1 ZX Gas-insulated medium voltage switchgear Instruction manual BA 435/0 E ABB Power Distribution

2

3 Your safety first always! That's why our instruction manual begins with these recommendations: Only install switchgear and/or switchboards in enclosed rooms suitable for electrical equipment. Ensure that installation, operation and maintenance are carried out by specialist electricians only. Comply in full with the legally recognized standards (DIN VDE / IEC), the connection conditions of the local electrical utility and the applicable safety at work regulations. Observe the relevant information in the instruction manual for all actions involving switchgear and switchboards. Danger! Pay special attention to the hazard notes in the instruction manual marked with this warning symbol. Make sure that under operation condition of the switchgear or switchboard the specified data are not exceeded. Keep the instruction manual accessible to all persons concerned with installation, operation and maintenance. The user s personnel are to act responsibly in all matters affecting safety at work and the correct handling of the switchgear. WARNUNG Anerkannte Regeln der Technik und Betriebsanleitungen beachten! Gefährliche Spannung kann elektrischen Schock und Verbrennungen verursachen. Vor Aufnahme von Arbeiten jeder Art dieses Gerät unbedingt freischalten, erden und kurzschließen. WARNING Always observe the instruction manual and follow the rules of good engineering practice! Hazardous voltage can cause electrical shock and burns. Disconnect power, then earth and short-circuit before proceeding with any work on this equipment. If you have any further questions on this instruction manual, the members of our field organization will be pleased to provide the required information.

4 Contents Page Contents Page 1 Summary General 6 1. Standards and specifications Switchgear manufacture Installation and operation Operating conditions Normal operating conditions Special operating conditions 7 Technical data 8.1 Panel type ZX 8. Disconnector/earthing switch type UXTE, and disconnector type UXT 9.3 Dimensions and weights 10.4 Resistance to internal arc faults 11 3 Design and function of the switchgear system and its equipment Design and equipment of the panels Gas system in the panels/switchgear Vacuum circuit-breakers, type VD4 X Disconnector/earthing switch, type UXTE Disconnector, type UXT Sensor systems High voltage connections Bay control and protection unit REF54 (SCU) Protection against maloperation/interlock dependencies/earthing of tee-off Interlock dependencies Earthing a tee-off in a single busbar system Earthing the busbar in a single busbar system Earthing a tee-off in a double busbar system Earthing the busbar in a double busbar system Test facilities 4 Despatch and storage Condition on delivery 8 4. Packaging Transport Delivery Intermediate storage 8 5 Erection of the switchgear at site General site requirements Construction data Fundamental notes on erection work Foundation frame Laying of the foundation frame Raised false floor Erection and connection of the panels Preparatory work Erection of the switchgear Connection of cables and wiring High voltage plastic-insulated cable with plug connectors Control cables and wiring Preparing the insulating gas system for operation Final erection work 44 6 Commissioning/operation Commissioning Preparatory work Initial start-up Switching operations Circuit-breaker Three-position switch and disconnector Undervoltage release Observation of the display and monitoring facilities Gas monitoring Electrical/mechanical display/monitoring 46 4 ABB Power Distribution

5 Contents Page 6.4 Test procedures Testing for the off-circuit condition Testing for the in-phase condition High voltage tests Current tests Maintenance earthing Application of the X-ray regulations 49 7 Maintenance General Inspection/servicing Vacuum circuit-breaker Three-position switch and disconnector Gas system and gas servicing Outlet filter Repair Working and auxiliary materials Working materials Auxiliary materials 55 We reserve all rights to this publication. Misuse, particularly including duplication and making available of this manual - or extracts to third parties is prohibited. The information supplied is without liability. Subject to alteration. ABB Calor Emag Mittelspannung GmbH, 000 ABB Power Distribution 5

6 1 Summary 1.1 General Fundamental features of the ZX panels: rated voltage up to 36 kv three-phase metal-enclosed gas-insulated gas-tight metal-clad busbar compartment gas-tight metal-clad circuit-breaker compartment computerised switchbay control system sensor technology for adapted measured value acquisition indoor installation factory-assembled type-tested. Basic panel variants: incoming and outgoing feeders bus sectionalisers in single and double busbar systems bus coupler panels in single and double busbar systems bus riser panels in single and double busbar systems metering panels in double busbar systems supplementary equipment: busbar metering system in single busbar systems Panel equipment, variants: vacuum circuit-breaker single or double busbar systems: busbar system 1 with disconnector/earthing switch (three-position switch) with functions of: busbar connection, disconnection, earthing. busbar system with disconnector with functions of: busbar connection, disconnection. Details on the technical design and equipment of a switchgear, such as technical data, detailed list of equipment fitted, detailed circuit diagrams, etc. can be found in the order documents. 1. Standards and specifications 1..1 Switchgear manufacture The panels comply with the following VDE standards and the corresponding IEC publications: VDE 0670 and IEC 60056, 6019, 6098 and VDE 0373 and IEC and Installation and operation The relevant standards are to be observed during installation and operation, in particular: DIN VDE 0101, Power installations exceeding AC 1 kv, VDE 0105, Operation of electrical installations DIN VDE 0141, Earthing systems for special power installations with rated voltages above 1 kv, the accident prevention regulations issued by the appropriate professional bodies, the safety guidelines for production materials, the order-related details provided by the switchgear manufacturer. 1.3 Operating conditions Normal operating conditions Designed in accordance with VDE 0670 Part 1000, Common specifications for high-voltage and controlgear standards and IEC Publication 60694, with the following limit values: Ambient temperature: Maximum +40 C Maximum 4 hour average +35 C Minimum (corresponding to minus 5 indoor class) 5 C Site altitude: 1000 m above sea level Ambient air: The ambient air is not to be significantly contaminated by dust, smoke, corrosive or flammable gases, or salt. 6 ABB Power Distribution

7 1.3. Special operating conditions Special operating conditions are to be agreed by the manufacturer and operator. The manufacturer is to be consulted in advance about each special operating condition: Site altitude above 1000 m: Adjustment of the gas monitoring system is required for greater altitudes. Increased ambient temperature: The current carrying capacity is reduced, Additional cooling facilities for heat dissipation are to be provided. Climate: The risk of corrosion or other impairment, e.g. in the control cabinets, is to be avoided in areas: with high humidity and/or with major, rapid temperature fluctuations. Take countermeasures to prevent condensation phenomena (e.g. provide electric heaters). ABB Power Distribution 7

8 Technical data.1 Panel type ZX Electrical data Rated voltage kv Rated power frequency withstand voltage kv Rated lightning impulse withstand voltage kv All voltages quoted apply to an insulating gas pressure, absolute, at 0 C, of bar ) Rated frequency Hz 50/60 Rated current of busbars A 150/500 Rated current of tee-offs 3) A...000/500 4) Rated peak withstand current 3) ka Rated short time current, 3 s 3) ka Rated short-circuit breaking current of the circuit-breaker ka Rated short-circuit making current of the circuit-breaker ka Rated operating sequence O-0.3 s CO-3 min CO 5) Break time: manual tripping ms protection tripping ms Closing time: manual tripping ms protection tripping ms Insulating gas system )6) Insulating gas N 7) SF 6 8) SF 6 8) SF 6 8) Design pressure, absolute bar Operating pressure, absolute, 0 C (equals filling pressure) bar Rated pressure, absolute, 0 C (minimum operating pressure) bar Motor and release data Charging motor W <00 <00 <00 <00 Closing coil W Opening coil W Rated supply voltage DC voltage V 60, 110, 0 9) Degree of protection (IEC 6059, DIN VDE Gas-tight enclosure IP 65 IP 65 IP 65 IP 65 Control cabinet IP 4X 10) IP 4X 10) IP 4X 10) IP 4X 10) Higher values in accordance with international standards on request ) 1 bar = 100 kpa 3) For details refer to table: "Panel width-classification" section.4 4) Cooling included 5) Other operating sequences on request 6) For further details see BA 47 - insulating gas system for ZX switchgear 7) Insulating gas: nitrogen 8) Insulating gas: sulphur hexafluoride 9) Other voltages on request 10) IP 5X on request 8 ABB Power Distribution

9 . Disconnector/earthing switch type UXTE, and disconnector type UXT Test voltages Rated voltage kv Rated power frequency withstand voltage across the isolating distance kv Rated lightning impulse withstand voltage across the isolating distance kv Insulating gas system ) Insulating gas N 3) SF 6 4) SF 6 4) SF 6 4) Operating pressure, absolute, 0 C ( equals filling pressure ) bar Rated pressure, absolute,0 C ( minimum operating pressure ) bar bar = 100 kpa ) For further details see BA 47 - insulating gas system for ZX switchgear 3) Insulating gas: nitrogen 4) Insulating gas: sulphur hexafluoride Rated voltage kv 1/17.5/4/36 Test currents Rated current A 630 5) ) Rated peak withstand current ka Rated short time current, 3 s ka Motor data Motor power, max 3). W Motor running times, max 3).: Centre position to BB s Centre position to earth s Rated supply voltage DC 4) V 60,110,0 Panel width: 600 mm ) Panel width: 800 mm 3) At rated supply voltage 4) Other voltages on request 5) Panel width: 400 mm ABB Power Distribution 9

10 .3 Dimensions and weights View X ZX A C D A B B ZX X n panels ) Figure /1: Dimensions, double busbar system Figure shows panels with rated currents 000 A. A Pressure relief duct with absorber B Pressure relief duct, top C Pressure relief duct, side D End cover E Pressure relief duct, rear Panels with rated currents greater than 000 A are also fitted with a cooling fan. The panel height is then increased by 00 mm to 500 mm or 800 mm. ) n 1 View X ZX A C D B ZX A B X E n panels ) Figure /: Dimensions, single busbar system Figure shows panels with rated currents 000 A. A Pressure relief duct with absorber B Pressure relief duct, top C Pressure relief duct, side Optionally also with voltage sensors for busbar metering D End cover E Pressure relief duct, rear Panels with rated currents greater than 000 A are also fitted with a cooling fan. The panel height is then increased by 00 mm to 500 mm or 800 mm. ) n 1 10 ABB Power Distribution

11 Weights: Weight of a standard panel, double busbar, panel width 400 mm, rated current 630 A: Weight of a standard panel, double busbar, panel width 600 mm, rated current 150 A: Weight of a standard panel, double busbar panel width 800 mm, rated current 000 A: approx. 650 kg approx. 100 kg approx kg See section 5. for dimensions of the switchroom (construction data)..4 Resistance to internal arc faults Panel width 400 mm 600 mm 800 mm Core modul/bb-compartment 5 ka, 1s 31.5 ka, 1s 40 ka, 1s Cable compartment 0 ka, 1s, three-pole 5 ka, 1s, three-pole 5 ka, 1s, three-pole Resistance to internal arc faults: Criteria 1-6 of PEHLA directive no. 4 (in conjunction with VDE 0670 Part 6 and IEC 6098) are fulfilled. The panels have integrated pressure relief ducts with the opportunity for: channelling out of the switchroom in a manner suitable for the building dimensions, or channelling through an absorber on the last two panels (when the ceiling height is sufficient). Table: Panel width-classification Rated voltage kv I K, 3s ka I P ka I tee-off A / / / 150/ / 500 Panel width mm Rated voltage kv 4 36 I K, 3s ka I P ka I tee-off A / 150/ 150/ / 150/ / 000/ 000/ 000/ Panel width mm ABB Power Distribution 11

12 3 Design and function of the switchgear system and its equipment Figure 3/1: Panel, front view Figure 3/: Panel type ZX with control cabinet open 1.1 Control cabinet door 3 Three-position switch operating mechanism 8 Circuit-breaker operating mechanism 0 Disconnector operating mechanism Figure 3/3: Bay control and protection unit REF54 5 Bay control and protection unit 5.1 LCD display (example) 5. LEDs 6 Measuring sockets for capacitive voltage indicator system 1 ABB Power Distribution

13 B 3.5 G 19 0 E H Figure 3/4: Panel, double busbar, with pressure relief ducts at top and rear The side walls of busbar compartments 1 and, of the circuit-breaker compartment and the cable termination compartment have been cut open to provide a better view. I B E G H I Pressure relief duct, top Pressure relief duct, rear Control cabinet Circuit-breaker compartment Cable compartment Disconnector/earthing switch (three-position switch) in busbar compartment 1 19 Disconnector -Q in busbar compartment 0 Operating mechanism for item Bushing for plug-in busbar connection Figure 3/5: Pressure relief disk for a busbar compartment in the upper pressure relief duct Figure 3/6: Vacuum circuit-breaker type VD4 X (before installation in the works) ABB Power Distribution 13

14 -Q5 -Q1 -Q5 -Q1 -Q16 -Q11 -Q15 -Q1 -Q0 -Q0 Feeder Cable connection Coupler Riser Busbar metering Figure 3/7a: Examples of panels type ZX, with single busbars -Q5 -Q1 -Q -Q5 -Q1 -Q15 -Q -Q16 -Q11 -Q15 -Q1 -Q6 -Q1-Q5 -Q -Q0 -Q0 -Q0 -Q0 Feeder Bus coupler Bus sectionaliser -Q16 -Q11 -Q6 -Q1 -Q15 -Q1 -Q5 -Q -Q51 -Q1 -Q5 -Q Bus sectionaliser (without C.B.) Trunking bar connection Busbar metering Figure 3/7b: Examples of panels type ZX, with double busbars 14 ABB Power Distribution

15 Figure 3/8: ZX panel, single busbar, 150 A Figure 3/9: ZX panel, single busbar, 000 A Figure 3/10: ZX panel, double busbar, 000 A ABB Power Distribution 15

