1 Appendix 1 Organisational Improvement Programme Management Highlight Report Highlight Report Overall RAG Status To I&E sub-committee Project / Programme Name Organisational Improvement Programme Reporting Period 22 nd Apr 10 To 6 th June 10 Report Author(s) Organisational Improvement Team Stage / Status Definition Start Date Oct 09 Proposed End Date Management Summary Both COE and the I&E Sub Committee have approved the creation of a single Organisational Improvement Programme, aimed at bringing together 3 key strands of work; Customer Access; Office Accommodation and Flexible Working and Back Office reform in order to deliver both efficiencies and improvements across the council. The main project areas have been signed off by COE and the I&E Sub-Committee. A summary of these projects is below.
2 Key progress during reporting Period and issues to be raised for information or escalated Tasks planned for next period RAG status Work Stream: Office Accommodation Project 1: Business case and implementation planning for office accommodation project Briefed external consultants to advise on overall property strategy. Proposal received w/c 18 May Confirmed working assumptions on PCT staff in 6-9 months from April. St Blaise solution agreed by Programme Board 22 April Started Capital Ambition project with ESD on flexible working to achieve 50% reduction in office space. Workstyle workshops held 13 May Working with ESD organisational improvement group on storage issues and extending to all departments on civic site, and linked in with storage project. Main : : Direction of workstream dependent on strategic decisions on property by Members. No funding approved pending above so all actions on minimal basis Current projects do not release Jo Lanc or Ann Springman. PCT staff numbers still uncertain CYP teams need to be together need to ensure enough space in St Blaise/PCT planning. Future accommodation/equipment solutions are not attractive to colleagues/partners Final decisions on one stop shop concept, remit and location could require some adjustment in this workstream. Short term priorities: Work with consultants to deliver evalution of strategic options to Members as soon as possible Progress PCT accommodation plan. Work with ESD working group on flexible working. Aim to reduce space in St Blaise by 50% for PCT occupation. Progress storage reduction through working with ESD and generally. Once overall strategy is agreed: Re-plan if necessary and Liaise with departments on allocation of space/location to enable building and ICT infrastructure works to be commissioned and detailed staff move plans to be developed.
3 Work stream: Self-service and ICT Website upgrade : Work planned: Work completed: Paper to COE ready for April was pulled to pursue potential of joint web platform bid with Bexley Joint bid for web development drawn up and consulted on with Head of ICT, Director of Resources, Director of Customer Services Visited Bexley to discuss strengthening the bid and other possible opportunities for joint working Mapping exercise undertaken across the two boroughs to establish where initial projects are required and where capital spend would be allocated if the bid was successful Specific cashable efficiencies very difficult to identify up front. : Investment from Capital Ambition refused. Business Case for investment (possibly still in partnership) will need to be made. If Capital Ambition bid is successful we will need to work with London Borough of Bexley to identify far more explicitly the project deliverables, governance and an implementation plan. If unsuccessful a further report into COE will be submitted setting out the options: Continue to work with Bexley regardless of bid money to share costs Investment all found internally to develop web self service functionality and revisit upgrading CMS at a later date due to cost Fund web upgrade plus development all internally as a priority investment for the council and its core systems SharePoint Review and Strategy Work planned: Revised Sharepoint Strategy developed and agreed by the Organisational Improvement Programme Board. Successfully rolled out a fix to the permissions levels on 15 th & 16 th May. Contacted departments regarding setting up super user groups Governance documentation finalised will be reviewed by BIKS and the Technical configuration of software does not meet business need or is inflexible to differing requirements SharePoint remains a technology rather than a communications/information management tool Super User teams in ACS to be used to highlight the potential business benefit of Sharepoint. Complete final technical development of Sharepoint System. Work with Communications to design re-launch of Sharepoint across the organisation. Introduce bite size chunks / lunchtime sessions to enhance training.
