M. Buckley, B. Handy and Z.K. Hillis

Size: px
Start display at page:

Download "M. Buckley, B. Handy and Z.K. Hillis"

Transcription

1 Literature Review of the Potential Application of Metal Melting in the UK Nuclear Sector by M. Buckley, B. Handy and Z.K. Hillis 11426/TR/001 Issue 04 November 2004

2 The work described in this report was carried out by NNC Ltd under contract to the Health and Safety Executive (HSE). Any views expressed have not been adopted or in any way approved by the HSE and should not be relied upon as a statement of the HSE s views All rights reserved. No part of this document, or any information or descriptive material within it may be disclosed, loaned, reproduced, copied, photocopied, translated or reduced to any electronic medium or machine readable form or used for any purpose without the written permission of the Company

3 Table of Contents List of Tables...ii List of Figures...iii Summary...iv Acronyms...vi Note on Definitions...viii 1 Introduction Waste Issues UK Market Potential Recycling of Metals Outside the Nuclear Industry (Public Domain) Recycling Within The Nuclear Sector Melting as Part of a Disposal Strategy Summary - Waste Issues Melting Technology Introduction Overview of the Process Of Melting Radioactively Contaminated Metals Proven Technology Used For Melting Radioactively Contaminated Metals Current Non-Nuclear Technologies Developing and Emerging Nuclear Melting Technologies Summary - Melting Technology Policy & Regulatory Control Introduction International Policy with Regard to Clearance UK Policy and its Implications for Melting Implications of Recent UK Decommissioning Policy Developments Summary Policy Constraints on the Implementation of UK Melting Facilities Regulatory Controls Stakeholder Issues Summary Constraining Issues Conclusions Recommendations References...49 Issue 04 Page (i)

4 List of Tables Table 1 Industrial scale melting facilities Table 2 Chemical components in LLW from all sources (Electrowatt-Ekono, 2002) Table 3 Chemical components in ILW from all sources (Electrowatt-Ekono, 2002) Table 4 Metal Wastes at UK sites (Electrowatt-Ekono, 2002) Table 5 Status of UK sites ( Table 6 Requirements for drums, boxes, reinforcement, grouts in UK disposal facilities currently in operation (European Commission, 1998a) Table 7 Partitioning factors for BOFs and EAFs (NCRP, 2002: Cheng et al, 2000; Nieves et al, 1995; NRC, 1999) Table 8 Summary of issues and recommendations Issue 04 Page (ii)

5 List of Figures Figure 1 Radioactively contaminated metal arisings in the UK Figure 2 Estimate of Metal Arisings from UK decommissioning Figure 3 Scrap metal for steel-making (NCRP, 2002) Figure 4 GERTA (Siempelkamp, 2004) Figure 5 Blast Furnace Basic Oxygen Furnace ( Figure 6 Plasma Arc Furnace (Fentiman et al.) Figure 7 IET Plasma Enhanced Melter Issue 04 Page (iii)

6 Summary Large quantities of radioactively contaminated waste metal are currently, and will continue to be, generated during decommissioning of nuclear facilities in the UK. The waste producers currently manage these wastes generally on a project, or on occasion, a site-wide basis. There is currently no UK-wide strategy for coordinating or integrating management of contaminated metallic wastes, other than for disposal at Drigg. Other countries, including France, Germany and Sweden, have developed more integrated strategies for managing radioactively contaminated metal wastes through the operation of central metal melting facilities. These strategies take advantage of economies of scale to process a wide range of metallic waste streams, which produce either metals cleared for unrestricted use in the scrap metal market, for recycling within the nuclear industry or material for disposal. This review examines the opportunities for developing similar integrated strategies in the UK for managing contaminated metal wastes arising from across UK nuclear sites, and compares with the experience of operating facilities internationally. It considers: A review of the UK waste market -UK arisings of radioactively contaminated metal waste -Review of the available metal reuse market A review of melting technologies -Proven metal melting technology in the nuclear market -Proven metal melting technology in the non-nuclear market -Developing and emerging nuclear melting technologies Review of Regulatory Policies and Principles Review of Barriers to implementing integrated melting technologies in the UK, including stakeholder issues. The conclusions of the review are as follows. 1 In the UK there is a significant inventory of unconditioned waste radioactive metals (70,000 tonne of ILW and 383,000 tonne of LLW), which will require management. 2 There are a number of proven technologies for melting radioactively contaminated metals operating in a number of countries including France, Germany and Sweden. These facilities manage a number of different radioactive waste streams arising from a range of nuclear sites. 3 Induction melting is the chosen technology for existing industrial radioactive metal melting facilities. Further developing technologies are also emerging, such as cold crucible and plasma arc technology. 4 Metal melting can be used to achieve three aims: Size or volume reduction of waste Segregation or separation of contaminants Issue 04 Page (iv)

7 Homogenisation of contaminants within the bulk metal. 5 Following processing in these melting facilities, the metals can follow one of three paths: I. Release outside the nuclear sector (clearance) II. Reuse within the nuclear sector III. Disposal, having achieved a reduction in disposal volume and activity concentration. 6 The establishment of melting facilities for radioactive waste metals is consistent with UK government decommissioning policy and the principles of: Waste minimisation Reuse and recycle Sustainability Environmental impact & resource management 7 There are a number of drivers for reviewing the need for melting facilities: Economic o Reducing waste disposal costs o Recovering costs through reuse and recycling o Conserving natural resources o Conserving the UK s LLW disposal resources Policy To comply with government policy, guidance and principles including: Waste minimisation Reuse and recycle Sustainability Environmental impact & resource management Strategic To review application of a proven technology for radioactive waste metals on a national rather than project or site basis. 8 There are significant stakeholder issues that must be considered and managed in order to implement an integrated metallic waste management strategy. These include: Public and (non-nuclear) metal industry unease with regards to reuse of previously radioactively contaminated metals and Public concern over the transport of radioactive waste Concern over new waste or radioactive management facilities involving heat treatment Issue 04 Page (v)

8 Acronyms AC AEAT AISI BAT BF-BOF BMRA BNFL BREF Note BSS CEA CSSIN DC Alternating Current AEA Technology (UK) American Iron and Steel Institute (USA) Best Availa ble Technique Blast Furnace Basic Oxygen Furnace British Metals Recycling Association British Nuclear Fuels plc (UK) Best Available Technique Reference Note Basic Safety Standards Commissariat à l'énergie atomique / Atomic Energy Commission (France) Nuclear Information and Safety Council (France) Direct Current DRIRE Direction régionale de l'industrie, de la recherche et de l'environnement / Regional directorate of industry, of research and of the environment (France) DSIN DTI EA EAF ENRESA EPA EU EUROFER HLW HPICCM HSE Direction de la sûreté des installations nucléaires / Nuclear installation safety directorate (France) Department of Trade and Industry (UK) Environment Agency (England & Wales) Electric Arc Furnace Empresa Nacional de Residuos Radiactivos SA (Spain) Environment Protection Act (UK) European Union European Confederation of Iron and Steel Making Industries High Level Waste Hybrid Plasma Induction Cold Crucible Melter Health & Safety Executive (UK) Issue 04 Page (vi)

9 IAEA IET ILW IPPC International Atomic Energy Agency Integrated Environmental Technologies Intermediate Level Waste Integrated Pollution & Prevention Control (UK) IRR99 Ionising Radiations Regulations 1999 JPDR LLRC LLW LSA MIRC NCRP NDA NEA NII NORM OCNS OECD OPRI PET PICCM RBMK R&D RSA93 SCS SCO SEPA SOCODEI Issue 04 Japanese Power Demonstration Reactor Low Level Radioactivity Campaign (UK) Low Level Waste Low Specific Activity Metals Industry Recycling Coalition (USA) National Council on Radiation Protection and Measurements (USA) Nuclear Decommissioning Authority (UK) Nuclear Energy Agency (part of the OECD) Nuclear Installations Inspectorate (UK) Naturally Occurring Radioactive Material Office of Civil Nuclear Security (UK) Organisation for Economic Co-operation and Development Office de protection contre les rayonnements ionisants / Office for protection against ionizing radiation (France) Plasma Enhanced Melter Plasmatron with Induction Cold Crucible Melter Large Power Boiling Reactor of Soviet Union design Research and Development Radioactive Substances Act 1993 (UK) Site Condition Survey Surface Contaminated Objects Scottish Environment Protection Agency Société pour le conditionnement des déchets industriels / Company for the conditioning of the industrial waste Page (vii)

10 conditioning of the industrial waste SoLA Radioactive Substances (Substances of Low Activity) Exemption Order 1986 UKAEA US DOE UK Atomic Energy Authority Department of Energy (USA) Note on Definitions In the literature both terms smelting and melting are used in relation to metal furnaces. The term smelting is most correctly reserved for the extraction of metals from their ores. This report focuses upon the recycling of scrap metal and so the term melting is used as the furnaces are being used to convert metal into the liquid phase as opposed to metal extraction and refinement. For the purpose of this study, contamination refers to radioactive contamination. Issue 04 Page (viii)

