1 Broxbourne Borough Council Contract Audit Project Management APPENDIX E INTERNAL AUDIT FINAL REPORT Project Management June 2013 Ref 18.12/13 June 2013 Page 1

2 Broxbourne Borough Council Contract Audit Project Management CONTENTS Section PAGE 1 Introduction 3 2 Background 3 3 Executive Summary 4 4 Conclusion Implementation of Agreed Recommendations 5 6 Acknowledgement 5 7 Management Action Plan 6-12 Appendices A Assurance Definitions 13 B Project sample 14 C s interviewed 15 June 2013 Page 2

3 Broxbourne Borough Council Contract Audit Project Management 1. Introduction 1.1 As part of the agreed 2012/13 Internal Audit Plan we have reviewed the processes and controls in place with regard to project management throughout the Council. 1.2 For the scope, objectives and methodology please refer to the Terms of Reference previously issued. 1.3 It is intended that the report will be presented to the next Audit Committee. The implementation of the recommendations will be monitored with a follow up review in six months time. Agreed recommendations that remain outstanding at the time of the follow up will continue to be tracked through a separate report to and the Audit Committee. 2. Background 2.1 Project management processes within Broxbourne Council have not been the subject of an audit in the past. Whilst IT projects have been flagged up as a high risk on the corporate risk register, this audit was scoped to review project management practices across the Council. 2.2 For the purposes of this audit, the definition of a project has been taken to be a unique set of co-ordinated activities, with definite starting and finishing points, undertaken by an individual or team to meet specific objectives within defined time, cost and performance parameters. 2.3 The Council s internal inter-disciplinary group (IDG), chaired by the Chief Executive, considers a schedule of Council projects and receives verbal updates from the lead officer on specific projects of importance to the Council and the community. A review of the remit of IDG is in progress. The review will also look at which projects will be monitored by the group and will consider the recommendations made in this review. 2.4 Capital projects are required to be supported by a business case before they receive funding. As part of the capital process, a quarterly monitor is produced that reviews large spend projects across the Council. This monitor has recently been extended to include details of slippage in projects and a more explanatory narrative around each project. 2.5 The audit approach adopted was to use a checklist to conduct a high level review. This checklist was applied to four current projects to understand current project management processes across the Council. In addition, key officers responsible for project management and delivery were interviewed over the course of the audit. 2.6 Projects reviewed and officers interviewed as part of this audit are set out at Appendices B and C. June 2013 Page 3

4 Broxbourne Borough Council Contract Audit Project Management 3. Executive Summary 3.1 An assessment of each of the control objectives reviewed is summarised in the table below: Control Objective 1. The corporate framework encourages effective project management. Each project is justified through an effective business case that sets out the aims and benefits to the Council of the project. Fully met Largely met Partly met Not met 2. An efficient and effective change control process is utilised, with key stakeholders kept informed. 3. Responsibility for deliverables, monitoring, reporting on actions and outcomes (as well as ensuring available resources) has been defined and helps meet the project s objectives. 4. Project risks are identified and appropriate mitigation occurs through the life of the project. 5. Projects are completed to budget and within agreed time frames. Post project reviews ensure stakeholder satisfaction with the project and lessons are learnt for future projects. 3.2 This report contains eleven recommendations. Of these eleven, two are fundamental, seven are significant and there are two recommendations that require attention. These recommendations should help improve control and address risks. 4. Conclusion 4.1 The overall audit opinion is that limited assurance can be given concerning the effectiveness of management s controls in meeting the objectives of the system. Our opinion is based on the evaluation of controls and testing of their effectiveness for the sample of four projects examined. 4.2 The key findings from the review are as follows: There is no formal project management guidance for project managers. This has resulted in different approaches to project management being prevalent throughout the Council. Important aspects such as risk management and change control are therefore not as well embedded in the process as best practice would expect. Development of any guidance needs to recognise the different requirements for managing low and high cost projects. There is evidence that joined up working between departments occurs for the majority of projects. It was found that officers are aware of both internal and June 2013 Page 4

5 Broxbourne Borough Council Contract Audit Project Management external stakeholders affected by a project, for which early consultation and changes in project status are delivered promptly. There is the need to establish a control/monitoring forum at senior management level to scrutinise and challenge the project management process. Whilst the IDG provides a forum for the formal discussion of Council projects at the corporate level, it does not provide rigorous monitoring and scrutiny of individual projects through out the project life cycle. Most emphasis is placed at the pre-project planning stage rather than rigorous monitoring once the project is under way and through to completion. There is scope to improve the challenge to project completion by developing a project monitoring procedure which could be a function of either this group or alternatively creating a group to take on this role, such as a capital monitoring group. There is a lack of formal review at the end of each project as to the success against its stated objectives and deliverables. Some examples of post project reviews had been carried out and were available at the time of the audit in respect of photovoltaic cells and neighbourhood projects. Existing officer groups could add more rigour by assisting in the peer review and scrutiny of completed projects. There is a need to ensure that risk management is embedded in the project process throughout the life of the project. The use of Microsoft Project software could be considered to ensure effective project management across the Council. 4.3 The audit report highlights areas of risk. These should be added to the current corporate and departmental risk registers as necessary and appropriate mitigating action taken. This will aid in the risk management process, help inform management decisions and assist with future audit plans. 5. Implementation of Agreed Actions 5.1 All of the recommendations in the report have been discussed with and will be taken forward through this forum. There is audit time allocated in the 2013/14 audit plan to follow through with the recommendations raised in this report and look at other aspects of project management. 6. Acknowledgement 6.1 We would like to thank all of the staff involved for their help and co-operation during the course of this audit. June 2013 Page 5

