. One product is designed to be constituted by one or more than one files so that more than one project members can share the works concerning one product. For example, process design document can be made of two following files, online process design document and batch process design document. We call this file as product file, and this product file will not show up to standard PRO-NAVI WBS. We simply call product file as product when it is not necessary to make distinction. A chronological order do exist among phases as listed, however, no peculiar relation in time exists among work steps and products. These work steps, work items correspond to activities and tasks of SLCP-JCF98, which is a common frame for software centric development and trades: [16] A project member may need to refer to prerequisite products to do a work. A project member may also be able to do works efficiently with common project know-how and knowledge of standards, procedures, and worksheets.so, we add two kinds of common information items to each of Standard PRO-NAVI WBS [17]: 1) prerequisite works prior to the current work, 2) common knowledge required, such as rules and procedures. (2) Optimization of Standard PRO-NAVI WBS A Standard PRO-NAVI WBS defines a standard business application software development process, and may cause excess or deficiency of works for actual projects. So, we made a concept of customized PRO-NAVI WBS, which is a derivative of Standard PRO-NAVI WBS, giving more details and layers, adding necessary works, deleting unnecessary works, renaming works, so as to optimize Standard PRO-NAVI WBS for a peculiar project. However, we have given restrictions on deletion or change of specific works in the Standard PRO-NAVI WBS in order to enforce a certain common structure to the customized PRO-NAVI WBSs for various projects. By this, we can easily promote standardization of project management method because the customized PRO-NAVI WBSs for various projects have same product names, work names, and similar basic structures. When there is no need to make distinctions between Standard PRO-NAVI WBS and customized PRO-NAVI WBS, we simply call them as PRO-NAVI WBS. We have prepared multiple, not one, Standard PRO-NAVI WBSs, so that the customized PRO-NAVI WBSs can be made with ease. When deriving a customized PRO-NAVI WBS, we also optimize prerequisite works and common information accordingly. The common information will be added common reference information of the project. (3) A project planning based on PRO-NAVI WBS A project plan can be clearly defined by deciding project start date, project finish date, project members, work start dates, work finish dates, work member assignments.
5 So, we add two kinds of information items to each work of PRO-NAVI WBS : 1) assigned members, due dates, and progress status of the work (started, not started, completed, reviewed and approved), 2) product files that constitutes an product, assigned member, updated time, version number and progress status. By this, we can have following effects: 1) A project plan and its progress status are clear to its members, and project plan and progress information can be easily accessed, because the PRO-NAVI WBS structure is identical to the project s development process. 2) Project s common knowledge such as products, rules, procedures and worksheets can be easily found and referred because they are not only uniformly managed but also related to respective works, thus higher quality, higher efficiency and standardization of works can be done. Fig.2. An example of attached information to PRO-NAVI WBS Figure 2 shows an example of information added to the PRO-NAVI WBS. In this example, customized PRO-NAVI WBS and project member information are added to project general information of a business administration project. Additionally, plan of work itself and prerequisite works, common references, and product files information are also added. Figure 2 shows one member HARADA is scheduled to finish a glossary of business terms by 2004/4/16, and manufacturer s part of the glossary of business terms is assigned to AWANE and was updated on 2004/4/16.
6 3. PRO-NAVI We have developed a project management system PRO-NAVI, based on PRO-NAVI WBS process model. In this chapter, we explain the schematics, functions and implementation of PRO-NAVI. 3.1 Structure and functions of PRO-NAVI (1) Structure of PRO-NAVI Figure 3 shows the structure of PRO-NAVI. Fig.3. The structure of PRO-NAVI PRO-NAVI is composed of the Web server and more than one client PCs, and they communicate through the Internet or intranet. The Web server is connected with the Project information DB and the Product DB. The Project information DB stores the information shown in Figure 2. The Product DB stores product files, which are entities of products. The Web server has project information processing part, project information display processing part and product management part. A project plan which is made on a manager s client PC will be sent to the Web server, and then processed by the project information processing part, and then stored in the Project information DB. A project information which is stored in the Project information DB,
7 will be processed by the project information display processing part, and then sent to the manager s client PC or to a developer s client PC, and then displayed. (2) Project information display function Two kinds of project information display functions for each project member s client PC are provided and are called private view and project view. (a) private view The private view is a screen to display the works, a list of product files, and the progress status of the project member who operates his or her client PC. Actual screen example is shown in Figure 4. This example shows multiple projects or sub projects one member participates in, works assigned, a list of product files made and registered. The project path (in Japanese) represents first and second layers of the PRO-NAVI WBS, and work path (in Japanese) represents the third layer or below. The first item of Figure 4 shows he or she is assigned to a business integration project (in Japanese), is assigned a project work definition of non-functional requirements (system requirements) (in Japanese), and the due date is 2004/12/10, and the progress status is started (in Japanese).If one member belongs to multiple projects, all the works assigned and a list of product files of those projects will be displayed. Fig.4. An example of private view (b)project view The project view is a screen to display PRO-NAVI WBS, product information of each WORK, and reference information of each WORK. A screen example is shown in Figure 5. If one selects a work on PRO-NAVI WBS display frame on the left of the screen, related WORK and a list of product files, assigned members, due dates, and progress status will be displayed as Product information display frame on the upper right of the screen. If one selects a product file in addition, he or she can view a file registered as a product.