11 1 Introduction Overview of Report Large quantities of radioactively contaminated waste metal are currently and will continue to be, generated during decommissioning of nuclear facilities in the UK. The waste producers currently manage these wastes generally on a project, or on occasion, a site-wide basis. There is currently no UK-wide strategy for coordinating or integrating the treatment of contaminated metallic wastes, other than for ultimate disposal at Drigg. Other countries, including France, Germany and Sweden, have developed more integrated strategies for managing radioactively contaminated metal wastes through the provision of proven, operating central metal melting facilities. These strategies take advantage of economies of scale to process a wide range of metallic waste streams which produce either metals cleared for unrestricted use in the scrap metal market, for recycling within the nuclear industry or material for disposal. A summary of operating metal melting facilities is shown in Table 1. There are a number of drivers for a review of UK radioactive metal waste management: Economic Policy Strategic - In order to review the most cost effective strategy for UK management of radioactive waste metal liabilities. - To comply with government policy, guidance and principles of waste minimisation and sustainability. - To review the application of proven technology of waste radioactive metals on a national rather than project or site basis. This review examines the opportunities for developing similar integrated strategies for managing contaminated metal wastes arising from across all UK nuclear sites, and compares with the experience of operating facilities internationally. It considers: A review of the UK waste market -UK arisings of radioactively contaminated metal waste -Review of the available metal reuse market A review of melting technologies -Proven metal melting technology in the nuclear market -Proven metal melting technology in the non-nuclear market -Developing and emerging nuclear melting technologies Review of regulatory policies and principles Review of the constraints to implementing melting technologies for contaminated metals in the UK, including stakeholder issues. Conclusions and Recommendations. Issue 04 Page 1

12 Table 1 Industrial scale melting facilities Sources: (NEA, 1999) [1], (Byrd Davis, 2003) [2], (Powell, 1999) [3], (Worchester et al, 1995) [4], (MSC, 2004) [5], (Byrd Davis, 2004) [6], (Greppo et al, 1998) [7], (Faugieres J., 2000) [8]. Facility INFANTE Plant, Marcoule, France (start 1992 now shutdown) [1], [2] STUDSVIK Melting Facility, Sweden (start 1987) [1] CARLA Plant, Siempelkamp, Germany (start 1989) [1] SEG Plant, Oak Ridge, USA (start 1992) [1] Capenhurst Melting Facility, UK (start 1994) [3] MSC, Oak Ridge, USA (start 1996) [4], [5] Centraco, France (start 1999) [6], [7], [8] Furnace type Electric arc melting furnace Induction for steel, small electric arc for aluminium Induction Induction Induction Reverberator y Induction Induction Types of metal treated Carbon steel, stainless steel Carbon steel, Stainless steel, Aluminium Carbon steel, stainless steel, aluminium, copper, lead (R & D) Carbon steel, stainless steel, aluminium, (planning to melt copper and titanium) Aluminium, (brass, copper,) steel Charge size (t) Products 12 Ingots, shield blocks, waste containers Radiologica l limitations Max. 250 Bq/g for Co-60, other limits for other nuclides 3 Ingots No specified limits 3.2 Ingots, shield blocks, waste containers 20 Ingots and shield blocks at present, waste containers and reinforcing steel after 1994 Max 200 Bq/g for betagamma nuclides, Max 100 Bq/g for alpha nuclides, separate limits for uranium Normally < 2 msv/hr, greater dose rates with prior review and approval Quantity of scrap melted (t) In excess of 5000t Recycled/released Stored/recycling in nuclear industry t released, remaining stored for decay (or disposal) t recycled in nuclear industry, 50 t free release 2000 Recycling in the nuclear industry 4 ingots 7000 For unrestricted use MSC's manufacturing plant is a fully integrated manufacturing facility with the capacity to melt, cast, roll or machine products from many specialty metals such as steel, aluminium, uranium, tantalum, and niobium. The company's facilities and equipment are ideally suited for small and medium batch sizes that are uneconomical for large metal producers to process. One of its key services is the recycling of depleted uranium. Stainless steel, carbon steel and to the lesser extent nonferrous metals 4 Ingots and tubes 370 Bq/g alpha, 20,000 Bq/g beta/gamma 1366 (in 2000) For restricted use: manufacture of storage drums or biological shield materials. Page 2 Issue 04

13 2 Waste Issues This section describes the potential market in the UK for melting of metals from the nuclear industry. It covers: UK Market Potential; Recycling of the metals outside of the nuclear industry (public domain); Recycling within the nuclear industry and, Melting as part of a disposal strategy. 2.1 UK Market Potential Quantities of Contaminated Metals Melting technology is most readily applicable to metal wastes. In the UK over 90% of the radioactively contaminated metal waste is ferrous, with lead, Magnox, aluminium and copper comprising most of the remainder. 85% of this metallic radioactive waste in the UK is categorised as low-level waste (LLW) with the remaining 15% being intermediate level waste (ILW). Some High Level Waste (HLW) also includes scrap plant items from vitrification plant maintenance that have been contaminated. The sources of radioactively contaminated metals are not confined to licensed nuclear operations; the oil and gas industry also routinely generate Naturally Occurring Radioactive Material (NORM) contaminated material (Electrowatt-Ekono, 2002). The extent of potential source material for a radioactively contaminated metal melter is outlined in Figure 1. Figure 1 Radioactively contaminated metal arisings in the UK (Derived from Electrowatt-Ekono, 2002) Metallic Radioactive Waste Quantity awaiting conditioning: LLW (85%) t ILW (15%) t Source: Decommissioning (D) / Operational (O) (O) t (D) t (O) t (D) t More detailed information as to the breakdown by individual metals is provided in Table 2 and Table 3. Issue 04 Page 3

14 Table 2 Chemical components in LLW from all sources (Electrowatt-Ekono, 2002) Weight (tonnes) (2) (3) Material (1) Stocks at Stocks and arisings Operational Decommissioning Total Operational Decommissioning Total METALS: Ferrous metals 2,171 2,400 4,571 52, , ,144 Aluminium 61 2,423 2,484 1,531 4,853 6,384 Copper ,578 4,166 5,744 Lead ,236 3,944 10,180 Zinc Magnox/Magnesium Zircaloy/Zirconium Boral Brass ,022 Bronze Dural Inconel Monel Nimonic Stellite Others ,776 1,829 STABLE ELEMENTS: Nickel ,051 5,600 7,650 Tin Niobium Selenium Molybdenum INORGANIC ANIONS: Fluorides ,326 1,347 Chlorides ,325 1,341 Iodides ,325 1,337 Cyanides Carbonates ,652 2,706 Nitrates ,325 1,341 Phosphates ,325 1,340 Sulphates ,649 2,664 Sulphides ,325 1,337 Other anions ORGANICS: Cellulosics ,501 8,422 94,923 Halogenated plastics ,607 8,437 19,044 Non-halogenated plastics ,142 5,623 13,765 Ion exchange materials Rubbers ,450 3,240 11,690 Other organics , ,852 COMPLEXING AGENTS TOXIC METALS AND COMPOUNDS: Cadmium Lead ,233 3,819 10,052 Mercury Beryllium Other toxic metals OTHER HAZARDOUS MATERIALS: Combustible metals Low flash point liquids Explosive materials Phosphorus Hydrides Materials reactive with water Strong oxidising agents Pyrophoric materials Generating or evolving toxic gases Putrescible wastes Biological, pathogenic materials Asbestos ,103 1,212 Free aqueous liquids (4) Free non-aqueous liquids (4) Powder (4) Notes: (1) The materials listed do not include all components of the wastes, e.g. soil. (2) Note that care needs to be taken if summing material weight as certain materials appear in more than one category (3) Only waste streams with a quantified material concentration contribute to this table. (4) Potentially hazardous for the process of supercompaction Page 4 Issue 04

15 Table 3 Chemical components in ILW from all sources (Electrowatt-Ekono, 2002) Weight (tonnes) (2) (3) Material (1) Stocks at Stocks and arisings Operational Decommissioning Total Operational Decommissioning Total METALS: Ferrous metals 19,659 1,694 21,353 29,826 30,318 60,144 Aluminium ,236 Copper Lead Zinc Magnox/Magnesium 5, ,300 7, ,079 Zircaloy/Zirconium , ,351 Boral Brass Bronze Dural Inconel Monel Nimonic Stellite Others ,038 STABLE ELEMENTS: Nickel 1, ,448 2, ,102 Tin Niobium Selenium Molybdenum INORGANIC ANIONS: Fluorides Chlorides Iodides Cyanides Carbonates Nitrates 1, ,232 1, ,373 Phosphates Sulphates Sulphides Other anions ORGANICS: Cellulosics 1, ,089 1, ,655 Halogenated plastics 2, ,096 2, ,258 Non-halogenated plastics 1, ,068 1, ,576 Ion exchange materials Rubbers ,143 Other organics COMPLEXING AGENTS TOXIC METALS AND COMPOUNDS: Cadmium Lead Mercury Beryllium Other toxic metals OTHER HAZARDOUS MATERIALS: Combustible metals 4, ,222 6, ,431 Low flash point liquids Explosive materials Phosphorus Hydrides Materials reactive with water 3, ,586 4, ,258 Strong oxidising agents 1, ,239 1, ,250 Pyrophoric materials Generating or evolving toxic gases 1, ,239 1, ,250 Putrescible wastes Biological, pathogenic materials Asbestos Free aqueous liquids (4) 12, ,410 14, ,876 Free non-aqueous liquids (4) Powder (4) Notes: (1) The materials listed do not include al components of the wastes, e.g. graphite. (2) Note that care needs to be taken if summing material weight as certain materials appear in more than one category (3) Only waste streams with a quantified material concentration contribute to this table. (4) Potentially hazardous for the process of supercompaction Issue 04 Page 5

