1 CIPS Exam Report for Learner Community: Qualification: Unit: Exam series: Advanced diploma in procurement and supply AD2 Management risk in supply chains November, 2013 Exam Series INFORMATION FOR CANDIDATES The Principal Marker s report is written in order to provide the learner community with feedback relating to the examination. It is designed as a tool for candidates - both those who have sat the examination and those who wish to use as part of their revision for future examinations. Candidates are advised to refer to the Examination Techniques Guide on the CIPS website as well as this Principal Marker s report. The Principal Marker s report aims to provide the following information: An indication of how to approach the examination question An indication of the points the answer should include An indication of candidate performance for the examination question Each question has a syllabus reference which highlights the learning objectives of the syllabus unit content that the question is testing. The unit content guides are available to download at the following link: ADDITIONAL SOURCES OF INFORMATION The Supply Management magazine is a useful source of information and candidates are advised to include it in their reading during their study. Please see the following link to the Supply Management website: Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 1/6
2 Question 1) - Learning Outcome 1 (LO 1.1) Analyse the main risks for GCRS, both internal and external, that should be included in the feasibility study produced by Innovative Solutions. (25 marks) This was a single mandatory question worth 25 marks which sought to test candidate ability to identify and analyse the different types and nature of risks faced by GCRS - drawing on material from the case study. Candidates were not required to discuss how the identified risks might be addressed. Syllabus ref: 1.1 refers. Candidates were expected to generally classify the analysis into 2 streams - namely: The Internal risks faced by GCRS and also the External risks faced by GCRS from the wider environment Candidates were also expected to discuss an appropriate model or technique to help identify and analyse either internal or external. Possible examples of INTERNAL RISKS faced by GCRS being: Human / Cultural risks, Group dynamics risk / Risk of Human error and inexperience, Business management risk, Corporate governance / security risk, Technology breakdown / implementation risk, Risk of lack of internal controls, Risk of poor employee relations, Loss of key personnel. Possible examples of EXTERNAL RISKS faced by GCRS being: Public relations / Media risk, Political / Government risk, Social cultural risk, Risk of Technology / Quality failure From external IT system supplier, Legal / Ethical risks. Whilst the question did not directly require the use of formal models, it was permissible to structure answers using a recognised model or technique - for example: Internal control systems, Auditing, PESTLE or STEEPLE, SWOT Analysis, PORTER S 5 Forces Model, SAUNDERS Model of environmental factors. Exam Question summary For this mandatory question - candidates were expected to identify and analyse the different types and nature of risks faced by GCRS - drawing on relevant content and material from the case study. Answers were generally classified into 2 streams; namely: 1. Internal risks faced by GCRS - These are the risks associated with the internal environment of GCRS vis-àvis its high profile services of Courts, Prison, Probation and Police. In other words the immediate micro environment. 2. External risks faced by GCRS from the wider environment - These are the risks associated with GCRS s macro wider environment - bearing in mind that the 4 internal component parts (Courts, Prison, Probation and Police) are all in the public eye and subject to close scrutiny. Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 2/6
3 Whilst many candidates did structure their answers into internal and external risks, surprisingly, others did not and as a result lost marks for structure. Some candidates went on to discuss an appropriate model or technique to help identify and analyse either an internal or external risk and consequently achieved more marks. Questions 2a) & 2b) - Learning Outcome 2 (LO 2.1) Q2a) Outline THREE different contract strategies available to GCRS for this IT project, and discuss the likely allocation of project risks between GCRS and the contractor, for each identified strategy. (15 marks) Q2b) Suggest how Innovative Solutions could be incentivised within a contractual relationship to achieve successful project outcomes. (10 marks) This was a two part mandatory question worth 15 marks and 10 marks respectively (25 marks in total) which sought to test candidate knowledge and understanding of different contract strategies available to GCRS for this IT project, and discuss the likely allocation of project risks between GCRS and the contractor, for each identified strategy. Additionally, to build on this by discussing incentivisation to achieve successful project outcomes. Syllabus ref: 2.1 refers. For part a) Answers