1 SECTION POLYVINYL CHLORIDE PIPE, AWWA C900/C905 PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Furnish and install AWWA C900 PVC, DR 18 for 4 through 12 size and AWWA C905 PVC, DR 25 for 14 and larger polyvinyl chloride piping as indicated on the Drawings, including all required jointing materials, fittings, restrained joint fittings, and other appurtenances indicated, specified, or required for a complete installation including testing. Provide locating wire on all OVC pipe 4 and larger. B. Related Sections: 1. Section Submittal Procedures 2. Section Earthwork 3. Section Systems Disinfection and VOC Testing 1.02 REFERENCES A. AWWA C900: Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 4 in. through 12 in., for Water Distribution. B. AWWA C905: Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 14 in. through 48 in., for Water Transmission and Distribution SUBMITTALS A. Submit in accordance with Section Submittal Procedures. 1. Layouts: a. Submit detailed installation drawings of piping, including fittings. b. Submit descriptive data to show that the following items conform to requirements of the Specifications.: 1) Pipe, fittings, and accessories. 2) Pipe couplings. 2. Submit certified test reports. a. Affidavit of compliance certifying: 1) all tests have been conducted. 2) all materials comply with applicable standards. 3) all materials comply with these specifications. b. Retain test information and make available to Resident Engineer on request

2 1.04 QUALITY ASSURANCE A. Source Quality Control: 1. Identification marks: Clearly and permanently mark each length of pipe, including couplings and short lengths, with pipe size, class, type, test pressure and manufacturer s name. B. Testing: 1. Sample and test all materials in accordance with AWWA C900 and C Pipe not manufactured in the United States to be tested by an approved laboratory within the United States PRODUCT DELIVERY, STORAGE, AND HANDLING A. Exercise care in transporting and handling to avoid damage to pipe and fittings. B. Store materials on site in enclosures or under protective coverings. C. Do not store materials directly on the ground. D. Keep inside of pipes and fittings free of dirt and debris, in accordance with City Standards. PART 2 PRODUCTS 2.01 MATERIALS A. Pipe: 1. AWWA C900 and C905, Class 200 PVC, dimension ratio (DR) 18, cast iron equivalent OD, material cell classification B per ASTM D1784. B. Joint Couplings: 1. PVC sleeve and two sealing rings. 2. Integrally cast bell and one sealing ring. 3. Rubber rings: ASTM D Fully restrain all bell joints. C. Fittings: a. JCM Sur-Grip Model 620 or EBBA Iron Series Gray iron: ANSI A21.10, 250 psi. 2. Ductile iron: ANSI A21.10, 350 psi. 3. Joints: a. Mechanical joints: ANSI A21.11 b. All mechanical joints shall be fully restrained. c. JCM Model 610 Sur-Grip Fitting Restrainer or EBBA Iron Series 2000PV

3 D. Coatings: 1. Heavy coal tar MIL-C-18480, Koppers 505 Bitumastic, Tnemec 476 Super Tnemecal, Porter Tarmastic 101, or equal. E. Lubricants: As recommended by the pipe manufacturer. F. Locating Wire: 1. Locating wire No. 10 AWG. PART 3 EXECUTION 3.01 INSPECTION A. Examine areas for: 1. Structural defects 2. Cracks and breaks 3. Deviations beyond allowable tolerances for pipe clearances. 4. Damage which penetrates deeper than 10% of pipe wall thickness as per awwa PREPARATION A. Shape trench foundation or bedding as required. 1. Dig bell or coupling holes. 2. Do not support pipe on blocks or mounds of earth INSTALLATION A. General: 1. Install pipe in accordance with AWWA C900 and C905 as modified herein or on the Drawings. 2. Perform all laying and jointing in Resident Engineer s presence. 3. Remove any identified defective material from the site as directed by the Resident Engineer. 4. Provide restrained joints at all deflections greater than 11-1/4 degrees unless otherwise noted on the Drawings. 5. Any damage greater than 10% wall thickness shall not be allowed in accordance with AWWA standards. B. Cutting: 1. Per pipe maufacturer s recommendations. 2. Do not fracture pipe, split ends, or leave ragged uneven edges. 3. Smooth cut ends to proper dimensions. 4. Bevel all field cuts 45degrees as per awwa