16 6 5 4 B B G 1 3 ( 0 SS SS1 3 (4) K H Q5 -Q1 -Q -Q0 -T I R1 -C1 Figure 3/11: ZX panel, double busbar, 150 A, fundamental structure SS1 Busbar system 1 SS Busbar system B Pressure relief duct, top E Pressure relief duct, rear G Control cabinet H Circuit-breaker compartment I Cable termination compartment -Q0 Circuit-breaker -Q1 Tee-off disconnector -Q Tee-off disconnector -Q5 Tee-off earthing switch -T1 Current sensor -R1 Voltage sensor -C1 Capacitive voltage divider 1 Panel enclosure Disconnector/earthing switch -Q1/-Q5 (three-position switch) 3 Three-position switch operating mechanism (4) Pressure sensor for busbar compartment 1 5 Bay control and protection unit REF54 6 Measuring sockets for capacitive voltage indicator system 7 Pressure sensor for circuit-breaker compartment 8 Circuit-breaker operating mechanism 9 Cable or test plug socket 10 Cable socket 11 Cable plug 1 Surge arrester 13 Floor plate, split 14 Connecting link panel/panel for item Main earthing bar 16 Combined current and voltage sensor 17 Pressure relief disk 18 Circuit-breaker 19 Disconnector -Q 0 Disconnector operating mechanism ( Pressure sensor for busbar compartment Tee-off conductor 3 Busbar connection, plug-in type 4 Busbar 5 Drying agent bag 6 Pressure relief disk Inert gas 16 ABB Power Distribution

17 3.1 Design and equipment of the panels (Figures /1, /, 3/1 to 3/1 The metal-enclosed ZX panels are laser cut and welded panel enclosures, completely earthed and thus protected against accidental contact. The stainless steel encapsulation and the insulating gas protect all live parts in the high voltage area permanently from soiling, humidity, foreign bodies and other injurious influences. The modular structure provides the conditions necessary for all panel variants normally required in a relatively simple manner. Facilities are also provided, for instance, for: one or two busbar systems, three-position switch or disconnector, different connection methods, such as multiple cables. Relieved pressure is guided into pressure relief ducts (A), (B), (C) and (E): In the case of internal arcing fault, the following pressure relief disks open: Pressure relief disk 17 on circuit-breaker compartment (H) into pressure relief duct (E). The gases are channelled out via ducts (C) and (A). Pressure relief disk 6 on the busbar compartment into pressure relief duct (B). In the case of an arc in the cable compartment (I), a pressure relief flap in pressure relief duct (E) opens. The gases are channelled out via ducts (C) and (A). Each panel is a unit, They are linked together by plug-in busbar connections 3. Basic equipment in the panels: Circuit-breaker VD4 X Three-position switch UXTE Disconnector UXT Sensor system Control cabinet with the bay control and protection unit REF54 Cable and test plug sockets. The insulation test criteria of VDE and IEC list are fulfilled by the ZX standard series up to and including 36 kv even when the gas filling is at atmospheric pressure. 3. Gas system in the panels/switchgear (Figures 3/11 and 3/15) A permanently protected climate for the entire live primary area is ensured by the gas-tight encapsulation of the panels and their filling with dry insulating gas. The circuit-breaker compartment and the busbar compartments in each panel are separate gas compartments with their own filling connectors. The gas compartments in the individual panels set up side by side are not connected together. The operating pressure (p e ) (equals filling pressure) in the individual compartments is monitored by temperature compensated pressure sensors: Pressure sensor 7 for the circuit-breaker compartment, Pressure sensors 4 and 1 for busbar compartments 1 and. When the pressure drops below the minimum operating pressure, a pressure loss signal is output. With a rapidly rising pressure as a consequence of an internal arc fault and a correspondingly high current, the bay control and protection unit REF54 shuts the incoming feeders or couplers down. Details on the gas system and gas servicing of the ZX switchgear can be found in instruction manual BA 47 Insulating gas system for ZX switchgear. The gas compartments contain drying agent bags 5. Further details on the drying agent material can be found in instruction manual BA Vacuum circuit-breakers, type VD4 X (Figures 3/, 3/6 and 3/11, and separate manual BA 436/E) Functions of the vacuum circuit-breaker 18: opening and closing on rated currents, short-circuit breaking operations, earthing function in conjunction with three-position switch. The earthing function of the three-position switch prepares - under no current - for the connection to earth. Earthing proper is performed by the circuitbreaker. This integration of functions is advantageous, as a circuit-breaker is of higher quality in the earthing function than any other earthing switch. The circuit-breaker poles are installed horizontally in the circuit-breaker compartment (H). The circuitbreaker operating mechanism is located outside the gas compartment and is therefore easily accessible. It is connected to the breaker poles by a gastight thrust bushing. ABB Power Distribution 17

18 3.4 Disconnector/earthing switch, type UXTE (Three-position switch) (Figures 3/, 3/4 and 3/1 The ZX panels are fitted with specially designed three-position disconnectors and earthing switches -Q1/-Q5. These switches are motor-operated rodtype switches whose live switching components are located in busbar compartment 1 (insulating gas compartment), while the operating mechanism block is easily accessible from the control cabinet (G). The operating mechanism block contains the drive motor, the position indicators (sensors and mechanical indicators) and the emergency manual operating system. The three-position switch performs the functions of: connecting, disconnecting, and earthing. The three switch positions are unequivocally specified by the operating mechanism. The switch has its disconnecting position at the centre. In the limit positions, disconnector ON and earthing switch ON, the moving contact (sliding part) driven by an insulating spindle, reaches the isolating contacts, which are fitted with one or two spiral contacts respectively. 3.5 Disconnector, type UXT (Figures 3/, 3/4 and 3/1 Disconnector -Q is a motor-operated rod-type switch. Its live switching components are located in busbar compartment (insulating gas compartment). The operating mechanism block is split and located outside the gas compartment. The drive motor is located at the rear of the panel behind a removable cover. The position indicators (sensors and mechanical indicators) and the emergency manual operating system are accessible from control cabinet (G). Disconnector -Q is structured similarly to the three-position switch, but without the earthing switch assembly. 3.6 Sensor systems (Figures 3/3, 3/11, 3/1 to 3/15, 6/3 and 6/7) In comparison with conventional inductive instrument transformers, sensors require much less space. They facilitate measured value acquisition suitable for the control and automation system REF54. The following sensors are used in ZX panels: Sensors for current measurement 16 Sensors for voltage measurement 16 Capacitive pick off for voltage display Sensors 4, 7 and 1 for insulating gas pressure monitoring Sensors to detect the switch positions of the circuit-breaker, disconnector/earthing switch and disconnector Sensor to detect the charging condition of the circuit-breaker spring energy store. Arrangement of the sensors: Current and voltage sensors are located in the rear part of the circuit-breaker compartment. The external connections allow wiring to be fed through the cable compartment (I) to the REF54. Sensors for pressure monitoring: B0G for the circuit-breaker compartment: on the circuit-breaker base plate in control cabinet (G). B1G for busbar compartment 1: beside the operating mechanism for the disconnector/earthing switch -Q1/-Q5 in the control cabinet (G). BG for busbar compartment : beside the base plate for the drive motor of disconnector -Q at the rear of the panel. Sensors for detection of the switch positions: B0E and B0A for the circuit-breaker: on its mechanism shaft. B1E, B1A, B5E and B5A for the disconnector/earthing switch: on its operating mechanism in the control cabinet. BE and BA for the disconnector: beside its emergency manual operating mechanism in the control cabinet. Sensor B0S for detection of the charging condition of the spring energy storage mechanism: above the spring drum in the circuit-breaker operating mechanism. 3.7 High voltage connections (Figures 3/4, 3/8 to 3/11, 5/15 and 5/16) Cable plug connector systems: high voltage plastic-insulated cable with internal cone cable plug connector system and sockets to DIN Plug-in cable sockets 9 and 10 mounted in a gastight manner in the floor plate of the circuit-breaker compartment maintain the partitioning between the insulating gas compartment and the cable termination compartment. 18 ABB Power Distribution

19 3.8 Bay control and protection unit REF54 (Figures 3/3 and 3/15) The following functions are integrated in the bay control and protection unit REF54: Busbar protection Tee-off protection Control Measurement Position indication Hazard and fault signalling Connection to control systems. Panel interlocks and the sequence of switching operations (e.g. isolation, testing of the off-circuit condition and earthing) are controlled by the REF54 panel unit. The single-line diagram providing information on switching device positions is made visible on LC display 5.1. Measured values such as conductor currents, phase voltages, energy metering and active and reactive power, number of operating cycles and number of operating hours appear numerically and/or as a bar diagram on the display. Further information, such as alarm and fault signals, is displayed with text by LEDs 5.. The bay control and protection unit REF54 can be connected to a control system via optical fibre cables. Electromagnetic interference is avoided by the use of optical fibre cables. Please consult the REF54 instruction manual no. BA 453 for details on handling of the bay control and protection unit and the detailed technical description. 3.9 Protection against maloperation/interlock dependencies/earthing of tee-off In order to prevent dangerous situations and maloperation, a series of interlocks are provided to protect the operators and the switchgear itself. In ZX panels with digital control systems, protection against maloperation is fundamentally effected by the software in the panel unit. The circuit-breaker, three-position switch and disconnector can be controlled directly at the panel or from the control room using the local/remote lock-switch. Operation at the panel is by selection on the REF Interlock dependencies 1. Limit position blocking of the switching devices.. Dependence of the disconnectors -Q1 or -Q on the earthing switch -Q5 and vice versa. 3. Dependence of the disconnectors -Q1 or -Q on the circuit-breaker -Q0. 4. Dependence of the circuit-breaker -Q0 on the earthing switch -Q5. 5. Interdependence of the disconnectors -Q1 and -Q. 6. Dependence of the disconnectors -Q1 and -Q on bus coupler circuit-breakers and vice versa. 7. Dependence of the bus section disconnector on the busbar tee-off disconnectors and vice versa (for bus sectionalising without circuit-breaker only). Details of interlocks/dependencies over and above those listed in points 1 to 7 (e.g. with neighbouring systems) can be found in the individual order documents. The interlock polling between panels is effected by loop lines from panel to panel. Operation on failure of the auxiliary power supply: On failure of the auxiliary power supply, the devices can be operated manually. No provision is however made for interlocked emergency manual operation of the three-position switches and disconnectors. Emergency manual operation: Intervention in the interlock concept is possible by opening the control cabinet door. Emergency manual operation without maloperation prevention is possible by means of a hand crank and mechanical push-button Earthing a tee-off in a single busbar system (Figure 3/7) 1. Manual earthing Operating sequence for tee-off earthing: Circuit-breaker -Q0 OFF. Disconnector -Q1 OFF. Earthing switch -Q5 ON. Test for off-circuit condition (display on REF54 or capacitive voltage indicator system (see section 6.4.). Circuit-breaker -Q0 ON (only possible when the REF54 has detected the off-circuit condition and enabled the switching operation). Secure panel to prevent reconnection (m.c.b. F101 and F106 OFF). Label the panel to indicate that earthing has been effected. ABB Power Distribution 19

20 . Automatic earthing by selecting the earthing sequence on the REF54 display (this facility depends on the order placed) Condition: circuit-breaker -Q0 OFF. Select and start the automatic earthing sequence: Disconnector -Q1 OFF. Earthing switch -Q5 ON. Check on off-circuit condition by REF54. Circuit-breaker -Q0 ON. M.c.b. F101 and F106 OFF. Feedback message Earthed and secured. Label the panel to indicate that earthing has been effected. 3. Cancelling the earthing of a tee-off Open the control cabinet door and switch on the m.c.b. F101 and F106 manually. Circuit-breaker -Q0 OFF Earthing the busbar in a single busbar system (Figures 3/7 and 6/7) Earthing of the busbar or a busbar section is dependent on the switchgear configuration. Systems with bus ties / risers permit the earthing of a single busbar section. 1. Manual earthing of a busbar section using the bus tie / riser Operating sequence: Circuit-breaker -Q0 in the bus tie (tie breaker) OFF. All disconnectors -Q1 in the busbar section to be earthed OFF. Disconnectors (-Q11 or -Q1) between the busbar section to be earthed and the tie breaker ON. Earthing switch (-Q15 or -Q16) on the opposite side of the tie breaker ON. Tie breaker -Q0 ON. M.c.b. F101 and F106 OFF. Label the busbar section to indicate that earthing has been effected. The busbar section is then earthed. All disconnectors in the earthed busbar section are blocked.. Automatic earthing of a busbar section by selecting the earthing sequence on the REF54 display (this facility depends on the order placed) Condition: Circuit-breaker -Q0 in the bus tie (tie breaker) OFF. All disconnectors -Q1 in the busbar section to be earthed OFF. Select and start the automatic earthing sequence: Disconnectors (-Q11 or -Q1) between the busbar section to be earthed and the tie breaker -Q0 ON. Earthing switch (-Q15 or -Q16) on the opposite side of the tie breaker -Q0 ON. Tie breaker -Q0 ON. M.c.b. F101, F10 and F106 OFF. Feedback message Earthed and secured. Label the busbar section to indicate that earthing has been effected. The selected busbar section is then earthed. All disconnectors in the earthed busbar section are blocked. 3. Cancelling the earthing of a busbar section Open the control cabinet door and switch on the m.c.b. F101, F10 and F106 manually. Circuit-breaker -Q0 in the bus tie OFF. 4. Maintenance earthing of a busbar via free sockets in a tee-off Condition: The tee-off is earthed. All disconnectors in the busbar to be earthed OFF. Operating sequence: Fit a short-circuiting bridge to the free sockets and connect to main earthing bar 14. Circuit-breaker OFF. Earthing switch OFF. Disconnector ON. Circuit-breaker ON. M.c.b. F101 and F106 OFF. Label the busbar to indicate that earthing has been effected. All relevant panels are to be secured to prevent switching operations, e.g. tripping m.c.b Earthing a tee-off in a double busbar system (Figures 3/7 and 3/1 1. Manual earthing Operating sequence for tee-off earthing: Circuit-breaker -Q0 OFF. Disconnectors -Q1 and -Q OFF. Earthing switch -Q5 ON. 0 ABB Power Distribution