6 7. Management Action Plan Ref Observation Risk Category Recommendation Manager Comments 1 Through discussions with officers responsible for project management, it was clear that processes followed for project management differ throughout the Council. Ineffective project delivery through an individualistic approach to project management. Fundamental We recommend that the Council devises a corporate framework that would assist project managers in their role and ensure a consistent approach to project management. A draft framework had been produced by the Head of Personnel & Payroll in 2009 (as a guide) but was not formally adopted. Concerns were raised about project effectiveness and strain on resources if any corporate guidance was too in depth and inflexible. The need to manage project risk (refer to recommendations at reference 2) and change control should be included within any devised framework. From discussions with project officers, the developments at Grundy Park and Cedars Park showed good examples of this. To compare, the Council s procurement guidance is split into a high and low level procurement. The lower level guidance is generally more This could be split into a high and low cost project checklist in order to; Ensure objectives and key deliverables are identified early in the projects design. That an effective methodology for project delivery is available e.g. use of project milestones. Produce a document that acknowledges the breadth of project that is managed throughout the Council and allows a degree of flexibility. Ensure that a consistent approach towards identifying risk and the use of change control is used throughout the organisation. The Head of Projects is revisiting the methodology proposed by the Head of Personnel and Payroll in 2009, to ensure it has more of a focus as to how project management should be undertaken at Broxbourne. During 13/14 A Cuffaro Head of Projects June 2013 Page 6

7 Ref Observation Risk Category Recommendation Manager Comments flexible than high level. A similar approach here may be useful. A checklist of expected project documents and key milestones should help project officers to apply a consistent approach. Through officer discussions it was apparent that there was some confusion as to the extent and the responsibilities that this lead role encompasses. Lead officers do not understand or perform their role adequately, which could jeopardise the success of projects. Significant We recommend that as part of a corporate framework, the Lead role for projects is clarified, to ensure officers are aware of their wider responsibilities. Whilst lead officer is generally meant to mean project manager, this is to be clarified as part of the revamped project management guidance stated in the above recommendation. During 13/14 From projects reviewed and through officer discussion, it was evident that responsibilities and accountabilities are not always defined at the start of the project. A Cuffaro Head of Projects There is a risk that where projects overlap with other departments, relevant officers are not involved or consulted until the latter stages of the project. 2 Post project procedures were discussed with lead officers as well as a number of officers who have responsibility for projects. Completed projects do not meet specifications. Fundamental We recommend that at the end of each project a formal review of the success of the project against its objectives and deliverables is undertaken by the project manager The remit for the Council s IDG is being reviewed. Within each meeting there is to be a greater focus on the constructive challenge June 2013 Page 7

8 Ref Observation Risk Category Recommendation Manager Comments and formally signed off as complete. A review of the completed project to the initial specification is not always undertaken. to projects as well as ensuring that there is a formal post project review at the end of completed projects. June 2013 As part of the officer led interdisciplinary group (IDG), project officers will notify the group upon project completion. The completed project is added to a completed projects list. However, this does not constitute a formal and rigourous debrief and assessment against original objectives. However, there is no requirement for a formal review to be undertaken by the project manager as to the success of the project in meeting its objectives. June 2013 Page 8

9 Ref Observation Risk Category Recommendation Manager Comments 3 From discussions with project officers, key risks and issues that have affected project delivery are not always recorded or brought to wider attention. Issues that have impeded project delivery are not communicated. Significant We recommend that consideration be given to establishing a central log of risk and issues arising from projects, as an extension to current corporate and departmental risk registers. As part of the changes to IDG, key issues relating to Council projects are to be discussed in a more open forum. Evidence of the appreciation of risk was found for a number of high priority and high value projects i.e. Grundy Park. With the informal arrangements for monitoring risk, there is a danger that mistakes/issues with a project will not be communicated to officers undertaking similar projects in the future. This would allow project officers to understand relevant issues when conducting similar projects. It is planned to keep an up to date log of the main risks and key issues arising from projects. The Treasury, Insurance & Risk Manager is to be consulted during this process. During 2013/14 A Cuffaro Head of Projects Through discussions with project officers, it is clear that a formal process for capturing and monitoring project risk(s) is not widespread. Project risk management is in most cases, undertaken informally and does not always take place throughout the life of the project. Risks throughout the project are not monitored or mitigated against. Significant We recommend that more gravitas should be given to project risk. Business cases could require more formal risk assessment and mitigating actions to risk should be identified and monitored throughout the life of the project. With the changes as to how future IDG meetings are to be run, there is to be greater scrutiny and challenge throughout the life of a project. Project risks will be discussed more openly by the group, with greater scrutiny of initial project proposals. During 2013/14 June 2013 Page 9