4 5. Provide metallic locating wire for all buried PVC pipe. Wire must daylight at each fitting in accordance with City Standards. C. Pipe Laying in Trenches: 1. Inspect pipe and accessories for defects before lowering into trench. 2. Repair or replace any defective, damaged, or unsound pipe. 3. Remove all foreign matter and dirt from the inside of pipe before laying. 4. Carefully lower pipe, fittings, valves, and accessories into the trench with derricks, ropes, and other suitable equipment to prevent damage. 5. Do not dump or drop pipe or accessories into the trench. 6. Lay to lines and grades indicated on the Drawings and specified. a. Closely joint to form a smooth flow line. b. Immediately before placing pipe, check bedding for firmness and uniformity of surface. c. Minimum length of pipe that can be used without exceeding the allowable curvature of pipe shall be determined. d. Maximum curvature of pipe as recommended by the manufacturer. e. Deflection at joint: As recommended by the manufacturer. f. If grade is not shown on Drawings, install pipe at smooth grade between elevations shown to allow drainage of pipe. 7. Utilize implements, tools, and facilities recommended by the manufacturer. 8. Keep inside of pipe clean during and after laying. 9. Close all open ends with watertight expandable pipe plugs for potable water application: a. At the end of each day s operations. b. Whenever pipe ends are left unattended. c. Deposit adequate backfill on pipe to prevent flotation. d. Do not use wood, burlap or other similar temporary plugs. 10. Remove and re-lay any pipe which has floated. 11. Do not lay pipe when: D. Jointing: a. There is water in the trench. b. Trench conditions are unsuitable. c. Weather conditions are unsuitable. 1. Assemble in accordance with the manufacturer s instructions

5 2. Wipe gasket and gasket seat clean before inserting gasket. 3. Lubricate the gasket and the outside of the clean pipe end. 4. Utilize an assembly tool as recommended by the manufacturer to center the sleeve over the pipe end. 5. Force the pipe into the collar. 6. Check gasket location after assembly with a suitable gauge. E. Fittings: a. Pipe shall be marked with a stab depth line to allow visual confirmation of correct installation. b. Gasket locations to be the distance from the sleeve end recommended by the coupling manufacturer for their full circumference. c. If not within the required limits, disassemble and reassemble the joint. 1. Install utilizing standard methods. 2. Lower into trench with rope, cable, chain or other means to prevent damage. 3. Attach rope, cable or chain around the exterior of fittings. Do not attach through the interior of fitting. 4. Carefully connect to pipe or other facility. 5. Check joint to ensure a sound and proper joint. F. Encasement: 1. Provide as indicated on the Drawings or as directed by the Resident Engineer. 2. Suitably support and block pipe and anchor against flotation. G. Corrosion Control: 1. Coat all steel clamp rods, bolts, fittings and other metal accessories used in anchorages or joint harness subject to submergence or contact with the earth and not concrete encased. 2. Apply two (2) coats of coal tar paint to clean, dry metal surfaces. 3. Allow the first coat to dry and harden before applying the second coat. H. Polyethylene Field wrap of all valves, fittings, joints, and connections: 1. Wrap all buried valves, flanges, couplings, fittings, joints and other mechanical pipe connections in two layers of polyethylene encasement per AWWA C105. Extend layers of polyethylene to overlap cement mortar coating (where applicable) and tape edges of polyethylene wrap with at least two circular wraps of PVC tape. I. Direct tapping of PVC not permitted. Saddles are required

6 3.04 FIELD QUALITY CONTROL A. Pressure Test: 1. Test in accordance with AWWA C605 as modified herein. 2. Provide all tools, pumps, fill points, gages, meters, temporary valves and bulkheads, bracing and other equipment required for testing. 3. Conduct the test with the trench completely backfilled. 4. Procedure: 3.05 Disinfection a. Test line in sections of 2,500 feet or less. b. Fill with water and allow to stand under slight pressure for at least 24 hours. c. Expel all air from line. d. Inspect for leakage and repair any leaks. e. Raise the pressure to 220 psi for water mains or 50 psi for drain conduits and hold by water addition for at least 1 hour. f. Allow line to stand for 1 hour without water addition and accurately record the quantity required. 5. If the quantity of water added to the line exceeds the value in Table 3 of AWWA C605, or should leaks otherwise be noted, locate the leaks, rework the line and retest. A. Disinfect all water piping per the requirements of Section 11201, Systems Disinfection and VOC Testing. B. Pipe will be flushed at 5 feet per second for three pipe volumes prior to disinfection. **END OF SECTION**

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS

SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS SECTION 15056 PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. A written request to use Ductile

More information

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials

More information

SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS

SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS PART 1: GENERAL 1.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of AW facilities. Closely coordinate construction work

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Section C-1 Pipes and Fittings

Section C-1 Pipes and Fittings Section C-1 Pipes and Fittings C1.00 Work Included The work under this Division of the Specifications shall include all labor, materials, and equipment necessary to furnish and install all piping, pipelines,

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

SECTION 15105 DUCTILE IRON PIPE AND FITTINGS

SECTION 15105 DUCTILE IRON PIPE AND FITTINGS SECTION 15105 DUCTILE IRON PIPE AND FITTINGS PART 1 GENERAL.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of Owner facilities. Closely coordinate construction work and connections