8 Fig.5. An example of project view A reference information display frame on the lower right of the screen displays products and common information of the organization to be referenced. If one selects one item, he or she can read a relevant document. For example, in Figure 5, one has selected definition of non-functional requirements (system requirements) (in Japanese) of PRO-NAVI WBS display frame, and the Product information display frame displays assigned member as HARADA (in Japanese), due date (in Japanese) as 2004/12/10, and status (in Japanese) as started are displayed. In addition, definition of non-functional requirements (system requirements) (in Japanese) is composed of three product files and displayed with assigned member names and status, namely, system requirement definition document, use model, percentage of band-width share weekly day and time wise. Also, the reference information display frame displays common information to refer when defining non-functional requirements (system requirements), namely, non-functional requirements setting guidance (in Japanese), Division standard, and system requirement examples. (3) Other functions (a) Managers functions 1) Project managers are able to make project plans based on PRO-NAVI WBS, by putting in necessary information through his or her client PC with ease, because prototypes of WBS, prerequisite WORKs, and common information are provided by Standard PRO-NAVI WBS. These project plans will be transmitted through the network and then stored in the Project information DB. 2) Project managers refer to Product information display frame of the project view and then evaluate progress status by project planning, and status of works and product files.
9 3) Project managers may directly read product files and confirm progress status or percentage of completion independent from project member s report, if necessary. 4) Project managers choose one product file from a list which is displayed in the Product information display frame, and check the contents, review, or approve, and then reflect the result to the status. (b) Developers functions 1) A developer refers to his or her client PC s private view or project view and confirms assigned works; this is called To Do management. 2) A developer refers to his or her project view and recognizes participating project s plan and progress status. 3) A developer selects product files and downloads them to the client PC from a list displayed in his or her private view or project view, and then do assigned works, update product files. 4) If prerequisite work products or a common reference of the organization is found to be required while making an assigned product, a developer selects a necessary material from Reference information display frame, and then downloads it to the client PC and refers to it. 5) An updated most recent product will be sent to the server and then stored in Product DB. At this time, version number of the product file will be also updated by 1, hence version management of product files are also performed by version numbers. 6) On completion of the assigned product, a developer changes status of the product and the product files to COMPLETED. By 1), start priorities and due dates of the products are shown, and by 4), directions and examples of contents and formats of the products are shown, and thus these are Navigator of works. We name this as NAVIGATION FUNCTION. 4 Evaluation We will state the application record and effects of PRO-NAVI. 4.1 Actual application record of PRO-NAVI Fig.6. The cumulative number of the projects using PRO-NAVI Figure 6 shows the cumulative number of the projects using PRO-NAVI. We started the operation of PRO-NAVI on March, By March, 2004, approximately 1200
10 projects are using PRO-NAVI. The number of product files registered counts approximately 310,000 by March, We think PRO-NAVI has become the standard project management system of in-house use. We have added new standard PRO-NAVI WBSs, as the number of PRO-NAVI users grows. We had just two standard WBSs at the beginning. Now we can choose from 13 types of standard PRO-NAVI WBSs for each project and then optimize it. Added standard PRO-NAVI WBSs are developed with name-changes, check-process-additions and unnecessary-work-deletions corresponding to our customer s business fields and their organizations, as shown in Figure 7. Fig.7. Types of standard PRO-NAVI WBSs For example, for the financial field WBS, we have added detailed improvements concerning systems operation. We have added detailed works such as emergency operation manuals and tests. A project manager selects an appropriate standard PRO-NAVI WBS, related with customer s business field and customer s role in the company, optimizes it, and then starts a project. We have favorable evaluations from PRO-NAVI users, as shown below. (1) Getting across job of the project standard document and project development plan to its project members has become easier. (2) Development errors due to version-mistakes have disappeared, because most recent products can be shared in a secured manner. (3) Search job for necessary products has become much easier. (4) Distribution job of products has become easier. (5) Hard copy document distribution has decreased. (6) Version management of products has become possible. (7) A project manager can easily verify the project status report, because the project manager can directly check the status of the product and its contents with PRO-NAVI.