10 Ref Observation Risk Category Recommendation Manager Comments 4 During 2011, a course on project management was run internally to highlight issues pertinent to Council projects. Attendees were mainly Directors and Heads of Service. Training courses do not cover important project management issues nor are attended by those with project lead Significant We recommend that the Council s internal training on project management covers project risk and is attended by those with project management responsibilities. responsibilities. Not all officers who have responsibilities for projects have attended this training. The Head of Projects has been asked to lead on producing a training course that meets the needs of the Council s project managers. The new Lead for Corporate Projects & Community Planning will assist in this training development. During 2013/14 It was not clear as to whether project risk was included as part this training. Consequentially, Council officers who are responsible for projects may not have been given the necessary skills to effectively carry out their duties. A Cuffaro Head of Projects A training course on project management was run by Wiz Training and Development and was attended by two ICT officers in December This was pitched at the beginner/intermediate level as an introduction to project management. Training is not attended or relevant to the needs of the Council s project managers. Significant We recommend that the Council ensures that its officers have access to project management training relevant to their experience and needs, before undertaking projects for the Council. Refer to above comments. Attendance on a project management training course relevant to their needs should June 2013 Page 10

11 Ref Observation Risk Category Recommendation Manager Comments be a pre-requisite for officers who have responsibilities for delivering projects. 5 Internal Audit attended a meeting of the officer led Interdisciplinary Group (IDG) to observe how the group functions and deals with key projects. The officer group is made up of the CEO (chair), directors and heads of service with project delivery responsibilities. A schedule of key projects is worked through at each meeting, with explanations for delays and the rectification of outstanding issues, sought. With the officers that attend and the matters discussed, potentially, this group is best positioned to formally challenge and to review completed Council projects. groups do not provide sufficient challenge and review of Council projects. Significant We recommend that a senior officer group should take on the remit for providing a rigourous monitoring process for Council projects. This could be an existing group such as the IDG or IT group, or a new group, such as a capital monitoring group. Terms of reference should be developed once an appropriate forum has been identified. IDG has been designated as the forum to give greater challenge and scrutiny to the Councils projects. The IDG is undergoing a revamp to ensure it offers greater support and challenge to the Council s projects. Whilst it is still a work in progress, some changes to the agenda and schedules have already been made. June 2013 At present the role of IDG does not expressly relate to project monitoring and review. 6 The detailed aspects of monitoring a project outside of its financial management, does If major projects are not rigorously monitored then Significant We recommend that a more structured project review process should be developed for use at the During 2013/14 June 2013 Page 11

12 Ref Observation Risk Category Recommendation Manager Comments not have a specific forum they may not meet designated for its discussion. their objectives. Whilst progress reports are given by project officers to IDG, peer review of progress against milestones and deliverables is not undertaken. monitoring forum identified in recommendation 5 above. This process should be linked into the project review stage. A Cuffaro Head of Projects June 2013 Page 12

13 Appendix A Definitions of Assurance and Recommendation Priorities Levels of Assurance Full Substantial Moderate Limited No Recommendation priorities Fundamental Significant Requires Attention There is a comprehensive system of control designed to achieve the system objectives and manage the risks in achieving those objectives. No weaknesses have been identified. Whilst there is a largely sound system of control, there are some minor weaknesses, which may put a limited number of the system objectives at risk. Basically sound control, with areas of weakness, which put system objectives at risk. (Any fundamental recommendations will prevent this level of assessment.) There are significant weaknesses in key control areas, which put system objectives at risk. There are fundamental control weaknesses, leaving the system open to material error or abuse. Recommendations relate to major weaknesses, which present material risks to objectives and require urgent attention by management, and the Audit Committee. (immediate action) Recommendations relate to significant control weaknesses whose impact or frequency, present a risk which needs to be addressed by management within their areas of responsibility. Recommendations relate to control weaknesses whose impact or frequency needs to be addressed by management within their areas of responsibility and/or recommendations are considered to be best practice. Managers responsibilities managers should develop and maintain sound systems for governance, risk management and internal control, including measures to prevent and detect error and fraud. Internal Audit is not a substitute for this. We plan our work to identify significant control weaknesses and do not guarantee to detect error or fraud managers should not rely on our work to replace their own monitoring and vigilance. June 2013 Page 13

14 Broxbourne Borough Council Appendix B Contract Audit Project Management Projects reviewed Project Department 12/13 Budget Cheshunt Park Golf Club Bore Hole Community Services Date of Original Request 40k 24k deferred from 2006/7. Concurrence for additional funding 2010/11 in Total Spend to date 34.6k Estimated Date of Completion Not detailed within the concurrence. Actual Date of Completion November 2012 West Cheshunt Skate Park Community Services and BLMSO 117k 100k in 2011/12 capital programme carried forward into 12/13, with additional funding given during 12/ k During 2012/13 April 2013 Telephone Migration (Telephony) Computer Services 95k 95k in 2012/13 capital programme 95k December 2012 In progress Theobalds Lane Footpath (cycle-way) Resources 8k Concurrence from 2009/10 7.5k Not detailed within the concurrence. March 2013 June 2013 Page 14