were expected to recognise that GCRS can achieve varying degrees of project risk allocation / risk transference through subtly different contracting strategies such as : full turnkey, partial turnkey, management contracting, traditional multiple contractors etc. The case study and the likely extent of GCRS s reliance on the expertise of an organisation such as Innovative Solutions - pointed strongly to these contract strategy options. GCRS did not have the necessary skills, expertise or resource capability to undertake such a complex IT project itself and therefore would have to transfer risk by contractual means to get the job done. The degree of risk allocation will depend on the contract strategy chosen - full risk allocation (turnkey) or something in between. For part b) Answers were expected to outline of some form of incentivised risk / reward relationship between two contractual parties. Essentially, what was indicated here was the theory behind both parties sharing risk / reward in some shape or form. The leverage comes from Innovative Solutions being contractually obligated Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 3/6
4 to take a meaningful stake in the success or outcome of the complex IT project -taking on the potential for both upside and downside risk. Key parameters in amongst this being quality, cost, time and post contract support or maintenance services. Additionally, answers will be expected to articulate a good example of an incentivised mechanism. Exam Question summary For Question 2a) This was a very clearly structured question enabling marks to be allocated for strong answers, some top scoring. Some candidates tended to focus on specific contractual conditions such as liability clauses and IPR, as opposed to contract strategies. Most did however recognise / capture that GCRS can achieve varying degrees of project risk allocation / risk transference through subtly different contracting strategies such as : full turnkey, partial turnkey, management contracting, traditional multiple contractors etc. The case study and the likely extent of GCRS s reliance on the expertise of an organisation such as Innovative Solutions - pointed strongly to these contract strategy options. For Question 2b) This was also a well structured question, with some good scores achieved. Most answers managed to outline a form of incentivised risk/reward relationship between two contractual parties plus the theory behind both parties sharing risk/reward in some shape or form. Most answers also recognised key parameters such as Quality, Cost, Time and Post Contract Support or Maintenance services. Question 3) - Learning Outcome 3 (LO 3.4) There are many potential risks for GCRS throughout this project. Outline a contingency or continuity planning process and suggest how this could be applied to overcome these risks. (25 marks) This was a single mandatory question worth 25 marks which sought to test candidate knowledge of contingency or continuity planning processes and their application in the context of the case study material to overcome risks. Syllabus ref: 3.4 refers Candidates are afforded a degree of flexibility in terms of the type of contingency or continuity plan process they chose to analyse. Answers were expected to discuss a planning structures or something equivalent which articulated substantive stages - such as: Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 4/6
5 Business risk assessment / Identification of critical risks Identification / Evaluation of impact / Solutions Continuity / Contingency action plans / activation of plan etc. Testing of Plan / Training those who will need to respond Communications Plan / Stakeholder involvement Examples of typical risks from the case study and how the contingency planning process may be used to reduce them were also indicated. Exam Question Summary There were some very good answers to this question with many candidates demonstrating their knowledge by listing both contingency planning and continuity planning processes, which was not necessarily required. In addition to missing the keyword or, some candidates missed the other keyword of process and did not describe any process at all. As a result, this was possibly the lowest scoring question. Stronger answers captured a contingency planning structures or something equivalent which articulated substantive stages as above. Questions 4a) & Q4b) - Learning Outcome 1 (LO 4.1 & 4.2) Q4a) Discuss FOUR potential risks that could be included in the risk register to be presented to the board of management at GCRS. (16 marks) Q4b) Discuss the use of a probability / impact matrix to manage THREE of the risks identified in your answer to Q4a). (9 marks) This was a two part question worth 16 marks and 9 marks respectively which sought to test candidate knowledge and understanding of potential risks that could be included a risk register and also the use of a probability/impact matrix to manage those risks. Syllabus refs: 4.1.and 4.2 refer. For part a) Answers were expected to identify and discuss FOUR relevant potential risks from the case study material (as viewed from the perspective of GCRS s Procurement Director looking at potential risk and vulnerability to the 4 government agencies of transitioning to a new system in such a tight aggressive timeframe. Possible examples being: Risk of Contract failure, Risk of financial instability, Risk of Quality failure, Risk of security of supply, Technology risks, Risk of overly complex logistics, Risks associated with outsourcing, Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 5/6