16 Table 4, derived from (Electrowatt-Ekono, 2002) shows predicted arisings of radioactive metal waste from the major nuclear operators. The evaluation of the application of metal melting technologies should therefore consider the timescales and policy governing these arisings. Table 5 produced by the Department of Trade and Industry (DTI) shows the status of UK nuclear sites and it can be seen that of the 20 sites listed, 13 are currently undergoing some form of decommissioning. The geographical location of the arisings will be a consideration for melting operators and waste owners for the siting of any proposed melting facility. Table 4 Metal Wastes at UK sites (Electrowatt-Ekono, 2002) Weight of Metals Stocks and Arisings (Tonnes) Operator Site BNFL BNFL Magnox British Energy Generation Ltd UKAEA Ministry of Defence Amersham Plc Capenhurst Sellafield Springfields Calder Hall Chapecross Berkeley Bradwell Dungeness A Hinkley Point A Oldbury Sizewell A Trawsfynydd Wylfa Hunterston A Berekeley Centre Dungeness B Hartlepool Heysham 1 Heysham 2 Hinkley point B Sizewell B Hunterston B Torness Dounreay Harwell Windscale Winfrith Culham Aldermaston Devonport Rosyth Royal Dockyard HMNB Clyde Rosyth and Devonport Eskmeals DSTL Fort Halstead DSDC North Defence Estates Organisation NRTE Vulcan Amersham Cardiff Harwell Capenhurst (Also minor producers) ILW LLW Operational Decommissioning Operational Decommissioning 26,077 6,505 44,624 80,855 4,008 6, ,679 1,711 6,209 1,401 65,109 7,282 6,126 4,043 96, ,166 2,872 8, Page 6 Issue 04

17 Table 5 Status of UK sites ( / w w w.dti.gov.uk/ nuclearcleanup/ tl.htm) RESPONSIBLE ORGANISATIONS SITE BNFL UKAEA Magnox Sellafield Capenhurst Works Springfield Works Drigg Disposal Site Dounreay Windscale Harwell Winfrith Culham Wylfa Oldbury Sizewell A Dungeness A Hinkley Point A Bradwell Hunterson A Trawsfynydd Berkeley STATUS Operational and decommissioning - fuel reprocessing and storage and management of nuclear wastes and materials Decommissioning/waste management and storage Operational and Decommissioning - fuel manufacture, nuclear services and decommissioning of redundant historic facilities Operational - low level waste disposal Decommissioning Decommissioning Decommissioning Decommissioning Operational Operational Operational Operational Operational Defuelling & Decommissioning Defuelling & Decommissioning Decommissioning Decommissioning Decommissioning Chapelcross Operational (will shut down by March 2005) Calder Hall Defuelling & Decommissioning Issue 04 Page 7

18 2.1.2 Nature of the Radioactive Contamination Metal contamination can be of two forms, either bulk or surface contamination. Bulk contamination usually arises from neutron activation of nuclides during the service life of the component. These components will usually be in-core components i.e. will have experienced high neutron fluxes. The main activation products will be Co-58, which arises from the nickel content of the metal (Inconel alloys and stainless steel), and Co-60, which arises from cobalt impurity. Other activation products of shorter half-life include Cr-51, Fe-55 and Mn-54. Surface activity can be loose contamination arising from deposition of nuclides from the interfacing medium, i.e. aqueous phase or gas phase during service. The deposited nuclides will depend on the environment of the component during service. Surface contamination can also be tightly bound, and this usually arises from the adsorption of deposited nuclides into the oxide layer formed on the metal. These require more aggressive decontamination techniques to remove such as melting. Much of the metallic waste arising during decommissioning is only surface contaminated rather than activated. As melting causes a homogenisation of the radionuclides mentioned above, the removal of surface contamination should be actively considered by waste owners and melt operators prior to melting if the aim is to reduce activity of the waste to as low as is possible. As will be later described in Section 3, melting redistributes radioactivity between the slag, the metal and off-gases depending on the radionuclides present. The radionuclides generally present within the radioactively contaminated scrap metal are Co-58, Cr-51, Fe-59, Ni-58, Zn-65 and Mn-54. These appear in combination with the main fission products Cs-134 and Cs137. The more volatile nuclides such as strontium and caesium leave the melt and are essentially transferred to the slag and the fumes. These are then retained by special filter systems. Other radionuclides such as cobalt, nickel, chromium, iron, zinc and manganese remain within the melt with only a small transfer to the slag (European Commission, 1998a). 2.2 Recycling of Metals Outside the Nuclear Industry (Public Domain) In order for material from the nuclear sector to enter the public domain it must be released from regulatory control i.e. it must be cleared. In the UK this is by means of the Radioactive Substances (Substances of Low Activity) Exemption Order. In addition to demonstrating compliance with these objective regulatory criteria, there are a number of subjective obstacles that must first be overcome. These include for example, the concerns of the scrap metal industry and the general public over radioactivity in the environment. These issues are discussed in more detail in Section 5. Assuming the barriers to recycling of radioactively contaminated material and its later use in the non-nuclear market can be addressed, there are two main options for release into the general scrap market: 1. Surface contamination is removed. The metal is authorised for release from the nuclear site to a commercial non-nuclear metal melting facility for Page 8 Issue 04

19 recycling along with normal scrap metal. After melting the ingots are free to be sold on the open market. This follows the route of specific or conditional clearance foreseen in RP 89 (see European Commission, 1998b). 2. Surface contamination is removed and the metal is melted at a designated/separate melting facility specifically for radioactive scrap metal. The resulting ingots are then cleared for the open market Specific Clearance The advantage of using existing operational (non-nuclear) melting facilities where radioactive waste metal is mixed with normal metal is that the expense of construction is avoided. In addition there are savings in efficiency as the plant will be able to operate at near-full capacity. There will be a dilution effect from the mixture of charges, as a result of mixing contaminated material from the nuclear industry with non-nuclear sourced scrap in the melting load. However, all waste metals would have to meet stringent specific clearance levels such as those recommended by the European Commission in RP 89 before release from a nuclear site could be authorised. RP 89 gives clearance levels for surface contamination in Bq/cm 2 as well as Bq/g limits. These specific clearance levels are radionuclide specific. They were derived on the basis of radiological assessments that assumed only a fraction of the scrap in the furnace came from cleared scrap (European Commission, 1998b). Specific or conditional clearance is where the material is released for a specific purpose e.g. for melting. In the case of general or unconditional clearance material is released from regulatory control without any future controls or restrictions. In UK legislation there are no specific clearance levels. Traceability and controls to ensure the material reached its defined destination, i.e. the melting facility, would have to be in place. Agreements also would have to be reached with furnace operators to accept the waste. Finding a commercial melting facility willing to melt material meeting the specific clearance standards is likely to prove difficult. In Germany there has been a reluctance from the non-nuclear steel industry to accept material from nuclear facilities even when the material is below the more restrictive general clearance criteria (European Commission, 1998a). In France a programme of recycling ran into problems due to the commercial steelm aker partner not wishing to be associated with the nuclear industry. The details of the French example are that the Atomic Energy Commission (CEA) set up a pilot program for recycling decontaminated scrap metal using a commercial steelworks. The key aspects of the system included: the choice of operators, the identification of objects, traceability with regard to operations and operators, the contractual basis of the services provided, the contracts between the owner of the containers, the decontamination contractor and the steelmaker, documentary control of operations, verification inspections and measurements, second-level supervision, auditing of operators, Issue 04 Page 9

20 environmental impact calculations and public information (Bordas, 2000). Despite a unanimous favourable decision from the Public Health Commission for the region which followed 3 years of reviews by the French authorities including the OPRI, DSIN, CSSIN, DRIRE, the Ministries of Health, Industry and the Environment and a public consultation, the operation has stalled due to the concerns of a key stakeholder, namely the steelmaker. A foreign owner bought the steelmaker partner, and was afraid of the consequences of adverse media publicity and refused to get involved (Bordas, 2000) General Clearance The alternative is to set-up a licensed melting facility dedicated to the melting of scrap metal from the nuclear industry. The melting would still be subject to regulatory control thus metals of higher activity could be melted. There is the opportunity to reduce the level of segregation and sorting on the basis of activity levels required in advance of melting. It may be possible also to reduce the extent of the surface decontamination and its verification. After melting, ingots could then be sorted into those that can be cleared, those that should be recycled within the nuclear industry and those that require disposal. There is no guarantee that after melting and after achieving radioactive decontamination below the general clearance levels such that the metal ingots can be sold on the open metal market that a buyer will be found. As mentioned previously, in Germany steel companies continued to be reluctant to take material from nuclear facilities even when the material is below clearance levels (European Commission, 1998a). As later described in Section 5, cleared material can set off gate alarms on the entrance to the steel facilities which steel producers procedures dictate they will reject; there is also a concern that the acceptance of cleared material into the system will have an adverse effect on the industry commercially by reducing demand for metal amongst consumers due to a nervousness regarding radiation. There have been some notable successes, including the aluminium melter at Capenhurst, UK where 7000 t of aluminium has been melted for unrestricted use (See Table 1). A matter for consideration by the melter operators in conjunction with the waste owners in this approach is achieving a cost efficient use of the facility i.e. maximising its use. 2.3 Recycling Within The Nuclear Sector Availability And Potential Usage Of The Recycled Material Within The Nuclear Sector Uses of recycled metals within the nuclear sector other than in radioactive waste disposal or storage facilities are limited, an example being in shielding blocks. A review of the amounts of waste steel, concrete, copper and aluminium generated from the decommissioning and normal operations of nuclear facilities in the EU from 1998 to 2050 was made in EUR (European Commission, 1998a). Twelve scenarios for the recycling and reuse of these materials within the controlled nuclear sector were analysed. The intended final product dictates the scrap grade that can be used. Product specifications and the inherent radioactivity must be appropriate to the intended future use. Thin cold rolled products (e.g. for waste drums) will require Page 10 Issue 04