11 4.2 An application example of PRO-NAVI A railroad company ticket system construction project: 800 Kilo source lines of code to be developed, by 200 project members in 10 separate development locations. This large scale project applied PRO-NAVI to achieve high efficiency development and management level and to share project progress status, product files and project common documents. (1) Optimized standard PRO-NAVI WBS for the project. Figure 8 shows the optimization process of standard PRO-NAVI WBS to the project above. Fig.8. An example of customization of PRO-NAVI WBS Optimization points are as follows: (a) Unnecessary works or products are deleted. Here, (system planning) and (I/O design document) are deleted. (b) Standard names of works are renamed to that of peculiar ones in the project. In Figure 8, the name of (business process design document) is renamed to (function design document comprehensive part-). (c) Divided works are added as 6 th layer, so that a project member can be assigned to a divided product. In Figure 8, (function design document comprehensive part-) is divided to (0. top cover/outline) and (1. Purpose and positioning). (2) Comprehensive management of products and common documents. The PRO-NAVI managed 391 product files as outcomes of design process, and 173 common documents. (3) Accurate grasp of the project progress status The PRO-NAVI s product information display frame provides products progress status, and a manager may directly access to each product. Thus, a project manager can directly feel and confirm progress status of products and their quality. The project is to have prescheduled progress meetings, and project members are to report their progresses. The project manager compared project member s report with PRO-NAVI confirmation result, and warned the project member, whose confirmation result was
12 much different, and realized early detection of progress problems and suitable countermeasures. (4) Application result of PRO-NAVI Effects of using PRO-NAVI are given in Table 1. Table 1. Effects of using PRO-NAVI On the other hand, product progress status gathering function is pointed out to be an issue. For example, to grasp project progress status, one needs to select a work in PRONAVI WBS display frame of the project view, and then check its progress work by work in product information display frame. This operation method has advantage in grasping percentage of completion of products, however, it costs effort to grasp project progress status, and requires a new function to sum up product progress. 4.3 Analysis and Considerations From application results of PRO-NAVI until now, we have confirmed three effects as follows: (1) Clarification and notification of project plan throughout the project. (2) Correct grasp of project progress status. (3) Higher quality, higher efficiency, standardization of the project due to easy access to products and common documents. It is also recognized, with PRO-NAVI, one can grasp progress status with ease, however to grasp comprehensive project progress status, one needs to select work by work from project view displays, and this costs effort. For this issue, an automatic collection apparatus of project progress status based on products is effective, and we should make research. 5. CONCLUSIONS In this paper, we have proposed a WBS process model to relate project process, project works, project products, and project s common knowledge such as know-how, rules,
13 and standards and a project management system PRO-NAVI. As is shown in chapter 4, PRO-NAVI provides (1) Clarification of software development process, work, and products of the project at the planning phase, (2) a grasp of project progress status, (3) standardization of software project development process and navigation, (4) sharing of project knowledge such as project products and know-how. We have confirmed the PRO-NAVI is an effective system to support a project management. On the other hand, project progress status gathering is pointed out to be a bothersome and burdensome job and requires much effort. Our next step will be the research and development of an automatic collection and evaluation function of project progress status based on products which are registered in PRO-NAVI. References 1. H. Kerzner, Project Management, John