6 For part b) Answers were expected to outline a risk assessment grid which plots / maps threats and hazards according to their likelihood of happening and also the seriousness of their effect if they do happen. In terms of application: any of the risks identified were capable of being mapped onto such a grid. Exam Question Summary For Question 4a) This was a straightforward question, which many candidates answered well. Some top scoring answers seen here by identifying and discussing 4 relevant potential risks from the case study material (as viewed from the perspective of GCRS s Procurement Director looking at potential risk and vulnerability to the 4 government agencies of transitioning to a new system in such a tight aggressive timeframe. For Question 4b) Most answers gave an outline of a risk assessment grid which plotted / mapped threats and hazards according to their likelihood of happening and also the seriousness of their effect if they did happen. Some good diagrams were provided, however, some did not clearly identify the axes. Others described the matrix well enough when it would have been simpler to have drawn it. Some good answers and high scores in the question. Nov13_EXAM_REPORT_LEARNER_COMMUNITY_FV 6/6
CIPS Exam Report for Learner Community:
CIPS Exam Report for Learner Community: Qualification: Unit: Exam series: Advanced diploma in procurement and supply AD2 - Managing risks in supply chains July, 2013 Exam Series INFORMATION FOR CANDIDATES
More informationLEVEL 5. Advanced Diploma in Purchasing and Supply. Senior Assessor s Report. July 2012. Risk Management and Supply Chain Vulnerability L5-02
LEVEL 5 Advanced Diploma in Purchasing and Supply Risk Management and Supply Chain Vulnerability L5-02 Senior Assessor s Report July 2012 L5-02 Senior Assessor Report July 2012 FV 1/8 SECTION A Candidates
More informationEXAM EXEMPLAR QUESTIONS
Level 4 Diploma in Procurement and Supply D2 - Business needs in procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 7 QUALIFICATIONS 2013 QUESTIONS AND MARKING
More informationSAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. D5 - Managing contracts and relationships in procurement and supply
Level 4 Diploma in Procurement and Supply D5 - Managing contracts and relationships in procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 6 QUALIFICATIONS
More informationCIPS Exam Report for Learner Community:
CIPS Exam Report for Learner Community: Qualification: Diploma in Procurement and Supply Unit: Unit D2: Business Needs in Procurement and Supply Exam series: November 2014 Question 1 Learning Outcome 1
More informationCIPS Exam Report for Learner Community:
CIPS Exam Report for Learner Community: Qualification: Diploma in Purchasing and Supply Unit: D1 Diploma in procurement and supply D1 - Contexts of P&S Exam series: January 2014 Question 1 Learning Outcome
More informationSAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD6 - Operations management in supply chains. Level 5 Advanced Diploma in Procurement and Supply
Level 5 Advanced Diploma in Procurement and Supply AD6 - Operations management in supply chains EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 8 QUALIFICATIONS 2013 QUESTIONS
More informationEXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD2 - Corporate and business strategy EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 8 QUALIFICATIONS 2013 QUESTIONS AND
More informationQuality Manual ISO 9001:2015 Quality Management System
Quality management input comprises the standard requirements from ISO 9001:2015 which are deployed by our organization to achieve customer satisfaction through process control. Quality Manual ISO 9001:2015
More informationInfo sheet : Considering labour standards in the procurement process
Info sheet : Considering labour standards in the procurement process In line with the EU procurement rules and the Government s value for money principle, contracting authorities can take steps to consider
More informationRELATIONAL DIAGRAM OF MAIN CAPABILITIES. Strategic Position position (A) Strategic Choices choices (B) Strategic Action action (C)
Business Analysis (P3) September 2015 to August 2016 Syllabus AIM FR (F7) BA (P3) AB (F1) APM (P5) PM (F5) To apply relevant knowledge, skills, and exercise professional judgement in assessing strategic
More informationA7/SA report/nov10 1
A7/SA report/nov10 1 INFORMATION FOR CANDIDATES The senior assessor s report is written in order to provide candidates with feedback relating to the examination. It is designed as a tool for candidates
More informationStrategic Marketing is a 15-credit mandatory module which sits within the suite of Level 6 modules.
