CONSTRUCTION MATERIAL
|
|
|
- Domenic Douglas
- 9 years ago
- Views:
Transcription
1 1
2 CONSTRUCTION OF WIRE-REINFORCED CEMENT MORTAR TANKS Note: this document has been scanned from earlier manuals and standardizations prepared by Neil Herath for CWSSP Sri Lanka ( April 1995), and as Manual 3 of the Technical Manual Series on Rural Water Supply and Sanitation; Gravity Water Supply Systems: design and construction (January 2005). It is redesigned to look like the 2005 CWSSP manual guiding field work on wirereinforced cement mortar tanks, commonly known as ferrocement tanks (Han Heijnen, October 2010) 1. CONSTRUCTION MATERIAL A small assortment of construction materials are required for the construction of these tanks. Ordinary portland cement River sand 1/2" - 3/4" metal Tor steel reinforcement (10 mm) 6.3mm Mild steel G.I. Straight wire G.I. Woven mesh (no. 4) 1.1 SAND The ideal type of sand to be used to mix the mortar is moderately course river sand with uniform grain structure. Finer sand produces weaker mortar and results in shrinkage cracking. It is best to use sand with a grading of coarse and fine particles free from dirt. It would produce a good workable mortar. 1.2 MORTAR MIX To make a satisfactory workable mortar mix it is necessary that the sand and cement are mixed in appropriate proportions. Stronger mixes (mixes with more cement) produces more workable mortar, increases its final strength, but will lead to greater risks with wider shrinkage cracks. Mortar mix of one part cement to three parts sand (1:3) is suitable for construction of these tanks. 1.3 WATER - CEMENT RATIO Mixes with least water produces strong mortar. However, workability of such dry mortar is poor. On the other hand mixes with too much water will be difficult to work on to the mesh, as it would start falling off. A water cement ratio of 0.5 : 1 (water : cement, by weight) recommended for ferrocement construction is ideally situated for the mortar mixes used in the construction of wire-reinforced-cement mortar tanks too. 2
3 Given below are some of the important areas where special attention is needed in fixing of reinforcements. 2. Anchoring of the skeletal steel of wall into the base. The length of the anchor should be 40d. (40 x diameter of rods) Provision of a minimum anchor length of 200mm of the wire mesh into the base concrete. Vertical overlaps of wire mesh to be 200mm and the horizontal overlaps to be at least 50mm. Lap length of the straight wire reinforcement to be at least 300mm. Ail free ends of the binding wire used for fixing steel in place are to be on the inside face in case of the walls and on the outside in the case of the cupola roof. Care shall be taken to flatten the wire ends against the mesh. SEQUENCE OF CONSTRUCTION Selection of site Excavation Positioning of pipework Screed concrete Fixing reinforcement for the floor slab Floor concreting. Reinforcement for the wall Application of cement mortar to outside of wall Application of cement mortar to inside of wall Floor rendering Reinforcement for the roof cupola Application of cement mortar to outside of cupola Application of cement mortar to soffit of cupola Completion of the access opening (upstand ring beam) Installation of the overflow and vent pipe. Installation of ladder and cover for access opening Painting Installation of valves and construction of valve chambers Landscaping 3. CONSTRUCTION PROCEDURE 3.1 SELECTION OF SITE Wire-Reinforced Cement Mortar tanks (hereafter called ferrocement tanks) are generally constructed above ground level. The excavation involved is minimal. Due to its thin walls ferrocement tanks could easily be affected by direct impact, Hence, it is advisable to construct these tanks away from locations where there is a potential danger from rolling or moving objects such as rock boulders, tree trunks, branches etc. 3
4 Due to the lightness of the structures, these could be sited conveniently in such locations where other comparatively heavier structure such as rubble masonry or reinforced concrete tanks cannot be erected, However, the bearing soil should be sufficiently firm so that there is no possibility of differential settlement or lateral movement or sliding. 3.2 EXCAVATION The only buried section of the ferrocement tank being the concrete base the extent of excavation involved is minimal. However, the top soil containing humus and other organic matter should be completely removed and the loose top layer of soil removed exposing the subgrade which should be firm. The excavated material other than the top soil should be disposed off at tips located away from the site. The removed top soil however could be re-used to stabilize and turf the exposed excavated surfaces and slopes adjacent to the structure after completion as protection against possible erosion. After levelling the exposed sub-grade the outline of the circular base of the tank is marked on the ground using a piece of rope. The excavation for the foundation is 150mm deep unless specified otherwise. Where the soil is firm care should be taken to keep the edge of the excavation straight and true to line. In certain types of soils it may be necessary to use some form of improvised formwork to protect the sides of the excavation from falling in. But the need to do so will be rarely felt, as the depth involved is very small. All pipe outlets of ferrocement tanks are laid to pass through the floor slab. Due to its relatively thin walls there is a possibility of leaks along the pipe surface if such outlets are provided through the wall, as is done in tanks built in the traditional way. 4
