A BPMN-based process map for the design and construction of façades
|
|
|
- Clement Nelson
- 9 years ago
- Views:
Transcription
1 Journal of Facade Design and Engineering 1 (2013) DOI /FDE IOS Press 17 A BPMN-based process map for the design and construction of façades Eleanor Voss a,, Qian Jin b and Mauro Overend b a Glass and Façade Technology Research Group, Department of Engineering, University of Cambridge, Cambridge, UK b Glass and Façade Technology Research Group, University of Cambridge, Cambridge, UK Received: 12 August 2013 Accepted: 20 November 2013 Abstract. Process mapping can lead to significant efficiency and quality improvements in construction engineering and is an ideal basis for developing IT support tools. The increasing complexity and multidisciplinary nature of façade design and construction suggest that a process map would be beneficial in this sector of the construction industry, but it has received limited attention to date. This paper presents a verified process map of the façade design and construction process. The map is the first of its kind to represent, in detail, the whole process relevant to all façade types, from commencement of the façade consultant s and contactor s participation, to the end of their involvement. The paper describes the process by which the mapping notation was selected, followed by the development and verification of the process map, including testing in two independent research projects. The BuildingSMART s BPMN notation is found to have superior system features and comprehensibility for this application and the resulting process map is easy to interpret and verify by industry experts. The trialling of the map in the two research projects indicate that the map is a useful tool for assessing process improvements in the façades sector. Keywords: Process map, façade design process, project management 1. Introduction Façade design and construction is a relatively new sector of the construction industry, as is the role of the professional façade engineer (Karsai, 1997). The sector is complex in terms of the range of materials employed, geometries involved, performance requirements and its collaborative multidisciplinary nature. These conditions suggest that a process map would be a very useful aid to researchers in this field The benefits of process mapping The main benefits of process mapping include: increasing understanding of actor s roles and activities (Klotz et al., 2008); aiding identification of strategic, process and IT requirements (Aouad et al., 1999); or forming the basis for IT systems (Tzortzopoulos et al., 2005). Mapping the as-is situation in the planning, design and construction of sustainable buildings, increases the understanding of the process by 5 27% and leads to efficiency and quality improvements Corresponding author: Eleanor Voss, Glass and Façade Technology Research Group, Department of Engineering, University of Cambridge, Trumpington Street, Cambridge, UK. [email protected]. ISSN X/13/$ IOS Press and the authors. All rights reserved This article is published online with Open Access and distributed under the terms of the Creative Commons Attribution Non-Commercial License.
2 18 E. Voss et al. / A BPMN-based process map for the design and construction of façades Klotz et al. (2008). This agrees with the findings of Tzortzopoulos et al. (2005), whose list of benefits to the construction industry includes supporting education and development of IT systems Process mapping in the façades sector There has been limited mapping of the façade design and construction process. Much of what does exist focuses on specific façade typologies or provides a low level of detail. However, some of the work conducted to date has been used to develop the map presented in this paper. Klein (2013) produced a high-level map showing the current involvement of stakeholders during different project stages and a set of maps showing a revised process for a new approach to façade design. In addition, a hierarchical set of façade design and construction process maps were developed in the CladdISS project (Pavitt & Gibb, 2003) by eliciting knowledge from industry through interviews and questionnaires (Pavitt & Gibb, 1999). These maps are presented in a tabulated format and capture the key stages, decisions and management issues related to the interface between the façade and other building components. In both research projects the maps fulfil the purpose for which they were intended, but they either work to a very high level of abstraction (and low level of detail) or describe an ideal (or proposed) process. Pavitt s and Gibb s work formed the basis of a set of maps developed subsequently by Vaz et al. (2008). The maps use the Integration Definition for Function Modelling (IDEF0) notation and were produced to improve the understanding of the façade design process and to identify façade-structure interface issues. These maps mainly provide a high-level overview of the façade design and construction process, showing the main project stages. However, a more detailed map focusing only on the design of the façadestructure interface was also developed. In addition, the IDEF0 notation used by Vaz et al. is significantly clearer than the tabulated format used in the CladdISS project. It is therefore evident that the choice of mapping notation should be considered carefully as it affects comprehensibility. The IDEF0 notation was also used in the CIMclad project to map the design-to-installation processes of rainscreen cladding (Agbasi et al., 2003). The map is constructed from the perspective of consulting façade engineers and it was used for the development of a rainscreen cladding product model. Although the process is mapped to a high level of detail, the work focuses on a single type of cladding. There are also several research projects on the mapping of the precast concrete cladding sector. Karhu (1997) worked on mapping the precast cladding process in order to develop a product data model using the IDEF0 notation. Gray and Al-Bizri (2007) proposed a knowledge-based-engineering (KBE) representation of design processes and illustrated the concept with a map of the precast cladding design process. The maps were intended to clarify the roles and responsibilities of the designer. Finally, Eastman et al. (2003) have developed several maps, using different notations, of the architectural precast design and fabrication processes. This body of work provides significant levels of detail, but the maps are limited to precast concrete cladding Process map production Mapping notations The IDEF0 mapping notation has been used in several processes mapping research projects, both in the façades sector (Kalian et al., 1997; Vaz et al., 2008) and the wider construction industry (Laitinen, 1999; Dawood, 2002; Pingtserng, 2004). The IDEF0 is a function modelling notation and is the standard initial step in the ISO-STEP methodology (Eastman et al., 2002). It aims to capture decisions, actions,