Wiley&Sons, Inc. New York (2001) 2. R. Rada, J. Craparo, " Standardizing software projects," Communications of the ACM, vol.43, no.12 (Dec. 2000) Watts S. Humphrey, Managing the Software Process, Addison-Wesley, Winthrop (1989) 4. Shunichi Fukuyama, Hideo Takagi, Ryoji Tanaka, Michihiro Watanabe, Isao Nakabayashi: Procedures for Implementing Checklists that Provide Guidance for Continuous Improvements in Software Processes, IPSJ Journal, vol.42, no.3 (March 2001) Department of Defense handbook Work Breakdown Structure(MIL-HDBK-881), Department of Defense, USA (1998) 6. A Guide to the Project Management Body of Knowledge 2000edition, Project Management Institute, Newtown Square (2000) Glossary 7. Gregory T. Haugan, Effective Work Breakdown Structures, Management Concepts, Vienna (2002) 8. Practice Standard for Work Breakdown Structures, Project Management Institute, Newtown Square (2001) 9. Eric Uyttewaal, Dynamic scheduling with Microsoft Project2002, J. Ross Publishing and International Institute for Learning, Boca Raton (2003) 10. KABUSHIKIKAISHA NEC, KORABOREISHON-GATA PUROJEKUTOKANRI SISUTEM ProcessDirector (in JAPANESE), KABUSHIKIKAISHA KOUZOUKEIKAKUKENKYUUJYO, SOFUTOUEA MITSUMORI TUURU KnowledgePLAN (in JAPANESE), KABUSHIKIKAISHA HITACHI SEISAKUSHO, BUNSHOKANRIKIBAN DocumentBroker Version2 (in JAPANESE), NIPPON DOKYUMENTAMU KABUSHIKIKAISHA documentum (in JAPANESE), C. Jones, Applied Software Measurement, The MeGraw-Hill Companies, New York (1996) 15. H. Kerzner, Applied Project Management, John Wiley&Sons, Inc., New York (2000) 16. KYOUTUUFUREIMU98 SLCP-JCF98-(1998 NENBAN), SLCP-JCF98IINKAI, KABUSHIKIKAISHA TSUUSANSIRYOUTYOUSAKAI, TOKYO (1998) (in Japanese) 17. Y. Oka, T. Tanida, S. Konno, C. Hirai, "Operation assistance method and system and recording medium for storing operation assistance method," U.S. Patent no , (Sep.2004)
An Empirical Study of Process Management and Metrics based on In-process Measurements of a Standardized Requirements Definition Phase
An Empirical Study of Process Management and Metrics based on In-process Measurements of a Standardized Requirements Definition Phase Yoshiki Mitani 1,2, Tomoko Matsumura 2, Mike Barker 2, Seishiro Tsuruho
Standardization of Development Process and Additional Efforts Focusing on Web Application Development
Standardization of Development Process and Additional Efforts Focusing on Web Application Development V Ryoko Saito V Satoru Okiyama V Fusami Hirai (Manuscript received March 14, 2006) In this time of
Application of Knowledge Management to System Development
Application of Knowledge Management to System Development V Kazuo Hosono (Manuscript received February 6, 2006) Fujitsu is currently undertaking the project advocated by PMI Co. of the U.S. based on PMBOK
Microsoft Project 2007 Level 1
Microsoft Project 2007 Level 1 One Day Course Course Description You need to gather information about the various tasks involved, resources required to accomplish the tasks, and the overall cost in order
IT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: [email protected] Mobile: 0502862400
Total System Operations and Management for Network Computing Environment
Total System Operations and Management for Network Computing Environment Hitachi Review Vol. 47 (1998), No. 6 291 Satoshi Miyazaki, D. Eng. Toshiaki Hirata Masaaki Ohya Eiji Matsumura OVERVIEW: The architecture
Applying the Work Breakdown Structure to the Project Management Lifecycle
Applying the Work Breakdown Structure to the Project Management Lifecycle Introduction Shelly A. Brotherton, PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP Today, Project Managers are more frequently
What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many
Manufacturing challenges of today and how Navision Axapta solves them- the solution for change; controlled by you. Manufacturing In the current explosive economy, many manufacturers are struggling to keep
Development Process Visualization and Project Management
Development Process Visualization and Project Management V Yuichi Arita V Noriyasu Nakayama V Yutaka Awata (Manuscript received May 31, 2006) The environment surrounding enterprises is complex and rapidly
Aras Corporation. 2005 Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability
Aras Corporation 2005 Aras Corporation. All rights reserved Notice of Rights All rights reserved. Aras Corporation (Aras) owns this document. No part of this document may be reproduced or transmitted in
Improvement of Software Quality and Productivity Using Development Tools
Improvement of Software Quality and Productivity Using Development Tools V Hideo Abotani V Tomoki Shiratori V Kouji Sasaki V Masaki Tonomura (Manuscript received March 24, 2006) Information systems, which
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
Project Management Development Scheduling Plan: Data Mart. By Turell Makins
Management Development Scheduling Plan: Data Mart By Turell Makins Contents Executive Summary Purpose of Customer s Requirements Resource List Gantt Chart Critical Questions/Risk Assessment Software Development
Incorporating Systems Engineering and Project Management Concepts in First Year Engineering Curriculum
Incorporating Systems Engineering and Project Management Concepts in First Year Engineering Curriculum Muhammad Faysal Islam 1 and Mohammed Nazrul Islam 2 1 Department of Engineering Management and Systems
TLS handshake method based on SIP
Proceedings of the International Multiconference on ISSN 1896-7094 Computer Science and Information Technology, pp. 467 475 2006 PIPS TLS handshake method based on SIP Tadashi Kaji 1, Kazuyoshi Hoshino
Approach of Applying Design Technology to System Development Process: From HCD to UX Design
Approach of Applying Design Technology to System Development Process: From HCD to UX Design Hideo Zempo Toshio Ogawa It is important that the practice of Human-Centered Design (HCD) is widely understood
Fujitsu s DFX Application
Fujitsu s DFX Application V Yukio Sekiya V Hideaki Takahashi (Manuscript received May 26, 2006) Improvements in product design are conventionally made after the start of massproduction, followed by reductions
Do you know? "7 Practices" for a Reliable Requirements Management. by Software Process Engineering Inc. translated by Sparx Systems Japan Co., Ltd.
Do you know? "7 Practices" for a Reliable Requirements Management by Software Process Engineering Inc. translated by Sparx Systems Japan Co., Ltd. In this white paper, we focus on the "Requirements Management,"
The QlikView deployment framework
Technical Brief The QlikView deployment framework January, 2014 Table of Contents Introduction 2 Who is this document for? 2 The QlikView deployment framework 3 A sample QDF setup 4 What s included in
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
SOFTWARE DEVELOPMENT PLAN
SOFTWARE DEVELOPMENT PLAN This document outline is based on the IEEE Standard 1058.1-1987 for Software Project Management Plans. This is the controlling document for managing a software project, and it
Fujitsu Enterprise Security Architecture
Fujitsu Enterprise Security Architecture V Tetsuo Shiozaki V Masayuki Okuhara V Nobuo Yoshikawa (Manuscript received November 9, 2006) Recently, there has been a growing need for enterprises to respond
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Chapter 13 BUILDING INFORMATION SYSTEMS. How does building new systems produce organizational change?
MANAGING THE DIGITAL FIRM, 12 TH EDITION Learning Objectives Chapter 13 BUILDING INFORMATION SYSTEMS VIDEO CASES Case 1: IBM: Business Process Management in a Service Oriented Architecture and Managing
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013 The purpose of these questions is to establish that the students understand the basic ideas that underpin the course. The answers
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
3SL. Requirements Definition and Management Using Cradle
3SL Requirements Definition and Management Using Cradle November 2014 1 1 Introduction This white paper describes Requirements Definition and Management activities for system/product development and modification
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Social Innovation through Utilization of Big Data
Social Innovation through Utilization of Big Data Hitachi Review Vol. 62 (2013), No. 7 384 Shuntaro Hitomi Keiro Muro OVERVIEW: The analysis and utilization of large amounts of actual operational data
Modeling Guidelines Manual
Modeling Guidelines Manual [Insert company name here] July 2014 Author: John Doe [email protected] Page 1 of 22 Table of Contents 1. Introduction... 3 2. Business Process Management (BPM)... 4 2.1.
