State Highway Maintenance and Operations Review consultation document
|
|
|
- Edwin Park
- 10 years ago
- Views:
Transcription
1 State Highway Maintenance and Operations Review consultation document The State Highway Maintenance and Operations Review was established to investigate options for improving efficiencies and outcomes for road users.
2 our purpose creating transport solutions for a thriving new zealand NZ Transport Agency Published July 2012 ISBN (print) ISBN (online) Copyright: July 2012 NZ Transport Agency If you have further queries, call our contact centre on or write to us: NZ Transport Agency Private Bag 6995 Wellington This publication is also available on NZ Transport Agency s website at
3 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 1 Contents 2 Foreword 3 Introduction 4 Issues for discussion and feedback 7 Next steps 8 Timeframes
4 2 NZ Transport Agency State Highway Maintenance and Operations Review July 2012 Foreword We have significant pressures from a constrained fiscal environment across the board, driven by the current international economic environment and its implications for the NZ economy. The entire public sector is being asked to find ways of driving greater efficiencies and to manage within existing budgets. For its part, the NZTA is facing a 6% annual increase on its maintenance, operations (M&O) and renewals expenditure during the next three years, without any corresponding increase in budget. This amounts to a $160 million shortfall over the next three years. We know that driving prices down to unsustainable levels for the industry is not the answer, so we need to look at other ways to drive efficiency through better economies of scale and the most efficient and effective use of resources across New Zealand. That is what the State Highway Maintenance and Operations Review (M&O Review) is all about. We would like to hear your views on our service delivery (procurement) ideas. This is a genuine consultation process and while we have views based on the analysis, no final decisions have been made. We encourage sector-wide engagement to ensure any changes are well informed and sustainable. Colin Crampton General Manager Highways and Network Operations NZ Transport Agency
5 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 3 Introduction The Road Maintenance Taskforce (RMTF), established by the government in July 2011, has been conducting a review to identify opportunities for road controlling authorities (RCAs) to deliver M&O more efficiently and effectively. The RMTF interim recommendations include options to unlock additional efficiency and effectiveness gains through increased collaboration between RCAs, better asset management and service delivery. In parallel with the RMTF review, the NZTA established the M&O Review in 2011 to investigate options for improved efficiencies and outcomes within its own state highway activities. Reflecting the critical role of the industry in the maintenance and operation of the state highway network, the M&O Review has been a collaborative process led by a working group comprising NZTA asset and business managers and representatives from contractors and consultants (Fulton Hogan, Downer, MWH, Transfield, Opus and Higgins). The working group has met regularly for the past nine months to contribute to the review process. As a working group, there are a number of things we all agree on: The need to strengthen our asset management capability even further, building on New Zealand s good international reputation. This will be implemented in the form of a new Asset Management Group working across the state highway business to ensure that we deliver optimised levels of service and performance across the 11,000km of state highway network. Work is already underway to determine the scope and areas of focus, and the form of the group is expected to be finalised by Christmas The need for the NZTA to continue driving improvements in programming, activity prioritisation and rationalising levels of service across the various levels of state highway through a range of value for money initiatives. The majority of this work is expected to be complete within the next 12 months. There is an opportunity for the NZTA to collaborate more with suppliers, customers and our RCA partners to achieve better transport outcomes. The working group has also considered in detail what efficiency opportunities there are in the service delivery (procurement) area. Key inputs considered by the working group and publicly available as part of the wider industry consultation now underway are: NZTA report, Summary of measurement phase output, April NZTA, Root cause analysis, July PWC report, Evaluating different approaches to maintenance and operations procurement, February Rationale report, Financial analysis of M&O procurement options, June Opus report, SH network physical works procurement survey, June 2012 NZTA report, Procurement Task Group discussion paper, June The next step is to seek wider industry feedback on proposed changes to the NZTA s M&O procurement practices based on the analysis. As part of the seven-week consultation period, the NZTA will hold a series of engagement sessions with key regional suppliers, territorial local authority representatives and NZTA asset managers to explore the ideas arising from the review.