15 Broxbourne Borough Council Contract Audit Project Management Appendix C s Interviewed Environmental Manager Dave Renouf Golf Club Manager Louise Sanderson Community Development Manager Steve Whitlam Head of Computer Services Janice Brooks ICT Consultant Matt Such Asst Director of Property Services Roland Childerhouse Strategy & Projects Manager Clare Watson Special Projects Co-ordinator Richard Grove Treasury & Insurance Manager Chris Wybrew June 2013 Page 15

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 This report has been prepared on the basis of the limitations set out on page 16. Contents Page

More information

Governance, Risk and Best Value Committee

Governance, Risk and Best Value Committee Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary

More information

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT ARGYLL AND BUTE COUNCIL EXECUTIVE SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT 1.0 SUMMARY 1.1 The service reviews for Customer and Support Services, Improvement and HR and Strategic Finance

More information

Internal Audit Strategic and Annual Plans 2015/16

Internal Audit Strategic and Annual Plans 2015/16 Internal Audit Strategic and Annual Plans 2015/16 Financial Scrutiny and Audit Committee 10 February 2015 Agenda Item No 8 Summary: This report provides an overview of the stages followed prior to the

More information

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Internal Audit Report () FINAL Risk Management: Follow Up of Previous Internal Audit Recommendations

More information

Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework

Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework Appendix 1e DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Performance Management Framework DISTRIBUTION LIST Audit Team David Esling, Head of Audit and Assurance - Risk Management

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Appendix 1c DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF CORPORATE GOVERNANCE, STRATEGIC PLANNING AND PERFORMANCE FRAMEWORKS INTEGRATING NEW AREAS OF GLA BUSINESS

More information

City of York Council Public Health 2014/15 Internal Audit Report

City of York Council Public Health 2014/15 Internal Audit Report City of York Council Public Health 2014/15 Internal Audit Report Business Unit: Communities & Neighbourhoods Responsible Officer: Interim Director of Public Health Service Manager: Public Health Consultants

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE. Appendix 2a FOLLOW UP REVIEW OF CORPORATE BUSINESS CONTINUITY

DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE. Appendix 2a FOLLOW UP REVIEW OF CORPORATE BUSINESS CONTINUITY DIRECTORATE OF AUDIT, RISK FF AND ASSURANCE Internal (Foundry Audit Forms Service San/ Font size to 20/ the RBG: 160, GLA 160, 170) Appendix 2a FOLLOW UP REVIEW OF CORPORATE BUSINESS CONTINUITY DISTRIBUTION

More information

Governance and Audit Committee 23 November 2015

Governance and Audit Committee 23 November 2015 Agenda Item 7 Governance and Audit Committee 23 November 2015 Welland Internal Audit Consortium Internal Audit Plan & Performance Update 2015/16 Purpose of report: To provide Members with information on

More information

Audit Committee, 13 March 2013. Internal Audit Report Project Management. Executive summary and recommendations. Introduction

Audit Committee, 13 March 2013. Internal Audit Report Project Management. Executive summary and recommendations. Introduction Audit Committee, 13 March 2013 Internal Audit Report Project Management Executive summary and recommendations Introduction Mazars has undertaken a review of the arrangements for project management in accordance

More information

Note the Chief Internal Auditor s findings to date and gain assurance from Officers that key issues raised are being addressed.

Note the Chief Internal Auditor s findings to date and gain assurance from Officers that key issues raised are being addressed. Agenda Item No: 9 To: Joint Audit Committee Date: 24 September 2014 By: Chief Internal Auditor Title: Internal Audit Update Report 2014-15 Purpose of Report: The purpose of this report is to give an opinion

More information

Internal Audit Report Project Management

Internal Audit Report Project Management Audit Committee, 20 Internal Audit Report Project Management Executive summary and recommendations Introduction As part of the Internal Audit Plan for 2013-14 Mazars have undertaken a review of arrangements

More information

Commissioning Strategy

Commissioning Strategy Commissioning Strategy This Commissioning Strategy sets out the mechanics of how Orkney Alcohol and Drugs Partnership (ADP) will implement its strategic aims as outlined in the ADP Strategy. Ensuring that

More information

Customer Engagement Strategy 2015/16-2017/18

Customer Engagement Strategy 2015/16-2017/18 Customer Engagement Strategy 2015/16-2017/18 1 Our Vision To provide a great quality customer engagement service that is accessible to all our customers and offers a wide range of opportunities to work

More information

Trust Board Report. Review of the effectiveness of the IM&T Committee

Trust Board Report. Review of the effectiveness of the IM&T Committee 1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments

More information

The Learning Zone - Project Management Arrangements

The Learning Zone - Project Management Arrangements Coleg Gwent Internal Audit Report () 6 June 2012 Overall Opinion The Learning Zone - Project Management Arrangements CONTENTS Section Page Executive Summary 1 Action Plan 4 Findings and Recommendations