21 Test for off-circuit condition (display on REF54 or capacitive voltage indicator system (see section 6.4.). Circuit-breaker -Q0 ON (only possible when the REF54 has detected the off-circuit condition and enabled the switching operation). Secure panel to prevent reconnection (m.c.b. F101, F10 and F106 OFF). Label the panel to indicate that earthing has been effected.. Automatic earthing by selecting the earthing sequence on the REF54 display (this facility depends on the order placed) Condition: circuit-breaker -Q0 OFF. Select and start the automatic earthing sequence: Disconnectors -Q1 and -Q OFF. Earthing switch -Q5 ON. Check on off-circuit condition (by REF54). Circuit-breaker -Q0 ON. M.c.b. F101, F10 and F106 OFF. Feedback message Earthed and secured. Label the panel to indicate that earthing has been effected. 3. Cancelling the earthing of a tee-off Open the control cabinet door and switch on the m.c.b. F101, F10 and F106 manually. Circuit-breaker -Q0 OFF Earthing the busbar in a double busbar system (Figures 3/7 and 3/1 Earthing of the busbar or a busbar section is dependent on the switchgear configuration. Systems with bus couplers permit the earthing of a single busbar section. 1. Manual earthing of a busbar section Operating sequence: a) Busbar 1: Circuit-breaker in the bus coupler OFF. Disconnector -Q in the bus coupler OFF. All disconnectors -Q1 in the busbar section to be earthed OFF. Disconnector -Q1 in the bus coupler ON. Earthing switch -Q15 in the bus coupler ON. Circuit-breaker in the bus coupler ON. M.c.b. F101, F10 and F106 OFF. Label the busbar section to indicate that earthing has been effected. The busbar section of busbar 1 is then earthed. All disconnectors in the earthed busbar section are blocked. b) Busbar : Circuit-breaker in the bus coupler OFF. Disconnector -Q1 in the bus coupler OFF. All disconnectors -Q in the busbar section to be earthed OFF. Disconnector -Q in the bus coupler ON. Earthing switch -Q5 in the bus coupler ON. Circuit-breaker in the bus coupler ON. M.c.b. F101, F10 and F106 OFF. Label the busbar section to indicate that earthing has been effected. The busbar section of busbar is then earthed. All disconnectors in the earthed busbar section are blocked.. Automatic earthing by selecting the earthing sequence on the REF54 display (this facility depends on the order placed) Condition: Circuit-breaker -Q0 in the bus coupler OFF. All disconnectors in the relevant busbar section OFF. Select the operating sequence: a) Busbar 1: Disconnector -Q in the bus coupler OFF. Disconnector -Q1 in the bus coupler ON. Earthing switch -Q15 in the bus coupler ON. Circuit-breaker in the bus coupler ON. M.c.b. F101, F10 and F106 OFF. Feedback message BB1 earthed and secured. Label the busbar section to indicate that earthing has been effected. The busbar section of busbar 1 is then earthed. All disconnectors in the earthed busbar section are blocked. b) Busbar : Disconnector -Q1 in the bus coupler OFF. Disconnector -Q in the bus coupler ON. Earthing switch -Q5 in the bus coupler ON. Circuit-breaker in the bus coupler ON. M.c.b. F101, F10 and F106 OFF. Feedback message BB earthed and secured. ABB Power Distribution 1

22 Label the busbar section to indicate that earthing has been effected. The busbar section of busbar is then earthed. All disconnectors in the earthed busbar section are blocked. 3. Cancelling the earthing of a busbar section Open the control cabinet door and switch on the m.c.b. F101, F10 and F106 manually. Circuit-breaker -Q0 in the bus coupler OFF Test facilities The panels are properly filled with insulating gas at the works and tested to the VDE or IEC standards. Testing on completion of switchgear installation is therefore unnecessary. Should there be any need to perform tests, the tests are to be performed as follows: For voltage and current tests, direct access to the conductors in the connection area is possible without removing the cable connection or extracting the insulating gas. Access is effected via free cable connecting sockets or via the cable sockets for the surge arresters. The surge arresters must be removed during voltage tests. Voltage tests: cable tests with DC voltage, cable fault location measurements with impulse voltage and system tests (without cables) with a AC voltage can be performed with a test plug as shown in Figure 6/8. A test plug for current tests as shown in figure 6/9 can be used to test the protection devices by primary current injection (see also the note in section 6.4.4). This configuration is short-circuit proof and can also be used as an additional maintenance earth. The possible testing processes are described in the following sections: testing for the off-circuit condition: Section testing for the in-phase condition: Section 6.4. high voltage tests: Section current tests: Section ABB Power Distribution

23 ABB Power Distribution 3

24 -XI..,-XU.. Terminal designation 1 Front view A /40A /640A /150mV Class 1 without correction factor 3 -XI.. 640A/150mV 40A/150mV 80A/ 150mV S1 S S3 S4 P1 Primary conductor In = 150 A Ip = 100 ka Ith 3sec = 40 ka Capacitance C1 35pF max 55pF 0kV/ V3 V/ V3 Class 1 Working area S1 - S: A S1 - S3: A S1 - S4: A -XU.. 1 Pick-off: :1 a n CK Leakage capacitance 5pF P Figure 3/1: Combined current and voltage sensor with capacitive pick-off KEVCI 4 AE1, for rated voltages up to 4 kv and panel width 600 mm -XI..,-XU.. Terminal designation 1 Front view The following changes apply to rated voltage 36kV: Sensor: KEVCI 36 AE1 Pick-off: 0 000:1 bzw. 30 kv / 3 1,5 V / 3 Capacitance: C1 18 pf, max. pf - 1 -XI A/150mV S1 S P1 Primary conductor In = 500 A Ip = 100 ka Ith 3sec = 40 ka 1600A/150mV Class 1 without correction factor 3 Capacitance C1 35pF max 55pF 0kV/ V3 V/ V3 Klasse 1 -XU.. 1 Pick-off: :1 a n CK Leakage capacitance 5pF Working area S1 - S: A P Figure 3/13: Combined current and voltage sensor with capacitive pick-off KEVCA 4 BE1, for rated voltages up to 4 kv and panel width 800 mm The following changes apply to rated voltage 36kV: Sensor: KEVCI 36 BE1 Pick-off: 0 000:1 bzw. 30 kv / 3 1,5 V / 3 Capacitance: C1 18 pf, max. pf 4 ABB Power Distribution

25 L1 L L3 I II -Q1/Q5 -Q0 -T1L1..L3 -R1L1..L3 0kV/ V 3 V/ V 3 150mV 3 P1 P 3 -Q -XI..,-XU.. Terminal designation Front view 1 -C1L1..L3 -A00 Tee-off protection; measurement, metering IL1 IL IL3 UL1 UL UL3 -X3 d8 z8 d4 z4 d0 z0 d16 z16 d1 z1 d8 z8 1 -XIL1 1 -XItL1 1 -XIL 1 -XItL 1 -XIL3 1 -XItL3 -XUL XUtL1 -XUL 1 -XUtL 1 -XUL XUtL3 T1L1 S1 S. a n T1L S1 a n S. R1L1 P P1 P1 P1 R1L T1L3 S1 S. P R1L3 a n P Current and voltage sensors 3 single core cables GND IL0 d4 z4 1 -XIL0 1 -XItL0 Figure 3/14: Current and voltage sensors in an outgoing cable feeder panel, up to 4 kv, double busbar The circuit diagram is identical for the single busbar system, but without tee-off disconnector -Q. -Q0 Circuit-breaker -Q1 Busbar tee-off disconnector -Q Busbar tee-off disconnector -Q5 Tee-off earthing switch -T1... Current sensors -R1... Voltage sensors -C1... Capacitive voltage divider Inputs and interfaces of the bay control and protection unit REF54: IL... Measurement inputs for current UL... Measurement inputs for voltage -XI... Interfaces of the current sensors -XU... Interfaces of the voltage sensors -XIt... Test interfaces of the current sensors and the inputs -XUt... Test interfaces of the voltage sensors and the inputs -A00 Bay control and protection unit REF54 ABB Power Distribution 5

26 + - - F SPA - BUS () - F101 -F F ( 3 4 -F10: 4 -B5E Figure 3/15a: BK BN BU -B5A ( () - F100 - F101 - F10 - F F106:4 -F A00 A15 X4: d10 X4: z10 X4: d18 X4: z18 X5: d6 X5: z6 X5: d4 X5: z4 X5: d X5: z X7: d X7: d0 X7: z0 X7: z X1: 1 X1: 3 X6: d18 X6: z18 X6: d10 X6: z10 X6: d6 X6: z6 X6: d X6: z -A00 MMK A5 A6 A7 A A1 A3 A4 E3 E1 E4 E7 E E1 E6 E8 X4: d6 X4: z6 BK BN BU X4: d4 X4: z4 X4: d8 BK BN BU X4: z8 -B1E X4: d14 X4: z14 BK BN BU -B1A X4: d4 BK X4: z4 BN BU -B0E X4: d X4: z BK BN BU -B0A X4: d1 X4: z1 BK BN BU -B0S X4: d16 X4: z16 4 -B5E3 3 -B5E -B5E1 1 X6: d X6: d0 X6: z0 X6: z M -M1 X6: d1 B X6: z1 M -M0 F X6: d8 X6: z8 X6: d4 X6: z4 -V3 -V C1 C C1 C -Y3 -Y X4: z0 X4: d0 X4: z8 X4: d8 X7: d18 X7: z18 4 E10 E14 A14 A13 A1 E5 E9 E17 E16 E kpa 140 kpa 140 kpa kpa kpa 140 kpa 140 kpa kpa kpa 140 kpa kpa 140 kpa BK BN BU -BA BK BN BU -BE M -M -B0G -B1G -BG Figure 3/15b:Continued from figure 3/15a 6 ABB Power Distribution

27 Figure 3/15: Circuit diagram of the panel controller for a double busbar system The circuit diagram is identical for the single busbar system, but without M, BG, BE, BA and F10. Inputs E15, E16 and E17 and outputs A1 to A15 on the REF54 are not then used. -B0A Sensor, Circuit-breaker -Q0 OFF signal -B0E Sensor, Circuit-breaker -Q0 ON signal -B0S Sensor, spring energy store charged signal -B5E Sensor, Earthing switch -Q5 ON signal -B5A Sensor, Earthing switch -Q5 OFF signal -B5E1 3 Reed contacts, Earthing switch -Q5 ON signal -B1E Sensor, Disconnector -Q1 ON signal -B1A Sensor, Disconnector -Q1 OFF signal -BE Sensor, Disconnector -Q ON signal -BA Sensor, Disconnector -Q OFF signal -B0G Pressure sensor for circuit-breaker compartment -B1G Pressure sensor for busbar compartment 1 -BG Pressure sensor for busbar compartment -M0 Charging motor for spring energy store, circuit-breaker -M1 Drive motor for disconnector/earthing switch -Q1/Q5 -M Drive motor for disconnector -Q -MMK Man/machine communications -Y and -V Shunt release off with series rectifier for -Q0 -Y3 and -V3 Shunt release on with series rectifier for -Q0 -A00 Bay control and protection unit REF54 -F100 M.c.b. for charging motor, circuit-breaker -F101 M.c.b. for drive motor, disconnector/earthing switch -Q1/-Q5 -F10 M.c.b. for drive motor, disconnector -Q -F106 M.c.b. for controller, circuit-breaker ON/OFF -F116 M.c.b. for auxiliary power supply to the REF54 ABB Power Distribution 7

28 4 Despatch and storage 4.1 Condition on delivery The factory-assembled panels are checked for proper assembly and function. Condition on delivery: Compliance of the equipment with the order checked. Routine testing to VDE 0670 Part 6 or ICE 6098 performed. Installation material and accessories packaged separately. Bushings for the busbars closed off with transport covers. Condition of the gas compartments: Filled with insulating gas at rated operating pressure, Fitted with drying agent bags. Note: Air freight is to be discussed and agreed in individual cases. 4. Packaging Panels with basic packaging or without packaging. Panels with seaworthy or similar packaging (also containerised for overseas transport): sealed in polythene sheeting, transport drying agent bags inserted, moisture indicators inserted, sight window fitted for checking of the indicator when AL composite sheeting is used. Observe the directions for the drying agent bags to DIN The following applies: Coloured indicator blue: contents dry. Coloured indicator pink: contents moist (e.g. relative humidity over 40%). 4.3 Transport (Figures 4/1 to 4/3) Note: Do not walk on the tops of the panels (rupture point for the pressure relief system!). The transport units are normally individual panels. Take account of the weights of the transport units. Take account of the high centre of gravity. Handle the panels in the upright position. Only perform loading operations taking account of all safety precautions to protect personnel and the material transported with: a crane, and/or fork-lift truck. Handling by crane: Attach suspension ropes of a sufficient loadbearing capacity with shackles (opening angle 30 mm). Fit these to the four lifting lugs. Attach rope guide harness to the top of the panel. Handling in the switchgear room can be effected by a trolley with steerable wheels. Take account of the high centre of gravity of the panels. Danger of tipping! 4.4 Delivery The responsibilities of the consignee include but are not limited to: Checking the delivery for completeness and freedom from damage (e.g. also for moisture and its injurious effects). Any deficiencies/transport damage noted are to be documented on the waybill, reported to the shipper/carrier in accordance with the ADSP or KVO liability conditions for German insurance. Note: Always document major damage with photographs. 4.5 Intermediate storage Conditions for optimum intermediate storage: 1. Panels with basic packaging or without packaging. Dry and well ventilated storage room. Climate in accordance with VDE 0670 Part 1000/ IEC Room temperature not falling below -5 C. No other injurious environmental influences. Store the panels upright. Do not stack panels. Panels with basic packaging: open the packaging at least partially. Panels without packaging: loosely cover with protective sheeting. sufficient air circulation must be preserved. Check regularly for any condensation.. Panels with seaworthy or similar packaging with internal protective sheeting: Store the transport units: protected from the weather, in a dry place, protected from damage. Check the packaging for damage. Check the drying agent (see section 4.): on delivery, later at appropriate intervals. When the service life from the date of packaging has been exceeded: the protective effect of the packaging is no longer ensured, take action for further intermediate storage. 8 ABB Power Distribution