21 higher purity steel to prevent surface defects and stress cracking during fabrication, whereas rebar and structural steel only requires lower quality steel. The report, (European Commission, 1998a), concluded that steel recycling by melting, and concrete recycling by crushing were the most likely forms of controlled release recycling that could be carried out economically. Copper and aluminium recycling within the nuclear sector was considered unfeasible. With respect to copper, refining processes are most likely to yield copper suitable for clearance. It was estimated by ENRESA and AEAT, the authors of the European Commission report, that there is insufficient copper arising as waste in the nuclear sector to run a plant dedicated to its refinement at full capacity. With respect to aluminium, recycling for unrestricted release (as demonstrated by operations at Capenhurst) would be the most likely form of recycling. Following a review of existing European radioactive waste disposal facilities by AEAT and ENRESA, the requirements for steels for rebars, boxes, drums, and concrete for boxes and grouts across Europe have been calculated (European Commission, 1998a), and the estimated UK requirements have been reproduced in Table 6. In the UK the final decommissioning of stations is delayed for around 100 years to take advantage of the decay of some radionuclides and thus reduce the amount of waste that may require final disposal in controlled facilities. Thus in the UK the large amounts of waste generated from decommissioning of nuclear power plants were outside the timescale being considered for the European Commission study. Table 6 Type of container used 500 litre drums (requires 0.13 t of stainless steel) Requirements for drums, boxes, reinforcement, grouts in UK disposal facilities currently in operation (European Commission, 1998a) UK Total/ yr Total Steel requirements (t) Timescale litre drums Concrete boxes (requires 0.62 t of carbon steel for reinforcing bars) 3m 3 boxes (requires 0.63 t of stainless steel) ISO containers (require 2.5 t steel plate) In the UK the waste container which will be in greatest demand is the 200 litre drum. The estimated annual arisings of metals are presented in Figure 2. Issue 04 Page 11

22 Figure 2 Estimate of metal arisings from UK decommissioning SOURCE DATA: European Commission, 1998a based upon figures from the 1994 United Kingdom Radioactive Waste Inventory. DOE/RAS/96.001, UK Nirex Report No Page 12 Issue 04

23 Figure 2 cont d The LLW arisings of aluminium within the UK are plotted above. Although it appears that there are significant arisings of aluminium in general it arises as only a small percentage of waste within any waste stream. As for aluminium the copper waste generally arises as a small percentage of a waste stream e.g. electrical components and cabling. Issue 04 Page 13

24 The data suggests that the arisings of material will always exceed the possible uses of that material identified for disposal facilities. Around 40 % of Europe-wide arisings of carbon steel could be recycled into waste containers and rebars. For stainless steel the fraction of material generated that could be recycled is smaller at around 20 % of arisings. For stainless steel it is suggested that in some cases storage of metals for later use should be considered, especially if disposal plans for the second half of the 21st century indicate that large quantities of stainless steel containers would be required for disposal or storage of ILW or spent fuel (European Commission, 1998a). The use of recycled metallic materials in the manufacture of spent fuel storage disposal containers is an attractive scenario because the activity of the final containers will be dominated by the activity of the waste contained therein rather than any residual activity in the recycled product. The review of practices in spent fuel management reveals several opportunities for the use of recycled steel for the manufacture of containers. For example, casks such as the CASTOR type used in Finland could be easily made at a plant similar to that proposed for the manufacture of cast boxes for disposal of LLW/ILW. However, Given that the plans for dealing with spent fuel are at an early stage in many countries, this gives suitable scope for examining the possibility of incorporating a controlled release strategy in this area Necessary Additional Processing Facilities One of the problems in the reuse of stainless steels that cannot be sold to the scrap market for unrestricted release is the requirement for processing of the metal into plate. Due to the high value of the material and its anti-corrosive properties, stainless steel products used in the nuclear industry are essentially formed and welded from plate. For production of containers such as a 500 litre drum used for disposal of ILW in the UK, a rolling mill would be required. If material is of an activity higher than that suitable for unrestricted release then a nuclear installation rolling mill would be required. Any facility of this nature would have to address operational complexities including maintenance of potentially contaminated equipment and the possible requirements for remotely operated machinery. Even mini-mills used in conventional industry have annual capacities of 200,000 tonne meaning that a nuclear facility of this type will be operating significantly under capacity. This raises problems in finding suitable sources of material for processing within the country of location of such a facility, and with it problems in transportation and legislation regarding movement of material across borders. The alternative of using the facility to also roll plate for unrestricted release may not be acceptable to the conventional market. Investment in such a facility for a short lifetime and the siting of a large facility may mean that this scenario may not be feasible within Europe. The alternative manufacturing process of back-extrusion instead of forming from plate, raises further possibilities for stainless steel controlled release recycling. However, further evaluation of this method of manufacture and analysis of the economics would be required (European Commission, 1998a). With respect to carbon steel used for the production of 200 litre / 220 litre drums from plate, the same problems of processing of the metal into plate would be encountered as those for stainless steel recycling. It should be noted, however, that because of the extensive use of such drums around the EU, the production of Page 14 Issue 04

25 these drums would provide a larger market for carbon steel. The requirement for drums in a single country would be much larger than for stainless steel containers, and may therefore support a facility dedicated to arisings from a single country. This would reduce problems in transportation, but those of siting of such a facility would still have to be resolved. The adoption of a strategy of recycling within the nuclear sector may require considerable collaboration between several organisations e.g. the waste owners, melter operator, disposal facilities and the regulators. In cases where the decommissioning operations, construction and placement of waste materials are carried out by the same organisation, the availability of disposal facilities (and thus options for restricted release recycling) and the arisings of materials suitable for recycling can be easily matched. Where this is not the case there is need for considerable collaboration (European Commission, 1998a) Experience Facilities in France, Sweden, Germany and the USA are currently melting material and producing waste containers and shielding. (See Table 1). 2.4 Melting as Part of a Disposal Strategy In addition to facilitating recycling as described above melting can be advantageous for disposal. SOCODEI in France has operated a contaminated scrap metal melting unit at CENTRACO since February CENTRACO has achieved volume reduction ratios from ten to one to twenty to one (Faugieres, 2000). However, this may take into account a degree of reuse of the metal for shielding blocks and packaging. A more conservative estimate of volume reduction is that Electric Arc Furnace (EAF) and induction furnaces can achieve a reduction factor of 4 6 (ISTC, 2004). The reduction in volume will be dependent on the geometry and form of the metal. It may be possible to redistribute activity of a number of ILW waste streams by combining them such that the eventual waste is a single waste stream reduced to it s maximum density with the volume of the waste reduced when compared to that of the initial separate waste streams. If the melter s purpose is purely to reduce the volume prior to disposal (i.e. there is no intention to recycle the material), there will be no requirement to decontaminate or sort the metals (other than to ensure there are no water containing vessels in the load). Melting technology can be chosen to avoid the production of slag or the slag can be added back into the melt and disposed of together. In addition to volume reduction melting provides: A homogeneous waste form which makes characterisation simpler and easier; A stabilised final waste package (Faugieres, 2000). It may be possible that once the metal is melted and formed into easily stacked ingots the need for further packaging for disposal could be avoided as the radioactivity is stabilised within the bulk metal. As a consequence of homogenisation during melting the activity concentration will fall which may affect the categorisation of the radioactive waste and thus the correct disposal facility for it. Issue 04 Page 15

26 2.5 Summary - Waste Issues There is a large quantity of metal in the UK that could be melted. The majority of this radioactively contaminated metal is LLW. 90% of the metal is ferrous. There are three main melting strategies for these wastes: Melting for release to the open market: Melting for release to the open market will require the product to meet stringent clearance criteria. There will also be exacting controls for the verification and monitoring of the process. There also remains the issue of whether there is a market for the material due to continuing nervousness amongst the public and steel producers over radiation. Melting for reuse within the nuclear sector, Melting for reuse within the nuclear market will permit the recycling of metals which would not achieve the more stringent clearance levels required for free release. It is likely that the UK supply of contaminated metal generated within the nuclear sector would outstrip the demand for recycled materials within this sector. Melting for disposal. Melting for size reduction, would require no prior surface decontamination and very little sorting of the waste material. Melting can achieve a volume reduction factor of 4 6, thus significantly reducing the disposal cost accordingly. Melting will homogenise and stabilise the waste reducing packaging requirements. These strategies have been described as three separate approaches. There is opportunity however to integrate the strategies such that were possible material can be cleared, reused within the nuclear sector or disposed of at Drigg or Nirex depending on the activity of the product and the available markets. Whatever the strategy or approach each will require to a lesser or greater extent the co-operation and acceptance by the public and the non-nuclear steel industry: Acceptance of metal products containing recycled metal from the nuclear sector (public), Acceptance of cleared material (steel maker), Acceptance of radioactive metals/ingots for controlled melting/rolling for the nuclear sector (steel maker), Acceptance of a melting facility for radioactive material (public), Acceptance of a variation in source material at an existing melter (public and steel maker). The issues which arise for each strategy are summarised in Table 8. Page 16 Issue 04