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Part Two Part One Not Protectively Marked DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy. The Dorset & Wiltshire Fire and Rescue Authority (DWFRA)

More information

Interim Audit Report. Borough of Broxbourne Audit 2010/11

Interim Audit Report. Borough of Broxbourne Audit 2010/11 Interim Audit Report Borough of Broxbourne Audit 2010/11 The Audit Commission is an independent watchdog, driving economy, efficiency and effectiveness in local public services to deliver better outcomes

More information

Project, Programme and Portfolio Management Delivery Plan 6

Project, Programme and Portfolio Management Delivery Plan 6 Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy

More information

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT 1 Scope of Internal Audit 1.1 Terms of Reference 1.1.1 Do terms of reference: (a) establish the responsibilities and objectives

More information

(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and

(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and Agenda Item No. 7 Governance Committee 23 November 2015 Partnership Governance for Contract Management Report by Director of Law Assurance and Strategy Executive Summary This report sets out some areas

More information

Good Practice Guide: the internal audit role in information assurance

Good Practice Guide: the internal audit role in information assurance Good Practice Guide: the internal audit role in information assurance Janaury 2010 Good Practice Guide: the internal audit role in information assurance January 2010 Official versions of this document

More information

The report rated this area Substantial Assurance and made 2 housekeeping recommendations.

The report rated this area Substantial Assurance and made 2 housekeeping recommendations. Audit Committee 21 June 2012 Internal audit report Risk Management review Executive summary and recommendations Introduction Mazars have undertaken a review of Risk Management, in accordance with the internal

More information

Quality Impact Assessment. Executive summary

Quality Impact Assessment. Executive summary Report to Public Trust Board 28 th February 2013 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Quality Impact Assessment Director of Quality and Safety/ Chief Nurse Director

More information

PERFORMANCE & PERSONAL DEVELOPMENT PROGRAMME Launched: April 2010

PERFORMANCE & PERSONAL DEVELOPMENT PROGRAMME Launched: April 2010 PERFORMANCE & PERSONAL DEVELOPMENT PROGRAMME Launched: April 2010 1 PERFORMANCE & PERSONAL DEVELOPMENT PROGRAMME INDEX Page Introduction 3 PPDP Cycle 4 Performance planning meeting 5 Performance planning

More information

Activate Learning Further Education Corporation

Activate Learning Further Education Corporation Activate Learning Further Education Corporation MINUTES of a meeting of the Audit Committee held on 10 June 2014 at 5.30 pm in room A106 at Oxford City College Campus. Present: In attendance: C Jones (Chairman);

More information

INVESTING IN REFORM INVESTING IN STOCKPORT DRAFT BUSINESS CASE

INVESTING IN REFORM INVESTING IN STOCKPORT DRAFT BUSINESS CASE INVESTING IN STOCKPORT DRAFT BUSINESS CASE INVESTING IN REFORM IIS Programme/Project Name: Project Name: Portfolio: IIS Outcome: IIS Board SRO: IIS Project Lead: Public Realm and Solutions SK Communities

More information

SMBC ICT Functional Review Recommendations (Amended 1 st June 2016)

SMBC ICT Functional Review Recommendations (Amended 1 st June 2016) SMBC ICT Functional Review Recommendations (Amended 1 st June 2016) No. Recommendation ICT and Peer Review Comments Responsibility Deadline Current 1. Whilst the ICT Strategy is well defined and documented,

More information

SUMMARY OF MONITOR S WELL-LED FRAMEWORK FOR GOVERNANCE REVIEWS: GUIDANCE FOR NHS FT S PUBLICATION Report by Trust Secretary

SUMMARY OF MONITOR S WELL-LED FRAMEWORK FOR GOVERNANCE REVIEWS: GUIDANCE FOR NHS FT S PUBLICATION Report by Trust Secretary SUMMARY OF MONITOR S WELL-LED FRAMEWORK FOR GOVERNANCE REVIEWS: GUIDANCE FOR NHS FT S PUBLICATION Report by Trust Secretary 1. Introduction Under the Risk Assessment Framework and in line with the NHS

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

The Audit Committee self-assessment checklist

The Audit Committee self-assessment checklist GOOD PRACTICE The Audit Committee self-assessment checklist 2nd edition January 2012 Financial Management and Reporting 2 The Audit Committee self-assessment checklist Our vision is to help the nation

More information

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY Zurich Management Services Limited Registered in England: No 2741053 Registered Office The Zurich Centre, 3000 Parkway Whiteley, Fareham Hampshire, PO15 7JZ CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY

More information

Complaints Policy. Complaints Policy. Page 1

Complaints Policy. Complaints Policy. Page 1 Complaints Policy Page 1 Complaints Policy Policy ref no: CCG 006/14 Author (inc job Kat Tucker Complaints & FOI Manager title) Date Approved 25 November 2014 Approved by CCG Governing Body Date of next

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK Appendix 1b DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK DISTRIBUTION LIST Audit Team Steve Hutton, Head of