6 4 NZ Transport Agency State Highway Maintenance and Operations Review July 2012 Issues for discussion and feedback 1. Longer-Term Contracts We are considering the benefits of longer term contracts, subject to performance. Currently most contracts are for three to five-year terms. The working group s findings based on best practice across other jurisdictions has led to a recommendation for nine-year term contracts, under a renewal structure subject to supplier performance. For suppliers, longer contract duration would reduce administrative costs associated with re-tendering after shorter terms and deliver increased certainty upon contract award, which enables better allocation of resources and longterm investment in learning and development. For the NZTA, it encourages greater competitiveness at tender time and will underpin future strengthening of our partnership/ collaboration with industry to deliver better outcomes. These potential gains would be undermined without appropriate performance tension, so the idea of having longer term contracts goes hand-in-hand with potential changes in contract type and incentives. 2. New M&O Contract Form We believe there are benefits in developing a new M&O contract model, based on the best attributes of the other existing contract types (hybrid, PSMC, traditional and alliance). The alliance model is likely to be retained but the new contract form would replace all other existing contract types. There could be some exceptions to this such as bridge management, tunnels, avalanche control, which may continue to be procured under a traditional contract form. Standardising the approach to contracts will drive better consistency across the regional state highway networks. It will help with benchmarking and understanding the reasons for variances in unit cost of activity, enabling NZTA asset managers and suppliers to work together to identify opportunities for innovation and/or knowledge-sharing across networks. Standardising contracts should also help reduce the administrative burden and commensurately increase efficiencies. It will also ensure all parties to a contract have clear and aligned expectations and can focus on performance. Drawing from the M&O Review s findings in relation to the best attributes of current contract models, it is proposed that the new M&O Value Service Delivery Model contract would: be based on the NZS:3910 form of contract with an independent engineer to the contract contain a mix of both output and outcomebased requirements clearly define the risk profile within the contract and look to transfer risk to the party best positioned to manage it. Where the scope of the works is clear, the basis of payment could be lump sum and where the scope of the works cannot be clearly defined, a more transparent cost approach could be adopted include cost fluctuation mechanisms and day works mechanisms for valuing works that cannot be adequately scoped, such as winter maintenance, emergency or additional works have flexibility to adjust quantities and levels of service throughout the contract period have clearly defined and measurable outcomes and value for money performance measures, and mechanisms to incentivise performance. This could result in pain/gain mechanisms which incentivise the supplier to deliver on the right outcomes have strong governance with formalised relationship-based partnerships through contract management boards and quality supervision of construction be based on an open book approach to provide more transparency on value and sufficient data to enable benchmarking across multiple networks. The NZTA s discussion paper discusses two options for the proposed Value Service Delivery Model. The first includes the single supplier approach and the second, a more conventional consultant, contractor and client relationship. We would like to engage with stakeholders on these ideas and gain a better understanding of the benefits and risks associated with each approach.
7 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 5 3. Contract Aggregation There is evidence which suggests that there are benefits in aggregating contracts across the state highway network. Currently, more than 80% of the contract areas are less than 500km long. Comprehensive analysis of data for the state highway network shows that in all cases as network length increases the corresponding network expenditure does not increase proportionally. In other words, the unit cost of maintenance per kilometre reduces. The analysis suggests that economies of scale deliver increased efficiency from an asset owner perspective. In addition, engagement with suppliers and asset managers across the regions undertaken as part of the review revealed that the optimum length per state highway contract is km to maximise efficiency and effectiveness of their own respective operations. This finding aligns well with the output from the rationale report, which suggests that the optimum state highway network length per contract is around lane km ( carriageway km based on a typical rural state highway). A smaller number of larger contracts would significantly reduce administrative and tendering overhead costs, enable optimal utilisation of resource (including plant), and support enhanced capability building across the industry through more strategic allocation of people and expertise. As well as being in line with international trends (United Kingdom, Australia and Canada), this approach is already emerging organically in the New Zealand market, with a natural trend towards contract aggregation (refer to the PWC report) that reflects the benefits inherent in aggregation supported by a robust subcontractor market. We would like to hear the views of our suppliers on this idea and engage in a discussion on the long term impacts on small and medium-sized suppliers and how this could be managed while achieving the aims of the review. The key to successful transition to contract aggregation is how the network is segmented. No specific network boundaries have been determined at this stage, but a range of obvious factors come into play including complexity, topography, traffic volumes, traffic management demands, distance from larger population centres, and expenditure. Refer to section 3 of the Procurement Task Group discussion paper for detail on the options and analysis. The working group has come up with a set of key criteria for assessing the various options for segmenting and configuring the network and seeks feedback on the options based on the following principles: Results in reduced overall costs to all parties in the maintenance and operation of existing and new infrastructure assets. Allows opportunity to utilise asset management expertise and reprioritise funding to areas of greatest need. Provides more consistent management of similar sections of state highway. Creates a scale and complexity that attracts and retains appropriately skilled staff with growth opportunities and long-term sustainability. Preserves opportunities for various degrees of collaboration between client organisations, that better match up the supply market and optimise economic factors. Ensures a competitive and sustainable market. Considers the primary purpose of the state highway and its contribution to both national and regional route availability and congestion. Considers the customers overall expectation and experience. Allows opportunity to explore and implement innovative concepts and manages risks that return benefits to all parties and the customer. Provides flexibility to redesign future network configurations. Resources are effectively and efficiently utilised and suppliers can benefit from current strong centres of labour skills and availability. Recognises the effect of change to suppliers, stakeholders, and client organisations and the ease of implementation to realise perceived benefits. Allows the wider supply chain to contribute to maintenance and operations activities.
