Care and Maintenance Mining Operations Plan. 6 May November Sunnyside Coal Mine. Report Number

Size: px
Start display at page:

Download "Care and Maintenance Mining Operations Plan. 6 May 2016 5 November 2020. Sunnyside Coal Mine. Report Number 634.10030."

Transcription

1 6 May 216 November 22 Report Number April 216 Whitehaven Coal Mining Limited Gunnedah NSW Version: Revision

2 Report Number April 216 Revision Page I 6 May 216 November 22 PREPARED BY: ABN PO Box 1134 Tamworth NSW 234 Australia M: F: tamworth@slrconsulting.com This report has been prepared by with all reasonable skill, care and diligence, and taking account of the timescale and resources allocated to it by agreement with the Client. Information reported herein is based on the interpretation of data collected, which has been accepted in good faith as being accurate and valid. This report is for the exclusive use of Whitehaven Coal Mining Limited. No warranties or guarantees are expressed or should be inferred by any third parties. This report may not be relied upon by other parties without written consent from SLR Consulting. SLR Consulting disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the work. DOCUMENT CONTROL Reference Status Date Prepared Checked Authorised Revision 7 April 216 P. Tett A. Hutton / J. Johnson J. Johnson

3

4 Report Number April 216 Revision Page III TABLE OF CONTENTS 1 INTRODUCTION History of Operations Scope of this MOP Consents, Authorisations and Licences Land Ownership and Land Use 3 1. Stakeholder Consultation 3 2 PROPOSED ACTIVITIES IN THE MOP TERM 2.1 Project Description 2.2 Asset Register 2.3 Activities over the MOP Term Exploration Construction Mining Operations Overburden Emplacement Processing Residues Waste Management Decommissioning and Demolition Activities Temporary Stabilisation Progressive Rehabilitation and Completion Material Production Schedule 7 3 ENVIRONMENTAL ISSUES MANAGEMENT Environmental Risk Assessment Environmental Risk Management Air Quality Surface and Ground Water Erosion and Sedimentation Contaminated Land Flora and Fauna Weeds and Pests Soil Resources and Management Noise Visual and Lighting Aboriginal and Cultural Heritage European Heritage Spontaneous Combustion Bushfire Mine Subsidence 13 4 POST MINING LAND USE Regulatory Requirements Post Mining Land Use Goals 17

5 Report Number April 216 Revision Page IV Biodiversity Enhancement Pasture Final Void Retained Infrastructure Rehabilitation Objectives ShortCterm rehabilitation objectives: LongCterm rehabilitation objectives: 18 REHABILITATION PLANNING 19.1 Domain Selection 19.2 Domain Rehabilitation Objectives 21.3 Rehabilitation Phases 22 6 PERFORMANCE INDICATORS AND COMPLETION CRITERIA 23 7 REHABILITATION IMPLEMENTATION Status at MOP Commencement Proposed Rehabilitation Activities during the MOP Term Summary of Rehabilitation Areas during the MOP Term Relinquishment Phase Achieved During MOP Period 37 8 REHABILITATION MONITORING AND RESEARCH Rehabilitation Monitoring Remote Sensing Pasture Areas Native Vegetation Monitoring Terrestrial Fauna and Habitat Monitoring Research and Rehabilitation Trials and Use of Analogue Sites Rehabilitation Trials Analogue Sites 4 9 INTERVENTION AND ADAPTIVE MANAGEMENT Threats to Rehabilitation Trigger Action Response Plan 42 1 REPORTING REVIEW AND IMPLEMENTATION OF THE MOP Review Implementation REFERENCES

6 Report Number April 216 Revision Page V TABLES Table 1: Consents, Authorisations and Licences Table 2: Asset Register Table 3: Inventory of Soil Volumes (stockpiled and spread to date) Table 4: Regulatory and Approval Requirements Relating to Post Mining Land Use and Rehabilitation Table : Primary Domains Table 6: Secondary Domains Table 7: Domain Rehabilitation Objectives Table 8: Rehabilitation Phases Table 9: Summary of Rehabilitation Phases throughout the MOP Term Table 1: Decommissioning Phase Table 11: Landform Establishment Phase Table 12: Growth Medium Development Phase Table 13: Ecosystem Establishment Phase Table 14: Ecosystem Sustainability Phase Table 1: Relinquishment Table 16: Rehabilitation Status and Proposed Activities at MOP Commencement Table 17: Summary of Rehabilitation Proposed during the MOP Term Table 18 Key Threats to Rehabilitation Table 19: Rehabilitation TARP Table 2: Responsibilities for Implementation of the MOP APPENDICES Appendix A MOP Plans Appendix B Sunnyside MOP Risk Register