More information

Review of the Management of Sickness Absence Conwy County Borough Council

Review of the Management of Sickness Absence Conwy County Borough Council Audit 2004/2005 Date: December 2005 Authors: Ros Adams and George Jones Ref: 1072A2005 Review of the Management of Sickness Absence Conwy County Borough Council Contents Summary Report Introduction 3 Background

More information

CAMBRIDGE CITY COUNCIL

CAMBRIDGE CITY COUNCIL Agenda Item CAMBRIDGE CITY COUNCIL REPORT OF: Director of Business Transformation TO: Civic Affairs Committee 25 June 2014 WARDS: All INTERNAL AUDIT: REVIEW OF EFFECTIVENESS 2013 / 2014 1 INTRODUCTION

More information

Consultation and Engagement Strategy

Consultation and Engagement Strategy Consultation and Engagement Strategy Contents: 1. Introduction 2 2. Purpose 3 3. Aims and Objectives 4 4. Key principles 5 5. Delivery of the Strategy 6 6. Action Plan 2011-12 7 Appendix 1 Understanding

More information

Financial Planning Assessment Vale of Glamorgan County Borough Council. Audit year: 2013-14 Issued: January 2015 Document reference: 620A2014

Financial Planning Assessment Vale of Glamorgan County Borough Council. Audit year: 2013-14 Issued: January 2015 Document reference: 620A2014 Financial Planning Assessment Vale of Glamorgan County Borough Council Audit year: 2013-14 Issued: January 2015 Document reference: 620A2014 Status of report This document has been prepared for the internal

More information

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08 Performance Detailed Report May 2008 Review of Performance Management Audit 2007/08 External audit is an essential element in the process of accountability for public money and makes an important contribution

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com

More information

Information Governance Management Framework

Information Governance Management Framework Information Governance Management Framework Responsible Officer Author Business Planning & Resources Director Governance Manager Date effective from October 2015 Date last amended October 2015 Review date

More information

Reporting The Project Board shall report to the sponsoring Department political board.

Reporting The Project Board shall report to the sponsoring Department political board. Appendix 13 La Mare de Carteret Schools Project Board Mandate Summary (Project restart version March 2014) Function The Project Board is accountable to the Education Department for all aspects contributing

More information

Annual Governance Statement

Annual Governance Statement Annual Governance Statement 2014/15 1 Fareham Borough Council Civic Offices, Civic Way, Fareham PO16 7AZ Scope of Responsibility Fareham Borough Council is responsible for ensuring that its business is

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

Corporate Risk Management Policy

Corporate Risk Management Policy Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

APPENDIX C. Internal Audit Report South Holland District Council Project Management

APPENDIX C. Internal Audit Report South Holland District Council Project Management APPENDIX C Internal Audit Report South Holland District Council Project Management Date: 20th December 2012 Contents Introduction and Scope 1 Executive Summary Assurance Opinion Key Messages 2 3 Management

More information

NHSBT Board January 28 2016. National Organ Retrieval Service Review Implementation

NHSBT Board January 28 2016. National Organ Retrieval Service Review Implementation NHSBT Board January 28 2016 National Organ Retrieval Service Review Implementation 1. Status Public Executive Summary This paper provides an update on implementation of the National Organ Retrieval Service

More information

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 INTERNAL AUDIT PLAN Report of the: Director of Finance Contact: John Turnbull or Gillian McTaggart Urgent Decision?(yes/no) No If yes, reason urgent decision required:

More information

Page 7. Area Served: Borough Wide Chair of the Committee: Cllr Tim Crowley

Page 7. Area Served: Borough Wide Chair of the Committee: Cllr Tim Crowley Report to: Date: Report of: Audit Committee Page 7 27 th September Executive Head Policy and Customer Services Agenda Item 4 Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Gill Bull,

More information

Business Continuity Policy & Plans

Business Continuity Policy & Plans Agenda Item 8.3a SNCCG Governing Body 11.03.2014 Business Continuity Policy & Plans Ref Number: Version: 1 Status: Pending Approval Author: A Brown Approval body Governing Body Date Approved Date Issued

More information

Case Study Addressing the Challenges of Project and Programme Management Manchester City Council

Case Study Addressing the Challenges of Project and Programme Management Manchester City Council Case Study Manchester City Council Addressing the Challenges of Project and Programme Management Capacity Building Programme Supported Communities and Local Government Published by: The Improvement and

More information

Project Management Policy and Procedure

Project Management Policy and Procedure Project Management Policy and Procedure Author(s): Laura Graham Peter Griggs Approved SMT: October 2006 Issue Date: October 2006 Policy Review Date Ref: Contents: 1. Purpose and Scope 2. Aims and Objectives

More information

Derbyshire County Council Performance and Improvement Framework. January 2012

Derbyshire County Council Performance and Improvement Framework. January 2012 Derbyshire County Council Performance and Improvement Framework January 2012 Contents 1. Introduction 3 2. About the framework 4 3. Planning 7 5. Monitoring Performance 8 6. Challenge and Review 11 7.