8 6 NZ Transport Agency State Highway Maintenance and Operations Review July Fence-to-Fence approach to Term Contracts Based on the analysis, the NZTA considers there may be benefits in moving to fence-to-fence (all inclusive) network maintenance contracts, with some rare exceptions on a case-by-case basis for highly specialist or one-off works. Qualitative and quantitative evidence suggests that this will drive greater supplier ownership and accountability for the overall performance of the network and therefore deliver efficiencies for the NZTA. As well as financial savings from improving the coordination of works on any specific network, this approach will improve the road user/customer experience by ensuring there is coordinated programming of works, which will deliver travel time benefits and contribute to the NZTA s mandate to support economic productivity growth. 5. Contract Incentives It is proposed to strengthen and more uniformly apply a consistent range of performance incentives to ensure that the benefits of other proposed changes to contract type and tenure can be realised and to ultimately deliver better value for money. Currently there is significant variability in both how contracts specify performance incentives and penalties, including risk sharing, and how these are interpreted and applied. The range of potential performance incentives draws from the mechanisms already in use with the following key enhancements: PACE: More consistent application of the PACE system and more regular training on its application. At-risk payment ( bucket system ): Consolidation to a single system and development of guidance on its use. Additional works: Given that variations are typically high margin activities for suppliers, a system that apportions the amount of variations a supplier gets based on their performance will be a compelling performance incentive. Contract extensions: It is recommended that a central NZTA decision-making team be given responsibility for adjudicating on contract extension decisions based on an overall measure of performance. At the end of each contract extension a rebasing of contract rates could be implemented to manage the impacts of cost fluctuations. Earned value: Earned value involves monitoring actual accomplishment. It is an early warning management tool that enables the client to identify and control problems before they become insurmountable. External audits of the client s performance: We are recommending the introduction of external audits to assess the NZTA s performance as a client.
9 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 7 Next steps Find out more The NZTA will be running industry specific workshops with key groups and Local Government NZ. Those groups will be responsible for inviting their own members. In addition to these sessions, nine workshops will be run in the state highway regions as shown below. We would like to limit the number of attendees in these regional workshops to per workshop made up of local authority and NZTA asset managers and a cross-section of local suppliers. Our state highway managers will organise their respective regional workshops. Presentations to industry Who RNZ NZCF ACENZ LGNZ Aggregate and Quarry Association of NZ Where (NZTA regional offices) Auckland Wellington Auckland Napier Wellington Dates 29 August (pm) 29 August (am) 30 August (am) 27 August (am) 6 September (am) Engagement workshops NZTA asset managers, key regional suppliers, and TLA partners. Napier Wellington Hamilton Auckland Christchurch Tauranga Dunedin Palmerston North Blenheim 4 September 13 September 12 September 30 August 11 September 3 September 10 September 5 September 21 September Contact Mark Kinvig ph or or [email protected] if you have any questions. Provide feedback We request those seeking to provide feedback do so via your associated industry groups identified above or, for NZTA asset managers and RCAs, via the NZTA state highway manager representing their NZTA regional office. You are welcome to provide your feedback in whatever form you choose, but below are a series of questions to assist you in structuring a response. The closing date for your feedback is 28 September Your feedback should be ed to m&[email protected] or posted to: M&O Review Attention: Mark Kinvig NZ Transport Agency PO Box 740 Napier 4140 Report back by the NZTA The NZTA is committed to timely decision-making and reporting to provide certainty around the path forward so that industry can begin planning for implementation. Once we have received your feedback, we will consider/analyse the information and report back by the end of October 2012.