Project Implementation Plan (PIP) User Guide
eea financial mechanism Project Implementation Plan (PIP) User Guide 23 November 2007 norwegian financial mechanism Page 2 of 20 1 Introduction The Project Implementation Plan (PIP) is a representation
Developing CMMI in IT Projects with Considering other Development Models
Developing CMMI in IT Projects with Considering other Development Models Anahita Ahmadi* MSc in Socio Economic Systems Engineering Organizational Process Development Engineer, International Systems Engineering
R&D for Construction of Remote Support Technology in the Equipment Control Department
[L1.1.9] R&D for Construction of Remote Support Technology in the Equipment Control Department (Remote support system group) Shibaura 401 Laboratory Goi 402 Laboratory Yokkaichi 402 Laboratory Ikunori
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Mobility Manager 9.5. Installation Guide
Mobility Manager 9.5 Installation Guide LANDESK MOBILITY MANAGER Copyright 2002-2013, LANDesk Software, Inc. and its affiliates. All rights reserved. LANDesk and its logos are registered trademarks or
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
A methodology for secure software design
A methodology for secure software design Eduardo B. Fernandez Dept. of Computer Science and Eng. Florida Atlantic University Boca Raton, FL 33431 [email protected] 1. Introduction A good percentage of the
A Case Study of Calculation of Source Code Module Importance
A Case Study of Calculation of Source Code Module Importance Takaaki Goto 1, Setsuo Yamada 2, Tetsuro Nishino 1, and Kensei Tsuchida 3 1 Graduate School of Informatics and Engineering, The University of
Manual on o Training Management
5 Project on Improvement of Local Administration in Cambodia Manual on o Training Management Introduction What is Training Management? How to Use the Manuals Table of Contents 1. Introduction...4 2. What
Takeda Pharmaceutical s E-Notebook Project Report
Takeda Pharmaceutical s E-Notebook Project Report Akihiko Harada Toshihiko Kuboki Minoru Hagiwara Takeda Pharmaceutical Company Limited faces three problems: controlling cost and time in activities to
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Synchronizing ProCurve IDM and Windows Active Directory
An HP ProCurve Networking Application Note Synchronizing ProCurve IDM and Windows Active Directory Contents 1. Introduction... 2 2. Prerequisites... 2 3. Network and Active Directory tree diagrams... 2
Architecture Centric Development in Software Product Lines
Architecture Centric Development in Software Product Lines Aurangzeb Khan DCE, College of E & ME National University of Science and Technology (NUST), Pakistan Farooque Azam DCE, College of E & ME National
The Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
ORACLE PROJECT MANAGEMENT
ORACLE PROJECT MANAGEMENT KEY FEATURES Oracle Project Management provides project managers the WORK MANAGEMENT Define the workplan and associated resources; publish and maintain versions View your schedule,
Microsoft Dynamics GP. Engineering Data Management Integration Administrator s Guide
Microsoft Dynamics GP Engineering Data Management Integration Administrator s Guide Copyright Copyright 2007 Microsoft Corporation. All rights reserved. Complying with all applicable copyright laws is
A Case Study in the Design of a Restaurant Management System
A Case Study in the Design of a Restaurant Management System Wesley Williams, Devon M. Simmonds Department of Computer Science University of North Carolina Wilmington {waw5709, simmondsd}@uncw.edu Abstract
How To Set Up Safetica Insight 9 (Safetica) For A Safetrica Management Service (Sms) For An Ipad Or Ipad (Smb) (Sbc) (For A Safetaica) (
SAFETICA INSIGHT INSTALLATION MANUAL SAFETICA INSIGHT INSTALLATION MANUAL for Safetica Insight version 6.1.2 Author: Safetica Technologies s.r.o. Safetica Insight was developed by Safetica Technologies
TWX-21 Business System Cloud for Global Corporations
TWX-21 Business System Cloud for Global Corporations 8 TWX-21 Business System Cloud for Global Corporations Hidenori Kiuchi Yasuyuki Suzuki Sho Obayashi Manabu Naganuma Seiichiro Hayashi Taku Tozawa OVERVIEW:
Novell ZENworks Asset Management 7.5
Novell ZENworks Asset Management 7.5 w w w. n o v e l l. c o m October 2006 USING THE WEB CONSOLE Table Of Contents Getting Started with ZENworks Asset Management Web Console... 1 How to Get Started...