4 departmental SharePoint Groups Initial discussion with Bromley Adult Education on provision of trainer to work within the team providing support to teams Reviewing training programme targeting both intermediate SharePoint training and specific how to areas to ensure the full functionality is exploited. : Business Change not sufficiently embedded during initial Sharepoint launch. Pull together plan around the closure of the current N:Drive. Work stream: Customer and Service Led Improvement CCC Service Migrations Work Completed Technical development of CRM in order to facilitate integration with the Confirm System is completed. Integration software coded to communicate between CRM & Confirm. Business requirements of CRM/integration formerly established and signed off with Street Services. Potential site for CCC expansion identified (Former ESD Post Room) CCC expansion project costs identified and currently being considered by relevant services and Chief Officer Evaluation of resource requirement for Landscapes Helpdesk calls to be migrated to the CCC. Funding for interim CCC expansion agreed by relevant Chief Officers Delay in decision making around the accommodation strategy is preventing long term decision making relating to the CCC taking place Failure to provide additional interim CCC capacity on time will prevent/delay delivery of projects in the Supporting Independence Programme, disrupt potential expansion of the waste trial and prevent further service migrations. Work Planned Complete technical development of Confirm Integration. Carry out User Acceptance Testing with Street Services of the integration solution. Go Live (15 th June) of Street Service calls within the Contact Centre Agree/Dismiss Landscapes migration Award tender for renovation and technical works to ESD Post room/interim CCC Capacity Customer insight analysis Received new public sector Mosaic profiling of Customer Contact Centre Multiple sources of data recorded differently make it difficult to draw like- Future work will include: Continued analysis of Mosaic profiling (CRM data and borough
5 profiling begun analysis Received up to date Mosaic profiling of the borough begun analysis Started gap analysis of template channel strategy against Bromley s foundation strategies (notably customer access; communications; IT) Market research into Bromley customer access preferences has now been completed, analysed and presented to the Customer Focus Group. This information will be used to update the information on customer transaction channel preferences and inform our web and channels shift strategy. Overview of E-forms available on and their hit rates overlaid with Bromley profiling data. for-like comparisons. Back office systems are principally address driven, rather than customer driven. The impact of the channel strategy should resonate across the LBB foundation strategies there is no secured resource (post July) for the implementation stage of the strategy. profile) Comparison of Bromley s borough profile to neighbouring local authorities (Bexley) Produce overview analysis report of insight provided by Experiancomparison of mosaic data with Bromley customer access research for verification purposes Complete gap analysis of template channel strategy against Bromley s foundation strategies Identify popular lifestyle groups in Bromley and liaise with Communications to begin process of web marketing strategy. Present findings of Customer Access Preferences Research to I&E Sub Presentation of project work to date and project handover. Voice Recognition Future work will include: VR Hard/Software installed on council corporate network. Remote connection to supplier established so 24/7 updating/support is possible. Council Staff/Member directory recorded by voice artist. Switchboard departmental directory revised and adapted for VR software with input from existing switchboard staff. Data cleansing of internal phone directory has now been completed. Test group for internal roll out identified. Grammar loaded into VR software unlikely to be sufficiently comprehensive initially. User acceptance testing crucial in order to identify additional grammar required. VR software does not accurately redirect calls and leads to avoidable contact being made with remaining human operators. Possible risk with data quality relating to phone numbers within the council work is being completed currently around this issue. Testing of the internal roll out to a selected group of staff members due date for Pilot 27 th May. Feedback from testing used to cleanse staff directory data and add grammar to VR software. Anticipated go live date:- 14 th June 2010 Extend to external calls (3 months) Investigate added functionality further using the Telephonetics software.