10 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 8 Timeframes The engagement programme: Engagement launch with Geoff Dangerfield Two weeks to absorb the information available on NZTA s website Engagement sessions with industry and regions Two weeks to provide feedback to the NZTA 13 August August 27 August 21 September September Decision on procurement approach End of October 2012 Questions Longer-term contracts The NZTA is considering contract terms of nine years, consisting of three-year separable portions. The option of longer terms (eg evergreen) could be considered where supplier performance is exceptional, there is a lack of competition or the activity is of a specialist nature. The NZTA seeks your views on: the concept of moving to longer-term contracts the specific challenges and/or opportunities the concept presents for you. Contract Delivery Model The NZTA is considering terminating the use of the traditional, hybrid and PSMC contract delivery models (see exceptions below) and replacing these over time with a new contract delivery model. If adopted, it is expected that this new model would be a performance based contract building on the successful attributes developed in the three existing contract forms, including some of the alliance based practices, eg open book contracting. The NZTA anticipates continuing to use the alliance delivery model in very special circumstances. Some specialist areas, such as bridge management may still be procured through traditional contract forms. The NZTA seeks your views on: The concept of creating a new M&O contract model combining the best attributes from all current models. The single supplier model contract form. Having two types of new contract form other than the alliance; a single supplier and more traditional contractor, consultant, client contract form.
11 State Highway Maintenance and Operations Review July 2012 NZ Transport Agency 9 Contract Aggregation If the NZTA ceases the use of traditional contracts (subject to exceptions above), it is expected that a new contract form would include the majority of maintenance activities in a fence to fence contract form as currently adopted in the Hybrid and PSMC contract forms. Furthermore, the NZTA is considering several aggregation options for reducing the number of network maintenance contracts. NZTA seeks your views on: The concept of moving to fence to fence contracts. What the optimum network maintenance length for the state highway network should be. The market impact of aggregation and how this can be mitigated into the future. The specific challenges you see in your region with respect to contract aggregation. Any other criteria you think would be appropriate in assessing options for segmenting the network. Having specific requirements within larger contracts to sub-contract components of the M&O work. Contract Incentives The NZTA is recommending a more consistent and stronger approach to measure supplier performance as described in the procurement discussion paper. The NZTA seeks your views on the suggestions provided in the procurement discussion paper whether they will drive the right outcomes and what the potential risks are to both the NZTA and suppliers.
12 If you have further queries, call our contact centre on or write to us: NZ Transport Agency Private Bag 6995 Wellington This publication is also available on NZ Transport Agency s website at Our contact details CONTACT ONE Mark Kinvig PO Box 740 Napier 1410 Telephone: Fax: [email protected] CONTACT TWO Jack Hansby Private Bag 6995 Wellington 6995 Telephone: Fax: [email protected] CONTACT THREE Karen Kiriona PO Box 740 Napier 1410 Telephone: Fax: [email protected] July 2012
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
Confident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
Schedule of Prices. Project Name Contract No. Contract Number
Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule
UNSOLICITED PROPOSALS
UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY
Highways & Network Operations Management System Manual
Highways & Network Operations Management System Manual NZ Transport Agency Effective from July 2012 ISBN number (print) ISBN number (online) Copyright information This publication is copyright NZ Transport
How are companies currently changing their facilities management delivery model...?
Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy
Integrated Fares and Ticketing Programme - update
Report 14.630 Date 26 November 2014 File TD/11/01/02 Committee Author Council Annika Lane, Project Manager, Integrated Fares and Ticketing Integrated Fares and Ticketing Programme - update 1. Purpose The
A Guidance Note to. Conditions of Contract for Consultancy Services (2005)
A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.
Slough Borough Council. Highway Asset Management Strategy
Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Engineering Innovation
Engineering Innovation In the Department of Transport and Main Roads September 2014 Foreword The Department of Transport and Main Roads role is to provide safe, functional transport infrastructure that
A responsible, sign. team up. front. Committing to where we re going and putting our hearts into what we do. We get engaged every day.