5 3.3 POSITIONING OF PIPE WORK Only two pipe outlets viz. common scour/main outlet and the overflow are provided in these tanks, both through the floor slab unless detailed otherwise. These pipes shall be laid in trenches excavated below the floor slab. Pipe positioning detail PVC pipes and specials are used for the two outlets. To prevent leaks along the length of the pipe the pipes are to be provided with PVC puddle collars at the section passing through the concrete base. After the pipes are laid the trenches are filled with compacted concrete 1:3:6 (20mm) embedding the pipes. It is advantageous to provide a Gl socket to the end of the outlets properly anchored in the concrete so as to prevent any danger to the pipe. Such damages would be due to differential settlement or torque when other pipe components such as valves etc. are fixed. The common outlet is positioned about the centre of the floor. This will enable easy and effective washing & cleaning of the tank. The overflow outlet however shall be positioned closer to the wall so that the upstand pipe could be supported from the wall if necessary. 5
6 3.4 SCREED CONCRETE A screed concrete 1:3:6 (20mm) of 50mm thickness is usually placed in the excavation for the foundation in all tanks before the floor slab is constructed. The screed concrete can be eliminated only in those cases where the floor is mass concrete. It is necessary to level the surface of the screed adequately using a hand ram and float. 3.5 FIXING REINFORCEMENT FOR THE FLOOR SLAB Reinforcement for the floor slab is nominal and is usually of 10mm Tor steel placed either way at the specified spacing indicated in the drawings. Clear cover to the reinforcement is 40mm. It is helpful to use cement spacer blocks with embedded binding wire strands for tying them securely to the mesh to prevent movement during concreting. At this point it is necessary to mark the perimeter of the wall on the floor reinforcement enabling assembly of wall reinforcement. For this purpose a circular ring having a diameter of (D+W) is constructed out of 6 mm steel bar, where 'D' is the internal diameter and W is the wall thickness. This is placed centrally to the floor, and securely tied, on the floor reinforcement mesh already assembled in place. As discussed in section 1.5 the vertical skeletal of 6 mm (M.S) and the G.I woven mesh have to be adequately embedded in the floor to strengthen the wall to floor joint. The mesh is usually available in 1 meter wide roils. A length of the circular wall plus the recommended horizontal lap length of 200 mm is cut from this roll. It is then bent to 'L' shape along its longer side, the shorter arm of the 'L' being 150 mm. It will be necessary to split the bent length of the mesh at shorter intervals to facilitate bending it to the required curvature. The 6 mm vertical skeletal steel is then assembled at specified spacing along the same perimeter of the mesh. It is possible to use shorter lengths of 6 mm M.S. rods as starters only. However, as indicated in the drawings it is recommended that the full lengths are used to avoid unnecessary lappings. 6
7 The reinforcement placement is now complete for receiving the concrete in the floor slab. 3.6 FLOOR CONCRETING The mix generally used for concrete works in water retaining structures is 1 : 1.5 : 3 (20mm). However for the floor concrete in these tanks 1:2:4 (20mm) concrete would suffice. This is possible as all internal facets of the tanks are being rendered and finished water tight using neat cement finish. Special care has to be taken to ensure that the wall reinforcement are not displaced or shifted during the concreting. 3.7 REINFORCEMENT FOR THE WALL After concreting the floor the starter reinforcement of the wall has to be straightened and cleaned free of all cement grout and other dirt. Assembly of wall reinforcement needs a good deal more care and attention than is needed in other operations. This is mainly to ensure that the structure is formed true to line and shape, a factor that determines the quality of the final construction. It is necessary therefore to use some supports internally to meet this requirement. For this purpose use two circular stiffeners made of 10mm Tor steel. One is placed halfway on the wall and the other at the maximum height of the wall. The two stiffeners are aligned vertically horizontally and held in position using cross supports. Once this is done the 6.4mm vertical skeletal