Strategic Marketing Strategic Marketing is a 15-credit mandatory module which sits within the suite of Level 6 modules. To gain the CIM Level 6 Diploma in Professional Marketing a pass in both mandatory
More informationA Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
More informationRelationship Manager (Banking) Assessment Plan
Relationship Manager (Banking) Assessment Plan ST0184/AP03 1. Introduction and Overview The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It
More informationBusiness-critical Insurance
Business-critical Insurance Identifying those insurances that support the business and its strategy Guide 2015 Contents Introduction... 4 Categories of insurance... 5 Determining which insurance covers
More informationThe senior assessor s report aims to provide the following information: An indication of how to approach the examination question
INFORMATION FOR CANDIDATES The senior assessor s report is written in order to provide candidates with feedback relating to the examination. It is designed as a tool for candidates for both those who have
More informationIQ Level 3 NVQ Diploma in Management (QCF) Specification
IQ Level 3 NVQ Diploma in Management (QCF) Specification Regulation No: 600/6699/4 Page 1 of 94 IQB/0.2/115 Version 1.0 10/10/2012 Author CZ Contents Page Introduction... 4 About this Qualification (Description,
More informationProcurement Capability Standards
IPAA PROFESSIONAL CAPABILITIES PROJECT Procurement Capability Standards Definition Professional Role Procurement is the process of acquiring goods and/or services. It can include: identifying a procurement
More informationLevel 4. Senior Assessor s Report. November 2008. Foundation Diploma in Purchasing and Supply. Effective Negotiation in Purchasing & Supply L4-01
Foundation Diploma in Purchasing and Supply Effective Negotiation in Purchasing & Supply L4-01 Level 4 Senior Assessor s Report November 2008 L4-01 SA report/nov 2008 1 INFORMATION FOR CANDIDATES The senior
More informationChapter 2 INDUSTRIAL BUYING BEHAVIOUR: DECISION MAKING IN PURCHASING
Chapter 1 THE ROLE OF PURCHASING IN THE VALUE CHAIN The role and importance of the purchasing and supply function in the value chain. The difference between concepts such as ordering, buying, purchasing,
More informationTECHNICALS LEVEL 2016 3 BUSINESS
2016 Suite Cambridge TECHNICALS LEVEL 3 BUSINESS Unit 16 Principles of project management M/507/8163 Guided learning hours: 60 Version 2 - Revised content - March 2016 ocr.org.uk/business LEVEL 3 UNIT
More informationITIL v3 Qualification Scheme
ITIL v3 Qualification Scheme ITIL Version 3 Qualification Scheme diagram Key for the Intermediate modules: Lifecycle modules SS Service Strategy SD Service Delivery ST Service Transition SO Service Operation
More informationRelationship Manager (Banking) Assessment Plan
1. Introduction and Overview Relationship Manager (Banking) Assessment Plan The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It forms a key
More informationStrategic Marketing is a 15-credit mandatory module which sits within the suite of Level 6 modules.