Service First is a core value of the Council, expressing its firm ambition to become a more customer focused organisation
Service First Customer Services Strategy 1. Introduction Service First is a core value of the Council, expressing its firm ambition to become a more customer focused organisation The aim of this document
Decision Request Form INDIVIDUAL CABINET MEMBER
Cabinet Office Location: 3E/05 Ext: 0472 DDI : 01895 250472 My Ref: SEC To: COUNCILLOR RAYMOND PUDDIFOOT LEADER OF THE COUNCIL COUNCILLOR JONATHAN BIANCO CABINET MEMBER FOR FINANCE AND BUSINESS SERVICES
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change For Decision Member Champion(s): Cllr A Alford, Corporate - Director:
CRM Initial Implementation PROJECT DOCUMENTATION PROJECT INITIATION DOCUMENT PID. Document Description. Version Number 0.1 Release Date Author
CRM Initial Implementation PROJECT DOCUMENTATION PROJECT INITIATION DOCUMENT PID Document Description Version Number 0.1 Release Date Author Sandy Spink Owner Spink Telecom Consultants Ltd Client Tunbridge
Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement
Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Recommendations That the Executive note CRM procurement will be put out to tender in 2010/11 and note the proposed phasing
Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
REPORT OF THE SERVICE DIRECTOR - HUMAN RESOURCES AND CUSTOMER SERVICE
Report to Personnel Committee 26 September 2012 Agenda Item: 6 REPORT OF THE SERVICE DIRECTOR - HUMAN RESOURCES AND CUSTOMER SERVICE INVESTORS IN PEOPLE RE-ACCREDITATION Purpose of the Report 1. The purpose
Appendix A: ICT and Information Management Strategy
Appendix A: ICT and Information Management 2014 2019 Head of Information and Business Change Sarah Caulkin October 2014 1 Version Control: Date Version Author Comments 04/08/14 0.1 Jo Harley First draft
Corporate Governance Service Business Plan 2011-2016. Modernising Services
Corporate Governance Service Business Plan 2011-2016 Modernising Services Index 1. Executive Summary 3 2. Vision and Strategy 4 3. Service Overview 3.1 What Services do we and Will we Deliver? 5 3.2 How
BRENT COUNCIL IT STRATEGY 2010-13
BRENT COUNCIL IT STRATEGY 2010-13 Contents 1 Introduction... 2 2 Empowering our customers... 3 2.1 Client Index... 3 2.2 Customer contact... 3 3 Tools for the Job... 4 3.1 Printing and scanning... 4 3.2
COMHAIRLE NAN EILEAN SIAR S CUSTOMER SERVICE STRATEGY
S September 2008 CONTENTS INTRODUCTION...3 CUSTOMER RELATIONSHIP MANAGEMENT (CRM)...7 ACCESS CHANNELS...9 CUSTOMER CARE STANDARDS...13 PERFORMANCE & CONTINUOUS IMPROVEMENT...15 2 INTRODUCTION Background
MONTHLY PROJECT PROGRESS REPORT
MONTHLY PROJECT PROGRESS REPORT Project name: Project description: UCL School of Pharmacy Merger - IT & Data Programme A Programme to ensure all IT & Data elements of the UCL SoP Merger are co-ordinated
CRM Phase 3 Development, support and maintenance - Questions and Answers
No. Question Answer 1. 2. 3. 4. 5. 6. 7. Are we able to discuss the requirements of this tender with the UKCES prior to submitting our proposal? Can we be placed on a list to be notified of future opportunities
The Danwood Group Professional Services Offering DANWOOD
The Danwood Group Professional Services Offering DANWOOD Our Professional Services Our Professional Services department can provide you with a variety of services from Audit and Assessment to Technical
ICT Digital Transformation Programme
Officer and Date Item Cabinet 11 th May 2016 Public ICT Digital Transformation Programme Responsible Officer: Clive Wright, Chief Executive Email: [email protected] Tel: 01743 252007 1.0 Summary
Digital Inclusion Programme Started. BL2a
PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects
Digital Experts Programme Tri-borough adult social care app case study
Digital Experts Programme Tri-borough adult social care app case study The issue and context Faced with an ageing population and increasing constraints on their finances, the City of Westminster, the London
Department for Work and Pensions Communication Capability Review. February 2013