27 3 Melting Technology 3.1 Introduction In Section 2, the extent of available radioactively contaminated metal in the UK was explored and the potential strategies for melting and their implications discussed. Section 3 concentrates upon the available technology for the achievement of those strategies. The section addresses: Overview of the process of melting radioactively contaminated metals, Proven technology used for melting radioactively contaminated metals, Current non-nuclear technologies, Developing and emerging nuclear melting technologies. 3.2 Overview of the Process Of Melting Radioactively Contaminated Metals In the 1990s, the melting of contaminated steel in purpose built plants for recycling developed as a new industry (NEA, 1999). Seven plants have been identified as having melting facilities or having melted contaminated metals on an industrial scale (see Table 1). The plants are located in France, Germany, Sweden, UK and the USA. Six out of seven of the facilities use induction melting, and the remaining plant used electric arc melting (see Section 3.3). To date, available information suggests that scrap metal has largely been recycled within the nuclear industry. A review of the feasibility of recycling and/or reuse of non-releasable components and materials arising from nuclear operations within the European Community has been undertaken by ENRESA and AEAT on behalf of the European Commission. The study concluded that the recycling of radioactive steels (carbon and stainless) is an already well researched area which requires no further development as regards the melting and refining of steel arising from nuclear facilities (European Commission, 1998a) The Treatment Process The treatment of radioactively contaminated steels will depend on whether the contamination lies within the bulk of the steel or on the surface. Surface Contamination In the case of surface contamination, the melting process will distribute the activity within the bulk. Consequently, if melting technologies are used to process steels and the aim is to maximise the reduction of activity, it is important to remove surface contamination before treatment if the reduction/removal of radioactivity is to be achieved (See Section 3.2.2). A pre-treatment, surface decontamination process will generate secondary waste arisings, which may require further treatment prior to disposal. Bulk Contamination A generic flow diagram for bulk-contaminated scrap is given in Figure 3. Prior to melting, items have to be size reduced to allow charging of the furnace through a Issue 04 Page 17

28 suitable air-lock which prevents the escape of aerosols during the loading process. The material must be sorted, for steel melting for example there must be no copper, lead or cadmium entering the melt, as this would result in an unacceptable final product for recycling. Sorting is also necessary to ensure there are no bodies containing water as this leads to formation of vapour in the melt and presents an explosion risk (European Commission, 1998a). Figure 3 Scrap metal for steel-making (NCRP, 2002) Melting The metal is melted usually either by heating by means of electrical induction heating or by electric arc in the furnace and flux potentially added, a slag phase containing the bulk of the contamination forms and floats on top of the metal phase. Fluxing agents may be added to im prove the slag separation; flux is a mixture of oxides added to the molten metal to enhance the capture of impurities (NCRP, 2002). Any combustible and volatile materials including volatile metals and metal oxides are either contained by vacuum melters and enter into the slag, or they enter an off-gas system (Garcia, 1996). Page 18 Issue 04

29 3.2.2 Distribution of Radioactive Material in the Metal-Melting Process When the aim is to maximise the reduction of activity, the first step is to remove as much surface contamination as possible. Melt refining can then be used to remove radionuclide contaminants from metals or alloys by preferential oxidation, and the oxidized contaminants are then separated from the metal. The removal of impurities can be achieved by vaporisation if they have a low boiling point. The vapours can be removed in the off-gas system or reacted with oxygen to form an oxide fume. For high boiling point impurities, they are combined with flux components and removed in the slag. The mode of removal is therefore a function of the chemistry of the furnace (acidic or basic), the thermodynamics of the system, and the chemistry of the impurities. Table 7 presents ranges of partitioning data for various radionuclides when melted in the electric arc furnace (EAF) steelmaking furnaces. Table 7 Partitioning factors for BOFs and EAFs (NCRP, 2002: Cheng et al, 2000; Nieves et al, 1995; NRC, 1999) Issue 04 Page 19

WASTE STREAM 2Y51 Analytical Services Process Facilities - North Labs

WASTE STREAM 2Y51 Analytical Services Process Facilities - North Labs WASTE STREAM 2Y51 Analytical Services Process Facilities North Labs SITE SITE OWNER WASTE CUSTODIAN WASTE TYPE Sellafield Nuclear Decommissioning Authority Sellafield Limited LLW WASTE VOLUMES Stocks:

More information

WASTE STREAM 2F35 Excellox-Type Transport Flasks and French-Design Dry Flasks

WASTE STREAM 2F35 Excellox-Type Transport Flasks and French-Design Dry Flasks SITE SITE OWR WASTE CUSTODIAN WASTE TYPE Sellafield Nuclear Decommissioning Authority Sellafield Limited LLW WASTE VOLUMES Stocks: At 1.4.2013... Future arisings - Total future arisings: 45.4 m³ Comment

More information

Guide to nuclear decommissioning

Guide to nuclear decommissioning Guide to nuclear decommissioning Contents: What is decommissioning? Stages of decommissioning Site restoration Waste management The UK decommissioning industry The international picture What is decommissioning?

More information

EUROPEAN COMMISSION NUCLEAR SAFETY AND THE ENVIRONMENT. Recycling and Reuse of radioactive Material in the Controlled Nuclear Sector.

EUROPEAN COMMISSION NUCLEAR SAFETY AND THE ENVIRONMENT. Recycling and Reuse of radioactive Material in the Controlled Nuclear Sector. EUROPEAN COMMISSION NUCLEAR SAFETY AND THE ENVIRONMENT Recycling and Reuse of radioactive Material in the Controlled Nuclear Sector Report EUR 18041 i Executive Summary A review of the feasibility of recycling

More information

THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES

THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES Introduction 1. This statement of the UK Government and devolved administrations policy on the decommissioning of nuclear facilities updates

More information

UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry

UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry August 2010 Executive Summary The UK strategy for the management of solid low level radioactive waste from

More information

EXTRACTION OF METALS

EXTRACTION OF METALS 1 EXTRACTION OF METALS Occurrence ores of some metals are very common (iron, aluminium) others occur only in limited quantities in selected areas ores need to be purified before being reduced to the metal

More information

Storage and Disposal of ILW and HLW in the UK: Implications for Copeland

Storage and Disposal of ILW and HLW in the UK: Implications for Copeland Storage and Disposal of ILW and HLW in the UK: Implications for Copeland BILL MILLER, JULIE TOOLEY & GAVIN THOMSON DECEMBER 2006 A REPORT FOR COPELAND BOROUGH COUNCIL Publication title CAN CO092 0003 Version

More information

Basic principles of radioactive waste management

Basic principles of radioactive waste management Title of publication Basic principles of radioactive waste management An introduction to the management of higher activity radioactive waste on nuclear licensed sites Joint guidance from the Office of

More information

Very low level waste management in Spain and in France

Very low level waste management in Spain and in France Very low level waste management in Spain and in France From safety to waste acceptance criteria Industrial experiences Elena Vico, Mariano Navarro ENRESA - Spain Michel Dutzer ANDRA - France Disponet Peine

More information

Treatment Centers for Radioactive Waste

Treatment Centers for Radioactive Waste Treatment Centers for Radioactive Waste TREATMENT CENTERS FOR RADIOACTIVE WASTE Introduction Nuclear facilities such as nuclear power plants, reprocessing plants, nuclear fuel cycle production units, laboratories

More information

Optimised Management of Orphan Wastes in the UK

Optimised Management of Orphan Wastes in the UK Optimised Management of Orphan Wastes in the UK ICEM13, Brussels, Belgium 9 th September 2013 Slimane Doudou, Jennifer McTeer, Stephen Wickham (Galson Sciences Ltd) Rob Thied, Richard Woodcock (Nuclear

More information

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Volume Reduction by Studsvik Nuclear AB Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Streams from Industry The Nuclear Industry generates operational waste during its lifetime as well

More information

Safely delivering excellence in decommissioning, waste management and reprocessing

Safely delivering excellence in decommissioning, waste management and reprocessing Sellafield site overview Safely delivering excellence in decommissioning, waste management and reprocessing www.nda.gov.uk www.sellafieldsites.com www.nuclearmanagementpartners.com People, partnerin Under

More information

Managing the Nuclear Legacy. A strategy for action

Managing the Nuclear Legacy. A strategy for action Managing the Nuclear Legacy A strategy for action Managing the Nuclear Legacy A strategy for action Presented to Parliament by the Secretary of State for Trade and Industry by Command of Her Majesty. July

More information

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader

More information

Secondary Lead Smelting

Secondary Lead Smelting Secondary Lead Smelting Secondary Lead Smelting Objectives Describe the basic smelting process terms: smelting, refining, and alloying List key chemicals associated with secondary lead smelting Define