Module Specification: Strategic Marketing Strategic Marketing is a 15-credit mandatory module which sits within the suite of Level 6 modules. To gain the CIM Level 6 Diploma in Professional Marketing a
More informationQTC Training & Education. Certificate IV of Project Management BSB41507 Study by Correspondence
Certificate IV of Project Management BSB41507 Study by Correspondence Career-relevant, Accredited and Industry Endorsed Because QTC vocational courses are developed in consultation with relevant industry
More informationAPMP. The APM Project Management Qualification. Syllabus, learning outcomes and assessment criteria aligned to the APM Body of Knowledge 6 th edition
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
More informationREPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme
REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013 Department for Culture, Media & Sport The rural broadband programme 4 Key facts The rural broadband programme Key facts
More informationHSCIC Audit of Data Sharing Activities:
Directorate / Programme Data Dissemination Services Project Data Sharing Audits Status Approved Director Terry Hill Version 1.0 Owner Rob Shaw Version issue date 20/04/2016 HSCIC Audit of Data Sharing
More informationAccountant in Business (FAB/F1) September 2015 (for CBE exams from 23 September 2015) to August 2016
Accountant in Business (FAB/F1) September 2015 (for CBE exams from 23 September 2015) to August 2016 This syllabus and study guide are designed to help with teaching and learning and is intended to provide
More informationBUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18
Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS BUSINESS PROJECT MANAGEMENT K/502/5459 LEVEL 3 UNIT 18 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 BUSINESS PROJECT
More informationAdvanced Certificate in Professional Business and Enterprise Support Services. Qualification and Unit Specification
Advanced Certificate in Professional Business and Enterprise Support Services Qualification and Unit Specification Contents Page Qualification Overview.............................................. 3 Unit
More informationModern Slavery Act 2015
Knowledge Insight Modern Slavery Act 2015 The Modern Slavery Act came into Force in 2015. This insight gives an overview of the Act; focusing on the impact on Supply Chains and the role of Procurement
More informationRole Description Metro Operations, Data Analyst
Role Description Metro Operations, Data Analyst Cluster Agency Division/Branch/Unit Location Transport Transport for NSW Infrastructure & Services / Service Delivery & Performance / Metro Service Delivery
More informationWork Profile. Overview of Program
Work Profile Position Title: Marketing Coordinator Position Number: Responsible To: Council Program: Classification Level: Team Leader- Strategic Marketing Marketing & Creative Services L4 Overview of
More informationAssessment plan: Mortgage Adviser
Assessment plan: Mortgage Adviser ST0182/AP 1. Introduction and Overview Mortgage advice is provided by a number of different types of businesses; direct to consumer through banks & building societies
More informationDiploma in Management Level 4
Diploma in Management Level 4 This qualification is accredited by OFQUAL as being Stand Alone and part of Apprenticeships. Learners must achieve 37 credits and above to gain the Diploma qualification.
More informationDigital Strategy is a 15-credit elective module which sits within the suite of Level 6 modules.
Module Specification: Digital Strategy Digital Strategy is a 15-credit elective module which sits within the suite of Level 6 modules. To gain the CIM Level 6 Diploma in Professional Marketing a pass in
More informationManagement. Level 3 Diploma in Management (QCF) 2014 Skills CFA Level 3 Diploma in Management (QCF) Page 1
Management Level 3 Diploma in Management (QCF) 2014 Skills CFA Level 3 Diploma in Management (QCF) Page 1 Level 3 Diploma in Management (combined qualification) Qualification Title Credit Value 55 Level
More informationCOBIT 5 IMPLEMENTATION SYLLABUS
COBIT 5 IMPLEMENTATION SYLLABUS 2013 Version 1.0 (Status Live) Page 0 Owner: Chief Examiner 1. Introduction The COBIT 5 Implementation Guide provides the main guidance for a practical approach to implementing
More informationCloud Sourcing G-Cloud 5 Framework
Cloud Sourcing G-Cloud 5 Framework Cloud Sourcing Service Definition Document April 2014 Warnford Court, 29 Throgmorton Street, London, EC2N 2AT T: +44 20 7947 4176 Table of contents 1 Cloud Sourcing 3
More informationWales Procurement Policy Statement
Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.