7 Report Number April 216 Revision Page 1 1 INTRODUCTION 1.1 History of Operations The (Sunnyside) is a conventional openccut coal mining operation, located in northern New South Wales (NSW), within the Gunnedah Shire, 1 km west of Gunnedah NSW (Plan 1A). The coal product is a thermal coal for the export market. The mine is located within Mining Lease (ML) 1624 which is 1624 issued to Namoi Mining Pty Ltd (NMPL)and is hectares in size. Sunnyside is wholly owned and managed by NMPL, a wholly owned subsidiary of Whitehaven Coal Limited (WCL) which is a publicly listed company on the Australian Stock Exchange. Project Approval for the was granted by the NSW Minister for Planning under Part 3A of the NSW Environmental Planning and Assessment Act, 1979 (EP&A Act) on 24 September 28 (PA 6_38). ML1624 was issued by the Minister for Mineral Resources on November 28. In addition, Environment Protection Licence (EPL) 1297 was granted on 1 December 28. The Project Approval provided for the extraction of approximately 7 million tonnes (Mt) of Run of Mine (ROM) coal, with a maximum rate of 1 million tonnes per annum (Mtpa). The approval also allows for the crushing and screening of ROM coal at Sunnyside, prior to transport to the Whitehaven Siding Coal Handling and Preparation Plant (CHPP) near Gunnedah. Mining occurred from the Hoskissons Coal Seam which is described as medium volatile bituminous coal. The seam is typically 9 m thick and subdivided into two runcofcmine (ROM) coal plies, including low ash comprising the lower 4 m of the seam and high ash comprising the upper m of the seam. Coal was recovered from the ROM stockpile and transported via road truck to the CHPP which is approximately 16 km from Sunnyside. Following processing the coal is loaded onto trains for transport to the Port of Newcastle for export. Due to unfavourable economic conditions, mining operations at Sunnyside ceased on 29 November 212, with stockpiled ROM coal continuing to be transported to the CHPP on a campaign basis until May 213. Activities at the mine site since then have been limited to environmental monitoring, ongoing rehabilitation, and care and maintenance of the site (including spontaneous combustion management). There have been three amendments to the original MOP for Sunnyside previous to this document. MOP (28) Original MOP; MOP Amendment A (August 214) C prepared to reflect the care and maintenance status of the site, and extend the MOP life to the end of 214 to allow WCM to develop and seek NSW Trade and Investment Division of Resources and Energy (DRE) approval for a suitable Care and Maintenance MOP; MOP Amendment B (November 214) C prepared to extend the term of the MOP until November 21 to coincide with the expiry of the Project Approval and facilitate preparation of a number of technical studies to inform the development of a preferred final landform that is achievable in the event of limited further mining at Sunnyside; and MOP Amendment C (November 21) prepared to extend the term of the MOP to May 216 due to delay in issue of the Project Approval Modification.

8 Report Number April 216 Revision Page Scope of this MOP It is estimated that approximately 1 Mt of mineable coal reserve remains within the current open cut consent area. Should it become economically viable, Whitehaven may recommence operations. Subsequently, an application to modify the Project Approval was submitted to the Department of Planning and Environment (DP&E). The primary purpose of the Project Approval modification was to extend the term of the approval until December 22. The modification to the Project Approval was approved on 3 November 21. This MOP has been prepared as a care and maintenance document and does not reflect any additional coal recovery, processing or transport. Should the recovery of the remaining coal become economically viable, a revised MOP will be submitted to the DRE to reflect the shift from care and maintenance to operational status. The scope of this MOP includes activities associated with: Ongoing management of issues such as spontaneous combustion and water; Ongoing environmental monitoring; and Ongoing rehabilitation monitoring and rehabilitation maintenance as required. This MOP has been prepared in accordance with the DRE guideline ESG3 Mining Operations Plan (MOP) Guidelines (ESG3) (DRE, September 213) and to meet all regulatory requirements including relevant consent conditions documented in Table 4. Sunnyside is a State Significant Development and subsequently is considered a Level 1 Mine for the purposes of ESG3. A rehabilitation cost estimate (RCE) was provided to DRE in 21 for the revised final landform and therefore will not be updated for this MOP. In accordance with the DRE guideline ESG1 Rehabilitation Cost Estimate Guidelines the RCE was calculated for the maximum disturbance during the MOP. 1.3 Consents, Authorisations and Licences Sunnyside s consents, authorisations and licenses are listed in Table 1. The ML and Project Approval areas are shown on the MOP Plans. Table 1: Consents, Authorisations and Licences Regulatory Authority Instrument Date of Issue Expiry Date Comments NSW Department of Industry, Skills and Regional Development Division of Resources and Energy ML 1624 November 28 November 229 NSW Department of Planning and Environment PA 6_38 24 September 28 November 21 NSW Department of Planning and Environment PA 6_38 MOD 1 3 November 21 November 22 To extend expiry of PA 6_38 and address revised final landform. NSW Environment Protection Authority (EPA) EPL November 28 C Includes two licensed surface water discharge points.