3 E. Voss et al. / A BPMN-based process map for the design and construction of façades 19 and activities of an organization or system. The notation comprises of hierarchical diagrams using box and arrow graphics, the box representing functions and the arrows represent inputs, outputs, controls and mechanisms (IDEF, 2010). An alternative notation is the Business Process Modelling Notation (BPMN) which is used by BuildingSMART to develop the IFCs (International Foundation Classes). The notation is based on a flowchart technique with graphical objects representing activities and flow controls describing their sequence. Hierarchical modelling is supported through a plus sign indicating expansion in the activity object (Wix & Karlshoj, 2010). A range of BPMN concepts are expressed in IFC-compatible format, for example, a swimlane, or zone of the map where the activities relating to a single professional role are placed, is represented by ifcactorrole (Wix & Karlshoj, 2010). Several process maps are now available through the BuildingSmart website (BuildingSmart, 2008), some of which include parts of the façade design process, for example, the Architectural Design to Building Energy Analysis map. In addition, Eastman et al. (2010) have developed a process map of the precast façade design process using the BuildingSMART BPM notation. Two main knowledge elicitation methods are frequently used in the development of these process maps: (1) An initial literature review to gather information about the design and construction process (Kagioglou et al., 2000; Gray & Al-Bizri, 2007), followed by; (2) an evaluation by industry members, through workshops or case studies, to either produce or enhance the map (Aouad et al., 1999; Kalian et al., 2004; Gray & Al-Bizri, 2007). Once completed, the accuracy of a process map may be quantified by means of interviews in which real-world case studies are compared with the original map (Austin et al., 1999) Evaluation of mapping notations Alternative mapping approaches may be analysed by means of the structure provided by Kochikar and Narendran (1994), who distinguished between modelling power and decision power, where: modelling power is the universe of system features that a notation can represent, and; decision power is the ease with which a map can be analysed. The features of each of these two characteristics are summarised by Koskela (p.g. 506, 1995). The IDEF notation has been reviewed in several research projects (Karhu, 2001; Eastman et al., 2002; Wynn, 2007), however, there is a lack of publications on evaluations of the BuildingSMART-BPM notation Scope of the paper and content to follow At present, there is no detailed façade design and construction process map that is applicable to all façade types. Such a map would be useful for identifying and quantifying possible improvements to the façade design and construction process. For example, in the development of software applications that support façade designers/fabricators without disrupting the existing processes, or in assessing the impact of a new procurement system. Therefore this paper presents a verified process map of the façade design and construction process from initial design to completion for use as a research resource. In Section 2, the two principal mapping notations (BPM-BuildingSMART and IDEF0) are evaluated and a preferred notation is selected. This is followed by a description of the iterative interview-approach used to develop the map, a description of the map itself, and a qualitative evaluation of its accuracy. The value of the map as a resource for further research and development in the façade industry is demonstrated in Section 3. Finally, Section 4 presents conclusions and areas of further work.
4 20 E. Voss et al. / A BPMN-based process map for the design and construction of façades Sufficient number of system features represented Table 1 Comparison of IDEF0 and BPMN-BuildingSMART notations IDEF0 Does not effectively model the information generated by, and used in, activities (Eastman et al., 2002) (Karhu, 2001) Cannot be used effectively to describe iterative activities which are a key characteristic of design processes (Wynn, 2007) Uses a diagram for each actor, making it difficult to compare actor s activities alongside other actors (Karhu, 2001) BPMN Represents generation and use of information with the specific information object (Wix & Karlshoj, 2010), see Fig. 1 Can represent repeat or iterative activities by a loop or a circular arrow respectively (Wix & Karlshoj, 2010) Uses swim lanes to easily identify which actor performs which activity (Wix & Karlshoj, 2010), allowing the whole process with every actor involved to be seen at once Hierarchical modelling and ability to represent different levels of abstraction IDEF0 BPMN Uses activity box labeling and a whole process map plan to indicate how the levels link together Uses a plus sign in the activity box to indicate that the box expands to reveal further detail on a lower hierarchical level Model verifiability IDEF0 Does not include an effective way to verify the accuracy of the map produced (Eastman et al., 2002) Produces complex models that are difficult to understand (Karhu, 2001), (IDEF, 2010), making verification through industry consultation difficult BPMN Lack of published research on the comprehensibility of the BPMN-BuildingSMART notation in the construction industry and so it will be reviewed as part of this mapping project in Section 2.5 Fig. 1. Example of (a) BPM notation and showing an activity and two information objects and (b) IDEF0 notation showing two activities and an information annotation. 2. Production of the process map 2.1. Selection of mapping notation BuildingSMART s adaptation of the BPMN is a strong candidate for the façade process map, as it supports an exchange schema (BuildingSMART IFC) that is particularly suitable for the development of computer based support tools. However, this modelling notation has not been used previously for
5 E. Voss et al. / A BPMN-based process map for the design and construction of façades 21 façade design process mapping. It is therefore sensible to evaluate it against the IDEF0 notation which is a recognised modelling standard (by American National Institute for Standards and Technology) and which has frequently been used for process mapping research projects. The comparison presented in Table 1 evaluates these two mapping notations against each other by considering each of Koskela s (1995) characteristics of modelling methods, however since the primary purpose of this map is modelling power, the evaluation disregarded, but did not penalise poor decision power. The accuracy of the whole façade design and construction process map presented in this paper has been verified through interview based consultation with industry, hence it is essential that the maps are understood with ease so that errors and omissions can be identified. Therefore comprehensibility is used to assess Model Verifiability. In addition, the purpose of this mapping project is to produce an as-is representation of the current process, rather than any changes to it. Therefore the criterion that the notation should be able to represent evolution of processes is neglected at this stage Conclusions on mapping notations From this evaluation it is evident that the BuildingSMART BPMN adaptation is at least as suitable as the IDEF0 notation for the production of a whole façade design and construction process map, and in some criteria, the BuildingSMART BPMN out-performs IDFE0. The areas where the IDEF0 notation under-performs in the context of this mapping project are: (1) available representation system features (particularly iterative activities and allocation of activities between industry professions), and; (2) model verifiability through review, which requires comprehensibility. Hence, the BPMN-BuildingSMART modelling notation was selected The process map development method Following initial consultation with the potential interviewees the following five step method was developed and employed: 1. Relevant information from existing façade-related process maps was extracted. The most relevant work was the CIMclad process maps (Kalian et al., 2004). The IDEF0 notation employed in the original map was difficult to understand (see Section 2.1.3), therefore, the maps were reformatted in the BPM-BuildingSMART notation. The maps produced by the CladdISS project (Pavitt & Gibb, 2003) were not used further in this project as they represent the ideal rather than the as-is activities and information exchanges. 2. Further knowledge was elicited from industry to ensure the map represented the design and construction process for all façade typologies. This started with the production of a highly simplified process map followed by interviews with selected industry experts. The interviewees were asked to work through the process map, adding information and making corrections. Four interviews were conducted, two with façade sub-contractors and two with façade consultants. 3. The two sources of information (from step 1 and 2) were merged to form the version 1.0 of the process map using the BPMN-BuildingSMART notation. When combining the information from the interviews, no judgement was made as to the relative authority or accuracy of different sources, instead leaving this to the later steps of review (step 4) and accuracy verification (step 5). Any process map element that was specified by any source was included, while clashes