4 NZ Transport Agency Statement of intent 214 18 A responsible, collaborative and agile organisation In order to deliver our desired targets and results effectively and efficiently, we continue to invest
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
Scrim And Texture Data Collection Contract Management S Chamberlain
Scrim And Texture Data Collection Contract Management S Chamberlain Introduction Transit New Zealand (Transit) has been successfully managing SCRIM and texture data collection through external suppliers
Provider considerations for delivering an outcome based contract. Croydon CCG and London Borough of Croydon
Provider considerations for delivering an outcome based contract Croydon CCG and London Borough of Croydon Contents Introduction and Background Introduction 4 Commissioning for Outcomes: Aims and Benefits
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
TEC Capital Asset Management Standard January 2011
TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining
Asset Management Policy March 2014
Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and
Performance Measurement
Brief 21 August 2011 Public Procurement Performance Measurement C O N T E N T S What is the rationale for measuring performance in public procurement? What are the benefits of effective performance management?
Technical Journal. Paper 142
Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager
Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education
EMAIL [email protected] WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education
Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)
Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
Outsourcing. Knowledge Summary
Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best
ETI PERSPECTIVE 2020: A FIVE YEAR STRATEGY
ETI PERSPECTIVE 2020: A FIVE YEAR STRATEGY Introduction This document is the final and Board approved version of ETI s strategic directions based on the ETI Board meeting discussion of 12 th March 2015.
COUNCIL OF AUSTRALIAN GOVERNMENTS
COUNCIL OF AUSTRALIAN GOVERNMENTS High-level Principles for a National Disability Insurance Scheme A National Disability Insurance Scheme 1. The Council of Australian Governments (COAG) has welcomed the
Contract risk and assurance
Contract risk and assurance Delivering value from your key contracts and suppliers Maximise performance, confirm costs and gain assurance over your third party relationships and suppliers Performance Risk
PRINCIPLES FOR EVALUATION OF DEVELOPMENT ASSISTANCE
PRINCIPLES FOR EVALUATION OF DEVELOPMENT ASSISTANCE DEVELOPMENT ASSISTANCE COMMITTEE PARIS, 1991 DAC Principles for Evaluation of Development Assistance Development Assistance Committee Abstract: The following
Statement of Procurement Conduct
Statement of Procurement Conduct December 2014 Copyright of Western Power Any use of this material except in accordance with a written agreement with Western Power is prohibited. Introduction Western Power
NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard
New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding
Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer
Procurement Capability Standards
IPAA PROFESSIONAL CAPABILITIES PROJECT Procurement Capability Standards Definition Professional Role Procurement is the process of acquiring goods and/or services. It can include: identifying a procurement
Intelligent Customer Function (ICF)
CAPABILITY AUDIT FOR HEIs Higher Education Institutions (HEIs) should organically develop their own to successfully manage the process of strategic sourcing. The capability audit provides an assessment
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process
CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should
Highway Asset Management Strategy
1. Introduction 1.1. Cheshire East Council (CEC) recognises the importance of its highway infrastructure and how an effectively maintained and managed network contributes to the achievement of its corporate
National Development Lead Catalogue and Master Data
Principles Vision Purpose Statement National Development Lead Catalogue and Master Data healthalliance Purpose, Vision and Principles healthalliance provides shared services to benefit NZ health organisations.
Better Bus Area Monitoring and Evaluation Framework
Do Better Bus Area Monitoring and Evaluation Framework March 2014 The Department for Transport has actively considered the needs of blind and partially sighted people in accessing this document. The text
4 Adoption of Asset Management Policy and Strategy
4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are
Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review
Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
Performance audit report. Ministry of Education: Management of the school property portfolio
Performance audit report Ministry of Education: Management of the school property portfolio Office of the Auditor-General Private Box 3928, Wellington Telephone: (04) 917 1500 Facsimile: (04) 917 1549
Capability Statement Change Management
Capability Statement Change Management Transformation doesn t happen by chance. The Starfish approach is to employ the right combination of tools, processes, skills and principles for managing the people
Supply Chain Guide Working together in partnership
CASE STUDIES Plan Smart, Deliver Lean Supply Chain Guide Working together in partnership Background to the ISA The Infrastructure Strategic Alliance (ISA) provides a site wide consistent approach to the
Delivering Customer Focused Outcomes and Value for Money through Commissioning and Procurement
Delivering Customer Focused Outcomes and Value for Money through Commissioning and Procurement Procurement Strategy 2012-2015 V1.0 Please consider the environment if you need to print this document and
Ministry Of Health Registration of Interest
Ministry Of Health Registration of Interest Intermediaries Social Bond Pilot(s) Part 1 Instructions and Supporting Information What s inside? Introduction to Social Bonds Purpose of the ROI Instructions
robust and scaleable software solutions for construction and engineering
robust and scaleable software solutions for construction and engineering LEVESYS Software presents information clearly and logically, meaning you can always keep track of what s happening across the business.