More information

Iron and Steel Manufacturing

Iron and Steel Manufacturing Pollution Prevention and Abatement Handbook WORLD BANK GROUP Effective July 1998 Iron and Steel Manufacturing Industry Description and Practices Steel is manufactured by the chemical reduction of iron

More information

Strategic Guidance on the Management of LLW and ILW / LLW Cross Boundary Pond Furniture

Strategic Guidance on the Management of LLW and ILW / LLW Cross Boundary Pond Furniture Strategic Guidance on the Management of LLW and ILW / LLW Cross Boundary Pond Furniture Old Shore Road, Drigg, Holmrook, Cumbria, United Kingdom, CA19 1XH Company Registration No. 05608448 Page 2 of 58

More information

THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM

THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM G. HOLT Magnox Electric pic, Berkeley Centre, Berkeley, Gloucestershire, United Kingdom Abstract

More information

2.0 Land Quality Programme

2.0 Land Quality Programme 2.0 Land Quality Programme The Sellafield site has a legacy of ground contamination from its historical use as a Royal Ordnance factory and its subsequent development as a nuclear facility. The ground

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ONR GUIDE CONTAINMENT: CHEMICAL PLANTS Document Type: Nuclear Safety Technical Assessment Guide Unique Document ID and Revision No: NS-TAST-GD-021 Revision 2 Date Issued: March 2013 Review Date: March

More information

Management of Radioactive Waste & Materials Inventory Data

Management of Radioactive Waste & Materials Inventory Data Management of Radioactive Waste & Materials Inventory Data Critical Enabler Contents Executive Summary... 3 1. Introduction... 4 2. Inventory Data Users... 5 3. Current Situation... 7 3.1 Management of

More information

Managing Radioactive Waste Safely. Proposals for developing a policy for managing solid radioactive waste in the UK

Managing Radioactive Waste Safely. Proposals for developing a policy for managing solid radioactive waste in the UK Managing Radioactive Waste Safely Proposals for developing a policy for managing solid radioactive waste in the UK Managing Radioactive Waste Safely Proposals for developing a policy for managing solid

More information

Hazardous Waste Procedures. Faculty of Science University of Ottawa

Hazardous Waste Procedures. Faculty of Science University of Ottawa Hazardous Waste Procedures University of Ottawa Contents Hazardous Materials Waste Overview:... 3 Regulations:... 3 General requirements related to packaging waste:... 4 Table 1: List of Appropriate Waste

More information

Open Government Status: FULLY OPEN. NuSAC/SCR/07/9 HEALTH AND SAFETY COMMISSION NUCLEAR SAFETY ADVISORY COMMITTEE SUB-COMMITTEE ON RESEARCH

Open Government Status: FULLY OPEN. NuSAC/SCR/07/9 HEALTH AND SAFETY COMMISSION NUCLEAR SAFETY ADVISORY COMMITTEE SUB-COMMITTEE ON RESEARCH Open Government Status: FULLY OPEN NuSAC/SCR/07/9 HEALTH AND SAFETY COMMISSION NUCLEAR SAFETY ADVISORY COMMITTEE SUB-COMMITTEE ON RESEARCH 6 February 2007 ACCESS TO INDEPENDENT TECHNICAL CAPABILITY Paper

More information

Fuel Cycle R&D to Safeguard Advanced Ceramic Fuel Skills Strategic Options

Fuel Cycle R&D to Safeguard Advanced Ceramic Fuel Skills Strategic Options Fuel Cycle R&D to Safeguard Advanced Ceramic Fuel Skills Strategic Options Fuel Cycle R&D to Safeguard Advanced Ceramic Fuel Skills The Nuclear Renaissance and Fuel Cycle Research and Development Nuclear

More information

International Action Plan On The Decommissioning of Nuclear Facilities

International Action Plan On The Decommissioning of Nuclear Facilities International Action Plan On The Decommissioning of Nuclear Facilities A. Introduction Decommissioning is defined by the International Atomic Energy Agency (the Agency) as the administrative and technical

More information

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Provisional Translation Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management National Report of Japan for the Second Review Meeting October 2005 Government

More information

Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment. A10.1 Introduction...

Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment. A10.1 Introduction... APPENDIX 10 Normally Occurring Radioactive Material (NORM) Contents A10.1 Introduction... A10/3 A10.2 Occurrence & Concentration of NORM in Oil and Gas Operations... A10/4 A10.2.1 Probability of NORM formation

More information

Decommissioning situation of Nuclear Power Plant in Japan

Decommissioning situation of Nuclear Power Plant in Japan Decommissioning situation of Nuclear Power Plant in Japan April, 2015 The Japan Atomic Power Co. The Kansai Electric Power Co., Inc. General Description 1 Operational years of commercial NPP in Japan 40

More information

D&D of the French High Enrichment Gaseous Diffusion Plant

D&D of the French High Enrichment Gaseous Diffusion Plant D&D of the French High Enrichment Gaseous Diffusion Plant Christophe BEHAR, Philippe GUIBERTEAU CEA/DAM BP12-91680 Bruyeres le Chatel France Bernard DUPERRET, Claude TAUZIN AREVA/COGEMA BP44-26701 Pierrelatte

More information

Metals and Non-metals. Comparison of physical properties of metals and non metals

Metals and Non-metals. Comparison of physical properties of metals and non metals Metals and Non-metals Comparison of physical properties of metals and non metals PHYSICAL PROPERTY METALS NON-METALS Physical State Metallic lustre (having a shining surface) Mostly solids (Liquid -mercury)

More information

Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling

Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling J.T. Greeves, J. Lieberman Talisman International, LLC 1000 Potomac Street, NW, Suite 300 Washington, DC

More information

Residues from aluminium dross recycling in cement

Residues from aluminium dross recycling in cement Characterisation of Mineral Wastes, Resources and Processing technologies Integrated waste management for the production of construction material WRT 177 / WR0115 Case Study: Residues from aluminium dross

More information

Product Bulletin INTEROX HYDROGEN PEROXIDE

Product Bulletin INTEROX HYDROGEN PEROXIDE Product Bulletin INTEROX HYDROGEN PEROXIDE UN 2014 35% - 59.5% SOLUTIONS TECHNICAL & SPECIALTY GRADES H 0 0 H Molecular weight: 34.02 FP 1.1.3 Version 03/13 Page 1 of 5 INTEROX Hydrogen Peroxide Description

More information

Cambridge International Examinations Cambridge International General Certificate of Secondary Education

Cambridge International Examinations Cambridge International General Certificate of Secondary Education Cambridge International Examinations Cambridge International General Certificate of Secondary Education *0123456789* CHEMISTRY 0620/03 Paper 3 Theory (Core) For Examination from 2016 SPECIMEN PAPER 1 hour

More information

Question Bank Electrolysis

Question Bank Electrolysis Question Bank Electrolysis 1. (a) What do you understand by the terms (i) electrolytes (ii) non-electrolytes? (b) Arrange electrolytes and non-electrolytes from the following substances (i) sugar solution

More information

Position paper on the implications of deep sea disposal of radioctive waste

Position paper on the implications of deep sea disposal of radioctive waste Agenda Item 4 English only OSPAR Convention for the Protection of the Marine Environment of the North-East Atlantic Meeting of the Radioactive Substances Committee (RSC) Stockholm (Sweden): 20-23 April

More information

Hazardous Waste Treatment Solutions

Hazardous Waste Treatment Solutions 50 years experience delivering ABOUT TETRONICS Tetronics International is the global leader in the supply of Direct Current (DC) plasma arc systems for a wide range of Hazardous Waste Treatment applications.

More information

Fundamentals of the management of radioactive waste

Fundamentals of the management of radioactive waste An introduction to the management of higher-level radioactive waste on nuclear licensed sites Guidance from the Health and Safety Executive, the Environment Agency and the Scottish Environment Protection

More information

British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006

British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006 British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006 Presented by: Dr Malcolm Pick, Senior Engineering Consultant, Decommissioning Support Branch, Engineering and Technical

More information

UTILISATION OF NON-FERROUS SCRAP

UTILISATION OF NON-FERROUS SCRAP UTILISATION OF NON-FERROUS SCRAP Every year in New Zealand significant quantities of scrap metal are produced both as industrial off-cuts and when metal products wear out. As there are no economically

More information

The company is listed on the Australian Securities Exchange (ASX code: ILU) and employs approximately 850 people, the majority in Australia.

The company is listed on the Australian Securities Exchange (ASX code: ILU) and employs approximately 850 people, the majority in Australia. Iluka Resources Limited Murray Basin Operations Radiation Management Plan and Radioactive Waste Management Plan Overview 2014 Purpose In accordance with legislative requirements, Iluka Resources conducts

More information

LASER CUTTING OF STAINLESS STEEL

LASER CUTTING OF STAINLESS STEEL LASER CUTTING OF STAINLESS STEEL Laser inert gas cutting is the most applicable process type used for cutting of stainless steel. Laser oxygen cutting is also applied in cases where the cut face oxidation

More information

Safety Data Sheet Aluminium profiles Apply for alloys Sapa EN AW 6060, 6063, 6005, 6005A, 6082, yellow chromated, with or without powder coating.