Department for Work and Pensions Communication Capability Review February 2013 Management summary 2.1 The Communication Capability Review of the Department for Work and Pensions (DWP) is one of a series
Information Commissioner's Office
Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: [email protected] Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: [email protected]
SCRUTINY PANEL. 12 February 2015 REVIEW OF ICT SERVICES. Report of the Director of Resources
REPORT NO: 49/2015 SCRUTINY PANEL 12 February 2015 REVIEW OF ICT SERVICES Report of the Director of Resources STRATEGIC AIM: All 1. PURPOSE OF THE REPORT 1.1 To update the panel on the plan for the review
Developing a Project. Management System. Using Project Agency Template. Approach. - the Process and the Benefits
Developing a Project Management System Using Project Agency Template Approach - the Process and the Benefits Project Agency June 2008 Developing your own Project Management System. Project Agency has worked
The Audit of Best Value and Community Planning The City of Edinburgh Council. Best Value audit 2016
The Audit of Best Value and Community Planning The City of Edinburgh Council Best Value audit 2016 Report from the Controller of Audit February 2016 The Accounts Commission The Accounts Commission is the
Digital Dictation Workflow & Clinical Documentation Library (CDL) Highlight Report as at 26/05/10 Accomplishments
Digital Dictation Workflow & Clinical Documentation Library (CDL) Highlight Report as at 26/05/10 Clinical Documentation Library delivered Migration process of historic documents completed and migration
Connect Renfrewshire
How the council will use its information and technology assets to achieve successful change Contents Strategy Context 2 Digital Delivery and Citizen Engagement 4 Operational Excellence and Transformation
Best Practice. Change Management. Guidelines
Best Practice Change Management Guidelines 1 Created by: Denise Phelan, Demand Management lead, (LPP) Reviewed by: Jonathan Porter, HR Workstream Lead, St George s Healthcare NHS Trust Approved by: Mick
Role Profile SERVICE DESK TEAM LEAD (TIER 1)
Role Profile SERVICE DESK TEAM LEAD (TIER 1) COMPANY OVERVIEW Informa is one of the world s leading knowledge providers. We create and deliver highly specialised information through publishing, events,
Consultation and Engagement Strategy
Consultation and Engagement Strategy Contents: 1. Introduction 2 2. Purpose 3 3. Aims and Objectives 4 4. Key principles 5 5. Delivery of the Strategy 6 6. Action Plan 2011-12 7 Appendix 1 Understanding
Derbyshire County Council
Derbyshire County Council Derbyshire County Council is situated in the East Midlands and is bordered by the cities of Nottingham, Sheffield and Manchester. Its role it to provide local government services
Government Communication Professional Competency Framework
Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their
ICT Service Desk Creation
ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:
Sustaining Progress Fourth Progress Report
Sustaining Progress Fourth Progress Report Name of Institution DUBLIN CITY UNIVERSITY I confirm that I have assessed and verified the extent of progress and co-operation which has been achieved to date
Quarterly Performance Report ICT & Customer Services
Quarterly Performance Report ICT & Customer Services Report Author Head of ICT & Customer Services Report Date 11th May 2012 Report Period Quarter 4: 1 st January 2012 to 31 st March 2012 Introduction
Senior Manager Information Technology (India) Duration of job
Role Profile Job Title Senior Manager Information Technology (India) Directorate or Region South Asia Department/Country Business Support Services, India Location of post Gurgaon Pay Band 6 / Grade G Reports
Service Improvement Plan. DRAFT v.0.1. Harrow IT Services
Harrow IT Services Service Improvement Plan DRAFT v.0.1 Harrow IT Services October 20 Contents 1. Introduction... Error! Bookmark not defined. 2. The Vision for HITS... Error! Bookmark not defined. 3.