steel bars are tied on to the stiffeners. The G! woven mesh is then tied round the vertical steel. The horizontal laps of the mesh shall be 50mm and the vertical laps 200mm as discussed earlier. On completion of tying the mesh in place it is necessary to re-check the verticality or the reinforcement structure. Any corrections of deviations from true shape or line should be carried out at this stage prior to proceeding any further. The main reinforcement of the wall viz. the G.I. straight wire is finally tied round the wall outside the mesh spirally at the specified spacing. It is advised to use a gauge cut to the appropriate spacing to ensure that the correct spacing is maintained. Verticaiity of the reinforcement structure has to be maintained at all times and any deformities have to be corrected immediately. Also, make sure that all free ends of the G.I. binding wire is on the inside face of the tank and are kept against the mesh. 7
8 IMPORTANT! It is essential at this stage to erect all necessary scaffoldings with an access to the inside of the tank. Make sure these are independent of the structure. 3.8 APPLICATION OF CEMENT MORTAR TO OUTSIDE OF WALL In the construction of these tanks it is necessary to plaster the outside before the inside. The following section explains how the outside plaster is applied. Before commencing plastering of wall ensure that the required number of masons and unskilled labour are available and adequate stocks of cement, sand etc. are available with easy access. It is necessary to sieve the sand beforehand. For measuring the volumes of sand for the mix it is advised to use a gauge box. Volume batching using head pans or wheel barrows should be avoided. The mortar mix used for piaster is 1:3 (cement: sand) Mixing of mortar should be carried out in small batches of not more than the equivalent of one bag of cement, it should be done on a pre-prepared surface either cement paved platform or a wooden plat from with a metal sheeting. Cement and sand in the correct proportions are to be dry mixed thoroughly. Add the required amount of water in small quantities to this pile mixing it thoroughly until a consistent workable mortar mix is obtained. Apply the mortar onto the reinforcement cage starting from bottom and gradually moving upwards. Care should be taken to force the mortar well into the mesh so that no cavities are formed between the wire and the mortar. The wall extends 100 mm above the operating water level of the tank. Once this level is reached it is necessary to ensure the verticality of the tank wail. For this purpose level pads are embedded in the wall which will define the vertical line. 8
9 A second layer of mortar is applied on the previous layer, and finished smooth with the surface of the level pad, thus ensuring verticality from bottom to top. This layer also should be applied from bottom to top. The combined thickness of the plaster should be approximately 20mm. This final application of the mortar should be carried out while the previous layer is still green and within minutes. The fillet at the wall joint too is formed at this stage. Since this is the final plastering operation it is necessary that it is finished smooth with neat cement, true to line and level. The top of the wall plaster has to be levelled off and adequate covers are to be provided to protect the fresh mortar application from damage. Curing of the finished outside plaster can commence 4 to 6 hours after completion of the application. A spray of water is appropriate for this purpose. 3.9 APPLICATION OF CEMENT MORTAR TO INSIDE WALL Internal wall plaster can commence on the following day. AH internal supports, steel stiffeners etc. are to be carefully, removed taking care not to exert any force on the wall, whilst removing such supports.. All loose material should be brushed off from the face of the old plaster using a coir brush. The inner face too is plastered using the same mortar mix. Before applying the mortar wet the receiving face adequately with lean cement grout. The fillet at the base wall joint too is laid along with the laying of internal wa!! plaster. In smaller tanks it is possible to complete the internal wall plaster and the floor rendering on the same day. However, in larger capacity tanks this will not be possible, and the recommended approach is as follows. The plastering of the wall section is carried out first, including the fillet in one continuous operation. This is also done in two stages the initial plastering and subsequent cement rendering making upto a finished thickness of approximate 20 mm. The floor rendering is carried out on the next day (see sketch under section 3.10). For better water tightness a water sealant compound such as pudlo cement could be used in the internal plaster in a proportion of 5% by volume. However, this is not an absolute requirement. The internal wall plaster too should be leveled off in line with the outer plaster. 9