More information

TECHNICALS LEVEL 2016 3 BUSINESS

TECHNICALS LEVEL 2016 3 BUSINESS 2016 Suite Cambridge TECHNICALS LEVEL 3 BUSINESS Unit 16 Principles of project management M/507/8163 Guided learning hours: 60 Version 2 - Revised content - March 2016 ocr.org.uk/business LEVEL 3 UNIT

More information

Ealing, Hammersmith and West London College

Ealing, Hammersmith and West London College FURTHER EDUCATION COMMISSIONER ASSESSMENT SUMMARY Ealing, Hammersmith and West London College JANUARY 2016 Contents Assessment... 3 Background... 3 Assessment Methodology... 3 The Role, Composition and

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT.

INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT. INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT July 2010 PREPARED BY THE INTERNAL AUDIT BRANCH (IAB) Project No:

More information

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart)

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) Audit activity is governed by the HEFCE Code of Audit Practice. 1. Determining audit activity a) Audits will be conducted

More information

Comhairle nan Eilean Siar Internal Audit Follow Up Review PERFORMANCE MANAGEMENT & MONITORING. Final Report FU17 12/13

Comhairle nan Eilean Siar Internal Audit Follow Up Review PERFORMANCE MANAGEMENT & MONITORING. Final Report FU17 12/13 Comhairle nan Eilean Siar Internal Audit Follow Up Review Final Report FU17 12/13 30 th May 2013 CONTENTS Page SECTION 1 - EXECUTIVE SUMMARY 1 3 SECTION 2 - DETAILED FINDINGS AND RECOMMENDATIONS 4 7 30

More information

Collaborative development of evaluation capacity and tools for natural resource management

Collaborative development of evaluation capacity and tools for natural resource management Collaborative development of evaluation capacity and tools for natural resource management Helen Watts (Adaptive Environmental Management, formerly NSW Department of Environment and Climate Change) Sandra

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report.

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report. REPORT TO: SCRUTINY COMMITTEE 25 JUNE 2013 REPORT ON: REPORT BY: INTERNAL AUDIT REPORTS CHIEF INTERNAL AUDITOR REPORT NO: 280-2013 1.0 PURPOSE OF REPORT To submit to Members of the Scrutiny Committee a

More information

Project organisation and establishing a programme management office

Project organisation and establishing a programme management office PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups

Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups Item 13 Strategic Estates Planning Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups Phase 1: Priorities and

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

EXECUTIVE SUMMARY...5

EXECUTIVE SUMMARY...5 Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9

More information

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited Investors in People Assessment Report for Bradstow School Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited 30 August 2013 Project Reference Number

More information

Financial Management Framework >> Overview Diagram

Financial Management Framework >> Overview Diagram June 2012 The State of Queensland (Queensland Treasury) June 2012 Except where otherwise noted you are free to copy, communicate and adapt this work, as long as you attribute the authors. This document

More information

States of Jersey Comptroller & Auditor General

States of Jersey Comptroller & Auditor General States of Jersey Comptroller & Auditor General Code of Audit Practice (Prepared under Article 18 of the Comptroller and Auditor General (Jersey) Law 2014) 28 November 2014 Foreword Independent external

More information

Which MPA Assurance Review?

Which MPA Assurance Review? Which MPA Assurance? A guide to choosing which MPA Assurance s to include in the Integrated Assurance and Approvals Plan for your Major Project Version 1.0 March 2012 Copyright and contacts Crown copyright

More information

Richmond-upon-Thames Performance Management Framework

Richmond-upon-Thames Performance Management Framework Richmond-upon-Thames Performance Management Framework Introduction Everyone at the Council has a role in Performance Management. It is therefore important that we all understand what is involved. This

More information

Report for Information. Subject: Annual Review of the System of Internal Audit 2009/10

Report for Information. Subject: Annual Review of the System of Internal Audit 2009/10 Report for Information Report To: Audit Committee - 3 June 2010 Subject: Annual Review of the System of Internal Audit 2009/10 Report of: City Treasurer Summary In accordance with the requirements of the

More information

ACADEMIC POLICY FRAMEWORK

ACADEMIC POLICY FRAMEWORK ACADEMIC POLICY FRAMEWORK Principles, Procedures and Guidance for the Development & Review of Academic Policies [V.1] Page 2 of 11 TABLE OF CONTENTS 1. FRAMEWORK OVERVIEW... 3 2. PRINCIPLES... 4 3. PROCESS...

More information

Performance Management and Service Improvement Framework

Performance Management and Service Improvement Framework Performance Management and Service Improvement Framework Author Marcus Evans, Operational Director - Performance and Customer Insight Date: September 2014 Contents Page 1. Introduction 3 2. Strategic ning

More information

Internal Audit (policy & procedure)

Internal Audit (policy & procedure) Internal Audit (policy & procedure) Objective (purpose) The purpose of this document is to ensure the Crime and Corruption Commission s (CCC) internal audit function operates efficiently and effectively

More information

Fundamental Performance Review Partnership Working 4

Fundamental Performance Review Partnership Working 4 Report title Agenda item Fundamental Performance Review Partnership Working 4 Meeting Performance Management & Community Safety Panel 19 May 2008 Date Report by Document Number Director of Corporate Services

More information

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010 Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0