More informationStage. service. Procure a solution. management. communication
Stage 4 communication management service Procure a solution Confi rm a procurement approach and select suppliers that offer best overall value for money (including risk and reward trade-offs). Key better
More informationDRAFT QUALIFICATION DETAILS
DRAFT QUALIFICATION DETAILS Qualification Title New Zealand Certificate in Infrastructure Procurement Procedures (Level 6) Version 2 Qualification type Certificate Level 6 Credits 51 TBC NZSCED DAS classification
More informationLevel 6 Certificate in Managing the Supply Chain
Level 6 Certificate in Managing the Supply Chain Regulator Ofqual Qualification Reference Number 600/7830/3 Qualification Start Date 1 February 2013 Last Date for Registration 31 December 2017 Available
More informationCertificate in procurement and supply operations
Certificate in procurement and supply operations Unit content guide Leading global excellence in procurement and supply Introduction The Chartered Institute of Purchasing & Supply qualifications ladder
More informationA Guide to Carrying Out a SWOT Analysis Introduction
A Guide to Carrying Out a SWOT Analysis Introduction Resource 1.4 A SWOT (strengths, weaknesses, opportunities and threats) analysis is often done as part of the process of developing a business plan or
More informationAchieve. Performance objectives
Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.
More informationProfessional Standards Capability Program
Procurement Title of document Professional - Avante Garde Capability 18pt, 80% Standard black Professional Standards Capability Program VERSION 1 5 th Feb 2014 IPAA PROCUREMENT PROFESSIONAL CAPABILITY
More informationSAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD4 - Category management in procurement and supply. Level 5 Advanced Diploma in Procurement and Supply
Level 5 Advanced Diploma in Procurement and Supply AD4 - Category management in procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 8 QUALIFICATIONS 2013 QUESTIONS
More informationHSCIC Audit of Data Sharing Activities:
Directorate / Programme Data Dissemination Services Project Data Sharing Audits Status Approved Director Terry Hill Version 1.0 Owner Rob Shaw Version issue date 20/04/2016 HSCIC Audit of Data Sharing
More informationQualification details
Qualification details Title New Zealand Diploma in Organisational Risk and Compliance (Level 6) Version 1 Qualification type Diploma Level 6 Credits 120 NZSCED 080317 Quality Management DAS classification
More informationHertsmere Borough Council. Data Quality Strategy. December 2009 1
Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.
More informationTo be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
More informationBusiness Analysis (P3) June 2013 to June 2014
Business Analysis (P3) June 2013 to June 2014 This syllabus and study guide is designed to help with planning study and to provide detailed information on what could be assessed in any examination session.
More informationHead of Commercial & Contract Management (BISRID_046)
Job Description Job Title: Reports to: Team: Location: Head of Commercial & Contract Management (BISRID_046) Head of IS Transition Business Information Services (BIS) Nelson, Treharris As a credible member
More informationSAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD5 - Sustainability in supply chains. Level 5 Advanced Diploma in Procurement and Supply
Level 5 Advanced Diploma in Procurement and Supply AD5 - Sustainability in supply chains EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 8 QUALIFICATIONS 2013 QUESTIONS AND MARKING
More informationLearning Outcome 1 The learner will: Be able to initiate the preliminary stages of a project.
Unit Title: Project Management Guided Learning Hours: 210 Level: Level 6 Number of Credits: 25 Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a 1.1 Identify an appropriate
More informationSet objectives and provide support for team members (B5) OCR Unit Number: 3
Unit Title: Set and provide support for team (B5) OCR Unit Number: 3 Unit Number: M/600/9600 Level: 3 Credit value: 5 Guided learning hours: 35 Unit purpose and aim This purpose of this unit is to provide
More informationPROCUREMENT. Embedding lesbian, gay and bisexual equality in the supply chain WORKPLACE GUIDES
PROCUREMENT Embedding lesbian, gay and bisexual equality in the supply chain WORKPLACE GUIDES PROCUREMENT Embedding lesbian, gay and bisexual equality in the supply chain WORKPLACE GUIDES PROCUREMENT
More informationMSc Management (Business Analytics) Programme Design. Academic Year 2014-15
MSc Management (Business Analytics) Programme Design Academic Year 2014-15 MSc Management (Business Analytics) The MSc Management programme is divided into three distinct sections: The first semester of