Vietnam's Experiences in Strengthening. Procurement and Public Financial Management Systems. in Harmonization, Alignment and Capacity Development
Vietnam's Experiences in Strengthening Procurement and Public Financial Management Systems in Harmonization, Alignment and Capacity Development Mr. Chairman, Ladies and gentlemen, Dr. Duong Duc Ung Director
Commissioning Strategy
Commissioning Strategy This Commissioning Strategy sets out the mechanics of how Orkney Alcohol and Drugs Partnership (ADP) will implement its strategic aims as outlined in the ADP Strategy. Ensuring that
Web & Customer Access Strategy
Page 1 of 14 DACORUM BOROUGH COUNCIL Web & Customer Access Strategy AUTHOR RESPONSIBLE OFFICER Katie Warner, Customer Insight Officer Murtaza Maqbool, Web Development Officer David Gill, Group Manager
Appendix 4 - Statutory Officers Protocol
Appendix 4 - Statutory Officers Protocol Accountability Protocol for role of Director of Children s Services within the London Borough of Barnet Introduction In September 2014, the Chief Executive of the
RISK MANAGEMENT POLICY (Revised October 2015)
UNIVERSITY OF LEICESTER RISK MANAGEMENT POLICY (Revised October 2015) 1. This risk management policy ( the policy ) forms part of the University s internal control and corporate governance arrangements.
CASE STUDY: Stockport Metropolitan Borough Council SECTOR: Local Government
CASE STUDY: Stockport Metropolitan Borough Council SECTOR: Local Government MSM ITSM Software is a key tool for Stockport Council ICT in the drive for continual service improvement and efficiencies MSM
CASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT:
CASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT: The Queen Elizabeth Hospital King s Lynn NHS Foundation Trust (QEH) is a 514 bed general hospital providing services to
SMBC ICT Functional Review Recommendations (Amended 1 st June 2016)
SMBC ICT Functional Review Recommendations (Amended 1 st June 2016) No. Recommendation ICT and Peer Review Comments Responsibility Deadline Current 1. Whilst the ICT Strategy is well defined and documented,
KPMG Advisory. Microsoft Dynamics CRM. Advisory, Design & Delivery Services. A KPMG Service for G-Cloud V. April 2014
KPMG Advisory Microsoft Dynamics CRM Advisory, Design & Delivery Services A KPMG Service for G-Cloud V April 2014 Table of Contents Service Definition Summary (What s the challenge?)... 3 Service Definition
Project, Programme and Portfolio Management Delivery Plan 6
Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy
PRINCE2:2009 Glossary of Terms (English)
accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain
Customer Service Strategy
Customer Service Strategy Gateshead Council Customer Services your bridge to council services. Foreword The Local Government Context Customer service the national context Customer expectations are continually
Customer Management Strategy (2014-2017)
Customer Management Strategy (2014-2017) Version 1.1 Page 1 Foreword As technology improves, the demand for Council services to be available online and accessible 24/7 will increase as our customers choose
Communications Manager
Job details Job title: Communications Manager Responsible to: Head of Communications Responsible for: Posts in the Communications Location: Liverpool with travel across all locations Overview of the role
Council, 6 February 2014. IT Report. Executive summary and recommendations. Introduction
Council, 6 February 2014 IT Report Executive summary and recommendations Introduction The report sets out the main activities of the IT Department since the last meeting of Council. It includes statistical
An Introduction to SharePoint Governance
An Introduction to SharePoint Governance A Guide to Enabling Effective Collaboration within the Workplace Christopher Woodill Vice President, Solutions and Strategy [email protected] 416-477-3945
Joint Surrey Carers Commissioning Strategy for 2012/3 to 2014/5 Key Priorities for Surrey Multi Agency Delivery Plan - May 2012
Joint Surrey Carers Commissioning Strategy for 2012/3 to 2014/5 Key Priorities for Surrey Multi Agency Delivery Plan - May 2012 Note this Delivery Plan will be updated & republished 3 times a year throughout
ISO 20000-1:2005 Requirements Summary
Contents 3. Requirements for a Management System... 3 3.1 Management Responsibility... 3 3.2 Documentation Requirements... 3 3.3 Competence, Awareness, and Training... 4 4. Planning and Implementing Service
CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY
Zurich Management Services Limited Registered in England: No 2741053 Registered Office The Zurich Centre, 3000 Parkway Whiteley, Fareham Hampshire, PO15 7JZ CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY
Method Statement Switchboard Services
CONFORMED COPY Method Statement Revision History Revision Date Reviewer Status 23 March 2007 Project Co Final Version 1 Table of Contents 1 Objectives... 3 2 Management Supervision and Organisation Structure...