Safety Data Sheet Aluminium profiles Apply for alloys Sapa EN AW 6060, 6063, 6005, 6005A, 6082, yellow chromated, with or without powder coating. Apply for alloys Sapa EN AW 6060, 6063, 6005, 6005A, 6082, yellow chromated, with or without powder coating. 1. Identification of the Substance/Preparation and Company Product name: (Alloys, Sapa EN AW

More information

Environmental Technology March/April 1998

Environmental Technology March/April 1998 Treating Metal Finishing Wastewater Sultan I. Amer, Ph.D. AQUACHEM INC. Environmental Technology March/April 1998 Wastewater from metal finishing industries contains high concentrations of contaminants

More information

THE ROLE OF METALLURGY IN ENHANCING BENEFICIATION IN THE SOUTH AFRICAN MINING INDUSTRY

THE ROLE OF METALLURGY IN ENHANCING BENEFICIATION IN THE SOUTH AFRICAN MINING INDUSTRY THE ROLE OF METALLURGY IN ENHANCING BENEFICIATION IN THE SOUTH AFRICAN MINING INDUSTRY Marek Dworzanowski, Presidential Address, SAIMM AGM, 22 August 2013 CONTENTS Introduction Definitions Phases of metallurgical

More information

Radiological Protection Principles concerning the Natural Radioactivity of Building Materials

Radiological Protection Principles concerning the Natural Radioactivity of Building Materials Radiological Protection Principles concerning the Natural Radioactivity of Building Materials European Commission Radiation protection 112 Radiological Protection Principles concerning the Natural Radioactivity

More information

GUIDANCE NOTES FOR WASTE MANAGEMENT

GUIDANCE NOTES FOR WASTE MANAGEMENT GUIDANCE NOTES FOR WASTE MANAGEMENT PERSONNEL DIVISION AUTUMN 1995 CONTENTS Page 1 INTRODUCTION 1 2 DOES MY WASTE REQUIRE SPECIAL DISPOSAL OR TREATMENT? 1 3 RESPONSIBILITIES 1 4 MANAGING WASTE 2 5 DISPOSAL

More information

NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission

NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission Background The U.S. Nuclear Regulatory Commission (NRC)

More information

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES MEXICO [2005] NATIONAL NUCLEAR ENERGY CONTEXT

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES MEXICO [2005] NATIONAL NUCLEAR ENERGY CONTEXT RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES MEXICO [2005] NATIONAL NUCLEAR ENERGY CONTEXT Commercial utilisation of nuclear power in Mexico started in 1990 and by 2002 there were

More information

PART 6 SPECIAL CONTRACT RULES FOR METALS CONTENTS

PART 6 SPECIAL CONTRACT RULES FOR METALS CONTENTS PART 6 SPECIAL CONTRACT RULES FOR METALS * CONTENTS Contracts Page High Grade Primary Aluminium 6-1 Aluminium Alloy 6-5 Copper - Grade A 6-11 Standard Lead 6-13 Primary Nickel 6-15 North American Special

More information

The Management of Radioactive Waste from the Nuclear Medicine Sector. Peter Hayes

The Management of Radioactive Waste from the Nuclear Medicine Sector. Peter Hayes The Management of Radioactive Waste from the Nuclear Medicine Sector Peter Hayes This is GE Healthcare Medical Diagnostic s From Organ to Cellular Contrast Agents Nuclear medicines & diagnostics Molecular

More information

MINERAL PRODUCT PRICING STUDY

MINERAL PRODUCT PRICING STUDY MINERAL PRODUCT PRICING STUDY Extractive Industries Conference. Bogota, Colombia Dan Devlin, Tax and Development Programme September 2015 BACKGROUND Background Challenges in raising revenue from extractives

More information

Magnox lifetime plan 2013

Magnox lifetime plan 2013 Magnox plan summary Magnox lifetime plan 2013 Magnox plan summary Magnox lifetime plan 2013 Magnox, owned by EnergySolutions, is the management and operations contractor responsible for ten nuclear sites

More information

Best Practicable Environmental Option Study for Management of Radioactive Waste Arisings from the Dounreay Site Restoration Plan. Issue 1.

Best Practicable Environmental Option Study for Management of Radioactive Waste Arisings from the Dounreay Site Restoration Plan. Issue 1. Best Practicable Environmental Option Study for Management of Radioactive Waste Arisings from the Dounreay Site Restoration Plan Issue 1.0 June 2003 Contents Project Team...iv Abbreviations and acronyms...v

More information

A review by HM Nuclear Installations Inspectorate. Magnox Electric plc s strategy for decommissioning its nuclear licensed sites

A review by HM Nuclear Installations Inspectorate. Magnox Electric plc s strategy for decommissioning its nuclear licensed sites A revie by HM Nuclear Installations Inspectorate Magnox Electric plc s strategy for decommissioning its nuclear licensed sites A revie by HM Nuclear Installations Inspectorate Magnox Electric plc s strategy

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

Welding. Module 19.2.1

Welding. Module 19.2.1 Welding Module 19.2.1 Hard Soldering Hard soldering is a general term for silver soldering and brazing. These are very similar thermal joining processes to soft soldering in as much that the parent metal

More information

Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation. G.. d Amored

Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation. G.. d Amored Sino-Italian Cooperation Project Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation G.. d Amored Environmental Protection Agency of Piedmont Region (ARPA

More information

FlyMe Environmental impact assessment MHI/ 24-1-2007 Page 1(6) 2 Description and assessment of the Production process

FlyMe Environmental impact assessment MHI/ 24-1-2007 Page 1(6) 2 Description and assessment of the Production process Page 1(6) Fly Me CHAIR 1 Description and assessment of the Materials used in the Product 2 Description and assessment of the Production process 3 Description and assessment of the Surface Treatment Methods

More information

BECHTEL JACOBS COMPANY ORR WASTE CERTIFICATION PROGRAM DOCUMENT CONTROL SYSTEM

BECHTEL JACOBS COMPANY ORR WASTE CERTIFICATION PROGRAM DOCUMENT CONTROL SYSTEM BECHTEL JACOBS COMPANY ORR WASTE CERTIFICATION PROGRAM DOCUMENT CONTROL SYSTEM If you print the following document, this page must be attached to the front of the document and you must fill in the information

More information

Tritium Gas Processing for Magnetic Fusion

Tritium Gas Processing for Magnetic Fusion Tritium Gas Processing for Magnetic Fusion SRNL-STI-2014-00168 The views and opinions expressed herein do not necessarily reflect those of any international organization, the US Government Bernice Rogers

More information

Rehabilitation and Remediation of POPs

Rehabilitation and Remediation of POPs and of POPs Module 3 and Overview of the course This module will cover various remediation and rehabilitation strategies. Contents Strategies (and part of ) Summary technologies Summary Learning outcomes

More information

Plasma Arc Technology

Plasma Arc Technology Engineering & Environmental Applications of Plasma Arc Technology Louis J. Circeo, Ph.D. Principal Research Scientist Director, Plasma Applications Research Program Electro-Optics, Environment and Materials

More information

Assessing the Management of Lead in Scrap Metal and Electric Arc Furnace Dust

Assessing the Management of Lead in Scrap Metal and Electric Arc Furnace Dust Assessing the Management of Lead in Scrap Metal and Electric Arc Furnace Dust Final Report EPA530-R-09-004 April 2009 U.S. Environmental Protection Agency Office of Resource Conservation and Recovery With

More information

IMPLEMENTING ISO 14001:2004. www.aecos.co.uk

IMPLEMENTING ISO 14001:2004. www.aecos.co.uk IMPLEMENTING ISO 14001:2004 www.aecos.co.uk What is an Environmental Management System? A systematic framework to manage the immediate and long term environmental impacts of an organisation s products,

More information

Decommissioning of Nuclear Facilities

Decommissioning of Nuclear Facilities International Atomic Energy Agency Decommissioning of Nuclear Facilities Decommissioning Planning Douglas G. Draper 1 Lesson Objectives Describe the requirements for and methods for the managing waste

More information

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001)

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) 1. Scope The scope of this Environmental Aspects Register covers the following operational areas: Aberdeen Region (A); Cumbernauld Region (C); Warrington Region

More information

Office for Nuclear Regulation Annual Report and Accounts 2014/15 HC 164

Office for Nuclear Regulation Annual Report and Accounts 2014/15 HC 164 Office for Nuclear Regulation Annual Report and Accounts 2014/15 HC 164 Office for Nuclear Regulation Annual Report and Accounts 2014/15 Presented to Parliament pursuant to Paragraphs 21 and 25(3) of

More information

MAKIN METAL POWDERS. Copper and Copper Alloy Powders WORLDWIDE. www.makin-metals.com (UK) LIMITED

MAKIN METAL POWDERS. Copper and Copper Alloy Powders WORLDWIDE. www.makin-metals.com (UK) LIMITED Copper and Copper Alloy Powders WORLDWIDE www.makin-metals.com INTRODUCTION We occupy a purpose built 10,000 sqm production facility. Our employees have a long history and a wealth of experience in the

More information

Project No. (FKZ) 3707 61 301/05 UBA-FB 001337. Summary. by Dr. Sonja Martens Dr. Bernd Eggers Thorsten Evertz Golder Associates GmbH, Celle

Project No. (FKZ) 3707 61 301/05 UBA-FB 001337. Summary. by Dr. Sonja Martens Dr. Bernd Eggers Thorsten Evertz Golder Associates GmbH, Celle TEXTE 34/2010 ENVIRONMENTAL RESEARCH OF THE FEDERAL MINISTRY OF THE ENVIRONMENT, NATURE CONSERVATION AND NUCLEAR SAFETY Project No. (FKZ) 3707 61 301/05 UBA-FB 001337 Applications of Nanomaterials in Environmental