Procurement and contract strategies
Achieving Excellence in Construction Procurement Guide 06 Procurement and contract strategies 06 Contents 01 The Achieving Excellence Procurement Guides 02 Introduction 02 Principles 05 Process 18 Annex
Producing Regional Profiles Based on Administrative and Statistical Data in New Zealand
Proceedings 59th ISI World Statistics Congress, 25-30 August 2013, Hong Kong (Session STS021) p.1489 Producing Regional Profiles Based on Administrative and Statistical Data in New Zealand Michael Slyuzberg
INTRODUCTION. The Merlin Principles. The Elements of each Principle
0 INTRODUCTION The development of the Merlin Standard has been progressed as a joint exercise between the Department for Work and Pensions (DWP) and its providers operating in the Welfare to Work (W2W)
MANAGING DIGITAL CONTINUITY
MANAGING DIGITAL CONTINUITY Project Name Digital Continuity Project DRAFT FOR CONSULTATION Date: November 2009 Page 1 of 56 Contents Introduction... 4 What is this Guidance about?... 4 Who is this guidance
HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 SECTION INTRODUCTION
HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 SECTION INTRODUCTION P1 P2 CONTENTS Executive Summary Financial Results Future
INTEGRATED PLANNING AND REPORTING
Government of Western Australia Department of Local Government INTEGRATED PLANNING AND REPORTING Framework and Guidelines Integrated Planning and Reporting Framework and Guidelines p1. Contents Foreword
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide
Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested
Specific Responsibilities Associated Performance Measures 1. Excellence in Commercial Management 2. Excellence in Contract Performance
OUR VISION is to be recognised as the leader in infrastructure service provision POSITION DESCRIPTION Commercial Manager National Maintenance Date reviewed: April 2012 EMPLOYEE NAME: Job Purpose: To achieve
Management of Business Support Service Contracts
The Auditor-General Audit Report No.37 2004 05 Business Support Process Audit Management of Business Support Service Contracts Australian National Audit Office Commonwealth of Australia 2005 ISSN 1036
Capability Statement Programme and Project Management
Capability Statement Programme and Project Management H Effective Programme and Project Management offers the means to ensure initiatives are successfully delivered and benefits are realised by your organisation.
WEATHERING QUALITY INDEX OF COARSE AGGREGATE PROFICIENCY PROGRAMME
TECHNICAL REPORT ON WEATHERING QUALITY INDEX OF COARSE AGGREGATE PROFICIENCY PROGRAMME CETANZ Technical Report TR 3 Author(s) Frank Hu, Downer NZ Ltd Report Date First Issue Oct 212 Report Revision Date
Performance Monitoring
7 Chapter 17 Performance Monitoring Performance Monitoring Contents: 17.1 Introduction 17.2 A Wider Perspective 17.3 Requirements for a Good Performance Indicator 17.4 Types of Performance Monitoring 17.5
How to get value for money from service providers on major projects
How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the
How To Manage A Contract
Contract Management Checklist Preparation This section deals with laying good foundations before a contract is let. The contract should be actively managed. You should have a plan for doing this, which
Capital Adequacy: Advanced Measurement Approaches to Operational Risk
Prudential Standard APS 115 Capital Adequacy: Advanced Measurement Approaches to Operational Risk Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements
DEVELOPMENT OF A QUALITY FRAMEWORK FOR THE MEDICARE BENEFITS SCHEDULE DISCUSSION PAPER
DEVELOPMENT OF A QUALITY FRAMEWORK FOR THE MEDICARE BENEFITS SCHEDULE DISCUSSION PAPER This paper has been prepared by the Department of Health and Ageing (the Department) as a basis for further consultation
Cost estimation manual (SM014)
Cost estimation manual (SM014) Cost estimation manual manual number: SM014 NZ Transport Agency www.nzta.govt.nz First edition ISBN 978-0-478-37104-8 (print) ISBN 978-0-478-37103-1 (online) Copyright information
Value for Money Assessment Guidance: Capital Programmes and Projects
Value for Money Assessment Guidance: Capital Programmes and Projects October 2011 Value for Money Assessment Guidance: Capital Programmes and Projects Foreword This guidance has been prepared and issued
MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT
MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT CONTENTS Foreword ------------------------------------------------------------------------ 3 Executive Summary ---------------------------------------------------------
Customer Service and Support. Our people make the difference to our customers.