Customer Service Software System Business Case Lead Officer:
Agenda item: 17 Committee: CABINET Date of meeting: 21 November 2012 Subject: Customer Service Software System Business Case Lead Officer: Head of ICT Portfolio Holder: Resources - Councillor T Oliver
1. Introduction. 2. Performance against service levels 1 THE HIGHLAND COUNCIL. Agenda Item. Resources Committee 26 th March 2003 RES/43/03
1 THE HIGHLAND COUNCIL Resources Committee 26 th March 2003 Performance report for January / February 2003 Report by the Information Systems Client Manager Agenda Item Report No 18 RES/43/03 Summary This
COLUMN. Planning your SharePoint intranet project. Intranet projects on SharePoint need a clear direction APRIL 2011. Challenges and opportunities
KM COLUMN APRIL 2011 Planning your SharePoint intranet project Starting a SharePoint intranet project, whether creating a new intranet or redeveloping an existing one, can be daunting. Alongside strategy
Head of ICT and Customer Services [M105] 1.1 To agree terms of reference and the timetable for the review of Customer Services.
SERVICE REVIEW CUSTOMER SERVICES AGENDA ITEM NO 9 Committee: Personnel and Corporate Services Committee Date: 20 September 2012 Author: Head of ICT and [M105] 1.0 ISSUE 1.1 To agree terms of reference
Agency Temporary Worker Processes (IA 12 140/F v1) Tricia Riley, HR Director. Audit Conclusion: Audit Closed
FINAL INTERNAL AUDIT REPORT Agency Temporary Worker Processes (IA 12 140/F v1) Tricia Riley, HR Director Audit Conclusion: Audit Closed 23 October 2014 Issue categories Agreed actions Satisfactorily addressed
Report to Trust Board 29.11.12. Executive summary
Report to Trust Board 29.11.12 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Transforming our Booking and Scheduling Systems Steve Peak - Director of Transformation Steve
Project Initiation Document
Project Sponsor: Richard Ellis Version: 1.0 Date: 2 nd July 2009 Document Control Project Sponsor Richard Ellis Project Initiation Document Project Call Recording and Workforce Management Document PID
ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY
CAB2304 FOR DECISION WARD(S): GENERAL CABINET 13 June 2012 ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY Contact Officer: Tony Fawcett Tel
Managing ICT contracts in central government. An update
Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government
The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS
PRIORITY RECOMMENDATIONS R1 BIS to elevate the profile of information risk in support of KIM strategy aims for the protection, management and exploitation of information. This would be supported by: Establishing
INTERNAL AUDIT FINAL REPORT. Project Management. June 2013
Broxbourne Borough Council Contract Audit Project Management APPENDIX E INTERNAL AUDIT FINAL REPORT Project Management June 2013 Ref 18.12/13 June 2013 Page 1 Broxbourne Borough Council Contract Audit
Horizon Scanning and Scenario Building: Scenarios for Skills 2020
Horizon Scanning and Scenario Building: Scenarios for Skills 2020 A report for the National Strategic Skills Audit for England 2010 Executive Summary 17 March 2010 Analysis Understanding Insight Expert
Risk Management Procedure
Purpose of this document Develop and document procedures and work instructions for Risk Management to cover the project Stages set out in the Project Process Map. The purpose of this procedure is to identify
Agency Board Meeting 28 July 2015
SEPA 22/15 Agency Board Meeting 28 July 2015 Report Number: SEPA 22/15 Audit Committee Annual Performance Report 2014-2015 Summary: Risks: Resource and Staffing Implications Equalities: Environmental and
Project Management Fact Sheet:
Project Management Fact Sheet: Project Documentation Version: 2.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that