10 3.10 FLOOR RENDERING The same mix proportion is used for the floor rendering. In finishing the floor it is necessary to make sure that the floor slopes towards the common outlet at the middle so as to facilitate complete draining. The construction joint between the floor rendering and the wall plaster may crack open due to shrinkage and leave room for leaks. This could be overcome by providing a thin groove at this joint and finally filling it up with cement grout or some bituminous sealer material. It is essential to ensure that continuous curing of all finished facets is carried out throughout REINFORCEMENT FOR THE ROOF CUPOLA Before proceeding with the roof construction it is necessary to seal the possible seepage path along the steel perimeter of the wall. This can be achieved to some extent by pouring a thin mix of cement grout filling the cavities at the line of steel, (joint of the internal and external plastering). A ring having a diameter equal to the diameter of the access opening is made with a 10mm tor steel rod. This is supported carefully with 4 props at the required height. The centre of this ring should align with the central axis of the tank, 6mm vertical bars are bent to conform to the shape of the roof dome and tied to the steel ring at the crown. A template can be used to guide the bending of these bars to the required shape. The mesh is tied in position over the vertical steel followed by the GI straight wire. At the roof the spacing of straight wire is increased to 100rnm. In tying the steel in place in the roof cupola it is advantageous to have the free ends of the binding wire to the outside unlike in the case of wall. Additional supports may be used if the roof span is larger. 10
11 3.12 APPLICATION OF CEMENT MORTAR TO OUTSIDE OF ROOF CUPOLA Application of mortar in the roof cupola too is similar to that on the wall. The same mortar mix is used and is done in two layers, the final layer being finished smooth with neat cement. Provision has to be kept for anchoring the access ladder hinges for the lid, vent outlet, etc. on the roof. In plastering the roof cupola it should be noted that absolutely no loading is exerted on the structure. It is therefore essential that all necessary scaffoldings are provided beforehand, independent of the structure and enabling easy access even to the inside of the tank. 11
12 3.13 APPLICATION OF CEMENT MORTAR TO THE UNDERSIDE OF ROOF CUPOLA It is possible to remove all supports of the roof cupola after 24 hours. However care shall be taken not to exert force in removing such supports. The plastering of the underside of the cupola is also finished in two layers. It is preferred to finish the underside too, smooth with neat cement COMPLETION OF THE ACCESS OPENING The access opening to the tank is provided at its crown. An upstand ring beam is formed with the same mix of mortar to a thickness of 50mm and upstanding 50 cms from the top of the roof INSTALLATION OF THE OVERFLOW & VENT PIPE The overflow outlet is provided from the floor of the tank. It is extended through the roof to form the vent as well. Since the section of the pipe projecting out of the tank is exposed to the sun, this part of the pipe should be G.I. The conversion from PVC to G.I. is carried out within the tank and the G.I. socket is embedded in the roof structure as shown in the figure at right INSTALLATION OF LADDER & COVER FOR ACCESS OPENING The access ladder is pre-fabricated and an integral hinged cover is provided for the access opening. 20 mm G.I. pipes and 10 mm Tor steel can be used for fabricating the ladder. The cover can be made with either sheet metal or glass fibre. It is preferable to make the lid out of lighter material even though it is possible to fabricate one out of cement mortar to. The ladder fabricated to the shape of the tank has to be simply supported anchored to the ground and to the crown of the cupola only PAINTING To protect the tank from the elements and also for aesthetics the tanks are painted in a lighter shade of weather proof paint. This paint shall be applied in two coats over a prime coat of lime wash. All metal parts are painted with anticorrosive paint applied in two coats. 12
13 3.18 INSTALLATION OF VALVES & CONSTRUCTION OF VALVE CHAMBERS. These tanks are usually provided with one valve chamber housing the inlet, outlet and scour valves provided as indicated in the detail drawings. The size of the chamber is decided to meet specific requirements. The construction is of 100 x 150 x 300 sandcrete blocks (cement/sand) in cement mortar LANDSCAPING As in all other construction works, it is of importance to ensure that, the area in the vicinity of the structure is kept free from debris, heaps of earth etc. It is necessary to level the immediate surrounding area of the structures and provide grass turfing or stone pitching where appropriate to arrest any possible damage due to erosion. The tank is liable to damage by impact from heavy objects such as large boulders, falling trees and other heavy articles etc. Hence it, is important to eliminate any such objects that may endanger the structure. 