29 min.45 o ZX Figure 4/1: Preparation for handling by crane, double busbar system (for panel width 800) 95 (for panel width 600) 75 (for panel width 400) ZX (170) 1464 (64) Figure 4/: Preparation for handling by crane, single busbar system Figure 4/3: Preparation for handling by fork-lift truck Note: The forks must support the full section length. ABB Power Distribution 9

30 5 Erection of the switchgear at site In the interests of the best possible erection sequence, and in order to ensure a high quality standard of the panels, local installation of the switchgear should only be carried out, or at least responsibly managed and supervised, by specially trained skilled personnel. 5.1 General site requirements At the start of erection, the switchgear room at site must be complete, fitted with lighting and power for the erection work, lockable, dry, and with good ventilation facilities. All necessary provisions for laying of the power and control cables such as openings, ducts, etc. must already be in place. Compliance with the conditions for indoor switchgear to VDE 0670 Part 1000 etc., including those for the minus 5 indoor temperature class, must be ensured. 5. Construction data (Figures 5/4 to 5/7) Panel width mm Rated current A > 000 Ceiling height ) : without additional absorber mm with additional absorber mm with additional cooling fan and without absorber mm 800 with additional cooling fan and with absorber mm 3100 Assembly opening : in ceilings: width mm length mm in doors: width mm height mm Aisle width 3) : Inspection aisle mm Operator aisle mm Panel weight kg ca. 650 ca. 100 ca ca (outgoing feeder, double busbar) Floor load kg/m ca. 100 ca ca ca Minimum dimensions ) Panel including top pressure relief duct 3) Governed by DIN VDE 0101 and the data on maximum panel width. The ZX switchgear installations are mounted on a foundation frame set into the screed, or on a raised false floor. The openings shown in figure 5/4 are intended as an aid to planning. Instead of the large openings shown, drill holes can also be used, depending on the number of high voltage cables. Openings (drill holes) for power cables in the station floor are to be constructed so as to be eddy-current free. Note: The following is to be taken into account in determining the foundation data: Single busbar systems: Any additional frame available for the voltage sensors in the busbar metering system. The distance from the additional frame including end coffer to the side wall of the room should be 500 mm to ensure sufficient room for movement (see also section.3). Double busbar systems: From 5 panels onwards, a pressure relief duct is required at both ends of the switchgear installation. 30 ABB Power Distribution

31 5.3 Fundamental notes on erection work DIN-bolts of tensile class 8.8 are to be used. Recommended tightening torque Nm Lubricant ) Thread Without Oil or grease M 6 10,5 4,5 M M8 3) 1 4,5 M M M The rated tightening torques for fasteners without lubrication are based on a coefficient of friction for the thread of 0.14 (the actual values are subject to an unavoidable, partly not inconsiderable, spread). Rated tightening torques for fasteners with lubrication in accordance with DIN ) Thread and head contact surface lubricated. 3) These values apply to welded on studbolts only. Any tightening torques which deviate from those in the general table (e.g. for contact systems or device terminals) are to be taken into account as stated in the detailed technical documentation. It is recommended that the threads and head contact surfaces of bolts should be lightly oiled or greased, so as to achieve a precise rated tightening torque. Remove any dirt from the surfaces in general and from insulating material surfaces. Observe the cleaning instructions in Section 7.. When handling SF 6, avoid any escape of gas into the switchroom: as incorrect readings may be caused during leakage testing. ventilate well if leakage occurs. 5.4 Foundation frame (Figures 5/1 to 5/3) Switchgear on a foundation frame: The relevant data for the order in hand can be found in the ABB documentation. The single or multiple panel foundation frame can be supplied with the switchgear. It is as a rule laid by site personnel and should be aligned and inspected under the supervision of a responsible specialist. The specifications of DIN are also to be maintained when laying the foundation frame, in particular the evenness and straightness tolerances as a condition for perfect switchgear assembly. Tolerance conditions for laying of the frame to DIN , version A: Evenness tolerance: +/- 1 mm per metre. Straightness tolerance: max. 1 mm per metre, but max. mm for the entire length of the frame. 5.5 Laying of the foundation frame (Figures 5/1 to 5/3) Bolt the individual parts of foundation frame elements 7 together. Bolt the individual sections composed of foundation frame elements 7 (where the switchgear has several panels) together using connecting links 7.1 and bolts 7.5. Set up the complete foundation frame on the concrete floor precisely at the specified position. Fasten the foundation frame to the concrete floor sufficiently firmly with the bolts and dished washers 7., checking the correct dimensional position continuously. Enter jacking screws 7.3 into the relevant threaded bores (different lengths to correspond to the height of the screed), inserting a steel shim 7.8 below each screw. Loosen the compensation bolts 7.4 and carefully align the entire surface of foundation frame 7 in the horizontal plane and at the correct height, using a levelling instrument and screwing in jacking screws 7.3 to the appropriate depth. The top edge of the foundation frame must be 1 to 3 mm above the screed (take account additionally of the material thickness of any additional floor covering). Tighten the compensation bolts 7.4, performing a final check on the dimensions and horizontal position of the frame. Weld jacking screws 7.3 firm to prevent inadvertent changes to their settings. Perform the necessary work for proper earthing of the foundation frame with 30 x 4 mm galvanised steel strip. Two connections are necessary in switchgear with more than 6 panels. Carefully backfill the foundation frame when applying the screed. Note: Before applying the screed, insert auxiliary bolts 7.9. These prevent the screed from penetrating into the rivet nuts. Remove auxiliary bolts 7.9 when the screed has hardened. The foundation frame must not be subjected to any undue impacts or pressures, particularly, during the installation phase. ABB Power Distribution 31

32 7.4 Figure 5/1: 7.1 Individual parts of a foundation frame element, -panel example version 7.1 Connecting link 7.4 Compensation bolt n x FT = a Panel width FT 7 (143) Panel width FT Foundation frame width a Number of panels n _ Figure 5/: Foundation frame 7 Foundation frame element, individual parts bolted together 7.1 Connecting link 7. Bolt and dished washer for foundation frame fastening to concrete floor 7.3 Jacking screw for foundation frame 7.6 Plug 7.9 Auxiliary bolt for frame mounting and panel fastening bolt ABB Power Distribution

33 Section A-A (without item (143) mm A h A ,7.6 Figure 5/3: Foundation frame on concrete floor (showing the panel) 1 Panel 1.4 Panel fastening bolt 7 Foundation frame element 7. Bolt and dished washer for fastening of the foundation frame to the concrete floor 7.3 Jacking screw for foundation frame 7.4 Compensation bolt 7.5 Bolt for the connecting link 7.6 Plug 7.8 Steel shim 7.9 Auxiliary bolt for frame installation h Screed height 40 to 50 mm 5.6 Raised false floor (Figures 5/6 and 5/7) When a raised false floor is used, the manufacturer s installation instructions are to be observed. The false floor must satisfy all requirements specific to the switchgear installation. ABB Power Distribution 33

34 ) A B C D (143) x x a 7 b c d A B C D (155) ( 7 Figure 5/4: Guideline construction data for a foundation frame on a concrete floor See figure 5/5 for sections Minimum 1 Inspection aisle Operator aisle 3 Basement entrance 4 Platform, approx. 5 kn 5 Pressure relief duct at side, including end cover 6 Instead of individual openings, continuous openings or drilled holes are possible 7 Earthing bar 8 Panel without cable connection, e.g. bus coupler panel 9 Door 10 Waste air opening 11 Intake air opening 1 Intake air opening, if required 13 Waste air opening 14 Or as shown in figure 5/7 15 Height of cable basement as required 16 To earthing bar 17 Opening for control cable 18 Opening for power cable, plug size 19 Opening for power cable, plug size 3 0 Instrument transformer for billing purposes 1 Screed, see also figure 5/3 Panel width a b c d in switchgear mm mm mm mm 600 mm mm or 600 mixed with 800 mm Room height : Rated Absorber Room height current A mm 000 with without 500 > 000 with 3100 > 000 without ABB Power Distribution

35 Section A - A c Section B - B c ZX (155) (7) 9 d ZX (155) (7) 9 d b b (143) a (143) a a) Panel width 600 mm, without instrument transformer b) Panel width 600 mm, with instrument transformer Section C - C c Section D - D c ZX (155) (7) 9 d ZX d (155) (7) b b (143) a (143) a c) Panel width 800 mm, with instrument transformer d) Panel width 800 mm, without instrument transformer Figure 5/5: Sections for figure 5/4 See figure 5/4 for legends and dimensional table Minimum ABB Power Distribution 35

36 A B x x a 7 b c 000 A B 100 M 10 M 10 M Figure 5/6: Guideline construction data for a raised false floor See figure 5/7 for sections Minimum 1 Inspection aisle Operator aisle 3 Basement entrance 4 Platform, approx. 5 kn 5 Pressure relief duct at side, including end cover 6 False floor structure, only shown in the area of the switchgear 7 Earthing bar 8 Panel without cable connection, e.g. bus coupler panel 9 Door 10 Waste air opening 11 Intake air opening 1 Intake air opening, if required 13 Waste air opening 14 Or as shown in figure 5/5 15 Height of cable basement as required 16 To earthing bar 17 False floor structure, supplied by others 18 Power cable, plug size 19 Power cable, plug size 3 0 Instrument transformer for billing purposes Panel width a b c in switchgear mm mm mm 600 mm mm or 600 mixed with 800 mm Room height 1 : Rated Absorber Room height current A mm 000 with without 500 > 000 with 3100 > 000 without ABB Power Distribution

37 Section A - A Section B - B b b ZX (7) c ZX c X a X 1333 (7) a 15 a) Panel width 600 mm, without instrument transformer b) Panel width 800 mm, with instrument transformer Detail X (7) 3 Figure 5/7: Sections for figure 5/6 See figure 5/6 for legends and dimensional table Minimum ABB Power Distribution 37

38 5.7 Erection and connection of the panels (Figures 5/3 and 5/8 to 5/14) Note: Do not walk on the top of the panels (rupture point for pressure relief system!) Preparatory work Grease the upper surfaces of the foundation frame (this facilitates erection and alignment of the individual panels). Enter the two or four guide pins 35 at the sides of the panels into the relevant bores (see figure 5/10, section A-A) Erection of the switchgear Erect the end panel of the switchgear at the precise position specified on the foundation frame. Lightly enter panel fastening bolts 1.4 into the relevant threaded bores in the foundation frame. Align the panel if necessary. Perform a final check on the aligned position of the panel and fasten it to the foundation frame by tightening the panel fastening bolts 1.4. Remove the protective caps from the busbar sockets 3.1. Carefully check insulating parts 3. and contact tubes 3.3 for any dirt, and clean if necessary (see also section 7.). Note: Only prepare insulating parts and contact tubes for the panel currently being erected. Protect them from further contamination! Evenly apply a thin coating of assembly paste AP to the conical surfaces A of insulating parts 3.. Note: Leave no ungreased areas on conical surface A. Carefully insert contact tubes 3.3 and insulating parts 3. into the busbar sockets 3.1. Slide the adjacent panel carefully and evenly (without tipping) against the erected panel in such a way that the contact tubes, insulating parts and guide pins slide into the corresponding bores without the use of force. If necessary, align the panel appropriately with the panel height adjustment bolts 1.5. As soon as the distance between the two panels is so small that bolts 36 and 37 can be entered in the bores in the erected panel, insert these, each with nuts and dished washers respectively. Spacer 38 is also to be fitted on socket head bolt 37 (see figure 5/9, section B-B). Then join the two panels together by tightening bolts 36 and 37 step by step. Completely bolt the panels together with bolts 40, each with dished washers (see figure 5/8). When the panels have been completely joined, check the second panel again for correct alignment and fasten it to the foundation frame with the panel fastening bolts 1.4. Dismantle connecting link 14 for the main earthing bar 15 in the cable compartment and lead it through to the adjacent panel. Bolt the connecting link to the main earthing bar with bolts 39 and one dished washer at each of the bolt head and nut ends. Check the bolted connection between main earthing bar 15 and the connecting link 14 in the previously erected panel and tighten bolt 39 if necessary. Erect the further panels by following the same procedure. Assembly of the top pressure relief duct, the absorber and the cooler if fitted can be effected during installation of the individual panels or when all panels have been joined together. 38 ABB Power Distribution

39 View X A A B B X C C a) Double busbar A B A B C C b) Single busbar Figure 5/8: Switchgear erection (See figure 5/9 for sections and details) 3 Busbar connection, plug-in type 3.1 Busbar socket 3. Insulating part 3.3 Contact tube 35 Guide pin 37.1 M8 hexagon nut 37. Dished washer 8 40 Socket head bolt M8 x 5 ABB Power Distribution 39

40 Section A-A Panel division ca. 50 Evenly greased with assembly paste AP A Busbar connection Insulating part Section B-B Section C-C Panel division 10 Panel division Panel/panel connection Earthing bar connection Figure 5/9: Switchgear erection (section for figure 5/8) 14 Panel/panel connecting link 15 Main earthing bar 3 Busbar connection, plug-in type 3.1 Busbar socket 3. Insulating part 3.4 O-ring 35.1 M10 hexagon nut 35. Dished washer Socket head bolt M8 x Dished washer 8 38 Spacer 39 Socket head bolt M10 x ABB Power Distribution

41 A B A B Section A-A Section B-B a) Panel joined up from the right b) Panel joined up from the left Figure 5/10: Switchgear erection panel/panel connection, view from top (without pressure relief duct) 35 Guide pin 35.1 M10 hexagon nut 35. Dished washer Socket head bolt M10 x 50 ABB Power Distribution 41