More informationGuidance Note XGN XXX.1
Guidance Note XGN XXX.1 Risk Assessment and Business Continuity Planning 1. This Guidance Note provides further detail on matters institutions should consider in assessing disruption scenarios and certain
More informationGeneral Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
More informationStakeholder Analysis toolkit
Stakeholder Analysis toolkit 1. What is Stakeholder Analysis A stakeholder is any person, group or institution with an interest in the project. A stakeholder may not necessarily be involved/included in
More informationExamination Guidance for the Advanced Certificate in PPSO Examinations. Version 1.0
Examination Guidance for the Advanced Certificate in PPSO Examinations Version 1.0 May 2010 Contents Introduction...3 Examination Objectives...3 Entry Requirements for the Examination...3 Preparation for
More informationthe role of the head of internal audit in public service organisations 2010
the role of the head of internal audit in public service organisations 2010 CIPFA Statement on the role of the Head of Internal Audit in public service organisations The Head of Internal Audit in a public
More informationEXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD5 - Programme and project management EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 10 QUALIFICATIONS 2013 QUESTIONS
More informationEXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD1 - Leadership in procurement and supply EXAM EXEMPLAR QUESTIONS CASE STUDY, QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 9 QUALIFICATIONS
More informationQuick Guide: Meeting ISO 55001 Requirements for Asset Management
Supplement to the IIMM 2011 Quick Guide: Meeting ISO 55001 Requirements for Asset Management Using the International Infrastructure Management Manual (IIMM) ISO 55001: What is required IIMM: How to get
More informationOngoing N/A TBC. Baseline
Position Title: Executive General Manager, Core Services Systems Operations Classification: SES Band 2 Position Number: 1018 Position Status (ongoing/nonongoing): Ongoing Division: Core Services Systems
More informationManagement & Leadership
Management & Leadership Overview The Management and Leadership qualifications aim to contribute to the skills, knowledge and overall performance of management and aid career progression. The qualifications
More informationBusiness Plan & Guidance Notes July 2014
Business Plan & Guidance Notes July 2014 For more information please contact: Iheanyi Ibe Enterprise Support Officer Cardiff University Enterprise Centre for Skills, Enterprise and Volunteering (CSEV)
More informationRISK MANAGEMENT POLICY (Revised October 2015)
UNIVERSITY OF LEICESTER RISK MANAGEMENT POLICY (Revised October 2015) 1. This risk management policy ( the policy ) forms part of the University s internal control and corporate governance arrangements.
More informationENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk
ENGINEERING COUNCIL Guidance on Risk for the Engineering Profession www.engc.org.uk/risk This guidance describes the role of professional engineers and technicians in dealing with risk, and their responsibilities
More informationMARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc
MARCH 2012 Version 1.10 Strategic Risk Policy Update March 2012 v1.10.doc Document History Current Version Document Name Risk Management Policy Statement and Strategic Framework Last Updated By Alan Till
More informationNational University of Ireland, Galway
National University of Ireland, Galway Recognition of Prior Learning (RPL) Policy and Practice 1. Introduction Recognition of Prior Learning (RPL) is a process that allows students to gain admission to
More informationSelecting a Standard Bidding Document for IT Procurement
The World Bank Operational Policy and Country Services Vice Presidency Procurement Unit IT Procurement Guidance Note 8 Selecting a Standard Bidding Document for IT Procurement CONTENTS I. Background on
More informationOur customer driven future
Our customer driven future Customer Strategy 2015-2020 Introduction At Energex, our customers are at the centre of our business. We want to meet our customers needs and expectations and we want to make
More informationMonitoring the Performance of Suppliers
CIPS Position on Practice Monitoring the Performance of Suppliers The term performance monitoring means measuring, analysing and managing a supplier's ability to comply with, and preferably exceed, their
More informationRole Description Director ICT Governance, Security and Risk
Role Description Director ICT Governance, Security and Risk Classification/Grade/Band Band 1 Senior Executive Work Level Standards ANZSCO Code 262112 PCAT Code 1226892 Date of Approval 03 March 2014 Work