9 Report Number April 216 Revision Page 3 Regulatory Authority Instrument Date of Issue Expiry Date Comments Department of Primary Industries Water (DPI Water) Water Licences WAL BL248 9BL2486 9BL2487 9BL2488 9BL2489 9BL BL BL1284 Various C Water Access License and Groundwater monitoring bores. 1.4 Land Ownership and Land Use Sunnyside is located on the Sunnyside property which is owned by NMPL. The Werona and Lilydale properties, located to the northwest and east of Sunnyside respectively, are also owned by NMPL. The Plain View property, located to the northeast of Sunnyside is privately owned, however the property is related to Sunnyside operations through leasing of the section of the property on which the coal transport route is located. Sunnyside is located on Lot 12 DP73 and Lot 1 DP3937 which are within the Parish of Gill in the Gunnedah Shire. These parcels are held in freehold title by NMPL. The subject land is zoned RU1 (Primary Production) under the Gunnedah Local Environment Plan 212. The general location of Sunnyside is shown on Plan 1A. PreCmining land use is shown on Plan 1B. Prior to mining, Sunnyside had predominantly been cleared for agricultural cultivation and grazing and was vegetated with open grassland. Land use immediately surrounding Sunnyside is also predominantly cropping and pastoral land use. A rocky escarpment with remnant vegetation and regrowth is located immediately south of the Sunnyside mine. This southern area is considered a valuable area of local habitat given the historical landscape clearing within the region and is proposed to be managed as Koala habitat. 1. Stakeholder Consultation Whitehaven and / or its representatives consulted with the following government agencies during the preparation of the 28 MOP and associated environmental management / monitoring plans. Department of Primary Industries C Mineral Resources (now DRE). Department of Environment and Climate Change (now EPA). Department of Water and Energy (now DPI Water). Whitehaven consulted with the DRE during preparation of MOP Amendments A, B and C and confirmed with DRE that the content of this MOP would specifically relate to care and maintenance activities. Whitehaven has been consulting with DRE on Care and Maintenance MOP requirements and the revised final landform since 214 and draft MOP plans were presented to DRE in January 216. Consultation regarding the rehabilitation of the was primarily undertaken during the preparation of the Sunnyside Coal Project Environmental Assessment 28 (SCPEA) and revolved around negotiating an acceptable compromise between: restoring areas of the final land form to a similar or better class of land than that prior to mining; and creating an aesthetically pleasing final landform.

10 Report Number April 216 Revision Page 4 Further consultation has occurred with relevant stakeholders during preparation of the Sunnyside Coal Mine Environmental Assessment 21 and, specific to rehabilitation, the integration of the site Rehabilitation and Landscape Management Plan into this MOP (refer Sections 48) in accordance with DRE direction. A Community Consultative Committee (CCC) has been established and routine meetings convened in accordance with the requirements of PA 6_38 MOD 1 (Schedule Condition 9). Meeting minutes are available on the Whitehaven website. Progress of rehabilitation and closure activities has been reported annually in the Annual Environmental Management Reports (AEMR) which are available on the Whitehaven website.