42 35. Detail X 35. X Detail Y Evenly greased, assembly paste AP 4 Y Figure 5/11: Busbar end in an end panel 35.1 M10 hexagon nut 35. Dished washer Dished washer 8 40 Socket head bolt M8 x 5 41 Plate for blanking plug 4 Blanking plug 43 Socket head bolt M10 x A 50 0 B F C D 600 Figure 5/1: Pressure relief duct, side, double busbar, right-hand side mounting shown A B C D F Pressure relief duct with absorber Pressure relief duct, top Pressure relief duct, side End cover Panel 44 Fastening material, packed in bag group Screw fasteners for side pressure relief duct 45 Plug 4 ABB Power Distribution

43 L3 L L1 Figure 5/13: Busbar connection 3.1 Busbar socket 3. Insulating part 3.3 Contact tube Figure 5/14: Assembly of the busbar connection, shown for 150 A L1: Protective cap removed L: Contact tube 3.3 fitted L3: Insulating part 3. and contact tube 3.3 fitted Figure 5/15: Plug connector for single-core plastic-insulated cable 10 Socket 11 Cable plug K Cable earthing conductor to be connected to switchgear earth, do not establish cable earthing via the plug Figure 5/16: Cable compartment (panel side wall cut out) 1 Surge arrester 13 Floor plate, split 13.1 Reducer ring 13. Cable mounting 13.3 Supporting section, at earth potential 13.4 Insulated earthing point for cable jacket (nonstandard) 7 High voltage cable ABB Power Distribution 43

44 5.8 Connection of cables and wiring The cable compartments (I) in the panels are fitted with cable connection fittings in accordance with the cable types and sizes specified in the project planning for the switchgear as a whole High voltage plastic-insulated cable with plug connectors (Figures 3/4, 3/11, 5/15 and 5/16) Lay the single-core plastic-insulated cables as specified in the project planning to the individual panels. Remove the transport covers fitted to protect the sockets. Expose the cable cores, check the correct phase assignment, and secure Final erection work Clean the external surfaces of the enclosure and control cabinets in the switchgear where necessary and check for any damage to the paintwork, touching up with a suitable paint if necessary (see Section 7.3). Properly refit any cladding and covers of operating mechanisms, cable ducts, etc. removed during the erection work. Remove all tools and other foreign bodies from the switchgear. Check the general condition of the switchgear. Check that the areas adjacent to the switchgear are in the proper condition. Fit cable plug 11 in accordance with the manufacturer s instructions. Fit the plugs to the sockets 10 mounted in the circuit-breaker compartment floor (without opening the insulating gas compartment) and secure them with bolts. Align the cables and fasten them at mountings 13. Close off any unused sockets, e.g. in spare panels, with suitable cable blanking plugs to ensure the necessary insulation Control cables and wiring (Figures 3/ and 5/1 Establish the necessary connections for incoming and outgoing cables and wiring, and cross connections. The control cables and wiring are to be laid in cable ducts at the right of the cable compartment (for external wiring). The connections from panel to panel are to be made by plug connectors in the control cabinets. 5.9 Preparing the insulating gas system for operation Observe the relevant data in instruction manual BA 47/E Insulating gas system for ZX switchgear. 44 ABB Power Distribution

45 6 Commissioning/operation Note on safety at work Operation by trained specialists familiar with the particular switchgear only. 6.1 Commissioning Preparatory work In preparation for commissioning, the following work is to be performed prior to connection with the high voltage power supply: Connect the auxiliary and control voltage and check the correct polarity. Check mechanical and electrical interlocks for compliance with the specified conditions. Perform a functional test on the protective devices (observe DIN VDE 014. Check the general condition of the switchgear and external conditions for detrimental factors of any kind. Display the instructions for handling SF 6 in the switchroom. The handling specifications for SF 6 also apply accordingly to nitrogen. Display the ABB instruction manual on the handling of insulating gas and behaviour during faults in the switchroom. Instruct the local operators on the fundamental details of operating the switchgear in normal service. Check the readiness for operation and the switching condition of the upstream and downstream electrical equipment. Perform further checks where necessary on the following equipment from the areas adjacent to the switchgear: power cables control wiring auxiliary voltage and its polarity remote controls external earth with connection to main earthing bar 15 switchroom equipment switchroom condition Initial start-up Comply with all relevant safety regulations Ensure that the switchgear circuit-breakers are in the OFF position. Close the disconnector for the relevant busbar system. Cancel any existing short-circuiting and earthing connections in the critical switching area. Energise the switchgear step by step, observing the displays on the REF54. Check that corresponding conductor sections are in phase where relevant with several incoming feeders and switchgear sections. Check measurements and functions dependant on high voltage. Look out for irregularities of any kind. 6. Switching operations 6..1 Circuit-breaker (Figures 3/, 6/1, 6/ and 6/4) The circuit-breaker is fitted with a charging motor. Charging of the spring energy storage mechanism takes place automatically. Opening and closing the circuit-breaker: Opening and closing are effected by selection on the bay control and protection unit REF54. ON-OFF switching operations may only be performed with the control cabinet door closed. Opening the control cabinet door constitutes intervention in the interlock system. Observe the position indicator. Emergency manual operation: 1. On failure of the charging motor, the charging process can be performed or completed by hand: Open control cabinet door 1.1. Insert charging lever 8.9 into recess 8.8 and pump for approx. 5 strokes until the charged condition is displayed. When the charged condition is reached, the charging mechanism automatically disengages and further strokes of the charging lever have no effect. Key to the charging condition displays: Discharged Charged. If the control voltage fails with the circuit-breaker closed, it is possible to open it using the mechanical OFF push-button 8.3. Note: On failure of the control voltage, there is no maloperation protection for the circuit-breaker, three-position switch and disconnector during emergency manual operation. ABB Power Distribution 45

46 6.. Three-position switch and disconnector (Figures 3/, 3/11, 6/3, 6/5 and 6/6) The three-position switch and the disconnector 19 are fitted with motor-operated mechanisms. Opening and closing are effected by selection on the bay control and protection unit. ON-OFF switching operations may only be performed with the control cabinet door closed. Opening the control cabinet door constitutes intervention in the interlock system. Observe the position indicator on LCD display 5.1 or on the control unit. Sensors 9 to 3 on the three-position switch operating mechanism 3 detect the following switch positions: Disconnector -Q1 ON and OFF, and earthing switch -Q5 ON and OFF. Sensors 33 and 34 on disconnector operating mechanism 0 detect the following switch positions: Disconnector -Q ON and OFF. Emergency manual operation: In place of motorised operation, the switching process can also be initiated and completed manually. Caution! The interlock is ineffective on emergency manual operation. Open control cabinet door 1.1 Prior to emergency manual operation, switch the relevant m.c.b. (F101 or F10) off. Insert the crank in the hollow shaft. Three-position switch -Q1/-Q5: If the three-position switch is in the central position (i.e. disconnector and earthing switch OFF), the disconnector can be closed with approx. 4 clockwise turns, and the earthing switch with approx. 4 anti-clockwise turns. If the earthing switch ON position is to be reached from the disconnector ON position, or vice versa, the crank is to be removed in the self-inhibiting central position (disconnector and earthing switch OFF) and refitted. When the crank is refitted, the further switching operation is automatically enabled. Disconnector -Q: Close the disconnector with approx. 4 clockwise turns and open it with approx. 4 anticlockwise turns. Note: Always perform every switching operation right up to the stop in the relevant limit position. Observe the mechanical and electrical position indicators Undervoltage release Undervoltage releases may be fitted as an option. In order to prevent the circuit-breaker being opened by the undervoltage release on power failure with teeoff earthing, an interlock rod or wire is provided. 6.3 Observation of the display and monitoring facilities Gas monitoring (Figures 3/11 and 6/ All high voltage compartments in the switchgear must have a sufficient insulating gas pressure during operation. The minimum operating gauge pressure (p e ) is listed in section.1. This is monitored by sensors 4, 7 and 1. If the gas pressure falls below the minimum operating gauge pressure, an LED on the bay control and protection unit signals that the gas should be topped up. Note: If a panel is isolated for a relatively long period (several weeks), m.c.b. F116 for the auxiliary voltage supply to the REF54 must remain on. Only in this way is monitoring of the insulating gas ensured. Details on the gas system of the ZX switchgear can be found in instruction manual BA Electrical/mechanical display/monitoring During operation of the switchgear, observe all visible operating data and condition displays in the secondary system and watch out for irregularities of any kind, including the external conditions of the switchgear. 6.4 Test procedures Testing for the off-circuit condition (Figure 6/ The panels are fitted with the low impedance, capacitive voltage indicator system LRM, including corresponding (hand-held) display units with connecting plugs for testing of the off-circuit condition. For details, see draft DIN VDE 068 Part 415, or IEC 6143 Part ABB Power Distribution

47 Note: Only display units which comply with the IEC or VDE standards and the technical design of the indicator system in the relevant switchgear may be used! Note: The measuring sockets must on no account be short-circuited, except during voltage testing of the system (e.g. with power frequency withstand voltage or impulse withstand voltage)! Testing for the off-circuit condition is performed with a plug in display unit at corresponding pairs of measuring sockets 6 in the vicinity of the panel controls. Use of the display unit: Perform a functional test on the display unit immediately before and after use, e.g. with interface tester KSP. The display must be clearly visible. The presence of operating voltage is indicated by a signal. Observe the individual operating instructions for the display unit for the relevant switchgear! Interface testing: Perform interface testing as a functional test on all coupling components, e.g. with interface tester KSP. The interface test is a repeat test to IEC 6143 Part 5 or draft DIN VDE 068 Part Testing for the in-phase condition Testing for the in-phase condition, e.g. when there is more than one incoming feeder, can be performed with a suitable phase comparator at measuring sockets 6 on the capacitive voltage indication system. Test procedure: Only use phase comparators which comply with the IEC or VDE specifications and the technical design of the display system in the relevant switchgear! Perform a functional test on the equipment at the start of testing. Do not exceed the maximum permissible length of measuring leads per phase. Connect the measuring leads precisely assigned to the corresponding main conductor sections. Always follow the details in the operating instructions for the phase comparator! High voltage tests (Figures 6/1 and 6/8) The test plugs available for high voltage tests, shown in figure 6/8, are suitable for the following applications up to and including 4 kv rated voltage. For high voltage tests on the 36 kv rated voltage level, separate test facilities are required. Information on these can be obtained from the switchgear manufacturer. Taking account of the sensor systems used and the bay control and protection unit, the test voltages must not exceed the following values: Cable tests with DC voltage: 1 kv switchgear: 48 kv 4/36 kv switchgear: 70 kv up to 1 hour. Higher values on request. Insulation testing of the switchgear at the relevant power frequency withstand voltage: 1 kv switchgear: 8 kv 4 kv switchgear: 50 kv 36 kv switchgear: 70 kv. Performance of voltage tests: Isolate the switchgear area in accordance with the safety rules of VDE 0105 and secure it to prevent reconnection. Verify the off-circuit condition with a suitable hand-held display unit at measuring sockets 6 on the capacitive voltage indicator system. Unscrew surge arresters where fitted, or unscrew the cable blanking plugs from the free cable sockets. Check the test plug to ensure that the surface is clean and dry, and clean it if necessary. Grease the silicone part of the test plugs in accordance with the directions. Insert the test plug into the prepared cable socket and screw it tight. Notes: Only fit the test plugs for voltage tests for the duration of those tests. Short-circuit the measuring sockets 6 in the panels concerned for the duration of the testing process at test voltages up to rated power frequency withstand voltage. Applies to integrated voltage sensors. With plug-in voltage sensors/instrument transformers, the cable test voltages permissible to DIN standards may be used if the sensors are withdrawn. ABB Power Distribution 47

48 For performance of cable tests, in the switching condition tee-off disconnected and earthed, earthing of the cable has to be cancelled by opening the circuit-breaker. This is accomplished by using the mechanical OFF button to open the circuit-breaker (see also Section 3.9) Current tests (Figures 6/1 and 6/9) The test plugs available for current test are suitable for the following applications: Testing of the protection functions in the bay control and protection unit REF54 by means of primary current injection. Test instruction: The following is to be observed when testing the protection system of the REF54: In order to prevent damage to the OFF-release coil during testing, either the OFF-release coil has to be disconnected or the protection test equipment must be deactivated by the trip command. This ensures that the opening release is not energised in the meantime by the trip command, which could lead to the coil burning out. Establishment of maintenance earthing in conjunction with an earthing and short-circuiting set. The short-circuit resistance of the current test plugs for the switchgear must correspond to the condition of the individual switchgear. Handling of the plugs for current tests: Isolate the switchgear area in accordance with the safety rules of VDE 0105 and secure it to prevent reconnection. Verify the off-circuit condition with a suitable (hand-held) display unit at measuring sockets 6 on the capacitive voltage indicator system. Unscrew surge arresters where fitted, or unscrew the cable blanking plugs on the free cable sockets. Check the test plug to verify that the surface is clean and dry, and clean it if necessary Maintenance earthing a) Double busbar systems: In the double busbar system, there is an opportunity to earth the busbar via the bus coupler. b) Single busbar systems: Earthing of the busbar with the bus tie / riser, as described in section Earthing with an earthing and short-circuiting set. Handling during earthing with an earthing and short-circuiting set: (Figures 6/1 and 6/9) The plugs for current tests described under are used in conjunction with corresponding cable sets for short-circuiting and earthing to establish maintenance earths. The short-circuit resistance of the cable set must correspond to the conditions of the switchgear. Caution! Observe the notes in Section 3.9 on the interlock dependencies for all work with earthing and shortcircuiting sets! Isolate the switchgear area in accordance with the safety rules of VDE 0105 and secure it to prevent reconnection. Verify the off-circuit condition with a suitable (hand-held) display unit at measuring sockets 6 on the capacitive voltage indicator system. Unscrew surge arresters if fitted, or unscrew the cable blanking plugs on the free cable sockets. Check the test plugs to ensure that the surface is clean and dry, and clean them if necessary. Carefully screw the short-circuiting and earthing cable set to the test plug. Connect the common earthing connector of the cable set to the earthing terminal of the panel. Insert the test plugs into the prepared cable sockets and screw them tight. Insert the test plug into the prepared cable socket and screw it tight. Only fit the test plugs for the duration of the tests. 48 ABB Power Distribution