More information

Appendix 4 - Statutory Officers Protocol

Appendix 4 - Statutory Officers Protocol Appendix 4 - Statutory Officers Protocol Accountability Protocol for role of Director of Children s Services within the London Borough of Barnet Introduction In September 2014, the Chief Executive of the

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

Audit Committee Institute Assessment of audit committees

Audit Committee Institute Assessment of audit committees Audit Committee Institute Assessment of audit committees KPMG s AUDIT COMMITTEE INSTITUTE In addition to reviewing its terms of reference, audit committee members should also review the effectiveness of

More information

VISION FOR LEARNING AND DEVELOPMENT

VISION FOR LEARNING AND DEVELOPMENT VISION FOR LEARNING AND DEVELOPMENT As a Council we will strive for excellence in our approach to developing our employees. We will: Value our employees and their impact on Cardiff Council s ability to

More information

Internal Audit Division

Internal Audit Division Internal Audit Division at the Financial Conduct Authority Information Pack April 2013 Contents of Information Pack A. Introduction B. Internal Audit Terms of Reference C. Organisation D. Skills and Competencies

More information

CENTRAL LINCOLNSHIRE LOCAL PLAN HIGHLIGHT REPORT

CENTRAL LINCOLNSHIRE LOCAL PLAN HIGHLIGHT REPORT Public Sector Auditing.. Private Sector Thinking CENTRAL LINCOLNSHIRE LOCAL PLAN HIGHLIGHT REPORT Date: 7 th November 2014 Author: Rachel Abbott Principal Auditor Introduction & Scope The National Planning

More information

Mathematics. Introduction

Mathematics. Introduction Mathematics Introduction Numeracy is a core subject within the National Curriculum. This policy outlines the purpose, nature and management of the mathematics taught and learned in our school. Mathematics

More information

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers Appendix 1 RISK MANAGEMENT POLICY AND STRATEGY Document Status: Draft Originator: A Struthers Updated: A Struthers Owner: Executive Director Corporate Services Version: 01.01.03 Date: 30/3/14 Approved

More information

PERFORMANCE DATA QUALITY POLICY

PERFORMANCE DATA QUALITY POLICY PERFORMANCE DATA QUALITY POLICY 2007 / 08 Improvement Service May 10 th 2007 Data Quality Policy V7 10.05.07 1 INTRODUCTION / BACKGROUND Good quality performance data is accurate, valid, reliable, timely,

More information

Business Continuity Management. Policy Statement and Strategy

Business Continuity Management. Policy Statement and Strategy Business Continuity Management Policy Statement and Strategy November 2011 Title Business Continuity Management Policy & Strategy Date of Publication: Cabinet Council Published by Borough Council of King

More information

NORTH YORKSHIRE FIRE AND RESCUE AUTHORITY AUDIT AND PERFORMANCE REVIEW COMMITTEE 25 JUNE 2014 INTERNAL AUDIT PROGRESS REPORT TO 31 MAY 2014

NORTH YORKSHIRE FIRE AND RESCUE AUTHORITY AUDIT AND PERFORMANCE REVIEW COMMITTEE 25 JUNE 2014 INTERNAL AUDIT PROGRESS REPORT TO 31 MAY 2014 ITEM 5 NORTH YORKSHIRE FIRE AND RESCUE AUTHORITY AUDIT AND PERFORMANCE REVIEW COMMITTEE 25 JUNE 2014 INTERNAL AUDIT PROGRESS REPORT TO 31 MAY 2014 Report of the Head of Internal Audit 1.0 PURPOSE OF THE

More information

Internal audit report Information Security / Data Protection review

Internal audit report Information Security / Data Protection review Audit Committee 29 September 2011 Internal audit report Information Security / Data Protection review Executive summary and recommendations Introduction Mazars have undertaken a review of Information Security

More information

Quality Governance Strategy 2011-2013

Quality Governance Strategy 2011-2013 Quality Governance Strategy 2011-2013 - 1 - Index Content Page Number Key Messages and context of the Strategy 3 Introduction What is Quality governance? What do we want to achieve? Trust Objectives Key

More information

NHS Greater Huddersfield Clinical Commissioning Group. Remuneration Committee. Terms of Reference

NHS Greater Huddersfield Clinical Commissioning Group. Remuneration Committee. Terms of Reference NHS Greater Huddersfield Clinical Commissioning Group Remuneration Committee Terms of Reference Version: 1.0 Committee Approved by: Governing Body NHS Greater Huddersfield CCG Date Approved 1 st May 2013

More information

Councillor Roger Bayliss 01530 411055 roger.bayliss@nwleicestershire.gov.uk. Director of Housing 01530 454819 glyn.jones@nwleicestershire.gov.

Councillor Roger Bayliss 01530 411055 roger.bayliss@nwleicestershire.gov.uk. Director of Housing 01530 454819 glyn.jones@nwleicestershire.gov. NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL POLICY DEVELOPMENT GROUP 1 JULY 2015 Title of report DRAFT VALUE FOR MONEY STRATEGY FOR THE HOUSING SERVICE Councillor Roger Bayliss 01530 411055 roger.bayliss@nwleicestershire.gov.uk

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information