6 22 E. Voss et al. / A BPMN-based process map for the design and construction of façades Table 2 Results of map validation in step 5 interviews. (Total number of map elements = 169) Interview (a) Missing (b) Redundant (c) Modified (d) Accuracy (%) # # # # Average in sequencing were resolved by representing these steps as potentially concurrent on the map. 4. The map was reviewed by industry experts using a workshop format and the suggested modifications were incorporated. The workshop participants consisted of three façade consultants from a single firm. The revised process map (v1.1) consisted of a total of 169 elements. 5. The revised map (v1.1) was verified by a further set of four interviews with industry experts using a case study format. The interviews were conducted with four different façade consultants, none of whom had been involved in the previous steps of the mapping process. During each of these interviews, the map was compared to the process undertaken in a recent real-world façade design projects and inaccuracies and omissions were recorded (Table 2). Each façade project had a construction cost of over 15 M and was either completed in 2012 or later. Three categories of inaccuracies were identified: (a) missing, which represent the process elements that were needed to capture the project but were not in the map; (b) redundant, which represent those elements that should be removed from the map to make it reflect the real project; (c) modified elements indicating process elements that required minor modification to conform to the process undertaken on the real project. From these the accuracy, of the map which quantifies the overall ability of the process map to represent each project, therefore accuracy d = [(169 b c))/(169 + a b)] 100% The process map The process map is large, therefore only extracts are reproduced in this paper. The full map (v1.1) is available through the Glass and Façade Technology Research Group website (gft, 2012), where it is possible to navigate electronically through the map hierarchy using hyperlinks. Two extracts have been selected to show a range of detail. Figure 2 shows the top level map that summarises the whole façade design and construction process and an expanded portion of activity A5. The top level map (Fig. 2a) illustrates the whole project process, ends of key stages are identified through double lined circles, and the whole process end is indicated by a bold lined circle. The map shows the façade consultant s activities in the top swimlane and the facade contractor s process step in the bottom swimlane. The plus signs at the base of each activity indicate that further detail on this activity is available and can be accessed by the user. The expansion of the main activities (Fig. 2b) includes details of the information used and produced in each sub-activity. For example, the construction information comments are generated by activity A5.3 Review of construction information including coordination with other systems.
7 E. Voss et al. / A BPMN-based process map for the design and construction of façades 23 Fig. 2. Map v1.1 (a) Top level map and (b) portion of activity A5 expanded Evaluation of process map and notation The accuracy verification step identified some errors in the map. However, the majority of the map accurately represented the real projects used in the verification interviews (step 5) interviews. On average v1.1 of the map was 85% successful in capturing the real-world project. It was noted that the same inaccuracies were identified in more than one interview, for example, the construction and review of visual and performance mock-ups had not been included in the map of step 5. All four interviews identified these as missing. Although further development and improvement of the map is underway, the validation by means of independent interviews indicates that the map provides a reasonably accurate representation of the façade design and construction process.
8 24 E. Voss et al. / A BPMN-based process map for the design and construction of façades During the interviews and workshops the industry experts were able to quickly interpret the map, indicating the notation is easily understood, and the industry processes were represented with ease, indicating that the notation has a sufficient number of system features. This practical evaluation confirmed that the BPMN-BuildingSmart notation was suitable for the mapping project, particularly with regards to the ability of mapping non-experts to interpret the map. 3. Use of process map in research projects A process map, such as the one presented in this paper, is particularly useful for assessing whether the outcomes of a research project are compatible with current industry processes (incremental /evolutionary innovation) or whether it would be beneficial to alter the current industry processes in order to exploit the benefits of the research (revolutionary / disruptive innovation). The BMPN Façade Process Map was deployed in two on-going research case studies, and the contributions of the map to the research projects are identified and discussed in this section Research case study 1 The Knowledge-Based Façade Design Development (KBFDD) research project aims to improve communication between construction industry domains thereby improving the process of designing, construction and operation of façades. The objective of the research project is to develop a prototype Building envelope Information Model (BeIM) tool that supports the façade consultant and indirectly the design team as they devise the panelisation scheme of façades. The BeIM tool encourages the users to generate design options that are feasible and cost effective to manufacture by increasing the users understanding of the effects of downstream design constraints. The project uses a construction industry neutral BIM digital format to improve communication of design information between members of the design team (Voss & Overend, 2012). The process map described in Section 2 played three key roles in the research project: Firstly, the process map described in this paper provided the researcher with an overview of the façade industry, placing the project in context. The map was used as graphical summary of the actors, information exchanges, and roles in the sector. Secondly, the map was used to identify patterns of use of specific information objects. For example, by identifying the repeated use of information objects that are not project-specific, a system can be developed to capture, store, and make accessible these elements of information for re-use in subsequent projects. In addition, by assessing when these information objects are used, the BeIM tool has been developed to encourage users to update the recycled information. For example, activity A1.5.1 (shown in Fig. 3) requires knowledge of size restrictions on façade panels to assess the panelisation scheme proposed by the project architect. This information is owned by the consultant and not specific to the project. The same information is used again for activity A1.5.2, a development rather than a review task. The information stored by the consultant can be updated during activity A4.6.1 when the same type of information, this time owned by the contractor, but communicated to the consultant, is used to review the design. Finally, the map provided the resource necessary to develop a tool that could be deployed in industry without disrupting the current process i.e. the tool will support and not hinder current practice. For example, the map enabled the researcher to ensure that the information required by the tool will be available at the stages in the design process that the tool is to be used. The BeIM tool can be
9 E. Voss et al. / A BPMN-based process map for the design and construction of façades 25 Fig. 3. Map v1.1, Portion of activity A1.5 expanded to show sub-activities A1.5.1a, A1.5.1b and A1.5.2 and the information required and produced during these activities.
10 26 E. Voss et al. / A BPMN-based process map for the design and construction of façades employed from activity A1.5, when the consultant has the Appointment Brief which documents the proposed panelisation scheme for the consultant to review. However, it is clear that the panelisation scheme becomes more detailed during the design phases so the BeIM tool must be able to handle a range of levels of scheme detail Research case study 2 The second case study used the process map to develop a whole-life value (WLV) based facade design and optimisation tool. The optimisation tool is developed for early design stage. It is accounts for the three major design objective values: (a) functional value (indoor environment quality, structural serviceability and safety, and durability); (b) financial value (initial capital cost, operating cost, replacement cost, and disposal cost); (c) environmental sustainability value (resources consumption and emission to ecosystem). The evaluation of the three objective values is performed using a simulation engine consisting of 3rd party software and specially developed MATLAB scripts. This optimisation tool is still under-development, and some preliminary results can be found in Jin et al. (2011, 2013). The BPMN Façade Process Map was used: (1) to assess whether the design optimisation tool is compatible with the current façade design process, i.e. whether the information available at early façade design stage is sufficient to run the design optimisation tool and whether the outputs from the design optimisation tool provide sufficient information for the subsequent design stages, and; (2) to identify how the current façade design process captured in the process maps could be modified to make better use of the design optimisation tool. The Façade Consultant swim lane encompassing activity A2 and activity A3 (Fig. 2) is relevant in this case. According to activity A2 (shown in Fig. 4) of the process map, the thermal performance criteria (e.g., U-value and g-value) are provided by the building services engineers for activity A2.X when initial thermal performance calculations are carried out by façade consultants to identify façade options that satisfy these criteria. This map shows that this activity is iterated until the proposed design satisfies the requirements set by both building services engineers and façade consultants. The building energy simulation module in the design optimisation tool can be deployed here, however, it performs a multiobjective optimisation i.e. the two tasks performed by the building services engineers and the façade consultants are considered simultaneously rather than separately. The process map indicates that all other input variables and constraints required for the optimisation tool (e.g. building geometry, location, orientation, plant size and plant type will be available at this stage from the RIBA (Royal Institute of British Architects) Stage C report. The output from the optimisation tool will also be timely as it can be included in the RIBA Stage D report. Therefore, the WLV façade design optimisation tool is partly compatible with the current design process and the process map successfully identified a problem that would arise when using the optimisation on real-world projects unless changes are made to the optimisation tool or to the current design process. A similar process was undertaken to assess the compatibility of the optimisation tool with the Structural analysis (activity A3.1) and detailed thermal analysis (activity A3.2), but are not reported in detail here for brevity. This showed that the inputs and outputs for the design optimisation tool are compatible with the current design process. 4. Conclusions and further work This work included a theoretical and a practical evaluation of two candidate process mapping notations from which BuildingSMART-Business Process Mapping Notation emerged as the more suitable
11 E. Voss et al. / A BPMN-based process map for the design and construction of façades 27 Fig. 4. Map v1.1, Portion of Activity A2 expanded showing the information required and produced during Initial Thermal Performance Calculations. notation for the façades sector. The theoretical evaluation, using the characteristics of modelling notations, indicated that the BPMN was more suitable than the IDEF0 notation to model the façade design and construction process. The practical evaluation, through use of the process map in interviews with construction industry members, concludes that the notation can represent a sufficient number of system features, and is sufficient comprehensible to enable rapid verification through industry consultation. This paper also presented the first ever detailed BPMN-based process map of the whole facade design-construction process from commencement of façade consultant and contractor participation to the end of their involvement. This map combines previous mapping efforts and recent developments in this sector elicited from industry. The map is intended as a research tool that captures existing construction practices thereby providing the research community with an increased understanding of the construction industry and a basis for the development of design theories. The full map v1.1 is freely available to view through the gft website (gft, 2012). On average version 1.1 of the map successfully captured 85% of the processes undertaken in each of the four real façade projects used in the verification step interviews. However, the sample size is likely to be too small to make significant further generalisations. The verification step identified
12 28 E. Voss et al. / A BPMN-based process map for the design and construction of façades some inaccuracies in the map that are being addressed at the time of writing to produce version v1.2, however, further testing will be required to verify the modifications. In addition, the map is limited by the sample size in both the map construction and map verification steps. In particular, the verification step (step 5), was limited to participants from façade consulting firms and none from contracting firms. This is likely to cause the design stages of the map to be more detailed and accurate than the construction stages. Furthermore, the map has been produced from the perspective of the façade consultant and façade sub-contractor roles. This limits the map s documentation of interaction of the core façade design and construction team with other project roles, for example the structural engineer. Both of these issues could be addressed through further development work, but currently this is not planned. Finally, the selection process for the notation deliberately neglected ability to represent process evolution. Therefore if the map is used in future research to consider ongoing modifications of processes, further work would be required to verify the suitability of the notation. The process map was successfully trialled in two independent research projects that involve the development of knowledge-based systems for the facades sector. The map was found to be very useful for assessing the interaction between the proposed knowledge-based system and the current façade design-construction processes. The process map was successfully used in case study one to detect the presence of non-project specific actor knowledge throughout the design process, thereby assessing whether Knowledge Based technologies would be effective. The process map was used successfully in the second case study to verify the availability of information required for the proposed design optimisation tool. In this latter case, the use of the process map highlighted a shortcoming in the current division of scope and responsibility between designers that may inhibit façade design optimisation. Acknowledgments Thanks are due to Focchi Ltd, Permasteelisa UK Ltd, and the Façade Team at Ramboll UK Ltd for their input into the map construction phases. Additional thanks are due to WSP Group, Arup, Newtechnic and Wintech for their contribution to the map verification phase. We would also like to acknowledge Ramboll UK Ltd and the EPSRC for funding this research project. References Agbasi, E., Mcwilliams, R., Stevens, W., Stapleton, J., Anumba, C. J., & Gibb, A. (2003). CIMclad, RAIS Report, Organisational-level issues bearing on CIM implementation: Facade Engineer s Perspectives. Whitby Bird and Partners Report. Aouad, G., Cooper, R., Kagioglou, M., & Sexton, M. (1999). The development of a process map for the construction sector. In CIB Working Groups W65/W55. South Africa. Austin, S., Baldwin, A., Li, B., & Waskett, P. (1999). Analytical design planning technique: A model of the detailed building design process. Design Studies, 20(3), BuildingSmart. (2008). Information Delivery Manual - Overview. Retrieved July 25, 2010, from Dawood, N. (2002). Development of automated communication of system for managing site information using internet technology. Automation in Construction, 11(5), doi: /s (01) Eastman, C., Lee, G., & Sacks, R. (2002). A New Formal and Analytical Approach to Modeling Engineering Project Information Processes. In CIB W78 (pp ), Aarhus, Denmark. Eastman, C. M., Jeong, Y.-S., Sacks, R., & Kaner, I. (2010). Exchange Model and Exchange Object Concepts for Implementation of National BIM Standards. Journal of Computing in Civil Engineering, 24(1), 25. doi: /(asce) (2010)24:1(25) Eastman, C., Sacks, R., & Lee, G. (2003). Development and implementation of advanced IT in the North American precast concrete industry. Precast Concrete, 1-16.
13 E. Voss et al. / A BPMN-based process map for the design and construction of façades 29 gft (2012). Glass and facade technology research group. Retrieved from Gray, C., & Al-Bizri, S. (2007). Modelling trade contractor information production. Architectural Engineering and Design Management, 3(1), IDEF (2010). Retrieved September 22, 2011, from Jin, Q., Overend, M., & Thompson, P. (2011). A whole-life value assessment and optimisation model for high-performance glazed facades. In Proceedings of International conference of Building Simulation, Sydney, Australia. Jin, Q., & Overend, M. (2013). A prototype whole-life value optimization tool for facade design. Journal of Building Performance Simulation. doi: / Kagioglou, M., Cooper, R., Aouad, G., & Sexton, M. (2000). Rethinking construction: The generic design and construction process protocol. Engineering Construction and Architectural Management, 7(2), doi: /j x x Kalian, A., Watson, A., Agbasi, E., Anumba, C., & Gibb, A. (2004). Modelling the building cladding attainment processes. Business Process Management Journal, 10(6), Karhu, V. (1997). Product Model Based Design of Precast Facades, Royal Institute of Technology, Stockholm, Sweden. Karhu, V. (2001). A generic construction process modelling method, Royal Institute of Technology, Stockholm, Sweden. Karsai, P. (1997). Facade Procurement: The role of the facade consultant. In ICBEST 97, Bath, UK. Klein, T. (2013). Integral Facade Construction. Rotterdam: Design: Sirene Ontwerpers. doi: Klotz, L., Horman, M., Bi, H. H., & Bechtel, J. (2008). The impact of process mapping on transparency. International Journal of Productivity and Performance Management, 57(8), Kochikar, V. P., & Narendran, T. T. (1994). On using abstract models for analysis of flexible manufacturing systems. International Journal of Production Research, 32(10), doi: / Koskela, L. (1995). On foundations of construction process modelling. In CIB Workshop on Computers and Information in Construction. Stanford, California. Laitinen. (1999). Model based construction process management. Durability of Building Materials and Components, 8, Pavitt, T. C., & Gibb, A. G. F. (1999). Managing organizational interfaces in the cladding supply chain: Initial Results From Expert Interviews. In W. Hughes (Ed.), 15th Annual ARCOM Conference, 2, Liverpool, UK. Pavitt, T. C., & Gibb, A.G.F. (2003). Interface management within construction: In Particular, Building Facade. Journal of Construction Engineering and Management, 129(1), 8. doi: /(asce) (2003)129:1(8) Pingtserng, H. (2004). Developing an activity-based knowledge management system for contractors. Automation in Construction, 13(6), doi: /j.autcon Tzortzopoulos, P., Sexton, M., & Cooper, R. (2005). Process models implementation in the construction industry: A literature synthesis. Engineering, Construction and Architectural Management, 12(5), Vaz, D., Al Bizri, S., & Gray, C. (2008). The management of the design of modern curtain wall cladding systems. In ARCOM 24th Annual Conference (pp ). Cardiff, UK. Voss, E., & Overend, M. (2012). A tool that combines building information modeling and knowledge based engineering to assess Façade manufacturability. In ABS 2012, Graz. Wix, J., & Karlshoj, J. (2010). BuildingSMART: Information Delivery Manual Guide to Components and Development Methods. Wynn. (2007). Model-based approaches to support process improvement in complex product development. University of Cambridge.
A Tool that Combines Building Information Modeling and Knowledge Based Engineering to Assess Façade Manufacturability
Prof. Dipl.-Ing. Dr.nat.techn. Oliver Englhardt Institute of Building Construction Graz University of Technology Copyright with the authors. All rights reserved. A Tool that Combines Building Information
DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM
DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM Joanna Poon, Keith Potts and Patricia Cooper School of Engineering and the Built Environment University of Wolverhampton Wolverhampton WV1 1SB UK
RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.
RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as
A Process is Not Just a Flowchart (or a BPMN model)
A Process is Not Just a Flowchart (or a BPMN model) The two methods of representing process designs that I see most frequently are process drawings (typically in Microsoft Visio) and BPMN models (and often
The Integrated Design Process
The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3 7EH,
CDC UNIFIED PROCESS PRACTICES GUIDE
Purpose The purpose of this document is to provide guidance on the practice of Modeling and to describe the practice overview, requirements, best practices, activities, and key terms related to these requirements.
CHAPTER 1: INTRODUCTION TO RAPID APPLICATION DEVELOPMENT (RAD)
CHAPTER 1: INTRODUCTION TO RAPID APPLICATION DEVELOPMENT (RAD) 1. INTRODUCTIONS RAD refers to a development life cycle designed Compare to traditional life cycle it is Faster development with higher quality
aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608
aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE
Business Process Modeling Information Systems in Industry (372-1-4207 )
Business Process Modeling Information Systems in Industry (372-1-4207 ) Arnon Sturm The material of this presentation is adopted from various people including:, Pnina Soffer, Iris Reinhartz-Berger 1 Outline
A Summary of Principles of Enterprise Architecture of Public Entities
A Summary of Principles of Enterprise Architecture of Public Entities Version: 1.0 17 June 2015 Introduction The document presents a summarized version of the principles of enterprise architecture of public
Quick Guide Business Process Modeling Notation (BPMN)
Quick Guide Business Process Modeling Notation (BPMN) IDM Technical Team January 2007 Quick Guide: BPMN 2 of 14 The scope of this document is to provide a quick guide to the concepts and usage of the Business
Automated construction schedule creation using project information model
Automated construction schedule creation using project information model Aleš Mrkela Faculty of civil engineering, University of Maribor, Maribor, Slovenia Danijel Rebolj Faculty of civil engineering,
Design without compromise. Autodesk Revit. Architecture 2010
Design without compromise. Autodesk Revit Architecture 2010 BIM Simply a Better Way of Working Deliver projects faster, more economically, and with enhanced potential for reduced environmental impact.
Introduction to Systems Analysis and Design
Introduction to Systems Analysis and Design What is a System? A system is a set of interrelated components that function together to achieve a common goal. The components of a system are called subsystems.
Introduction to BPMN
Stephen A. White, IBM Corporation Abstract This paper is intended to provide a high-level overview and introduction to the Business Process Modeling Notation (BPMN). The context and general uses for BPMN
MEASURING SOFTWARE FUNCTIONAL SIZE FROM BUSINESS PROCESS MODELS
International Journal of Software Engineering and Knowledge Engineering World Scientific Publishing Company MEASURING SOFTWARE FUNCTIONAL SIZE FROM BUSINESS PROCESS MODELS CARLOS MONSALVE CIDIS-FIEC, Escuela
To introduce software process models To describe three generic process models and when they may be used
Software Processes Objectives To introduce software process models To describe three generic process models and when they may be used To describe outline process models for requirements engineering, software
Background: Business Value of Enterprise Architecture TOGAF Architectures and the Business Services Architecture
Business Business Services Services and Enterprise and Enterprise This Workshop Two parts Background: Business Value of Enterprise TOGAF s and the Business Services We will use the key steps, methods and
Ming Sun 1, Ghassan Aouad, Nick Bakis, Stuart Birchall, William Swan
The ASCE 8th International Conference on Computing in Civil and Building EngineeringStandford University California, USA, August 14-17, 2000, pp130-137 Integrated Information Management and Exchange for
Building Information Modelling and collaborative construction
Building Information Modelling and collaborative construction How technology is transforming construction For today s CEO in the construction industry, the drive for faster, more efficient delivery of
Software Engineering. Software Processes. Based on Software Engineering, 7 th Edition by Ian Sommerville
Software Engineering Software Processes Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To introduce software process models To describe three generic process models and when
Program Advisory Committee (PAC) Agenda. December 14, 2011 9:00am 3:00pm PST. Agenda Items:
BOULDER NASHVILLE SAN FRANCISCO KANSAS CITY SPRINGFIELD, MO FAIRFAX, VA 2540 Frontier Avenue, Suite 100 Boulder, Colorado 80301 303.444.4149 SUBJECT: Date: Program Advisory Committee (PAC) Agenda December
Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering
Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty
Value Creation by Process-Oriented Project Management
558 CIB World Building Congress 2007 CIB2007-309 Value Creation by Process-Oriented Project Management W. Geijtenbeek 2, P. Geradts 1, B. van Eekelen 2, H. Kleine 2, R. Favié 2 and G.J. Maas 2 ABSTRACT
Benefits and Barriers of Building Information Modelling
Benefits and Barriers of Building Information Modelling Han Yan and Peter Damian Department of Civil and Building Engineering, Loughborough University, Abstract: Building Information Modelling (BIM) as
Systems Selection Enclosure Systems Material Selection Assessment and Mitigation
Return to Curriculum Home CES Home Find an AIA/CES Registered Course Self Report a Learning Activity MATERIALS AND METHODS To develop professionally in Practice with a focus on sustainable design, you
Tekla Structures More than a detailing tool. Precast concrete
Tekla Structures More than a detailing tool Precast concrete Much more Than a detailing tool a Tekla Structures is much more than design and detailing software: it is the most accurate and comprehensive
STSG Methodologies and Support Structure
STSG Methodologies and Support Structure STSG Application Life Cycle Management STSG utilizes comprehensive lifecycle tools that are fully integrated and provide capabilities for most of the roles in its
TECH. Requirements. Why are requirements important? The Requirements Process REQUIREMENTS ELICITATION AND ANALYSIS. Requirements vs.
CH04 Capturing the Requirements Understanding what the customers and users expect the system to do * The Requirements Process * Types of Requirements * Characteristics of Requirements * How to Express
Space project management
ECSS-M-ST-80C Space project management Risk management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of ECSS Standards
Quantification and Traceability of Requirements
Quantification and Traceability of Requirements Gyrd Norvoll Master of Science in Computer Science Submission date: May 2007 Supervisor: Tor Stålhane, IDI Norwegian University of Science and Technology
ACR+ position paper on the Circular Economy Package 2.0
Brussels, March 2016 ACR+ position paper on the Circular Economy Package 2.0 ACR+ welcomes the European Commission s Circular Economy Package 2.0 and supports once more the efforts to make all actors of
Development of an Ontology for the Document Management Systems for Construction
Development of an Ontology for the Document Management Systems for Construction Alba Fuertes a,1, Núria Forcada a, Miquel Casals a, Marta Gangolells a and Xavier Roca a a Construction Engineering Department.
A Methodology for Variability Reduction in Manufacturing Cost Estimating in the Automotive Industry based on Design Features
A Methodology for Variability Reduction in Manufacturing Cost Estimating in the Automotive Industry based on Design Features F. J. Romero Rojo, R. Roy, E. Shehab Decision Engineering Centre, Manufacturing
BUILDING INFORMATION MODELLING. The Designer. CIC East and IDBE. David Hymas
BUILDING INFORMATION MODELLING The Designer CIC East and IDBE David Hymas David Hymas Technical Director - BNI Building Services Engineer Building Services BIM Champion for MM Mott MacDonald 4 Years 18
Performance Management Systems: Conceptual Modeling
2011 International Conference on Economics and Business Information IPEDR vol.9 (2011) (2011) IACSIT Press, Bangkok, Thailand Performance Management Systems: Conceptual Modeling Dmitry Isaev Business Analytics
BIM-BASED KNOWLEDGE MANAGEMENT FOR BUILDING MAINTENANCE
BIM-BASED KNOWLEDGE MANAGEMENT FOR BUILDING MAINTENANCE Abdulkareem Almarshad, MSc. PhD student, [email protected] School of the Built Environment, Heriot-Watt University, Edinburgh, UK Ibrahim Motawa, PhD.
Requirements Analysis Concepts & Principles. Instructor: Dr. Jerry Gao
Requirements Analysis Concepts & Principles Instructor: Dr. Jerry Gao Requirements Analysis Concepts and Principles - Requirements Analysis - Communication Techniques - Initiating the Process - Facilitated
Unit 1 Learning Objectives
Fundamentals: Software Engineering Dr. Rami Bahsoon School of Computer Science The University Of Birmingham [email protected] www.cs.bham.ac.uk/~rzb Office 112 Y9- Computer Science Unit 1. Introduction
MWA Project. Configuration Management Plan
Document No.: 46-01002 Revision: 0004 Date: 22-Oct-2009 MWA Project Configuration Management Plan MWA Project MWA Consortium Copyright 2009, MWA Consortium. All Rights Reserved. Control Status Document
Conceptual Design and Analysis in Autodesk Revit Architecture 2011
AUTODESK REVIT ARCHITECTURE 2011 Conceptual Design and Analysis in Autodesk Revit Architecture 2011 In this white paper, CASE Design, a design technology consultancy based in New York City, describes how
Ontology-Based Semantic Modeling of Safety Management Knowledge
2254 Ontology-Based Semantic Modeling of Safety Management Knowledge Sijie Zhang 1, Frank Boukamp 2 and Jochen Teizer 3 1 Ph.D. Candidate, School of Civil and Environmental Engineering, Georgia Institute
Performing Early Feasibility Studies of Software Development Projects Using Business Process Models
Performing Early Feasibility Studies of Software Development Projects Using Business Process Models Ayman A. Issa, Faisal A. Abu Rub ABSTRACT A new approach to perform feasibility studies using business
Nr.: Fakultät für Informatik Otto-von-Guericke-Universität Magdeburg
Nr.: Fakultät für Informatik Otto-von-Guericke-Universität Magdeburg Nr.: Fakultät für Informatik Otto-von-Guericke-Universität Magdeburg Impressum ( 5 TMG) Herausgeber: Otto-von-Guericke-Universität Magdeburg
Product data model for PLM system
roduct data model for LM system Li Yumei, Wan Li, Xiong Tifan (National CAD Support Software Engineering Research Center, Huazhong University of Science and Technology, Wuhan 430074) Abstract: roduct lifecycle
Masters of Science in Software & Information Systems
Masters of Science in Software & Information Systems To be developed and delivered in conjunction with Regis University, School for Professional Studies Object Oriented Design Table of Contents January
Applying 4+1 View Architecture with UML 2. White Paper
Applying 4+1 View Architecture with UML 2 White Paper Copyright 2007 FCGSS, all rights reserved. www.fcgss.com Introduction Unified Modeling Language (UML) has been available since 1997, and UML 2 was
Requirements Analysis through Viewpoints Oriented Requirements Model (VORD)
Requirements Analysis through Viewpoints Oriented Requirements Model (VORD) Ahmed M. Salem Computer Science Department California State University, Sacramento Sacramento, CA 95819 USA Email: [email protected]
Case Study: Vitamix. Improving strategic business integration using IT service management practices and technology
Improving strategic business integration using IT service management practices and technology Publication Date: 17 Sep 2014 Product code: IT0022-000180 Adam Holtby Summary Catalyst For Vitamix, a key driver
Design and Analysis of Automobiles Manufacturing System Based on Simulation Model
Design and Analysis of Automobiles Manufacturing System Based on Simulation Model Razman Bin Mat Tahar & Ali Asghar J.Adham Faculty of Technology Management, University Malaysia Pahang, Kuantan 26300,
Procurement requirements for reducing waste and using resources efficiently
Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction
Developing Business Architecture with TOGAF
Developing Business Architecture with TOGAF Building Business Capability 2013 Las Vegas, NV Armstrong Process Group, Inc. www.aprocessgroup.com Objectives Introduce The Open Group Architecture Framework
Process Modelling Notations
Process Modelling Notations Event-driven Process Chains (EPC) Business Process Modelling Notation (BPMN) Workflow Management Agenda Motivation for BPM EPC BPMN Case Study 1 Why Business Process Modelling
Cisco and VMware Virtualization Planning and Design Service
Cisco and VMware Virtualization Planning and Design Service Create an End-to-End Virtualization Strategy with Combined Services from Cisco and VMware Service Overview A Collaborative Approach to Virtualization
The role of integrated requirements management in software delivery.
Software development White paper October 2007 The role of integrated requirements Jim Heumann, requirements evangelist, IBM Rational 2 Contents 2 Introduction 2 What is integrated requirements management?
University of Cambridge: Programme Specifications MASTER OF STUDIES IN INTERDISCIPLINARY DESIGN FOR THE BUILT ENVIRONMENT
University of Cambridge: Programme Specifications Every effort has been made to ensure the accuracy of the information in this programme specification. Programme specifications are produced and then reviewed
11 Tips to make the requirements definition process more effective and results more usable
1 11 Tips to make the s definition process more effective and results more usable This article discusses what I believe are the key techniques for making s definition process repeatable from project to
Chap 1. Introduction to Software Architecture
Chap 1. Introduction to Software Architecture 1. Introduction 2. IEEE Recommended Practice for Architecture Modeling 3. Architecture Description Language: the UML 4. The Rational Unified Process (RUP)
Modeling Guidelines Manual
Modeling Guidelines Manual [Insert company name here] July 2014 Author: John Doe [email protected] Page 1 of 22 Table of Contents 1. Introduction... 3 2. Business Process Management (BPM)... 4 2.1.
BCS Foundation Certificate in Business Analysis Syllabus. Version 3.8 July 2016
BCS Foundation Certificate in Business Analysis Syllabus Version 3.8 July 2016 Copyright BCS 2015 BA Foundation Syllabus Change History Any changes made to the syllabus shall be clearly documented with
Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad
Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad Debasis Sarkar 1 & Raj Modi 2 Associate Professor and Head, Department of Civil Engineering, School of Technology,
Building Information Modeling Execution Planning Guide
1 EXECUTIVE SUMMARY A Building Information Model (BIM) is a digital representation of physical and functional characteristics of a facility. 1 To successfully implement BIM, a project team must perform
The Business Process Model
The Business Process Model by Sparx Systems All material Sparx Systems 2007 Sparx Systems 2007 Page: 1 Table of Contents INTRODUCTION...3 BUSINESS PROCESS MODELING NOTATION (BPMN)...4 FLOW ELEMENTS...4
Issues in Information Systems Volume 15, Issue I, pp. 52-60, 2014
ORGANIZATIONALLY AGNOSTIC BUSINESS MODELING: HOW TO MAKE BUSINESS ARCHITECTURE ADAPTABLE TO ORGANIZATIONAL CHANGE Carlos E. Martinez, The MITRE Corporation, [email protected] Sheila A. Cane, The MITRE
Qlik UKI Consulting Services Catalogue
Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction
MWA Project. Configuration Management Plan
Document No.: MWA-XXX-XXX Revision: 0002 Date: 07-OCT-2009 MWA Project Configuration Management Plan MWA Project MWA Consortium Copyright 2009, MWA Consortium. All Rights Reserved. Control Status Document
BUSINESS RULES AS PART OF INFORMATION SYSTEMS LIFE CYCLE: POSSIBLE SCENARIOS Kestutis Kapocius 1,2,3, Gintautas Garsva 1,2,4
International Conference 20th EURO Mini Conference Continuous Optimization and Knowledge-Based Technologies (EurOPT-2008) May 20 23, 2008, Neringa, LITHUANIA ISBN 978-9955-28-283-9 L. Sakalauskas, G.W.
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING
White Paper: Conceptual Engineering
White Paper: Conceptual Engineering CAD Tools that Promote Invention Executive Summary Today s mechanical engineers are challenged to produce new products in less time than ever before. Over the past ten
Chapter 4 Software Lifecycle and Performance Analysis
Chapter 4 Software Lifecycle and Performance Analysis This chapter is aimed at illustrating performance modeling and analysis issues within the software lifecycle. After having introduced software and
REQUIREMENTS SPECIFICATION AND MANAGEMENT. Requirements Analysis and Specification
REQUIREMENTS SPECIFICATION AND MANAGEMENT In this note we give the requirements process in a software organization, a template for the requirements document, and the process to manage changes to the requirements.
GENERIC STANDARDS CUSTOMER RELATIONSHIPS FURTHER EXCELLENCE CUSTOMISED SOLUTIONS INDUSTRY STANDARDS TRAINING SERVICES THE ROUTE TO
PROCESSES SUPPLY CHAIN SKILLED TALENT CUSTOMER RELATIONSHIPS FURTHER EXCELLENCE GENERIC STANDARDS INDUSTRY STANDARDS CUSTOMISED SOLUTIONS TRAINING SERVICES THE ROUTE TO ISO 9001:2015 FOREWORD The purpose
Component-based Development Process and Component Lifecycle Ivica Crnkovic 1, Stig Larsson 2, Michel Chaudron 3
Component-based Development Process and Component Lifecycle Ivica Crnkovic 1, Stig Larsson 2, Michel Chaudron 3 1 Mälardalen University, Västerås, Sweden, [email protected] 2 ABB Corporate Research,
Partnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
Lecture 9: Requirements Modelling
A little refresher: What are we modelling? Lecture 9: Requirements Modelling Requirements; Systems; Systems Thinking Role of Modelling in RE Why modelling is important Limitations of modelling Brief overview
BUILDING INFORMATION MODEL (BIM) PROTOCOL
BUILDING INFORMATION MODEL (BIM) PROTOCOL 2013 Standard Protocol for use in projects using Building Information Models The CIC acknowledges the technical input and leadership provided by the BIM Task Group
CS 389 Software Engineering. Lecture 2 Chapter 2 Software Processes. Adapted from: Chap 1. Sommerville 9 th ed. Chap 1. Pressman 6 th ed.
CS 389 Software Engineering Lecture 2 Chapter 2 Software Processes Adapted from: Chap 1. Sommerville 9 th ed. Chap 1. Pressman 6 th ed. Topics covered Software process models Process activities Coping
Improving Traceability of Requirements Through Qualitative Data Analysis
Improving Traceability of Requirements Through Qualitative Data Analysis Andreas Kaufmann, Dirk Riehle Open Source Research Group, Computer Science Department Friedrich-Alexander University Erlangen Nürnberg
MASTER OF ARTS MANAGEMENT
The Master of Arts Management degree is taught at the world renowned Sydney Opera House. MASTER OF ARTS MANAGEMENT COURSE STRUCTURE To become eligible to graduate with a Master of Arts Management degree,
STEPS IN THEATRE PROJECT PLANNING
Janis A. Barlow & Associates Research, Planning and Management Consultants Specializing in Theatre since 1981 STEPS IN THEATRE PROJECT PLANNING Janis A. Barlow & Associates www.barlowandassociates.com
Software Processes. The software process. Generic software process models. Waterfall model. Waterfall model phases
Software Processes CSC 221 Introduction to Software Engineering software processes extract from Sommerville s chapter 3 slides Alan Dix Coherent sets of activities for specifying, designing, implementing
Unit I. Introduction
Unit I Introduction Product Life Cycles Products also have life cycles The Systems Development Life Cycle (SDLC) is a framework for describing the phases involved in developing and maintaining information
Opening the Bonnet. Prof Darren Woolf WYSINWYG 1
Opening the Bonnet Prof Darren Woolf WYSINWYG 1 WYSINWYG What You See Is NOT What You Get: Looking inside the Pandora s Box Prof Darren Woolf WYSINWYG 2 WYSIWYG implies a user interface that allows the
Space Project Management
EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space Project Management Configuration Management Secretariat ESA ESTEC Requirements & Standards Division Noordwijk, The Netherlands Published by: Price:
What is effective Design Management?
What is effective Design Management? Design Management is becoming increasingly recognised as critical to the success of complex construction projects. However, the role of the Design Manager is poorly
Chapter 3. Technology review. 3.1. Introduction
Technology review Chapter 3 3.1. Introduction Previous chapter covers detail description about problem domain. In this chapter I will discuss the technologies currently available to solve a problem in
Exhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015
Applications... 3 1. Programmer Analyst... 3 2. Programmer... 5 3. Software Test Analyst... 6 4. Technical Writer... 9 5. Business Analyst... 10 6. System Analyst... 12 7. Software Solutions Architect...
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Guide to CQI Qualifications for learners
Guide to CQI Qualifications for learners CQI Qualifications and Professional Recognition Quality management is about improving organisational performance in delivering product and service that meet customer
A UML Introduction Tutorial
A UML Introduction Tutorial 1/27/08 9:55 PM A UML Introduction Tutorial In this tutorial you will learn about the fundamentals of object oriented modelling, the Unified Modelling Language and the software
Test Automation Architectures: Planning for Test Automation
Test Automation Architectures: Planning for Test Automation Douglas Hoffman Software Quality Methods, LLC. 24646 Heather Heights Place Saratoga, California 95070-9710 Phone 408-741-4830 Fax 408-867-4550
Application of the analytical design planning technique to construction project management
Loughborough University Institutional Repository Application of the analytical design planning technique to construction project management This item was submitted to Loughborough University's Institutional