More information

MEMORANDUM OF UNDERSTANDING BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE NUCLEAR REGULATORY COMMISSION

MEMORANDUM OF UNDERSTANDING BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE NUCLEAR REGULATORY COMMISSION MEMORANDUM OF UNDERSTANDING BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE NUCLEAR REGULATORY COMMISSION CONSULTATION AND FINALITY ON DECOMMISSIONING AND DECONTAMINATION OF CONTAMINATED SITES I. Introduction

More information

7. Chemical Waste Disposal Procedures

7. Chemical Waste Disposal Procedures 7. Chemical Waste Disposal Procedures Substances that Can and Cannot be Disposed of via Sink Drains or in Regular Solid Refuse Containers 1. It is prohibited to pour down a sink or floor drain, or place

More information

Chemical and Isotopic Signatures for Environmental Remediation and Nuclear Forensic Analysis

Chemical and Isotopic Signatures for Environmental Remediation and Nuclear Forensic Analysis Chemical and Isotopic Signatures for Environmental Remediation and Nuclear Forensic Analysis Sue B. Clark Washington State University, Department of Chemistry, Pullman, WA 99163 s_clark@wsu.edu Abstract

More information

TABLET DETERGENTS Towards A More Sustainable Future

TABLET DETERGENTS Towards A More Sustainable Future TABLET DETERGENTS Towards A More Sustainable Future Unilever Supports Sustainable Development of Detergents with Tablets THE CONTRIBUTION OF TABLETS Unilever is committed to meeting the needs of customers

More information

LCA EXPERIENCE IN THE FIELD OF RECYCLING OF PLASTICS FROM ELECTRONIC WASTE

LCA EXPERIENCE IN THE FIELD OF RECYCLING OF PLASTICS FROM ELECTRONIC WASTE LCA EXPERIENCE IN THE FIELD OF RECYCLING OF PLASTICS FROM ELECTRONIC WASTE B. DeBenedetti, L. Maffia, G.L. Baldo 2 Dipartimento di Scienza dei Materiali ed Ingegneria Chimica, Politecnico di Torino, Italy

More information

ZERO WASTE ELECTRIC ARC FURNACE (EAF) STEELMAKING CHAPARRAL STEEL COMPANY TARGET

ZERO WASTE ELECTRIC ARC FURNACE (EAF) STEELMAKING CHAPARRAL STEEL COMPANY TARGET ZERO WASTE ELECTRIC ARC FURNACE (EAF) STEELMAKING CHAPARRAL STEEL COMPANY TARGET Libor F. Rostik ChaparraI Steel Company Midlothian Texas EPA Region III Waste Minimization/Pollution Prevention Technical

More information

MATERIAL SAFETY DATA SHEET SECTION 1 CHEMICAL PRODUCT AND COMPANY INFORMATION SECTION 2 COMPOSITION/INFORMATION ON INGREDIENTS

MATERIAL SAFETY DATA SHEET SECTION 1 CHEMICAL PRODUCT AND COMPANY INFORMATION SECTION 2 COMPOSITION/INFORMATION ON INGREDIENTS SECTION 1 CHEMICAL PRODUCT AND COMPANY INFORMATION Chemical Name: Stainless Steel Product Use: Manufacturer Information: OMNISOURCE CORPORATION Telephone: (260)422-5541 Safety Department 1610 North Calhoun

More information

TOXIC METALS FROM NON-FERROUS METAL MELTING (Adopted December 15, 1994) For the purpose of this rule, the following definitions shall apply:

TOXIC METALS FROM NON-FERROUS METAL MELTING (Adopted December 15, 1994) For the purpose of this rule, the following definitions shall apply: RULE 7060 TOXIC METALS FROM NON-FERROUS METAL MELTING (Adopted December 15, 1994) 1.0 Purpose The purpose of this rule is to control airborne emissions of toxic metals from non-ferrous metal melting. Compliance

More information

SDS SC-000-033 Rev 11 01/15

SDS SC-000-033 Rev 11 01/15 SAFETY DATA SHEET (SDS) Society, Inc. 205 American Foundry Meets the Requirements of OSHA Standard 29 CFR 90.200 Hazard Communication and EPA Supplier Notification Requirements under Section 33 of the

More information

This is Outokumpu Tornio Site

This is Outokumpu Tornio Site Investor visit, 7th October 2015 Hannu Hautala, SVP - Business Line Tornio This is Outokumpu Tornio Site October 7, 2015 1 October 7, 2015 2 We believe that all accidents are preventable. Our target is

More information

Form 0.5 chair, 2805 and 2806

Form 0.5 chair, 2805 and 2806 Page 1(8) Form 0.5 chair, 2805 and 2806 1 Description and assessment of the Materials used in the Product 2 Description and assessment of the Production process 3 Description and assessment of the Surface

More information

Introduction to Waste Treatment Technologies. Contents. Household waste

Introduction to Waste Treatment Technologies. Contents. Household waste Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting

More information

IAEA Recommendations on a Decommissioning Plan (DP)

IAEA Recommendations on a Decommissioning Plan (DP) IAEA Recommendations on a Decommissioning Plan (DP) Ernst Warnecke, IAEA-NSRW Patrick O Sullivan, IAEA-NEFW Research Reactor Decommissioning Demonstration Project (R²D²P) Review of a Decommissioning Plan

More information

10 Nuclear Power Reactors Figure 10.1

10 Nuclear Power Reactors Figure 10.1 10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of

More information

Efficient Recycling and Waste Management»

Efficient Recycling and Waste Management» Efficient Recycling and Waste Management» EnBW KernkraftGmbH Jörg Klasen, Head of Nuclear Decommissioning Services with Frank Bolles, Burkhard Hartmann, Sönke Pingel 46th Annual Meeting on Nuclear Technology

More information

SPECIFICATIONS FOR STEEL PIPE

SPECIFICATIONS FOR STEEL PIPE SPECIFICATIONS FOR STEEL PIPE Published pipe standards serve three functions. 1. They dictate manufacturing and testing requirements and prescribed methods of measuring the required mechanical and physical

More information

Urea and Nitric Acid Plants: Improvement of Shut-Down, Revamping, Debottlenecking and Refurbishment

Urea and Nitric Acid Plants: Improvement of Shut-Down, Revamping, Debottlenecking and Refurbishment pp Urea and Nitric Acid Plants: Improvement of Shut-Down, Revamping, Debottlenecking and Refurbishment J. M. SLUYTERS GEMACO SA Herstal, Belgium A presentation on special corrosion-resistant steels for

More information

North American Stainless

North American Stainless North American Stainless Flat Products Stainless Steel Grade Sheet 310S (S31008)/ EN 1.4845 Introduction: SS310 is a highly alloyed austenitic stainless steel designed for elevated-temperature service.

More information

North American Stainless

North American Stainless Introduction: North American Stainless Flat Products Stainless Steel Grade Sheet 309S (S30908)/ EN1.4833 SS309 is a highly alloyed austenitic stainless steel used for its excellent oxidation resistance,

More information

Chem 1101. Highlights of last lecture. This lecture. Australian Mining Sites. A/Prof Sébastien Perrier. Metallurgy: (Extracting metal from ore)

Chem 1101. Highlights of last lecture. This lecture. Australian Mining Sites. A/Prof Sébastien Perrier. Metallurgy: (Extracting metal from ore) Chem 111 A/Prof Sébastien Perrier Room: 351 Phone: 9351-3366 Email: s.perrier@chem.usyd.edu.au Unless otherwise stated, all images in this file have been reproduced from: Blackman, Bottle, Schmid, Mocerino

More information

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND 1. NATIONAL FRAMEWORK FOR MANAGEMENT AND REGULATION OF RADIOACTIVE WASTE AND DECOMMISSIONING 1.1 National framework 1.1.1 Overview of national

More information

Licensing Nuclear Installations

Licensing Nuclear Installations Licensing Nuclear Installations 4th edition: January 2015 Office for Nuclear Regulation page 1 of 80 This guide provides an overview of the nuclear regulatory regime and the processes for licensing and

More information

Nuclear Decommissioning Authority Business Plan

Nuclear Decommissioning Authority Business Plan Nuclear Decommissioning Authority Business Plan Financial year beginning April 2015 to fi nancial year ending March 2018 March 2015 23117210 2 Nuclear Decommissioning Authority Business Plan Financial

More information

Nuclear Decommissioning Authority. Business Plan 2012-2015

Nuclear Decommissioning Authority. Business Plan 2012-2015 Business Plan 2012-2015 Business Plan 2012-2015 Business Plan presented to Parliament pursuant to Schedule 3 of the Energy Act 2004. Business Plan laid before Scottish Parliament by the Scottish Ministers

More information

Instructions Answer all questions in the spaces provided. Do all rough work in this book. Cross through any work you do not want to be marked.

Instructions Answer all questions in the spaces provided. Do all rough work in this book. Cross through any work you do not want to be marked. GCSE CHEMISTRY Higher Tier Chemistry 1H H Specimen 2018 Time allowed: 1 hour 45 minutes Materials For this paper you must have: a ruler a calculator the periodic table (enclosed). Instructions Answer all

More information