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

SECTION 603 SANITARY SEWER FORCE MAINS

SECTION 603 SANITARY SEWER FORCE MAINS SECTION 603 SANITARY SEWER FORCE MAINS 1. GENERAL Pipelines for sanitary sewer force main systems shall conform to the following specifications and shall be installed at the locations indicated on the

More information

SECTION 02401 - SANITARY SEWER PIPE

SECTION 02401 - SANITARY SEWER PIPE PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS

SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS PART 1: GENERAL 1.01 SECTION INCLUDES Furnishing and installing up to 16-inch high density polyethylene (HDPE) pipe and fittings for

More information

SECTION 33 12 19 FIRE HYDRANTS

SECTION 33 12 19 FIRE HYDRANTS SECTION 33 12 19 FIRE HYDRANTS PART 1: GENERAL 1.01 SCOPE A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 - Submittals.

More information

INDEX. Sec. No. Items Page Nos.

INDEX. Sec. No. Items Page Nos. INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............

More information

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors. SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

STANDARD SPECIFICATION SECTION 15292 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE (AWWA C900)

STANDARD SPECIFICATION SECTION 15292 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE (AWWA C900) STANDARD SPECIFICATION SECTION 15292 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE (AWWA C900) PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, installation, and testing of PVC pressure pipe

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223 STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE

SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, materials, tools, equipment, services, and incidentals necessary

More information

SECTION 15064 PVC PRESSURE PIPE AWWA C900

SECTION 15064 PVC PRESSURE PIPE AWWA C900 SECTION 15064 PVC PRESSURE PIPE (AWWA C900) PART 1 GENERAL 1.01 DESCRIPTION This section includes materials, installation, and testing of polyvinyl chloride (PVC) pressure pipe conforming to AWWA C900.

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing

More information

SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General

SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,

More information

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water 105 Decker Court, Suite 825, Irving, TX 75062 P: 469-499-1044 F: 469-499-1063 www.plasticpipe.org HDPE

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers. SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted. SECTION 3000 - SANITARY SEWERS 3001 SCOPE. This section applies to sanitary sewer construction and shall consist of furnishing all labor, materials, and equipment for the complete installation of sewers

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification Number: 3503-11.2.610 Rev. 2 Rubber Lined Steel Pipe and Fittings Mechanically Coupled Plain End Type System Issued Revised Approved

More information

SECTION 221413 FACILITY STORM DRAINAGE PIPING

SECTION 221413 FACILITY STORM DRAINAGE PIPING SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21 September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION WATER MAIN CONSTRUCTION TECHNIQUES Overview Water Main - Materials Specifications Installation Future? Water Main Materials Material Types There are various material types used for water mains, these include:

More information

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200 STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

Section 3510: Reclaimed water Pipes, Valves, and Appurtenances February 11, 2011

Section 3510: Reclaimed water Pipes, Valves, and Appurtenances February 11, 2011 STANDARDS AND CONSTRUCTION MANUAL : Reclaimed water Pipes, Valves, and Appurtenances February 11, 2011 PART 1 - GENERAL 1.01 SCOPE OF WORK A. These specifications cover the pipes, fittings, and appurtenances

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

SECTION 03400 PRECAST CONCRETE STRUCTURES

SECTION 03400 PRECAST CONCRETE STRUCTURES SECTION 03400 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for precast concrete structures, including fabrication and erection. 1.02 REFERENCE STANDARDS A. American Society for

More information

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of

More information

PREFACE PURPOSE. t,t). PROCEDURES FOR APPROVAL AND ACCEPTANCE. l^zg -,s" DEFINITIONS TABLE OF CONTENTS. Page No.

PREFACE PURPOSE. t,t). PROCEDURES FOR APPROVAL AND ACCEPTANCE. l^zg -,s DEFINITIONS TABLE OF CONTENTS. Page No. PREFACE PURPOSE PROCEDURES FOR APPROVAL AND ACCEPTANCE DEFINITIONS TABLE OF CONTENTS t,t). l^zg -,s" Page No. 1. WATER SYSTEM DESIGN REQUIREMENTS 1 1.1 GENERAL DESIGN REQUIREMENTS 1 1.2 MATERIALS OF CONSTRUCTION

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

08003-1 WATER SERVICE 2

08003-1 WATER SERVICE 2 08003_Mar08_2011.pdf Page 1 of 7 INDEX Page 08003-1 WATER SERVICE 2 1.1 Pipe 2 1.1.1 Copper 2 1.1.2 Polyethylene 2 1.2 Valves and Fittings 2 1.2.1 Main Stops 3 1.2.2 Curb Stops 3 1.2.3 Curb Box 3 1.2.4

More information

Fire Hydrant Troubleshooting

Fire Hydrant Troubleshooting Fire Hydrant Troubleshooting Pulsation or chatter during opening and flow of water from hydrant. Loose condition in stem at lower valve plate nut. Tighten lower valve plate nut and secure with SS lock