4. CURING Continuous curing of the various components of construction is of utmost importance. The final strength and quality of the structure depends to a great extent on the effectiveness of curing process apart from the other contributing factors. Wet hessian cloth hung over the completed faces is one way of carrying out effective curing or on the alternative continuous spraying of water has to be done. 5. IMPOUNDING Impounding of the tank should be phased out and done in stages. This could begin immediately after finishing the wall and the floor rendering. Filling should be done at the rate of not more than 150mm (6") layer of water every day. Normally the tank could be fully impounded within a few days after the completion of the structure if this process is followed. 13
14 14
15 15
16 16
17 17
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
CHAPTER NO. 27 QUANTITIES OF MATERIALS
CHAPTER NO. 27 QUANTITIES OF MATERIALS Note :- One cement bag weighs 50 kg. and measures 0.03472 cum. Sr. No. Description Unit Quantities Fine aggregates Coarse aggregates 1 2 3 4 5 6 27.1 Cement concrete
BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"
BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP" Sl. 1 DISMANTLING WORK 1.1 Stripping off worn out plaster (outside and inside) and raking out joints
After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE
86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
Chapter 2 Basis of design and materials
Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural
Free-Form Concrete Pool
The tranquil beauty and playful shimmer of a reflecting pool or fountain is just the thing to enhance the charm of your garden or patio. Best of all, you can do all the work yourself. Add goldfish or water
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE
Sl.No. PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Description of item Qty Unit Rate Amount 1 Demolishing tile work/cement concrete/( carefully taking out the closet and other
GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS
GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS 13.1 13.2 2006 Edition SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS GENERAL
TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER
TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER I. Scope of Work Work done under this item shall consist of the construction, reconstruction, or alteration of a one-course Portland
LAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
How to build a Pizza Oven in 4 days
How to build a Pizza Oven in 4 days Preparation day (slab) 1. Foundation 1500 deep x 1300 wide x 75mm deep Required 20 bags cement pre mix. If you already have a concrete base, you save this prep day DAY
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Watershed Works Manual
National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
Chapter. Earthquake Damage: Types, Process, Categories
3 Chapter Earthquake Damage: Types, Process, Categories Earthquakes leave behind a trail of damage and destruction. People s lives are affected by the loss of loved ones, destruction of property, economic
If stepping is required, step at 180mm as seen in this picture.
Cast Foundations to standard building regulations requirements. Foundations must be cast completely level, 600mm wide by 230mm deep for single storey, double storey is not allowed by NHBRC. If stepping
PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY
PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY GENERAL SPECIFICATIONS These specifications are intended to cover the construction of the
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
Construction Specification for Concrete Curb and Concrete Curb and Gutter
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.50 April 2015 for Concrete Curb and Table of Contents TS 3.50.01 SCOPE... 3 TS 3.50.02 REFERENCES... 3 TS 3.50.03
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,
CONSTRUCTION OF PERIMETER FENCE - COMMERCIAL AND T&D OFFICE COMPOUND, ONVERWAGT
BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS CONSTRUCTION OF PERIMETER FENCE - COMMERCIAL 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg,
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.
CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
K2 STONE NATURAL VENEER
INTRODUCTION WHAT IS K2 NATURAL THINSTONE VENEER? Natural K2 Stone veneer is real stone, cut 1 inch thick, making it light enough to be installed as a veneer. Sometimes referred to as thin veneer, thin
Storm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
FORM DESIGN. easy to work with, and generally available.
Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Minor Cracks in Horizontal Surfaces
Cracks, chips and broken or flaking areas in concrete are not only unsightly, they can lead to further deterioration of the surface. The result is a costly replacement project as opposed to a simple repair.
Laying the First Course. 1. Excavate the site and construct the footing.