49 6.5 Application of the X-ray regulations One of the physical properties of vacuum insulation is the possibility of x-ray emissions when the contact gap is open. The specified type test performed by the Physikalisch-Technische Bundesanstalt (PTB) in Brunswick demonstrates that the local dosage output of 1 µsv/h at a distance of 10 cm from the touchable surface is not exceeded. The results are as follows: The use of the vacuum interrupters at rated voltage is completely safe. Application of the rated power frequency withstand voltage specified for the switching device by VDE 0670 and IEC or a DC voltage of 48 kv or 70 kv during cable tests is also safe. Higher voltages than the rated power frequency withstand voltage specified in DIN VDE or IEC standards or the DC voltage must not be applied! Fulfilment of the above requirement with the vacuum interrupter in the open position is dependent on maintenance of the specified distance between the contacts (which is automatically ensured with correct mechanism function and force transmission). ABB Power Distribution 49

50 (8.) Figure 6/1: Display area on the panel Figure 6/: Handling of the door-lock 1.1 Control cabinet door 5 Bay control and protection unit REF LCD display (example) 5. Light-emitting diode (LED) 6 Measuring sockets for capacitive voltage indicator system Opening the control cabinet door: - Open the safety lock (if fitted) - Release the catch with the double bit key - Draw the closing lever out to an angle of 45 and then swing it upwards to the left through approx. 135 until the stop is reached Closing the control cabinet door: - reverse the procedure for opening 1.1 Control cabinet door 8 Door-lock 8.1 Catch (8.) Safety lock (if ordered) 8.3 Double bit key 8.4 Closing lever Figure 6/3: Operating mechanisms for the three-position switch and disconnector 3 Three-position switch mechanism 3.1 Hollow shaft (emergency manual operation shaft) 3. Mechanical position indicator 3.3 Cam for OFF position of the three-position switch 3.4 Drive motor for three-position switch 0 Disconnector mechanism 0.1 Hollow shaft (emergency manual operation shaft) 0. Mechanical position indicator 9 Sensor, disconnector -Q1 ON 30 Sensor, disconnector -Q1 OFF 31 Sensor, earthing switch ON 3 Sensor, earthing switch OFF 33 Sensor, disconnector -Q ON 34 Sensor, disconnector -Q OFF 50 ABB Power Distribution

51 Figure 6/4: Emergency manual operation, circuit-breaker type VD4 X Figure 6/5: Emergency manual operation, three-position switch UXTE 8 Circuit-breaker operating mechanism 8.1 Front plate 8. ON push-button 8.3 OFF push-button 8.4 Operating cycle counter 8.5 Mechanical position indicator 8.6 Rating plate 8.7 Charging condition indicator 8.8 Recess for charging lever Charging lever for emergency manual operation Figure 6/6: Emergency manual operation, disconnector UXT Figure 6/7: View of the stored-energy spring mechanism for the circuit-breaker, front plate removed ABB Power Distribution 51

52 Figure 6/8: Test plug for high voltage tests up to 4 kv rated voltage Figure 6/9: Test plug for current tests Also usable as a maintenance earth in conjunction with an earthing and short-circuiting set 5 ABB Power Distribution

53 7 Maintenance Maintenance serves to preserve trouble-free operation and achieve the longest possible working life of the switchgear. In accordance with DIN and IEC 6108, it comprises the following closely related activities: Inspection: Determination of the actual condition Servicing: Repairs: Measures to maintain the specified condition Measures to re-establish the specified condition 7.1 General It is essential to observe the following during all maintenance work: The relevant regulations in section 1.. The notes on safety at work in section 6 Standards and specifications in the country where the switchgear is erected. It is recommended that ABB after sales service personnel be called in to perform servicing and repair work. Follow/observe the instructions on SF 6 systems and the ABB instruction manual on the handling of insulating gases and procedures for fault conditions. The handling regulations for SF 6 also apply accordingly to nitrogen. Keep these instructions and manual permanently on display and available in the switchroom. The inspection and servicing intervals for the switching devices are determined by fixed criteria such as switching frequency and number of shortcircuit breaking operations. The length of the intervals for inspection and servicing of the control cabinet and its equipment is influenced by ambient conditions (for instance pollution and aggressive atmosphere). In addition to this instruction manual, the following instruction manuals must be observed: Insulating gas system BA 47/E Bay control and protection unit REF54 BA 453/E Circuit-breaker VD4 X BA 436/E Further details can be found in the technical documentation for the switchgear installation (including, for example, any agreed special operating conditions). 7. Inspection/servicing Under normal operating conditions (see section 1.3), checking of the operating mechanisms is to be carried out by a suitably qualified electrician after 10 years at the latest or after 10,000 operating cycles of the circuit-breaker and,000 operating cycles of the three-position switch or disconnector. In exceptional operating conditions (including adverse climatic conditions) and/or particularly adverse environments (including heavy contamination and aggressive atmosphere) inspection at shorter intervals may be required. Inspection is first and foremost to be visual examination for contamination, corrosion and moisture. The inspection should however also include checking of the mechanical and electrical functions of the following devices: Switching devices Bay control and protection unit REF54. If an incorrect condition is found, the corresponding repair work is to be initiated immediately. Cleaning If the necessity of cleaning is established during inspections, the following procedure is to be adopted: Prior to cleaning, isolate and secure the working area if necessary in accordance with the safety rules of DIN VDE and IEC. Cleaning of surfaces in general: Remove weakly adhering dry dust deposits with a soft dry cloth. Remove more strongly adhering contamination with slightly alkaline household cleanser, or with Rivolta BWR 10. Cleaning of insulating material surfaces and conductive parts (outside the gas compartments): Minor contamination with Rivolta BWR 10. Strongly adhering contamination with Cold cleanser 716 Cleaning of busbar insulating parts, cable sockets and busbar sockets with cable cleanser MAB. Observe the manufacturer s instructions and the special ABB instruction manuals BA 100/E and BA 1006/E on safety at work. Wipe down after cleaning, using clean water, and dry properly. ABB Power Distribution 53

54 7..1 Vacuum circuit-breaker (Figure 6/7) The vacuum circuit-breaker has a long service life. It has a low maintenance operating mechanism and the breaker poles are maintenancefree. Consult the relevant sections of instruction manual BA 436/E for further information. 7.. Three-position switch and disconnector The three-position switch and disconnector are maintenance-free for 000 operating cycles Gas system and gas servicing Consult the relevant sections of instruction manual BA 47/E for further information Outlet filter The filter mats in the outlet filter are to be changed as required. Note the information on inspection and servicing in section 7.. Replacement procedure: Draw off the grille. This is done by prising off with the fingertips in the recesses at the bottom end of the filter. Change the filter mat. Replace the grille. Spare filter mats: Part no. (order ref.) Filter mat for fan system: GCE P Repair Remove all rust from damaged paintwork areas on sheet steel and other steel parts mechanically, e.g. with a wire brush. Lightly grind the surrounding paint coat and carefully degrease the entire area. Then immediately apply an anti-rust primer and, after an appropriate hardening period, apply the top coat. Only use suitable and compatible paint products. Use top coat paint in the standard colour RAL 703, or the relevant special colour. Carefully remove any white rust from galvanised and chromium plated functional parts and rust on phosphated parts with a wire brush or a cleaning pad, e.g. Scotch-Brite, and clean with a dry cloth. Then grease evenly with Isoflex Topas NB 5. Notes: It is essential to observe the section on safety at work in instruction manual BA 47/E for all work on gas compartments. Caution when working in gas compartments! High gas concentrations may result in a danger of asphyxiation! Filter mat for control cabinet: GCE P ABB Power Distribution

55 7.4 Working and auxiliary materials Working materials Part no. (Order ref.) Insulating gas system: Nitrogen (N ) GCE099067P0100 Degree of purity 4.6 Delivery form: liquid gas in steel cylinders Observe the relevant ABB instruction manual BA 1007/E on safety at work! GCEA901007P010 Sulphur hexafluoride (SF 6 ) GCE099053P0103 Delivery form: liquid gas in steel cylinders Observe the quality requirements to IEC 60376/ VDE 0373! Observe the relevant ABB instruction manual GCEA901004P010 BA 1004/E, pp. 1 to 3, on safety at work! Note: If extreme temperatures 50 C cannot be ruled out where gas cylinders are stored, transported or temporarily stored in the open air in direct sunlight, a reduced filling factor of 0.75 kg/l cylinder contents is to be required when ordering for safety reasons! Drying agent material: Drying agent bag to DIN , capacity per bag 10 g GCE P Auxiliary materials Lubricants: Isoflex Topas NB 5, GCE000749P0100 Assembly paste AP, for insulating part/cast resin plug connections GCE P0100 Cleaning agents for general cleaning: Rivolta BWR 10, GCE P0100 Observe the relevant ABB instruction manual BA 100/E GCEA90100P010 Cleaning agent for conductive parts, parts in insulating material, and all parts with heavy contamination: Cold cleaner 716, GCE P0100 Observe the relevant ABB instruction manual BA 1006/E GCEA901006P010 Cleaning agent for busbar insulating parts, busbar sockets and cable sockets: Cable cleaner MAB GCE P0100 Paintwork: Paint in standard colour RAL kg-box GCE R0103 Spray tin GCE P0100 ABB Power Distribution 55

56 Instruction manual no. GCEA P010 Printed in Germany ( PPI) We reserve the right to make changes in the course of technical development. ABB Calor Emag Mittelspannung GmbH ABB Sace T.M.S. S.p.A Oberhausener Strasse 33 Petzower Strasse 8 Via Friuli, 4 D-4047 Ratingen D-1454 Glindow I-4044 Dalmine Phone: +49(0)1 0/1-1 30, Fax: +49(0)1 0/ Phone: /395111, Fax: / [email protected] [email protected] Internet: Internet:

ZS1 Air-insulated medium voltage switchgear, 12 kv/17.5 kv Instruction manual BA 372/04 E

ZS1 Air-insulated medium voltage switchgear, 12 kv/17.5 kv Instruction manual BA 372/04 E ZS1 Air-insulated medium voltage switchgear, 12 kv/17.5 kv Instruction manual BA 372/04 E ABB Power Distribution 1 Your safety first always! That's why our instruction manual begins with these recommendations:

More information

NATUS NES / NES-H Draw-out Type Medium Voltage Switchgear Systems. Safe energy distribution that meets the highest industrial requirements

NATUS NES / NES-H Draw-out Type Medium Voltage Switchgear Systems. Safe energy distribution that meets the highest industrial requirements NATUS NES / NES-H Draw-out Type Medium Voltage Switchgear Systems Safe energy distribution that meets the highest industrial requirements NATUS switchgear systems your advantages minimal use of insulant

More information

The Intelligent AX1 Switchgear for Medium Voltage

The Intelligent AX1 Switchgear for Medium Voltage The Intelligent AX1 Switchgear for Medium Voltage Leif Lundin, Manager of Research and Development, Division Medium Voltage and Compact Substations, ABB Distribution, Sweden Abstract The newly launched

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

Our brand POWER DYNAMIC PASSION COMMITMENT CREATIVITY. A strong brand for strong products: 8PU Premium. MV Energy

Our brand POWER DYNAMIC PASSION COMMITMENT CREATIVITY. A strong brand for strong products: 8PU Premium. MV Energy Our brand A strong brand for strong products: The ENERGOLINE brand represents our product portfolio of INDUSTRIAL SWITCHGEAR SYSTEMS. Our products are characterized by a high degree of safety, flexibility

More information

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance SPECIFICATION FOR LOW VOLTAGE SWITCHBOARD SEN I N D E X Description 10 STANDARD TECHNICAL REQUIREMENTS 11 Standards 12 General Operating Conditions 13 General Description Of Switchboard 131 Structure 132

More information

INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002

INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002 INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002 NEW GAS INSULATED SWITCHGEAR (GIS) FOR ALL MEDIUM VOLTAGE APPLICATIONS H. Fink, ABB Calor Emag Mittelspannungs GmbH; M. Hyrenbach, ABB Calor

More information

Voltage Rated operating voltage [kv] 12 24 Rated power frequency withstand voltage [kv] 28 50 Rated lightning impulse withstand voltage [kv] 75 125

Voltage Rated operating voltage [kv] 12 24 Rated power frequency withstand voltage [kv] 28 50 Rated lightning impulse withstand voltage [kv] 75 125 Standards and Regulations IEC 62271-200 ; VDE 0671-200 ; BS EN 62271-200 Technical Data MC3-12 MC3-24 Voltage Rated operating voltage [kv] 12 24 Rated power frequency withstand voltage [kv] 28 50 Rated

More information

UniGear ZS1. Medium voltage, arc proof, air insulated switchgear for primary distribution

UniGear ZS1. Medium voltage, arc proof, air insulated switchgear for primary distribution UniGear ZS1 Medium voltage, arc proof, air insulated switchgear for primary distribution UniGear ZS1: an innovative solution for all installation requirements ABB UniGear is medium voltage metal-clad,

More information

e 2 ALPHA Medium Voltage Switchgear Data Sheet K-1.1.2 EN

e 2 ALPHA Medium Voltage Switchgear Data Sheet K-1.1.2 EN e 2 ALPHA Medium Voltage Switchgear Data Sheet K-1.1.2 EN We create ideas with power! ELEKTROMETAL ENERGETYKA SA is a new Polish company providing solutions for electrical power engineering. Our services

More information

METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV. tgood.com. Energy. Fast.

METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV. tgood.com. Energy. Fast. METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW Integral substation component

More information

Technical catalogue TK 503/01 E. ZX0.2 Gas-insulated medium voltage switchgear

Technical catalogue TK 503/01 E. ZX0.2 Gas-insulated medium voltage switchgear Technical catalogue TK 503/01 E ZX0.2 Gas-insulated medium voltage switchgear Contents Page 1 Applications 4 2 Characteristics 5 3 Your benefit 6 4 Technical data 7 4.1 Technical data of the panel 7 4.2

More information

Installation, Operation and Maintenance Instructions. Uniflex ABB PTMV

Installation, Operation and Maintenance Instructions. Uniflex ABB PTMV Installation, Operation and Maintenance Instructions Uniflex ABB PTMV SAFETY FIRST! For safe and correct usage note the following recommendations: Only install switchgear and switchboards in enclosed rooms

More information

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number

More information

ELEKTROTEHNI KO PODJETJE Leskoπkova cesta 12, 1000 Ljubljana, SLOVENIA

ELEKTROTEHNI KO PODJETJE Leskoπkova cesta 12, 1000 Ljubljana, SLOVENIA MRO Modularne Razdelilne Omare d.o.o. ELEKTROTEHNI KO PODJETJE Leskoπkova cesta 2, 000 Ljubljana, LOVENIA MC GENERAL When to use? MC - modular switchgear cabinets are type-tested, factory built switchgears,

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

Type-Tested Power Distribution Board 8PT with Rear Busbars. sivacon

Type-Tested Power Distribution Board 8PT with Rear Busbars. sivacon Type-Tested Power Distribution Board 8PT with Rear Busbars sivacon The Obvious Solution for Global Challenges SIVACON Type-testing is one of today s important issues for low-voltage technology and will

More information

DF-DT (G) MEDIUM VOLTAGE SWITCHGEAR THE MODULAR CONCEPT. User Manual. SGC - SwitchGear Company nv - Moorstraat 24 - B-9850 Nevele - Belgium

DF-DT (G) MEDIUM VOLTAGE SWITCHGEAR THE MODULAR CONCEPT. User Manual. SGC - SwitchGear Company nv - Moorstraat 24 - B-9850 Nevele - Belgium DF-DT (G) MEDIUM VOLTAGE SWITCHGEAR THE MODULAR CONCEPT User Manual SGC - SwitchGear Company nv - Moorstraat 24 - B-9850 Nevele - Belgium +32 (0)9/321.91.12 - Fax +32 (0)9/321.91.13 - e-mail: [email protected]

More information

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw 4 937 DESIO Current valve for AC 24 V pulse/pause control of electrical loads up to 30 kw SEA45.1 Use The current valve is used for the control of electric heating elements in heating, ventilation and

More information

Technical data UNIBLOCK UBSF 180 625

Technical data UNIBLOCK UBSF 180 625 Data TECHNICL DT Technical data UNIBLOCK UBSF 80 6 Output data Type UBSF 80 UBSF 0 UBSF 00 UBSF 6 Output power 80 kv 0 kv 00 kv 6 kv Output voltage 80/77 V 0/ V 0/ V 0/ V Output current 7 8 66 80 Power

More information

Medium Voltage Switchgear

Medium Voltage Switchgear Uniswitch Medium Voltage Switchgear 12 kv, 17.5 kv, 24 kv 630 A and 1250 A Operation and TABLE OF CONTENTS 1 Summary...1 1.1 General...1 1.2 Standards and specifications...2 1.3 Service conditions...3

More information

Advantages of Fixed Circuit Breaker Switchgear

Advantages of Fixed Circuit Breaker Switchgear Advantages of Fixed Circuit Breaker Switchgear by Lionel Mackay, EDF Energy, and Mike Adams, Schneider Electric Ltd Introduction The purpose of this paper is to review the advantages of fixed circuit breaker

More information

High-Voltage Compact Switchgear 3AP1 DTC for 145 kv and 245 kv

High-Voltage Compact Switchgear 3AP1 DTC for 145 kv and 245 kv High-Voltage Compact Switchgear AP1 DTC for 1 kv and kv Answers for energy. The AP1 DTC Complying with our Customers demands Experience you can rely on - at anytime, anywhere Decades of experience in high-voltage

More information

MEDIUM VOLTAGE SWITCHGEAR CATALOGUE. Code: P2490_xx

MEDIUM VOLTAGE SWITCHGEAR CATALOGUE. Code: P2490_xx MEDIUM VOLTAGE SWITCHGEAR for secondary distribution CATALOGUE Code: P2490_xx CONTENTS 1 About us 2 Medium Voltage Business Unit Portfolio 3 Overview 8 Medium Voltage Switchgear Types. Equipment used.

More information

Mounting Instructions. Torque Transducer. A0329 3.2 en

Mounting Instructions. Torque Transducer. A0329 3.2 en Mounting Instructions Torque Transducer T5 T5 Contents 3 Page Safety instructions.............................................. 4 1 Measuring characteristics..................................... 7 2 Mounting.....................................................

More information

Magnetic and Hydraulic-Magnetic Circuit Breaker 8340-G2...

Magnetic and Hydraulic-Magnetic Circuit Breaker 8340-G2... Magnetic and Hydraulic-Magnetic Circuit Breaker 840-G2... Description Single, two and three pole magnetic circuit breakers with trip-free mechanism and push/pull on/off manual actuation. A choice of fast

More information

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution Medium Voltage Products ZN1 12 kv arc-proof air-insulated switchgear for primary distribution ZN1 an innovative switchgear for power distribution requirements ABB ZN1 primary distribution switchgear is

More information

Cross-beam scanning system to detect slim objects. 100 mm 3.937 in

Cross-beam scanning system to detect slim objects. 100 mm 3.937 in 891 Object Area Sensor General terms and conditions... F-17 Related Information Glossary of terms... P.1359~ Sensor selection guide...p.831~ General precautions... P.1405 PHOTO PHOTO Conforming to EMC

More information

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in

More information

VM1. Vacuum circuit-breaker Instruction manual BA 504/02 E

VM1. Vacuum circuit-breaker Instruction manual BA 504/02 E VM1 Vacuum circuit-breaker Instruction manual BA 0/0 E Your safety first always! That's why our instruction manual begins with these recommendations: Only install switchgear and/or switchboards in enclosed

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

SF 6 Gas Insulated Switchgear Type SDF for 170 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDF for 170 kv 06B1-E-0001 With Trustworthy Technology, Structure Fuji Electric as a manufacturer of comprehensive substation equipment

More information

PPS-PPQ-BT-PIAS RESIN INSULATORS FOR OIL INSULATED ELECTRICAL MACHINES

PPS-PPQ-BT-PIAS RESIN INSULATORS FOR OIL INSULATED ELECTRICAL MACHINES PPS-PPQ-BT-PIAS RESIN INSULATORS FOR OIL INSULATED ELECTRICAL MACHINES BUSHING WITH PLUG CONNECTION WITH OUTER CONE PPS CHARACTERISTICS The PPS bushing can be used as a fixed section for the entry of medium

More information

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU George CURCANU, Constantin ILINCA, Ilie SBORA ICMET Craiova, Romania, Calea Bucuresti 144, phone:

More information

Type: DILM115(RAC240) Article No.: 239548 Sales text Contactor,55kW/400V,AC operated. Ordering information

Type: DILM115(RAC240) Article No.: 239548 Sales text Contactor,55kW/400V,AC operated. Ordering information Type: DILM115(RAC240) Article No.: 239548 Sales text Contactor,55kW/400V,AC operated Ordering information Connection technique Description Description Rated operational current Screw terminals 3 pole AC

More information

High-Voltage Circuit-Breakers 3AP1/2 72.5 kv up to 550 kv. Power Transmission and Distribution

High-Voltage Circuit-Breakers 3AP1/2 72.5 kv up to 550 kv. Power Transmission and Distribution High-Voltage Circuit-Breakers AP/ 7.5 kv up to 550 kv Power Transmission and Distribution The AP/ High-Voltage Circuit-Breakers Now Applicable for 550 kv Decades of our experience in high-voltage switching

More information

VD4. Vacuum circuit-breaker

VD4. Vacuum circuit-breaker VD4 Vacuum circuit-breaker VD4. The economical solution in power distribution. Applications: Power stations Transformer stations Chemicals industry Steel industry Automotive industry Airport power supply

More information

OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd

OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd ACTOM OUTDOOR DISCONNECTORS Single Side Break (SSB) Disconnector 22-132 kv, 800-1 A, 25 ka - 3s Typical bearing assembly. Voltage range 11 kv to 132

More information

HERZ-Thermal Actuators

HERZ-Thermal Actuators HERZ-Thermal Actuators Data Sheet 7708-7990, Issue 1011 Dimensions in mm 1 7710 00 1 7710 01 1 7711 18 1 7710 80 1 7710 81 1 7711 80 1 7711 81 1 7990 00 1 7980 00 1 7708 11 1 7708 10 1 7708 23 1 7709 01

More information

Max primary circuit temperature 90ºC Max primary circuit temp. 90ºC Max secondary circuit temperature 45ºC Max secondary circuit temp.

Max primary circuit temperature 90ºC Max primary circuit temp. 90ºC Max secondary circuit temperature 45ºC Max secondary circuit temp. EGLISH 1 Product description exchanger equipped with an electronic control unit and circulation pump for the primary circuit. All Aqua-Mex variants can be ordered with an interior coil of either titanium

More information

Sample - No Commercial Use

Sample - No Commercial Use COMPLETE REVISION October 2010 Electrical PIP ELSSG01 Design and Fabrication of Low-Voltage Metal-Enclosed AC Power Circuit Breaker Switchgear PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort

More information

SIVACON The Versatile Low-Voltage Switchboard

SIVACON The Versatile Low-Voltage Switchboard s SIVACON The Versatile Low-Voltage Switchboard Type-Tested Power Distribution Board 8PT The Obvious Solution for Global Challenges SIVACON Type testing in low-voltage switchgear is increasingly becoming

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

R.C.C.B. s two-pole LEXIC

R.C.C.B. s two-pole LEXIC 87045 LIMOGES Cedex Telephone : (+33) 05 55 06 87 87 Fax : (+ 33) 05 55 06 88 88 R.C.C.B. s two-pole LEXIC 089 06/09/10/11/12/15/16/17/18/ 27/28/29/30/35, CONTENTS PAGES 1. Electrical and mechanical characteristics...

More information

CAS 36 Ring Main Unit

CAS 36 Ring Main Unit Power distribution networks Ring Main Unit Catalogue 2008 A new path for achieving your electrical installations A comprehensive offer The range is part of a comprehensive offer of products that are perfectly

More information

Low Voltage Switchboards The Best Technical Solution for Your Ship

Low Voltage Switchboards The Best Technical Solution for Your Ship The Best Technical Solution for Your Ship Wärtsilä SAM Electronics Optimal Power Distribution The uninterrupted supply of power to systems and consumers onboard modern ships is an extremly important matter.

More information

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK Pressure monitoring equipment for oil-sf 6 bushings, type GOEK Installation and maintenance guide 5693 827-6 en, Rev. 3, 2002-01-30 This document must not be copied without our written permission, and

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

Siemens AG Power Transmission and Distribution Medium Voltage Division Mozartstr. 31c 91052 Erlangen Germany. www.siemens.

Siemens AG Power Transmission and Distribution Medium Voltage Division Mozartstr. 31c 91052 Erlangen Germany. www.siemens. Siemens AG Power Transmission and Distribution Medium Voltage Division Mozartstr. 31c 91052 Erlangen Germany www.siemens.com/energy For questions on power transmission and distribution, please contact

More information

Voltage Regulator SPAU 341 C. Product Guide

Voltage Regulator SPAU 341 C. Product Guide Issued: July 1998 Status: Updated Version: D/25.04.2006 Data subject to change without notice Features Comprehensive voltage regulation for power transformers with on-load tapchangers in distribution substations

More information

Installation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: 1996. No.: SE-...