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

STANDARD SPECIFICATIONS SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE. 1. Trenching, Backfilling, and Compacting: 02223

STANDARD SPECIFICATIONS SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE. 1. Trenching, Backfilling, and Compacting: 02223 STANDARD SPECIFICATIONS SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE PART 1 - GENERAL A. Description This section describes materials, fabrication, installation, and testing of cement-mortar

More information

2013 Edition. Flanged fittings 30"-64" NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61

2013 Edition. Flanged fittings 30-64 NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61 30"-64" Ductile Iron industrial Applications, water & Wastewater 2 Table of Contents Flanged Fittings for Water 3 Flange Details 5 Flanged Fittings 6 90º and 45º Bend 6 22-1/2º and 11-1/4º Bends 7 Tees

More information

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE 1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint

More information

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.) CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection

More information

SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE

SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes

More information

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General

More information

September 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM

September 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM 1.0 General Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM a) It is the intent of this specification to ensure that all gravity sewer system infrastructure constructed within the service

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride

More information

SECTION 200: STORM SEWER CONSTRUCTION STANDARDS

SECTION 200: STORM SEWER CONSTRUCTION STANDARDS SECTION 200: STORM SEWER CONSTRUCTION STANDARDS Page No. Description 200-2 201 GENERAL 200-2 201.1 SPECIFICATIONS 200-2 201.2 CONNECTION TO EXISTING FACILITIES 200-3 202 MATERIALS 200-3 202.1 PIPES 200-4

More information

DIVISION 5 SANITARY SEWERS

DIVISION 5 SANITARY SEWERS 501 SANITARY SEWER PIPE AND FITTINGS... 5-1 501.01 DESCRIPTION... 5-1 501.02 MATERIALS... 5-1 501.03 CONSTRUCTION... 5-6 501.04 MEASUREMENT AND PAYMENT... 5-21 502 MANHOLES AND CONCRETE STRUCTURES... 5-22

More information

WATER & SEWER CORROSIVE RESISTANT PRODUCTS

WATER & SEWER CORROSIVE RESISTANT PRODUCTS WATER & SEWER CORROSIVE RESISTANT PRODUCTS The Standard of Excellence in the Industry CASING SPACERS COUPLINGS & FLANGE COUPLING ADAPTERS REPAIR CLAMPS DUCTILE IRON SADDLES STAINLESS STEEL SADDLES TAPPING

More information

SECTION 03400 PRECAST CONCRETE STRUCTURES

SECTION 03400 PRECAST CONCRETE STRUCTURES PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

PVC Installation and Tapping For Potable Water and Sanitary Sewer. Handling and Installation Practices Manual

PVC Installation and Tapping For Potable Water and Sanitary Sewer. Handling and Installation Practices Manual PVC Installation and Tapping For Potable Water and Sanitary Sewer Handling and Installation Practices Manual Table of Contents Introduction...1 Shipping and Handling...1 Handling and storage of pipe and

More information

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

All work shall comply with applicable codes and ordinances. Work shall comply with the BOCA National Plumbing Code, latest edition.

All work shall comply with applicable codes and ordinances. Work shall comply with the BOCA National Plumbing Code, latest edition. DIVISION 15 MECHANICAL SECTION 15100 - PLUMBING PART 1 - GENERAL SCOPE Plumbing work includes all domestic water, gas, and sanitary sewer systems as shown on plans. Also all fixtures and equipment which

More information

SECTION 16402 UNDERGROUND ELECTRIC SERVICE

SECTION 16402 UNDERGROUND ELECTRIC SERVICE SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and

More information

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer

More information

Chapter 7 Plumbing Connections

Chapter 7 Plumbing Connections Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions

More information

TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN

TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN Starts on Page 500 GENERAL... 2 501 MATERIALS... 2 502 CONSTRUCTION PROCEDURES... 7 503 ABANDONMENT OF EXISTING SANITARY SEWER FACILITIES...

More information

Suggested Specifications: Steel Pipe for Water Transmission

Suggested Specifications: Steel Pipe for Water Transmission Suggested Specifications: Steel Pipe for Water Transmission. Suggested Specifications - Steel Pipe for Water Transmisssion Cement-mortar Lined and Tape Coated PART 1 - GENERAL 1.01 Description Scope of

More information

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL 155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of

More information

AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller

AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller January 2013 AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller Milliken Valve Company 190 Brodhead Avenue, Suite 100 Bethlehem, PA 18017 Phone: (610) 861-8803 Fax:

More information

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water

More information

AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM):

AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM): SECTION 02832 AIRPORT SECURITY FENCING PART 1-GENERAL 1.1 SUMMARY A. Section includes: Construct airport security chain-link fence and gate at specified areas and conforming lines, grades, details indicated

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information