Use QUIKRETE Mortar Mix or Mason Mix lay up a concrete block wall as shown. QUIKRETE Mortar Mix or Mason Mix Concrete block Mason's line Line blocks 4' level brick trowel Jointer Mason's hammer Stiff brush
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
SE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors
Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors The Right Concrete Mix Placing and Finishing Joints Correctly Spaced Curing for Durability "Concrete durability is the ability to
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
International Greenhouse Company
Greenhouse Foundation Design As with any building, a good solid foundation is crucial for the long term durability and functionality of your greenhouse. A weak foundation will cause your greenhouse to
:: ARTIFICIAL SAND :: Zone One Sand : Zone Two Sand :
:: ARTIFICIAL SAND :: Natural sand are weathered and worn out particles of rocks and are of various grades or size depending on the accounting of wearing. The main natural and cheapest resource of sand
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
SEE HOW TO MAKE LIME PLASTER WHY USE LIME? PATTI STOUTER, BUILD SIMPLE INC. FEBRUARY 2013
SEE HOW TO MAKE LIME PLASTER PATTI STOUTER, BUILD SIMPLE INC. FEBRUARY 2013 WHY USE LIME? Lime plaster forms a light, clean, and durable surface that is resistant to weather and mold. A thin layer attaches
HOUSE BUILDING DIGEST
HOUSE BUILDING DIGEST (Construction Specifications-Foundations) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information
SECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS
AN ERGONARMOR COMPANY TECHNICAL INFORMATION SPECIFICATION FOR INSTALLATION 07/11 SUPERSEDES 04/00 PAGE 1 OF 6 CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS 1. SCOPE 1.1 This specification
Schlüter -KERDI-BOARD Substrate, structural panel, bonded waterproofing
Substrate, structural panel, bonded waterproofing The universal substrate for tiles Perfect covering No matter whether you work with mosaics or large format tiles, an absolutely level substrate with straight
ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT
ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : DOHUK SUMEL SUMEL GO code : IRAK GEN ASSENG0 TITLE : Sharia / PHCC / Rehabilitation SO n : SO 03 WPA n : KIR16 0015 Job
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything
Issue of the Guidelines on Prevention of Water Seepage in New Buildings
graphic: Buildings Department Your REF 來 函 檔 號 :. OUR REF 本 處 檔 號 :.BD GR/1-55/173 FAX 圖 文 傳 真 :..28400451 TEL 電 話 :..2626 1717 www.info.gov.hk/bd To : All Authorized Persons 7 March 2005 Registered Structural
SECTION 32 31 13 CHAIN LINK FENCES AND GATES
PART 1 GENERAL 1.1 DESCRIPTION SECTION 32 31 13 CHAIN LINK FENCES AND GATES SPEC WRITER NOTES: 1. Delete or add information between //---// and any other items applicable to project. Cover any item added
Installation PowerPoint for Grasscrete Formers
Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold
SECTION 4Aggegate Subbase
The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
How to Install Pavers
1 of 6 9/11/2012 10:41 AM How to Install Pavers Looking to give your property a durable driveway, a whimsical walkway, or a patio with pizazz? If you're reading this article, you're probably already on
Welcome: What is U Drain? Drain Materials. Flow
Welcome: Thank you for looking into the U Drain floor drain system. This paper will explore the functional features of the U Drain and why it is superior to other grated systems in the marketplace. We
BOQ for Plumbing, Sanitary Works
BOQ for Plumbing, Sanitary Works Page 1 of 6 Sr.No Item Description Quantity Unit Rate Amount (Rs.) 1 SANITARY FIXTURES Providing & Fixing star white colour vitreous china wall mounted wc with 1a heavy
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio
Seven Easy Steps to Installing Your Own Walkway, Driveway and Patio Without Mortar or Concrete Brick is one of the world s oldest and most enduring building materials. Those same qualities also make it
SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General
SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,
SECTION 03300 CAST-IN-PLACE CONCRETE
SECTION 03300 PART 1 GENERAL 1.01 DESCRIPTION This section describes materials and methods for formwork, reinforcement, mixing, placement, curing and repairs of concrete, and the use of cementations materials
The University of Toledo Soil Mechanics Laboratory
1 Grain Size Distribution Sieve Analysis The University of Toledo Soil Mechanics Laboratory Introduction The grain size distribution is a representation of the approximate distribution of soil grain sizes
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
STEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet.