Recent Technologies in Nuclear Power Plant Supervisory and Control Systems
Hitachi Review Vol. 49 (2000), No. 2 61 Recent Technologies in Nuclear Power Plant Supervisory and Control Systems Toshiharu Yamamori Takashi Ichikawa Satoshi Kawaguchi Hiroyuki Honma OVERVIEW: Supervisory
Producing Listings and Reports Using SAS and Crystal Reports Krishna (Balakrishna) Dandamudi, PharmaNet - SPS, Kennett Square, PA
Producing Listings and Reports Using SAS and Crystal Reports Krishna (Balakrishna) Dandamudi, PharmaNet - SPS, Kennett Square, PA ABSTRACT The SAS Institute has a long history of commitment to openness
FUJITSU Software Systemwalker Desktop Patrol V15 Introducing July 2015 Fujitsu Limited
FUJITSU Software Systemwalker Desktop Patrol V15 Introducing July 2015 Fujitsu Limited Using a Client Terminal in an Enterprise The usage scenarios of the client terminal for TPO have expanded In the office
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
Graphical Web based Tool for Generating Query from Star Schema
Graphical Web based Tool for Generating Query from Star Schema Mohammed Anbar a, Ku Ruhana Ku-Mahamud b a College of Arts and Sciences Universiti Utara Malaysia, 0600 Sintok, Kedah, Malaysia Tel: 604-2449604
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
2015-11-16. Project Proposal PDT401: Automatic deployment of operating system, drivers and software using MDT, Chocolatey and Powershell.
2015-11-16 Project Proposal PDT401: Automatic deployment of operating system, drivers and software using MDT, Chocolatey and Powershell. Gus Johansson Thomas Rovala Table of contents 1 Introduction...
ENOVIA Aerospace and Defense Accelerator for Program Management
ENOVIA Aerospace and Defense Accelerator for Program Management Through project pipeline dashboards, ENOVIA Aerospace and Defense Accelerator for Program Management provides real-time visibility into a
2. Research and Development on the Autonomic Operation. Control Infrastructure Technologies in the Cloud Computing Environment
R&D supporting future cloud computing infrastructure technologies Research and Development on Autonomic Operation Control Infrastructure Technologies in the Cloud Computing Environment DEMPO Hiroshi, KAMI
Methodology Framework for Analysis and Design of Business Intelligence Systems
Applied Mathematical Sciences, Vol. 7, 2013, no. 31, 1523-1528 HIKARI Ltd, www.m-hikari.com Methodology Framework for Analysis and Design of Business Intelligence Systems Martin Závodný Department of Information
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
Function Point Measurement from Java Programs
Function Point Measurement from Java Programs Shinji Kusumoto, Masahiro Imagawa, Katsuro Inoue Graduate School of Engineering Science Osaka University Toyonaka, Osaka, Japan {kusumoto, imagawa, inoue}@icsesosaka-uacjp
Quality Perspective: Managing Software Development Projects
Economy Informatics, vol. 11, no. 1/2011 99 Quality Perspective: Managing Software Development Projects Felician ALECU Academy of Economic Studies, Bucharest, Romania [email protected] In order to better achieve
The Essentials of Project Management, 4 th Edition By Dennis Lock (Review by R. Max Wideman, FPMI)
The Essentials of Project Management, 4 th Edition By Dennis Lock (Review by R. Max Wideman, FPMI) 12/13/15 Introduction The views expressed in this article are strictly those of Max Wideman. The contents
Project Management Courses
"A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the
Administration and Business Collaboration. User Manual
Administration and Business Collaboration User Manual Copyright 2007 by Eurekify Ltd., 8 Hasadna Street Raanana 43651, ISRAEL. All Rights Reserved. This document maybe used in its complete form only and
Topology Diagrams with Jalasoft Xian and Savision Live Maps
Topology Diagrams with Jalasoft Xian and Savision Live Maps Extending System Center Operations Manager 2007 with Jalasoft and Savision Authors: Roberto Alcocer, Jalasoft Version: 1.0 March 2009 Some Rights
// Benchmarking Project Schedules
// Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over
CA Clarity PPM. Project Management User Guide. v13.0.00
CA Clarity PPM Project Management User Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation )
44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
Axiomatic design of software systems
Axiomatic design of software systems N.P. Suh (1), S.H. Do Abstract Software is playing an increasingly important role in manufacturing. Many manufacturing firms have problems with software development.
< IMPACT > START ACCELERATE IMPACT
START ACCELERATE IMPACT IMPACT project has received funding from the European Union Seventh Framework Programme (FP7/2007-2013) under grant agreement n 632828 START ACCELERATE IMPACT WEBINAR #2 Technology