11 Report Number April 216 Revision Page 2 PROPOSED ACTIVITIES IN THE MOP TERM 2.1 Project Description Mining ceased at Sunnyside in November 212 due to unfavourable economic conditions and the operation was placed into care and maintenance. Approximately 1 Mt of mineable coal reserve coal remains within the pit. At present the recommencement of mining to recover the remaining coal is not scheduled within the term of this MOP. Subsequently, completion of the final landform development is not possible until mining is completed or the decision taken to forgo the remaining coal. The activities during the term of this MOP will include: Ongoing management of issues such as spontaneous combustion and water; Ongoing environmental monitoring; and Ongoing rehabilitation monitoring and rehabilitation maintenance as required. Whitehaven propose, not necessarily within this MOP term, to partially backfill the remaining open cut void to encapsulate exposed carboniferous material susceptible to spontaneous combustion and buttress the final highwall to achieve long term stability of the void. Whitehaven propose to use overburden material rehandled from the northern outcofcpit emplacement. Review of the environmental technical studies was undertaken to support the application for modification of the Project Approval made to DP&E. These included: Surface and ground water studies including a water balance for the proposed final void; Geotechnical assessment of the proposed highwall treatment options; and Visual amenity assessment for the proposed rehabilitated high wall and final landform. 2.2 Asset Register Primary domains have been defined in accordance with the requirements of ESG3 and represent the set of discrete areas that have a particular operational or functional purpose. All areas previously disturbed by mining, or proposed to be subject to the activities described in the sections below, have been assigned to an appropriate primary domain. The relevant primary domains at Sunnyside are defined in Section.1. The asset register (Table 2) provides a summary of the key features of each primary domain and principal activities required for decommissioning and rehabilitation. The areas for each primary domain represent the footprint for each domain depicted on Plan 2. Table 2: Asset Register Domain Domain 1: Infrastructure Area (ha) Major Assets 23.2 Ablutions block; Sealed access road and haul route to the Coocooboonah Lane intersection at the ML boundary); Unsealed access roads; Hardstand; Administration buildings; Helipad; Amenity bund; Vehicle washcdown sump; Maintenance Facility; and

12 Report Number April 216 Revision Page 6 Domain Domain 3: Water management areas Domain : Overburden emplacement areas Area (ha) Major Assets Explosives Magazine and bund..1 Sediment dams, clean water storage dams, pipelines and pumps 8.41 Spoil emplacements required for operations or under rehabilitation for native vegetation and pasture land uses. Domain 4: Stockpiled material.91 Areas disturbed for stockpiling material for future management, (e.g. soil resources). Domain 6: Void (Open cut void) Void footprint Domain 7: Rehabilitation areas Footprint of existing rehabilitation areas. 2.3 Activities over the MOP Term Exploration To date, exploration activity has identified additional satellite reserves to the northc west and southc east of the project site. Development of these areas would maximise resource recovery in the area, with additional exploration activity to further confirm mineable reserves. Any additional mineable reserves may allow for the continued utilisation of infrastructure on the Sunnyside site for extraction of those reserves at identified satellite deposits. Development of these incremental reserves would be subject to an environmental impact assessment and a new MOP. No exploration activities are expected to be undertaken within ML 1624 during the term of the MOP Construction No construction activities are expected to be undertaken during the term of the MOP Mining Operations No mining operations are proposed during the term of the MOP Overburden Emplacement No significant overburden handling or changes to the overburden emplacement, other than which may be required for rehabilitation management during care and maintenance, are proposed in the MOP term Processing Residues No processing is proposed during the term of the MOP Waste Management Waste generated during the period of care and maintenance will be minimal due to the limited on site activities. Any waste generated during the care and maintenance period will be disposed of in the appropriate remaining on site bins / receptacles. Waste collections will be scheduled during care and maintenance on an ascneeds basis Decommissioning and Demolition Activities Decommissioning of some onsite infrastructure may occur during the MOP period.

13 Report Number April 216 Revision Page Temporary Stabilisation No temporary stabilisation is proposed, but may be undertaken during the MOP period Progressive Rehabilitation and Completion Rehabilitation at Sunnyside has been progressed as far as practicable considering the remaining coal and activities necessary for closure of the site. Approximately three quarters of the outcofcpit dump has been reshaped, drainage infrastructure developed, subsoil and topsoil spread and seeding completed. However, as a component of the final landform it is proposed to reduce the height of the outcofcpit overburden dump by approximately 7 m and use the recovered overburden to stabilise the highwall and partially backfill the void above the reinstated groundwater equilibrium level. No rehabilitation activities, other than rehabilitation maintenance as required, are proposed during the term of the MOP. Plan 4 and Plan shows the intended final landform and post mining land use. A closure schedule for decommissioning and final rehabilitation will be developed prior to the completion of mining activities should they restart. Should mining not recommence, a Closure MOP will be developed to address the final rehabilitation of the site from its current status. Final rehabilitation and closure schedules will be developed in consultation with the relevant authorities Material Production Schedule No production is proposed during the term of the MOP.