Customer Service and Support. Our people make the difference to our customers. 1 Fuji Xerox Customer Service and Support at a glance. NZ wide service network Support of rural and remote areas Our people
Water Mains Rehabilitation Framework (NI) Northern Ireland Water
PROJECT: CLIENT: MAIN CONTRACTOR: Water Mains Rehabilitation Framework (NI) Northern Ireland Water Farrans Background Northern Ireland Water manages a water mains infrastructure that supplies 625 million
Wales Procurement Policy Statement
Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.
Aggregation. Is bigger always better?
Aggregation Is bigger always better? Contents Purpose of this guidance 1 What is aggregation? 2 When should aggregation be considered? 4 Why use aggregation? 6 Some practical considerations 8 Further reading
Helping our clients win in the changing world of work:
Helping our clients win in the changing world of work: Recruitment Process: Why Outsource? A Manpower Insights Paper The future of RPO looks strong despite or perhaps aided by the current global recession.
NZ Transport Agency Page 1 of 23
NZ Transport Agency Page 1 of 23 Risk Management 1 Introduction The Highways and Network Operations (HNO) group supports the NZ Transport Agencies strategic objectives through the delivery of Capital Projects
10.0 ASSET MANAGEMENT PRACTICES
10.0 ASSET MANAGEMENT PRACTICES 10.1 Current Asset Management Practices This section outlines the decision making tools Taupō District Council (TDC) currently uses to determine long term maintenance, renewal
Procurement driving better value for money. Guide 7 to Sustainable Procurement. Manage the contract and disposal route
Procurement driving better value for money Guide 7 to Sustainable Procurement Manage the contract and disposal route A guide for agencies July 2010 This guide is part of a series of documents focussed
WORLD-CLASS FINANCIAL PERFORMANCE MANAGEMENT FOR GOVERNMENT & NON PROFIT ORGANISATIONS
WORLD-CLASS FINANCIAL PERFORMANCE MANAGEMENT FOR GOVERNMENT & NON PROFIT ORGANISATIONS CONTENTS 2 SUMMARY 3 WHAT IS INFORMATION EDGE? 4 WHY WAS INFORMATION EDGE DEVELOPED? 4 A proven track record 5 WHAT
Mining & Construction Transforming your fleet performance
Mining & Construction Transforming your fleet performance Giving you greater focus on your business Today s difficult economy challenges organisations within the mining and construction sector to deliver
What is world class commissioning?
...? series New title The NHS and HTA Supported by sanofi-aventis What is world class commissioning? Michael Sobanja Dip HSM Dip IoD Cert HE FRSM Chief Executive, NHS Alliance For further titles in the
Volunteer Managers National Occupational Standards
Volunteer Managers National Occupational Standards Contents 00 Forward 00 Section 1 Introduction 00 Who are these standards for? 00 Why should you use them? 00 How can you use them? 00 What s in a Standard?
Ethical Trading Initiative Management Benchmarks
Ethical Trading Initiative Management Benchmarks The Management Benchmarks are the means by which ETI (a) sets out its expectations of members and (b) measures members progress in applying the ETI Base
The Asset Management Landscape
The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces
Procurement & Supply Chain Management
New Skills. New Thinking Procurement & Supply Chain Management Supply Chain Effectiveness Audit - Implementing lean processes in your supply chain 20 September 2012 Auckland 24 September 2012 Wellington
DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1
DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 Guideline: DRAFT Planning the opening of a road project guideline Version: 1.1 Issue: September 2009 Approved By: Phil Margison General Manager,
ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000
ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 Florentina Mihai, BEng, GDipMgt, MIEAust Main Roads Western Australia Neville Binning,
Analyst - EDI. healthalliance Purpose, Vision and Principles. Purpose Statement
Principles Vision Purpose Statement Analyst - EDI healthalliance Purpose, Vision and Principles healthalliance provides shared services to benefit NZ health organisations. We will deliver increasing value