More informationCorporate objectives. Communications strategy. Digital marketing and inclusion strategy
marketing and inclusion strategy 2014-2019 (draft) Introduction Corporate objectives Communications strategy marketing and inclusion strategy This digital marketing and inclusion strategy is a supplementary
More informationLevel: 3 Credit value: 5 GLH: 28 Relationship to NOS:
Unit 341 Implement UAN: Level: 3 Credit value: 5 GLH: 28 Relationship to NOS: Assessment requirements specified by a sector or regulatory body: Aim: T/506/1929 Management & Leadership (2012) National Occupational
More informationNHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY
NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY AUTHOR/ APPROVAL DETAILS Document Author Written By: Human Resources Authorised Signature Authorised By: Helen Shields Date: 20
More informationRelease: 1. BSBPMG510A Manage projects
Release: 1 BSBPMG510A Manage projects BSBPMG510A Manage projects Modification History Not applicable. Unit Descriptor Unit descriptor This unit describes the performance outcomes, skills and knowledge
More informationFramework for an Aviation Security Management System (SeMS)
Framework for an Aviation Security Management System (SeMS) CAP 1223 Civil Aviation Authority 2014 All rights reserved. Copies of this publication may be reproduced for personal use, or for use within
More informationOutsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process
CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should
More informationQualification details
Qualification details PLEASE note that this strand to the proposed level 5 diploma will shortly be submitted for approval to develop further. What follows here is the Project Management strand with the
More information4.1 Identify what is working well and what needs adjustment. 4.1.1 Outline broad strategies that will help to effect these adjustments.
(Overview) Step 1 Prepare 1.1 Identify specific issues or choices that the planning process should address. 1.2 Develop an organizational profile. 1.3 Identify any information that must be collected to
More informationContact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux
Version 6.3 Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux France Secretariat email: gfsinfo@theconsumergoodsforum.com
More informationPROFESSIONAL ACCOUNTANCY OR FINANCE BODY EXEMPTIONS: ICAEW ACCA CIMA AIA ACT FOR STUDENTS ON:
PROFESSIONAL ACCOUNTANCY OR FINANCE BODY EXEMPTIONS: ICAEW ACCA CIMA AIA ACT FOR STUDENTS ON: BSc ACCOUNTING & FINANCE BSc MANAGEMENT BSc INTERNATIONAL MANAGEMENT BSc INTERNATIONAL BUSINESS BA LAW & BUSINESS
More information2015 Trends & Insights
Asia Pacific Mobility The Asia Pacific Mobility Brookfield Global Relocation Services Trends & Insights report is reflective of the global economy which is strongly tied with the economic realities of
More informationCouncil Tax. Guidance to local councils on good practice in the collection of Council Tax arrears
Council Tax Guidance to local councils on good practice in the collection of Council Tax arrears June 2013 Department for Communities and Local Government Crown copyright, 2013 Copyright in the typographical
More informationSpecification. Edexcel NVQ qualification. Edexcel Level 3 NVQ Certificate in Management (QCF)
Specification Edexcel NVQ qualification Edexcel Level 3 NVQ Certificate in Management (QCF) For first registration August 2010 Edexcel, a Pearson company, is the UK s largest awarding organisation offering
More informationJob Grade: Band 5. Job Reference Number:
Job Title: Business Analyst Job Grade: Band 5 Directorate: Job Reference Number: People and Transformation P01216 The Role: This is a challenging role working with and across all services to support the
More informationEXAM EXEMPLAR QUESTIONS
Level 4 Diploma in Procurement and Supply D4 - Negotiating and contracting in procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 9 QUALIFICATIONS 2013 QUESTIONS
More informationBusiness Continuity Management For Small to Medium-Sized Businesses
Business Continuity Management For Small to Medium-Sized Businesses Produced by NORMIT and Norfolk County Council Resilience Team For an electronic copy of this document visit www.normit.org Telephone
More informationThe South African Council for the Project and Construction Management Professions (SACPCMP)
The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act
More informationA GOOD PRACTICE GUIDE FOR EMPLOYERS
MITIGATING SECURITY RISK IN THE NATIONAL INFRASTRUCTURE SUPPLY CHAIN A GOOD PRACTICE GUIDE FOR EMPLOYERS April 2015 Disclaimer: Reference to any specific commercial product, process or service by trade
More informationThe Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible