The Integrated Design Process
|
|
|
- Charleen Nash
- 9 years ago
- Views:
Transcription
1 The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000 program. This program was designed in 1993 as a small demonstration of very high levels of performance, and its technical requirements cover energy performance, environmental impacts, indoor environment, functionality and a range of other related parameters. The ambitious performance goals of the program led its managers to believe that the incremental costs for design and construction would be substantial, and provision was made for support of incremental costs in both the design and construction phase. However, after the first six projects were designed and two of them had been completed, it was found that that incremental capital costs were less than expected, partly due to the fact that designers used less sophisticated and expensive technologies than anticipated. Despite this, the projects reached the required performance targets. The designers all agreed that application of the design process required by the C-2000 program was the main reason why high levels of performance could still be reached. It also appeared that most of the benefit of intervention was achieved during the early stages of the design process. The C-2000 process is now called the Integrated Design Process (IDP), and most project interventions are now focused on providing advice on the design process at the very early stage of design. Eight projects have been constructed on this basis, and all have achieved the C-2000 performance requirements, or have come very close, and capital costs have been either slightly above or slightly below base budgets. The most hopeful sign that the IDP approach is taking root is that several owners have subsequently used the same process for buildings that have not benefitted from any subsidy. The Conventional Design Process In order to understand what the IDP is, it is useful to first characterize the more conventional design process. The process often begins with the architect and the client agreeing on a design concept, consisting of a general massing scheme, orientation, fenestration and, usually, the general exterior appearance as determined by these characteristics as well as by basic materials. The mechanical and electrical engineers are then asked to implement the design and to suggest appropriate systems. Although this is vastly oversimplified, such a process is one that is followed by the large majority of general-purpose design firms, and it generally limits the achievable performance to conventional levels. The traditional design process has a mainly linear structure due to the successive contributions of the members of the design team. There is a limited possibility of optimization during the traditional process, while optimization in the later stages of the process is often troublesome or even impossible. For example, little advantage may be taken of passive solar potential, there may be excessive exposure to high solar gain during the summer, and poor daylighting and discomfort for the occupants. All these potential outcomes reflect a design process that appears to be quick and simple, but actual results are often high operating costs and an interior environment that is sub-standard; and these factors in turn may greatly reduce the long-term rental or asset value of a property. Since the conventional design process usually does not involve computer simulations of predicted energy performance, the resulting poor performance and high operating costs will most often come as a surprise to the owners, operators or users. 1
2 If the engineers involved in such a process are clever, they may suggest advanced, highperformance heating, cooling and lighting systems, but their inclusion at a late stage in the design process will result in only marginal performance increases, combined with considerable capital cost increases. The underlying cause is that the introduction of high-performance systems late in the design process cannot overcome the handicaps imposed by initial incompatible or otherwise poor design decisions. The Integrated Design Process The Integrated Design Process has impacts on the design team that differentiate it from a conventional design process in several respects. The client takes a more active role than usual; the architect becomes a team leader rather than the sole form-giver; and the structural, mechanical and electrical engineers take on active roles at early design stages. The team always includes an energy specialist and, in some cases, an independent Design Facilitator. The IDP process contains no elements that are radically new, but integrates well-proven approaches into a systematic total process. The skills and experience of mechanical and electrical engineers, and those of more specialized consultants, can be integrated at the concept design level from the very beginning of the design process. When carried out in a spirit of cooperation among key actors, this results in a design that is highly efficient with minimal, and sometimes zero, incremental capital costs, along with reduced long-term operating and maintenance costs. The benefits of the IDP process are not limited to the improvement of environmental performance. Experience shows that the open inter-disciplinary discussion and synergistic approach will often lead to improvements in the functional program, in the selection of structural systems and in architectural expression. The IDP process is based on the well-proven observation that changes and improvements in any design process are relatively easy to make at the beginning of the process, but become increasingly difficult and disruptive as the process unfolds. Although this may seem obvious, it is a fact that most clients and designers have not followed up on the implications. As well, the existence of a defined roadmap gives credence and form to the process, making it easier to promote and implement. Typical IDP elements include the following: inter-disciplinary work between architects, engineers, costing specialists, operations people and other relevant actors right from the beginning of the design process; discussion of the relative importance of various performance issues and the establishment of a consensus on this matter between client and designers; budget restrictions applied at the whole-building level, with no strict separation of budgets for individual building systems, such as HVAC or the building structure. This reflects the experience that extra expenditures for one system, e.g. for sun shading devices, may reduce costs in another systems, e,g, capital and operating costs for a cooling system; the addition of a specialist in the field of energy engineering and energy simulation; testing of various design assumptions through the use of energy simulations throughout the process, to provide relatively objective information on this key aspect of performance; the addition of subject specialists (e.g. for daylighting, thermal storage, comfort, materials selection etc.) for short consultations with the design team; clear articulation of performance targets and strategies, to be updated throughout the process by the design team; and 2
3 in some cases, a Design Facilitator is added to the team to raise performance issues throughout the process and ensure specialist inputs as required. Based on experience in Europe and North America, an IDP is especially characterized by a series of design loops per stage of the design process, separated by transitions with decisions about milestones. In each of the design loops the design team members relevant for that stage participate in the process. The design process itself emphasizes the following broad sequence. 1. Establish performance targets for a broad range of parameters, and develop preliminary strategies to achieve these targets. This sounds obvious, but in the context of an integrated design team approach it can bring engineering skills and perspectives to bear at the concept design stage, thereby helping the owner and architect to avoid committing to a sub-optimal design solution. 2. Minimize heating and cooling loads and maximize daylighting potential through orientation, building configuration, an efficient building envelope and careful consideration of the amount, type and location of fenestration. 3. Meet heating and cooling loads through the maximum use of solar and other renewable technologies and the use of efficient HVAC systems, while maintaining performance targets for indoor air quality, thermal comfort, illumination levels and quality, and noise control. 4. Iterate the process to produce at least two, and preferably three, concept design alternatives, using energy simulations as a test of progress, and then select the most promising of these for further development. The process diagram and the outline of IDP steps shown in Appendices 1 and 2, give some idea of how IDP may be applied to a typical design project. Future applications of IDP One of the interesting lessons of using IDP is that, unlike many other design support methods or systems, it is applicable to a wide range of situations and building types. Thus, even though IDP was developed for a few building types and assumed new construction, the approach has now been applied to a wide variety of building types and to renovation projects. We foresee a wide application of the IDP around the world. A generic international version has been developed within Task 23, a working group of the International Energy Agency. What is needed now are the resources to develop supporting software and to develop an educational campaign for international use, especially to developing countries. Prepared by: Nils Larsson Executive Director International Initiative for a Sustainable Built Environment (iisbe) Ottawa, January 31, 2004 <larsson@ 3
4 Appendix 1: Graphic representation of the IDP Process 4
5 Appendix 2: Generic steps in the IDP Process A. Assess site conditions 01 A01 Assess soil stability and bearing strength 02 A02 Assess the ecological quality of the site 03 A03 If a brownfield site, take steps to remediate conditions 04 A04 Examine soil for presence of radon 05 A05 Identify any features in adjacent properties that may place constraints on the design of the subject building 06 A06 Assess suitability of any existing structure(s) on the site for adaptation to the new uses planned for the site. 07 A07 Identify approximate gross area of existing structure on the site that can be totally or partially re-used. 08 A08 Assess suitability of materials and components in any existing structure(s) on the site for re-use in the new building(s) planned for the site. 09 A09 Prepare a Site Conditions Report B. Examine program; establish performance targets and strategies 10 B01 Determine if the proposed space requirements can be satisfied by renovations instead of new construction. 11 B02 Consider possible impact of location on the transportation requirements of the facility. 12 B03 Assess the capacity of the functional program to support mixed uses and green operations. 13 B04 Confirm client s commitment to supporting measures required for high performance. 14 B05 Develop an initial statement of performance goals, targets and supporting strategies. 15 B07 Ensure that the program is capable of supporting high performance. 16 B07 Review budget and pay-back requirements for compatibility with performance goals. 17 B08 Prepare a Functional Program and Performance Goals Report. C. Assemble the Design Team 18 C01 Ensure that the proposed design team is aware that the project has high-performance goals. 19 C02 Identify and retain design team members with skills and experience related to the program. 20 C03 Ensure that contract conditions do not create a disincentive for the mechanical engineer. 21 C04 If the budget permits, include performance incentive payments in contracts for the principal designers. D. Hold a Design Workshop 22 D01 Develop schematic drawings for a reference or baseline design with minimal performance. 23 D02 Carry out energy simulations for the reference building. 24 D03 Invite design workshop participants, including the client, design team and specialists. 25 D04 At the workshop, table the energy simulations to provide a starting point for discussion. 26 D05 Develop two or three schematic options for improved performance. 27 D06 Hold an open discussion on performance, cost and other implications. 28 D07 Carry on with more detailed development of the most attractive option after the workshop, including preliminary energy simulations or estimates. 29 D08 Add new talent to the design team if necessary. 30 D09 Summarize the results of the workshop in a Design Workshop Report, and distribute to all stakeholders 5
6 E. Consider site development issues 31 E01 Minimize building footprint on site. 32 E02 Minimize loss of solar or daylight potential of adjacent property. 33 E03 Consider measures to minimize impacts on subsurface ecology and aquifers. 34 E04 Develop preliminary landscape plans to provide windbreaks, shading, and to minimize water demand. 35 E05 Ensure that the building will form a positive contribution to the streetscape. 36 E06 Carry out an Environmental Impact Assessment. 37 E07 Summarize site development issues in a Draft Site Impact Plan. F. Develop Concept Design. 38 F01 Finalize performance targets 39 F02 Develop a concept plan, using functional requirements as a starting point. 40 F03 Orient the building to optimize passive solar potential, and relate fenestration requirements to orientation. 41 F04 Establish configuration & floor plate depth to balance daylighting & thermal performance. 42 F05 Consider the possible roles of natural, hybrid or mechanical ventilation systems. 43 F06 Consider whether cooling will be needed. 44 F07 Examine the potential role of renewable energy systems. 45 F08 Examine the most efficient forms of non-renewable heating, cooling and ventilation systems. 46 F09 Determine floor-to-floor heights, taking into account possible future uses. 47 F10 Carry out a first set of detailed energy simulations or energy analysis. 48 F11 Prepare the Concept Design Report. G. Select building structure. 49 G01 Consider column spacing and core position. 50 G02 Consider measures to reduce embodied energy of the structure. 51 G03 Consider thermal storage options using the structure as a heat sink. 52 G04 In residential occupancies, consider appropriate balcony design. 53 G05 Decide on building structure type taking into account the considerations above. H. Develop building envelope design 54 H01 Select basic exterior wall systems. 55 H02 Assign fenestration on each orientation to optimize daylighting and thermal benefits 56 H03 Optimize the daylighting and thermal performance of fenestration. 57 H04 Consider the use of operable windows. 58 H05 Consider measures to reduce the embodied energy of the building envelope. 59 H06 Optimize envelope detailing and thermal performance 60 H07 Carry out a second set of detailed energy simulations J. Develop preliminary lighting and power system design. 61 J01 Develop preliminary lighting system design. 62 J02 Develop preliminary lighting control system. 63 J03 Estimate the power requirements for future tenant and occupant equipment. 64 J04 Optimize the energy efficiency of vertical transportation systems. 65 J05 Develop strategies to shave peak demand. 66 J06 Summarize lighting issues for Comfort and Productivity Performance Plan. 6
7 K. Develop preliminary Ventilation, Heating and Cooling system designs. 67 K01 Develop preliminary ventilation system design. 68 K02 Develop preliminary design for heating central plant. 69 K03 Develop preliminary design for cooling central plant. 70 K04 Consider thermal storage options using mechanical systems. 71 K05 Develop preliminary design for ventilation, heating, and cooling delivery systems. 72 K06 Develop preliminary ventilation, heating and cooling control systems. 73 K07 Complete energy simulations assessing whole building design performance. 74 K08 Summarize HVAC issues for the Comfort and Productivity Performance Plan. 75 K09 Prepare a Design Development Report. L. Select materials. 76 L01 Minimize use of materials or components that rely on scarce material resources. 77 L02 Select materials that balance durability and low embodied energy. 78 L03 Consider re-use of components and recycled materials. 79 L04 Design assemblies and their connections to facilitate future demountability. 80 L05 Select indoor finishing materials to minimize VOC and other emissions. M. Complete design and documentation. 81 M01 Complete site development plan to minimize potable water consumption. 82 M02 Design plumbing and sanitary systems to minimize water consumption. 83 M03 Complete appropriate rain screen and pressure equalization envelope details. 84 M04 Finalize lighting system design. 85 M05 Finalize ventilation, heating, and cooling system designs. 86 M06 Confirm adequate space exists for data and communications systems. 87 M07 Select building energy management control systems. 88 M08 Review the use of materials to minimize waste. 89 M09 Carry out a final set of energy simulations. 90 M10 Produce a final Longevity and Adaptability Plan 91 M11 Prepare a final Life Cycle Cost Report. 92 M12 Produce a final Occupant Comfort and Productivity Plan. N. Develop QA strategies for construction. 93 N01 Develop plan to minimize C&D wastes during construction. 94 N02 Develop Final Site Impact Management Plan. 95 N03 Develop a Final Quality Assurance Plan 96 N04 Develop a Commissioning Plan for all major systems. 97 N05 Prepare the Pre-Construction Report. P. Develop QA strategies for operation. 98 P01 Appoint an owner's Commissioning Agent. 99 P02 Develop a maintenance plan. 100 P03 Develop a Final Environmental Impact Management Plan. 101 P04 Develop lease instruments with tenant incentives to operate space efficiently. 102 P05 Train building staff to operate equipment efficiently. 103 P06 Prepare a Project Completion Report. Q. Monitoring 104 Q01 Owner / Operator to provide reports on operations, maintenance, & utility bills. 105 Q02 Carry out a Post-Occupancy Evaluation (POE) study 7
Systems Selection Enclosure Systems Material Selection Assessment and Mitigation
Return to Curriculum Home CES Home Find an AIA/CES Registered Course Self Report a Learning Activity MATERIALS AND METHODS To develop professionally in Practice with a focus on sustainable design, you
Step 2: Define Project Objectives
Why GREEN Small-scale renovations to large-scale new construction and master planning, owners are embracing sustainable practices in order to lessen their environmental impact and to reduce their operating
Civil Engineering and Architecture (CEA) Detailed Outline
Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of
Los Angeles Mission College Facilities Master Plan Draft Program Environmental Impact Report 3.5 ENERGY CONSERVATION AND SUSTAINABILITY.
3.5 ENERGY CONSERVATION AND SUSTAINABILITY As a result of the analysis undertaken in the Initial Study 1 for the Los Angeles Mission College Facilities Master Plan, the LACCD determined that the proposed
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services May 200 Table of Contents NEW CONSTRUCTION/MAJOR RENOVATION Process... Design... 3 MINOR RENOVATIONS/PROJECTS Process...
Sustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure
Sustainable Features High-performance HVAC High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure Sustainable Landscaping Recycled and Regional Materials Storm-water Management District
Energy Analysis and Design
Excerpt from The Architect s Handbook of Professional Practice, 13th edition, 2000 Energy Analysis and Design Donald Prowler, FAIA Architects who can offer combined expertise in energy-related design factors
LEED PRESENTATION OUTLINE
16902 BOLSA CHICA STREET, SUITE 101 HUNTINGTON BEACH, CA 92649 TELEPHONE (714) 840-8230 FACSIMILE (714) 840-2490 LEED PRESENTATION OUTLINE I. Overview of Green Building and Risks Involved with Sustainability
Green BIM/ Early BIM/
Green BIM/ Early BIM/ Agenda/ Introduction to Sustainability Process Environmental Analysis Tools Environmental Analysis Relation to LOD Conclusion Disclaimer/ This seminar is looking at Building Performance
Millennium Hall, Philadelphia, Pennsylvania is a Residence Hall/Dormitory building of approximately 102,680 ft². The client is Drexel University.
Page 1 of 6 INTRODUCTION Millennium Hall, Philadelphia, Pennsylvania is a Residence Hall/Dormitory building of approximately 102,680 ft². The client is Drexel University. Millennium Hall is described as
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing
ENERGY MODELING: A GUIDE FOR THE BUILDING PROFESSIONAL
Prepared for: Colorado Governor s Energy Office ENERGY MODELING: A GUIDE FOR THE BUILDING PROFESSIONAL Prepared by: M.E. GROUP and Hutton Architecture Studio Date: May 2011 www.rechargecolorado.com ENERGY
Building Energy Modelling. prescriptive
Building Energy Modelling prescriptive An alternative to Design for SANS 10400-XA Contents Complying with the new building energy standard - SANS 10400-XA 3 Compliance options Two rational design routes
Za abeel Energy City Master Plan. Dubai, United Arab Emirates
Dubai, United Arab Emirates Dubai, United Arab Emirates The Energy Master Plan is uniquely positioned as a center for both commerce and residential development. The project will embody modern, sustainable
Green Globes for New Construction Pre-Assessment Checklist for Project Managers
1 Green Globes for New Construction Pre-Assessment Checklist for Project Managers What is Stage I assessment? As the design phase draws to a close, and your Green Globes questionnaire is completed through
Introduction to Energy Codes & Green Building Programs
Introduction to Energy Codes & Green Building Programs David Neiger B.S. Arch, LEED AP Homes, Certified HERS Rater Principal Populus Sustainable Design Consulting Why green homes? The Building Sector:
3-D Modeller Rendered Visualisations
Recognised energy Dynamic Simulation Modelling (DSM) software DesignBuilder is a user interface to the EnergyPlus DSM. EnergyPlus builds on the most popular features and capabilities of BLAST and DOE-2
research highlight Highly Energy Efficient Building Envelope Retrofits for Houses
research highlight June 2012 Technical Series 12-103 Highly Energy Efficient Building Envelope Retrofits for Houses introduction In Canada approximately 30% of all energy is consumed in buildings, with
The Industry s Most Advanced Sun-Sensing, Adaptive-Tinting Technology For Dynamic Windows
by The Industry s Most Advanced Sun-Sensing, Adaptive-Tinting Technology For Dynamic Windows In Alliance with OCCUPANT COMFORT All of the windows above have the same exterior tint of glass. Why such a
National Building Code of Canada 2010
National Building Code of Canada 2010 Emergency Change Issued by the Canadian Commission on Building and Fire Codes The table that follows lists two emergency changes that apply to the National Building
Post Occupancy Evaluation (POE) Technical Instructions
1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational
Decision-making Methodology & Selection Tools for High-performance Window Systems in U.S. Climates Kerry L. Haglund 1
ABSTRACT Decision-making Methodology & Selection Tools for High-performance Window Systems in U.S. Climates Kerry L. Haglund 1 Selecting a glazing system requires an understanding of a series of variables
Code for Sustainable Homes Guidelines
Canoldir Penrhos Anglesey LL65 2TS Phone: 01407 860666 Email: [email protected] www.easonline.co.uk Code for Sustainable Homes Guidelines A CSH rating is the responsibility of the Developer/ Architect
Building Energy Labels: The Swiss MINERGIE Label
Building Energy Labels: The Swiss MINERGIE Label Chennai, October 8 th, 2010 Heinrich Gugerli, Head Sustainable Building Group [email protected] www.stadt-zuerich.ch/nachhaltiges-bauen Energy
DISCOVERY HALL, UNIVERSITY OF WASHINGTON BOTHELL Bothell, Washington 78,200 sf
DISCOVERY HALL, UNIVERSITY OF WASHINGTON BOTHELL Bothell, Washington 78,200 sf Discovery Hall reflects its dynamic program and dramatic site, as well as the collaborative and student-centered spirit of
High Performance School Buildings Resource and Strategy Guide
High Performance School Buildings Resource and Strategy Guide Published by: Sustainable Buildings Industry Council With support from: California Energy Commission National Concrete Masonry Association
Protocol for the Certification of Energy Simulation Software: Second edition, September 2011
Copyright Agrément South Africa, September 2011 The master copy of this document appears on the website: http://www.agrement.co.za SANS 10400: The application of the National Building Regulations: Protocol
WORKSHOP: The roles of wood in green building and green building effects on the forest sector of in the UNECE region.
WORKSHOP: The roles of wood in green building and green building effects on the forest sector of in the UNECE region. Are ENGO s ready to promote the use of wood as the preferred building material? Alison
Using Simulation to Improve Data Center Efficiency
A WHITE PAPER FROM FUTURE FACILITIES INCORPORATED Using Simulation to Improve Data Center Efficiency Cooling Path Management for maximizing cooling system efficiency without sacrificing equipment resilience
Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series
Best Practices : Project Phase Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA members without endorsement
PROJECT ON THE ECO-FRIENDLY RENOVATION OF SCHOOL BUILDINGS AND ENVIRONMENTAL EDUCATION
17-014 The 2005 World Sustainable Building Conference, PROJECT ON THE ECO-FRIENDLY RENOVATION OF SCHOOL BUILDINGS AND ENVIRONMENTAL EDUCATION Sachiko ZENYOJI 1 Naoki TAKIGUCHI 2 1 2 Organic Table K.K.,
OEGNB - Open Source Building Assessment
OEGNB - Open Source Building Assessment Mag. Dr. Susanne Geissler SB13 26th September 2013 Graz ÖGNB sustainable building assessment/quality label The ÖGNB quality label is based on the TQB assessment
HVAC Costs. Reducing Building. Building owners are caught between two powerful forces the need to lower energy costs. By Stephen J.
Reducing Building HVAC Costs of site rec By Stephen J. Pargeter Building owners are caught between two powerful forces the need to lower energy costs and the need to meet or exceed outdoor air ventilation
ADVANCED ARCHITECTURAL DESIGN ESSENTIAL CURRICULUM
ADVANCED ARCHITECTURAL DESIGN ESSENTIAL CURRICULUM 2008 Advanced Architectural Design OVERARCHING GOALS Unit: SR 1.1 Solar Space Heating / Alternative Energy Sources Goal(s): Describe the importance of
Holistic Approach in Delivering Government Buildings The Low Carbon Concept
International Conference on Planning for Low Carbon Cities 22 May 2009 Holistic Approach in Delivering Government Buildings The Low Carbon Concept Ir. HO Sai-king, Assistant Director (Building Services),
Solar Homes Catch the Sun. Are you planning a new house? Discover how you can apply solar architecture principles to:
PASSIVE Solar Design Solar Homes Catch the Sun Are you planning a new house? Discover how you can apply solar architecture principles to: keep your heating bills to a minimum enjoy the comfort of a warm
Achieving Net Zero. Bradley Berneche, President Alouette Homes. National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008
Achieving Net Zero Bradley Berneche, President Alouette Homes National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008 Overview Who Is Alouette Homes? The EQuilibrium Initiative
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING PURPOSE: With this Memorandum of Understanding (MOU), signatory agencies commit to federal leadership in the
Methods for Effective Room Air Distribution. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas
Methods for Effective Room Air Distribution Dan Int-Hout Chief Engineer, Krueger Richardson, Texas Agenda Overview LEED issues and Update Perimeter Acoustics Thermal Comfort IAQ / Standard 62.1 Update
Queen Lane Addition, Philadelphia, Pennsylvania is a building of approximately 25,000 ft². The client is Drexel University.
Page 1 of 5 INTRODUCTION Queen Lane Addition, Philadelphia, Pennsylvania is a building of approximately 25,000 ft². The client is Drexel University. Queen Lane Addition is described as follows: Medical
SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP
research journal 2013 / VOL 05.01 www.perkinswill.com SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP ARCHITECTURE AND ENGINEERING OF SUSTAINABLE BUILDINGS Current Trends in Low-Energy HVAC Design
Innovation in Affordable Housing Incorporating GREEN in Development
Innovation in Affordable Housing Incorporating GREEN in Development 2014 Housing Innovation Marketplace Conference INTRODUCTION A small idea can grow into something that really bears fruit and, if good
CTBUH Copyright. What every tenant wants. Chairman, Jones Lang LaSalle. Dan Probst
What every tenant wants Dan Probst Chairman, Jones Lang LaSalle Chicago, USA Industry drivers Converging forces Mass acceptance of global warming, climate change Rising energy prices Widely accepted green
SYSTEMS INTEGRATION SYSTEMS INTEGRATION. Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight
100% outside air intake Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight Smoke evacuation Natural convection exhaust Atrium skylight Phase change material
Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering
Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty
DESIGN OF NATURAL VENTILATION WITH CFD CHAPTER SEVEN. Qingyan Chen. difficult to understand and model, even for simple
CHAPTER SEVEN L. Glicksman and J. Lin (eds), Sustainable Urban Housing in China, 116-123 2006 Springer. Printed in the Netherlands. DESIGN OF NATURAL VENTILATION WITH CFD Qingyan Chen INTRODUCTION As the
Protocol for the Certification of Energy Simulation Software: First edition, December 2009
Copyright Agrément South Africa, December 2009 The master copy of this document appears on the website: http://www.agrement.co.za Protocol for the Certification of Energy Simulation Software: First edition,
Dienstleistung. Certification as "Quality Approved Passive House" Criteria for Residential-Use Passive Houses
Passiv Haus Institut Passivhaus Dienstleistung GmbH Dr. Wolfgang Feist Rheinstr. 44/46 Rheinstr. 44/46 D-64283 Darmstadt D-64283 Darmstadt www.passiv.de www.passivhaus-info.de Certification as "Quality
Realizing the Future of Sustainable Design through BIM and Analysis
MEP ENGINEERING Realizing the Future of Sustainable Design through BIM and Analysis By Robert E Middlebrooks, AIA In the United States, buildings are responsible for almost half of all annual green house
Benchmarking Questionnaire on Facility Management Costs and Business Practices
Benchmarking Questionnaire on Facility Management Costs and Business Practices April 21, 2004 Introduction KPMG has been contracted by Hydro Quebec s Facility Management Division to perform a benchmark
BOMA BESt Assessment Overview
BOMA BESt Assessment Overview BOMA Building Environmental Standards OFFICE Module August 2013 The Voice of the Commercial Real Estate Industry in Canada The Building Owners and Managers Association of
BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust
BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched
Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA
Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Boggarm S. Setty, P.E., Fellow ASHRAE Setty & Associates, Ltd. 3040 Williams Drive, Suite 600, Fairfax,
Building Performance Evaluation Guide Version 1.7
Building Performance Evaluation Guide Version 1.7 Prepared by Center for Energy and Environment January 2014 Minnesota Sustainable Building 2030: Building Performance Evaluation Guide p 1 1. Schematic
Design Development Quality Management Phase Checklist Project Phase Checklist Series
Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA
Passive & Active Design
Passive & Active Design CIBSE Building Simulations Group Peter A. Brown CEng, MBA October 2010 Introduction Passive & Active Design Introduction What are the interactions between passive and active design?
Climate and Energy Responsive Housing in Continental Climates. The Suitability of Passive Houses for Iran's Dry and Cold Climate. Farshad Nasrollahi
Climate and Energy Responsive Housing in Continental Climates The Suitability of Passive Houses for Iran's Dry and Cold Climate Farshad Nasrollahi Table of Contents Abstract German Abstract Introduction
HVAC Design and Operation for Green Buildings
Hui, S. C. M., 2001. HVAC Design and Operation for Green Buildings, In Proc. of the Shaanxi-Hong Kong Refrigeration and HVAC Seminar 2001, 11-13 June 2001, Xian, China, pp. A44-51. (in English with a Chinese
ENERGY STAR Data Verification Checklist
ENERGY STAR Data Verification Checklist 86 ENERGY STAR Score 1 Sample Property Primary Function: Office Gross Floor Area (ft²): 200,000 Built: 1980 For Year Ending: 04/30/2013 Date Generated: 06/28/2013
Green Codes & IGCC Update
City of Houston Code Enforcement Green Codes & IGCC Update CATEE Conference Dallas, TX November 9, 2011 Sheila Blake MBA, CBO, LEED AP Assistant Director, PWE Planning and Development Services 1 Houston
Integrating Landscape Irrigation Control With Building Automation Issues and Opportunities
Integrating Landscape Irrigation Control With Building Automation Issues and Opportunities Gaylen Atkinson, Chairman and Founder, Atkinson Electronics Inc. Salt Lake City, UT April 27, 2015 Agenda Benefits
Portuguese Certification System for Energy an Indoor Air Quality Statistical Information about the Portuguese Certification System
Portuguese Certification System for Energy an Indoor Air Quality Statistical Information about the Portuguese Certification System Manuel Casquiço/ ADENE Tabula Expert Workshop - Energy Assessment of National
Windows are one of the most important components of a
design concepts Arjun Kamal MAKING BETTER INDOOR ENVIRONMENTS WITH ENERGY-EFFICIENT WINDOW DESIGN An insight into the various technologies used for constructing windows, and an attempt at understanding
CITY OF FERNDALE EAGLE Checklist
CITY OF FERNDALE EAGLE Checklist Purpose of the Checklist: The City of Ferndale has adopted EAGLE, an indicator-based program intended to provide the citizens of Ferndale, the applicant, and the City with
Architect: Cigler Marani Architects
Architect: Cigler Marani Architects SOLUTIONS FOR SUSTAINABLE BUILDINGS THE GUIDE TO Leed Reynaers develops innovative and sustainable aluminium solutions, for windows, doors, curtain walls and sun screening,
Residential HVAC Load Sizing Training October 14, 2015. David Kaiser Green Code Plan Reviewer
Residential HVAC Load Sizing Training October 14, 2015 David Kaiser Green Code Plan Reviewer DCRA - Green Building Division Regulations of green codes including: Green Building Act Green Construction Code
PROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS
PROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS Regione Lombardia ALER Bergamo Lecco Sondrio Treviglio via Dei Mulini n. 10/20 via Filzi n. 11/13 Prospectus Template provided by TEH-Ambrosetti.
European Commission DG Research ALTENER FINAL REPORT. Cluster 9. (4.1030/C/00-009/2000) Solar Passive Heating and Cooling
European Commission DG Research ALTENER FINAL REPORT Cluster 9 (4.1030/C/00-009/2000) Solar Passive Heating and Cooling Prepared by: Edited by: Authorised by: Raul Moura, Brian Ford Raul Moura Brian Ford
THE NATIONAL BUILDING REGULATIONS PART XA: ENERGY EFFICIENCY. Presentation by Peter Henshall-Howard: HEAD: BUILDING DEVELOPMENT MANAGEMENT.
THE NATIONAL BUILDING REGULATIONS PART XA: ENERGY EFFICIENCY. Presentation by Peter Henshall-Howard: HEAD: BUILDING DEVELOPMENT MANAGEMENT. A Diagrammatic representation of the relationship between the
STEPS IN THEATRE PROJECT PLANNING
Janis A. Barlow & Associates Research, Planning and Management Consultants Specializing in Theatre since 1981 STEPS IN THEATRE PROJECT PLANNING Janis A. Barlow & Associates www.barlowandassociates.com
GREEN SCHOOL DESIGN (Revision no.1, Dated 07/14/2010)
I. Introduction: GREEN SCHOOL DESIGN (Revision no.1, Dated 07/14/2010) Public school facilities must be designed and constructed to be efficient, effective, and sustainable for their expected building
Every Student I Every Day I Every Possibility
For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools
RAPID ENERGY MODELING FOR EXISTING BUILDINGS:
EXECUTIVE SUMMARY RAPID ENERGY MODELING FOR EXISTING BUILDINGS: Testing the Business and Environmental Potential through an Experiment at Autodesk NOVEMBER 2009 1. Executive Summary Retrofits of existing
Green Buildings Guidelines for Harvard
Green Buildings Guidelines for Harvard Presentation to the Administrative Deans. October 26th 2007 Leith Sharp, Director, Harvard Green Campus Initiative What is a Green Building? Average Savings of Green
Carbon Management Plan
E-2015-02-02 Addendum Carbon Management Plan Date: 14 May 2014 Owners: Approval: K.W.Bullimore & M.Sackett A.Burrell Executive Summary This document sets out the Carbon Management Plan (CMP) for The Open
GREEN FACTS. Marina Bay Sands
Marina Bay Sands GREEN FACTS Marina Bay Sands is committed to integrating sustainability into the core business strategy. We drive sustainability through our Sands ECO360 Sustainability programme, a global
Diego Ibarra Christoph Reinhart Harvard Graduate School of Design
Building Performance Simulation for Designers - Energy DesignBuilder // EnergyPlus Tutorial #2 Load Schedules GEOMETRY LOADS RESULTS Diego Ibarra Christoph Reinhart Harvard Graduate School of Design OVERVIEW
Can old buildings be just as energy-efficient as new ones?
Can old buildings be just as energy-efficient as new ones? Intelligent, energy-efficient building automation reduces emissions and costs in every building. Answers for infrastructure. Efficient energy
Comments of PU Europe on the Energy Efficiency Plan 2011 Commission Communication COM(2011) 109 final
Comments of PU Europe on the Energy Efficiency Plan 2011 Commission Communication COM(2011) 109 final PU Europe is the European association representing the polyurethane insulation industry (PUR/PIR).
250 St Georges Tce, Perth, WA (QV1)
250 St Georges Tce, Perth, WA (QV1) Building Profile Building Construction date 1991 Refurbishment date Owner Building Size Refurbishment Team Building Management Awards Ratings QV.1, 250 St Georges Terrace,
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING PURPOSE: With this Memorandum of Understanding (MOU), signatory agencies commit to federal leadership in the
BUILDING ENERGY EFFICIENCY. A Certification System for Building Efficiency ORTUGAL
BUILDING ENERGY EFFICIENCY A Certification System for Building Efficiency ORTUGAL ENERGY PERFORMANCE Portugal s certification system for buildings encourages efficiency Portugal has significant potential
School in Schwanenstadt, Austria
School in Schwanenstadt, Austria 1. INTRODUCTION PROJECT SUMMARY - building period 1960s - numerous expansions SPECIAL FEATURES - Renovation to meet Passive House Standard - decentralized ventilation system
Retrofit EnerLogic Low-e Window Films
Retrofit EnerLogic Low-e Window Films Steve DeBusk Global Architectural Technical Services Manager May 18, 2015 ORNL Envelope Stakeholder Workshop Eastman Overview Eastman Global specialty chemical company.
HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget
A PRIMER Educational HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget Contents: Introduction: The best HVAC system is durable, reliable
Conceptual Design and Analysis in Autodesk Revit Architecture 2011
AUTODESK REVIT ARCHITECTURE 2011 Conceptual Design and Analysis in Autodesk Revit Architecture 2011 In this white paper, CASE Design, a design technology consultancy based in New York City, describes how
Thermal Optimization: A Private Sector Program for Energy Efficiency in Existing Residential Buildings
Thermal Optimization: A Private Sector Program for Energy Efficiency in Existing Residential Buildings Rick Barnett June 2016 The Challenge The climate agreement signed at COP21 in December 2015 set ambitious
Steel Solutions for Green Building
Steel Solutions for Green Building Createsima transforming tomorrow Steel Solutions for Green Building As society makes determined moves towards sustainability, construction has a very important role to
The Empire State Building Repositioning an Icon as a Model of Energy Efficient Investment
The Empire State Building Repositioning an Icon as a Model of Energy Efficient Investment Motivation The goal with ESB has been to define intelligent choices which will either save money, spend the same
Green House, Hungary
Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support [email protected] Green House, Hungary Case Study 109 Aspects of Sustainability This project
The Reunion experience
Barcelona Workshop Experience on Net Zero Energy Buildings October 3rd 2012 1 The challenge of designing Net Zero Energy Buildings in Tropical Climates The Reunion experience Prof. François GARDE, PhD,
Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit?
Industrial Green Building 101 Opportunities and Challenges Joanne Sawatzky Senior Project Manager, Light House Sustainability at Work Re-visioning a Sustainable False Creek Flats Light Industrial Green
Honeywell Building Envelope Solutions. Optimizing Performance For A Better Bottom Line
Honeywell Building Envelope Solutions Optimizing Performance For A Better Bottom Line Building Envelope Solutions Roofing Systems Insulation Windows/Window Film Air Sealing Special Structures pipes, tanks,