STEP-BY-STEP construction guide Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. Welcome to our CONSERVATORY AND SUNROOM CONSTRUCTION GUIDE What is the specification
Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits
Attachment G-1: Pit Latrine Diagram Fig E.1a: Pit Latrine Fig E.1b: Plan View of Twin Pits Fig E.1c: Section of a water-sealed pan Fig E.1d: 3D view of Overflow Pipe Fig E.1e: 2D view of Overflow Pipe
L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.
L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
STANDARD INSPECTION & TEST PLAN (ITP) FOR CIVIL WORKS :
CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD (ITP) F CIVIL KS : 1.0 GENERAL NOTES: Inspection & Test Plan (ITP) given herein is indicative only. Contractor shall prepare and submit ITP for all activities.
METHOD A10 (a) THE DETERMINATION OF THE IN-PLACE DRY DENSITY OF SOIL OR GRAVEL BY THE SAND REPLACEMENT METHOD
METHOD A10 (a) THE DETERMINATION OF THE IN-PLACE DRY DENSITY OF SOIL OR GRAVEL BY THE SAND REPLACEMENT METHOD 1 SCOPE The in-place dry density of compacted soil or gravel, as defined below, is determined
Improving the flood resistance of your home. Advice sheet 6: Flood-resilient floors
Improving the flood resistance of your home Advice sheet 6: Flood-resilient This sheet provides guidance on identifying different types of floor, assessing the routes floodwater may enter, and describes
PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.
PERMEABILITY TEST A. CONSTANT HEAD OBJECTIVE To determine the coefficient of permeability of a soil using constant head method. need and Scope The knowledge of this property is much useful in solving problems
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
COATING & WRAPPING OF UNDERGROUND PIPING
CONSTRUCTION STANDARD SPECIFICATION DOCUMENT NO :SEC-PJ-000-SPC-PI-008 TOTAL PAGES : 8 Page 1 of 8 CONTENTS 1. SCOPE 2. DEFINITION 3. CODES AND STANDARDS 4. MATERIALS Page 2 of 8 1. SCOPE This specification
AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM):
SECTION 02832 AIRPORT SECURITY FENCING PART 1-GENERAL 1.1 SUMMARY A. Section includes: Construct airport security chain-link fence and gate at specified areas and conforming lines, grades, details indicated
Design and Construction of Cantilevered Reinforced Concrete Structures
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures
Shingle Installation Guide
Shingle Installation Guide Getting Started Dedicated to improving the environment, NewTech manufactures roofing tiles that are composed of up to 90% recycled post-industrial plastic. The manufacture of
Tested to BS 6375: Part 1: 1989 and achieved a weathertightness classification of 2000 Pa (Special)
THE B6 GLAZING SYSTEM GLAZING SYSTEMS FOR SEPTEMBER 2013 THE B6 HEEL BEAD SEAL SECURITY GLAZING SYSTEM Page 1 DESCRIPTION The B6 Heel Bead Seal Security Glazing System is suitable for installing all types
No allowance will be made for classification of different types of material encountered.
PROJECT : Repair/ Maintenance of Flood Control and Drainage Structures Along Butuan City Cagayan de Oro City Iligan City Road LOCATION : San Antonio, Jasaan, Misamis Oriental SUBJECT : General Notes and
Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction
Welded Fabric 1.0 Introduction Welded fabric, often referred to as mesh, is a machine welded grid arrangement of reinforcing bars or wires. It is covered by British Standard BS4483. This was revised in
Elevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
Item No. 432S Portland Cement Concrete Sidewalks. 432S.1 Description
Item No. 432S Portland Cement Concrete Sidewalks 432S.1 This item shall govern the construction of Portland cement concrete sidewalks (Standard Detail No. 432S-1), as herein specified, on an approved subgrade
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION
CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION 1 This item shall consist of furnishing and erecting Chain-Link fence in accordance with these specifications and the details shown on the plans and in
50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance
02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW
Designed and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
7. Installation. installation 7.1.1. CAST-IN WINDOW SYSTEM 7.1. INSTALLATION OF WINDOW MAIN FRAME
7. Installation Window involves the fixing of window frame at an earlier construction stage and subsequent of the window sashes. This is a highly workmanship dependent process. Only trained and approved
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the
Gas Meter Clearances and Service Installation Requirements
March 2016 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE's Customer Construction Services 1 888 321 7779 or visit PSE.com/CustomerConstruction
Brick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
Residential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
The minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