Installation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: 1996. No.: SE-... Installation guide for the SafeLine type anchorage device Tested in compliance with EN 795: 1996 No.: SE-... Version: 09.10.2008 SE 67 Subject to technical alterations! Contents 1. General information

More information

MOUNTING AND OPERATING INSTRUCTIONS

MOUNTING AND OPERATING INSTRUCTIONS MOUNTING AND OPERATING INSTRUCTIONS CF 51/55 1. Delivery CF 51/55-1 calculator with battery (optionally with mains power supply) - 1 wall mounting bracket - package with material for sealing, screws, wall

More information

Disconnectors and Earthing Switches 36 kv up to 800 kv

Disconnectors and Earthing Switches 36 kv up to 800 kv Power Transmission and Distribution Disconnectors and Earthing Switches 36 kv up to 800 kv Ruhrtal & Siemens: A strong and successful team We manufacture high quality high-voltage disconnectors and earthing

More information

VD4 Vacuum Circuit-breaker. With Embeded Poles 36...40.5 kv, 1250...2500A, 25...31.5kA Instruction Manual

VD4 Vacuum Circuit-breaker. With Embeded Poles 36...40.5 kv, 1250...2500A, 25...31.5kA Instruction Manual VD4 Vacuum Circuit-breaker With Embeded Poles 36...40.5 kv, 1250...2500A, 25...31.5kA Instruction Manual Your safety first always! That's why our instruction manual begins with these recommendations:

More information

INFRARED QUARTZ WALL HEATER

INFRARED QUARTZ WALL HEATER INFRARED QUARTZ WALL HEATER MODEL NO: IQ2000 PART NO: 6939004 MOUNTING & OPERATION INSTRUCTIONS GC0715 INTRODUCTION Thank you for purchasing this CLARKE Infrared Wall Heater. Before attempting to use this

More information

Safe and secure distribution of medium voltage with AX1

Safe and secure distribution of medium voltage with AX1 Safe and secure distribution of medium voltage with AX1 The intelligent switchgear AX1 is a modern, air-insulated switchgear that lies at the very front line of safety and security safety for operating

More information

METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS

METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS Revision Date Prepared By Approved By Method Statement IF Kits BAC Corrosion Control Limited Stafford Park 11 Telford TF3 3AY Tel: 01952 290321 Fax:

More information

R4D0-FB-IA* FieldBarrier. Features. Assembly. Function. Connection IN + - S OUT ... ... Spur 2. Spur 1. Zone 1. Zone 0

R4D0-FB-IA* FieldBarrier. Features. Assembly. Function. Connection IN + - S OUT ... ... Spur 2. Spur 1. Zone 1. Zone 0 FieldBarrier Features Assembly 8... 12 outputs Ex ia IIC, FISCO and Entity Advanced fault isolation and diagnostics at the spur FieldBarrier in Zone 1/Div. 2 Instruments in Zone 0...1/Div. 1 For FOUNDATION

More information

FAQs-Main switchboard design criteria

FAQs-Main switchboard design criteria FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard

More information

DRM75A 230V 20/100A DIN rail single phase two wire energy meter

DRM75A 230V 20/100A DIN rail single phase two wire energy meter DRM75A 230V 20/100A DIN rail single phase two wire energy meter 1.1 Safety instruction 1.2 Foreword 1.3 Performance criteria 1.4 Specifications 1.5 Basic errors 1.6 Description 1.7 Dimensions 1.8 Installation

More information

Vario-Series Accessories

Vario-Series Accessories Accessories and spare parts for GMW analogue panel meters and controllers Current Transformers pages 2-9 Shunt Resistors 10-11 Voltage Dividers 12 Power supply for indicator/controllers 13 Blanking Plates

More information

ABB Drives. User s Manual. Pulse Encoder Interface Module RTAC-01

ABB Drives. User s Manual. Pulse Encoder Interface Module RTAC-01 ABB Drives User s Manual Pulse Encoder Interface Module RTAC-0 Pulse Encoder Interface Module RTAC-0 User s Manual 3AFE 64486853 REV A EN EFFECTIVE:.5.00 00 ABB Oy. All Rights Reserved. Safety instructions

More information

ADM1TE 5/30A DIN rail single phase two wire energy meter

ADM1TE 5/30A DIN rail single phase two wire energy meter ADMTE 5/30A DIN rail single phase two wire energy meter. Safety instruction.2 Foreword.3 Performance criteria.4 Specifications.5 Basic errors.6 Description.7 Dimensions.8 Installation.9 Operating.0 Troubleshooting.

More information

5SV Residual Current Protective Devices

5SV Residual Current Protective Devices s Siemens AG 2013 SENTRON 5SV Residual Current Protective Devices New portfolio for reliable personnel, material and fire protection Safe protection against residual currents Residual current protective

More information

Transformer oil cooler ALFA A02

Transformer oil cooler ALFA A02 A02 Transformer oil cooler ALFA Transformer oil cooler ALFA The transformer oil cooler ALFA is used to cool power transformers by means of forced air and oil flow. The oil in the cooler is circulated using

More information

Permissible ambient temperature Operation Storage, transport

Permissible ambient temperature Operation Storage, transport The Sitras PRO combined DC protective unit and controller is used in the power supply for DC railways in mass transit and main-line systems up 3,000 V DC. It protects DC switch gear and contact line systems

More information

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H. POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,

More information

Operating Instructions

Operating Instructions Important information: These instructions contain safety information, read and follow them carefully. Dialight will not accept any responsibility for injury, damage or loss which may occur due to incorrect

More information

ABB i-bus EIB / KNX Analogue Input AE/S 4.2

ABB i-bus EIB / KNX Analogue Input AE/S 4.2 Product Manual ABB i-bus EIB / KNX Analogue Input AE/S 4.2 Intelligent Installation Systems This manual describes the functionality of Analogue Input AE/S 4.2. Subject to changes and errors excepted. Exclusion

More information

www.siemens.com/energy High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy.

www.siemens.com/energy High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy. s www.siemens.com/energy High Voltage Circuit Breakers AP Type 7.5 kv to 800 kv Answers for energy. The AP High Voltage Circuit Breakers Available up to 800 kv Decades of our experience in high voltage

More information

INSTALLATION INSTRUCTIONS: Viewline 52 mm

INSTALLATION INSTRUCTIONS: Viewline 52 mm -5 Safety information The product was developed, manufactured and inspected according to the basic safety requirements of EC Guidelines and state-of-the-art technology. The instrument is designed for use

More information

Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points

Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points Features SELV Compliant No Detection Passive Injector Gigabit Compatible Full Protection

More information

LUCCI AIRFUSION QUEST II CEILING FAN

LUCCI AIRFUSION QUEST II CEILING FAN LUCCI AIRFUSION QUEST II CEILING FAN WITH IR REMOTE INSTALLATION OPERATION MAINTENANCE WARRANTY INFORMATION CAUTION READ INSTRUCTIONS CAREFULLY FOR SAFE INSTALLATION AND FAN OPERATION. V1.0 QUEST II IR

More information

Adjustment functions for both span and shift have been incorporated

Adjustment functions for both span and shift have been incorporated SENSORS FOR SERIES LED Type Wafer Alignment Sensor FX-0-F FT-F9 FD-F7 EX-F70/F60 M SH-7 FD-L4 M-DW The use of a safe LED light beam now allows for high precision detection with a resolution of 0!m (.8

More information

33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application

33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application 33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application Features Compliant with the IEEE802.3at Standard -40 to +60 C Temperature Range Diagnostic LEDs Full Protection

More information

Three-phase monitoring relay CM-PFE

Three-phase monitoring relay CM-PFE Data sheet Three-phase monitoring relay CM-PFE The CM-PFE is a three-phase monitoring relay that monitors the phase parameter phase sequence and phase failure in three-phase mains. 2CDC 251 005 S0012 Characteristics

More information

TIG INVERTER INSTRUCTION MANUAL

TIG INVERTER INSTRUCTION MANUAL TIG INVERTER INSTRUCTION MANUAL Contents Warning General Description Block Diagram Main Parameters Circuit Diagram Installation and Operation Caution Maintenance Spare Parts List Troubleshooting 3 4 4

More information

SHOWER WATER HEATER MODEL BS 35 / 45 / 60 BS 35 E / 45 E / 60 E OPERATION AND INSTALLATION INSTRUCTIONS

SHOWER WATER HEATER MODEL BS 35 / 45 / 60 BS 35 E / 45 E / 60 E OPERATION AND INSTALLATION INSTRUCTIONS SHOWER WATER HEATER MODEL BS 35 / 45 / 60 BS 35 E / 45 E / 60 E OPERATION AND INSTALLATION INSTRUCTIONS 2 This water heater must be installed (water and electrical installation), commissioned and serviced

More information

REVIEWED BY CAPITAL PROJECTS MANAGER (DAN REDDY) GENERAL MANAGER EQUIPMENT ENGINEERING & ASSET MANAGEMENT (HAMILTON NXUMALO)

REVIEWED BY CAPITAL PROJECTS MANAGER (DAN REDDY) GENERAL MANAGER EQUIPMENT ENGINEERING & ASSET MANAGEMENT (HAMILTON NXUMALO) SA Port Operations DOCUMENT TYPE: REFERENCE EEAM-Q-014 (ORIGINAL SPECIFICATION HE8.2.3 Ver5) REVISION 0 SPECIFICATION TITLE: SPECIFICATION FOR ELECTRICAL MOTORS AND GENERATORS PAGE 0 of 07 COMPILED BY

More information

Securing your electrical installations Prisma,

Securing your electrical installations Prisma, Securing your electrical installations Prisma, an optimised solution for type tested low voltage switchboards up to 3200 A Table of contents Developing installation safety 4 Prisma P * Electrical switchboards

More information

CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE. General purpose single phase thyristors and solid state relays Product data.

CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE. General purpose single phase thyristors and solid state relays Product data. 425 CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE General purpose single phase thyristors and solid state relays Product data abc 425 EUROCUBE A complete range of low cost solid state relays and

More information

Portable Air Conditioner

Portable Air Conditioner Portable Air Conditioner Owner's Manual Model:3 in 1 12,000 Btu/h Series 3 Please read this owner s manual carefully before operation and retain it for future reference. CONTENTS 1. SUMMARY...1 2. PORTABLE

More information

Incubator with mechanical convection

Incubator with mechanical convection BF series 400 Incubators and cooling incubators Incubator with mechanical convection The BINDER incubator of the BF series with mechanical convection is suitable for all gentle incubation applications,

More information

Paper on Basbar Trunking System for Electrical Supply to Industrial & commercial Installation

Paper on Basbar Trunking System for Electrical Supply to Industrial & commercial Installation IOSR Journal of Engineering (IOSRJEN) ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 01 (January. 2014), V6 PP 01-12 www.iosrjen.org Paper on Basbar Trunking System for Electrical Supply to Industrial

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

Catalog. Arc Guard System TM TVOC-2

Catalog. Arc Guard System TM TVOC-2 Catalog Arc Guard System TM TVOC-2 Introduction An even better Arc Guard System TVOC-2, ABB s latest Arc Monitor, builds on the well known TVOC design. Its new functions and features improve an already

More information

SECTION 16461 DRY-TYPE TRANSFORMERS

SECTION 16461 DRY-TYPE TRANSFORMERS SECTION 16461 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Furnishing and installation of and testing of cast resin dry type MV/LV distribution transformer in accordance with specifications and drawings. Any

More information

Molded Case Circuit Breaker Specifications Bulletin Number 140U-D

Molded Case Circuit Breaker Specifications Bulletin Number 140U-D Technical Data Molded Case Circuit Breaker Specifications Bulletin Number 140U-D Topic Page Product Line Overview 2 Specifications 3 Trip Curves 4 Approximate Dimensions 6 Additional Resources These documents

More information

CORNER FRIDGE REFRIGERATION UNIT INSTALLATION AND OPERATION INSTRUCTIONS

CORNER FRIDGE REFRIGERATION UNIT INSTALLATION AND OPERATION INSTRUCTIONS CORNER FRIDGE REFRIGERATION UNIT INSTALLATION AND OPERATION INSTRUCTIONS D E F Y I N G C O N V E N T I O N Congratulations on your new Corner Fridge Your new corner fridge may have different functions

More information

Installation. Smart-UPS VT MGE Galaxy 3500. Maintenance Bypass Panel. 10-40 kva 400 V

Installation. Smart-UPS VT MGE Galaxy 3500. Maintenance Bypass Panel. 10-40 kva 400 V Installation Smart-UPS VT MGE Galaxy 3500 Maintenance Bypass Panel 10-40 kva 400 V Contents Safety.................................................. 1 Save these instructions...................................

More information

Daker DK 1, 2, 3 kva. Manuel d installation Installation manual. Part. LE05334AC-07/13-01 GF

Daker DK 1, 2, 3 kva. Manuel d installation Installation manual. Part. LE05334AC-07/13-01 GF Daker DK 1, 2, 3 kva Manuel d installation Installation manual Part. LE05334AC-07/13-01 GF Daker DK 1, 2, 3 kva Index 1 Introduction 24 2 Conditions of use 24 3 LCD Panel 25 4 Installation 28 5 UPS communicator

More information

Power Supply Unit, Primary Switched, Narrow Design MINI-PS-12-24DC/24DC/1

Power Supply Unit, Primary Switched, Narrow Design MINI-PS-12-24DC/24DC/1 Power Supply Unit, Primary Switched, Narrow Design MINI POWER provides: Extra narrow design with widths of 22.5 mm, 45 mm, and 67.5 mm (0.886, 1.772, and 2.657 in.) Global use due to a wide-range input

More information

Nothing s BetterThan the Original MODAN Power Distribution Systems

Nothing s BetterThan the Original MODAN Power Distribution Systems MODAN www.eaton.com Nothing s BetterThan the Original MODAN Power Distribution Systems Modan Modular switchboard system Controlling and Distributing Power Safely Thinking further. Questioning the well-established

More information

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS PLEASE READ COMPLETE INSTRUCTIONS BEFORE YOU BEGIN LEAVE INSTALLATION INSTRUCTIONS AND USER'S GUIDE WITH OWNER ALL ELECTRIC WIRING AND PLUMBING MUST BE DONE

More information

Positive-guided relay outputs: 3 safety contacts (N/O), instantaneous. 1 auxiliary contact (N/C), instantaneous

Positive-guided relay outputs: 3 safety contacts (N/O), instantaneous. 1 auxiliary contact (N/C), instantaneous Safety relay for monitoring E-STOP pushbuttons. Approvals Unit features Positive-guided relay outputs: 3 safety contacts (N/O), instantaneous 1 auxiliary contact (N/C), instantaneous Safe separation of

More information

OPERATING INSTRUCTIONS

OPERATING INSTRUCTIONS GB OPERATING INSTRUCTIONS Automatic Wedge Welding Machine Please read operating instructions carefully before use and keep for further reference. APPLICATION The is an automatic wedge welding machine for

More information

RM4TG20 three-phase network control relay RM4-T - range 200..500 V

RM4TG20 three-phase network control relay RM4-T - range 200..500 V Characteristics three-phase network control relay RM4-T - range 200..500 V Complementary [Us] rated supply voltage Output contacts Setting accuracy of time delay Delay at power up Measuring cycle Marking

More information

SIRCOVER. Manual changeover switches from 125 to 3200 A. Changeover switches. Function. Advantages. The solution for.

SIRCOVER. Manual changeover switches from 125 to 3200 A. Changeover switches. Function. Advantages. The solution for. The solution for Changeover switches svr_099_b_1_cat > Manufacturing industry. > Power distribution. 3200 Strong points svr_059_a_1_cat > complete range. > Easy connections. > Stable positions. > mproved

More information