14 Report Number April 216 Revision Page 8 3 ENVIRONMENTAL ISSUES MANAGEMENT 3.1 Environmental Risk Assessment Environmental risks associated with the Sunnyside project were assessed during development of the initial Sunnyside Open Cut MOP (28). The risk assessment was undertaken in accordance with the WHC Qualitative Likelihood Rating and Risk Rating Matrix which is consistent with the requirements of Joint Australian and New Zealand Standard AS / NZS 31:29 Risk Management Principles and Guidelines. The risk assessment was revised during the development of this MOP. The focus of the risk assessment revision was to identify key risks associated with care and maintenance, closure and rehabilitation and analyse risks using a qualitative approach that identifying: Issue aspects, associated risks, and the unmitigated risk rating; The anticipated consequences and likelihood; Existing and proposed additional controls; and The residual risk rating after implementation of nominated controls. The key environmental risks and risks to rehabilitation identified for the MOP are reproduced in Appendix B and were all assessed to be of a Low risk ranking. 3.2 Environmental Risk Management All operations (including care and maintenance) at Sunnyside are undertaken in accordance with environmental management plans, including: Environmental Management Strategy (28); Environmental Monitoring Program (211); Aboriginal Cultural Heritage Management Plan (28); and Site Water Management Plan (28); These plans are available on the Whitehaven website.

15 Report Number April 216 Revision Page Air Quality During the care and maintenance phase, deposited dust and PM 1 may be monitored, however, monitoring is not required by the PA 6_38 MOD 1 until prior to ROM coal production recommencing. Controls to minimise the impact and risk of air pollution during care and maintenance are: Maintenance of groundcover on rehabilitation areas; and Restriction of vehicular access to minimise exposed surfaces from traffic Surface and Ground Water Surface Water The mine site is located within an essentially dry, ephemeral first order stream catchment which drains to the north and northwest into the essentially dry, ephemeral Coocooboonah Creek. It is located within a low rainfall, high evaporation climatic regime. Ultimately, water from the site flows to the Namoi River approximately 2 km to the north. The surface water management system at Sunnyside includes: Diversion banks to divert clean water flows away from disturbed areas to clean water storage dams; Storage dams that harvest clean water and clarified dirty water discharged from sediment dams. Storage Dams SDC3 and SDC4 are licenced discharge points (LDPs) for water discharges from site; Catch drains to collect and direct potentially sedimentcladen water generated from the existing mining operations to sediment basins; Sediment basins to detain potentially sedimentcladen water and the controlled release of clarified water; Contour banks and rock lining of waterways on, or to direct water from, the postcmining landform to the natural surface; and Agricultural contour banks and farm dams. Discharges from Sunnyside report to Coocooboonah Creek. To minimise potential for dirty water discharges entering receiving waters, sediment dams are regularly inspected and maintained as required to retain the design capacity. Water quality monitoring is undertaken at each LDP during each overflow event (i.e. while discharging) and upstream and downstream of Sunnyside in Coocooboonah Creek to verify compliance with EPL water quality discharge limits. Sediment basins will continue to be maintained until the rehabilitated catchment has met rehabilitation completion criteria and water quality monitoring at the LDP satisfies the NSW EPA s requirements to remove the LDP for the catchment from the EPL. Once discharge from a given catchment is considered clean water, sediment dams will be dewatered, desilted, and (where required) embankments will be graded and seeded to convert the basins to clean water storage dams for post mining use. Groundwater The final landform will incorporate partial backfilling of the void and shaping of the floor. Backfilling will be higher than the RL of the extracted coal seam which is expected to limit groundwater seepage into the void.

16 Report Number April 216 Revision Page 1 Water monitoring in the void has been undertaken since 21. Electrical Conductivity (EC) has ranged between approximately 1,8 Os/cm to 7,2 Os/cm. There has been a general increase in EC during the period since ceasing mining operations. This increase is as expected with less volume of water held due to decreased surface water runoff and evaporation caused by increasingly drier conditions experienced during the care and maintenance phase. The ph of the void water has remained in the low to mid 8 ph unit range since monitoring began Erosion and Sedimentation Final landform drainage structures including contour banks, drains and rock lines structures have been, or will be, designed and constructed on rehabilitated landforms to manage runcoff from rehabilitation areas at subcerosive velocities. As outlined in Section 3.2.2, all runoff from rehabilitation areas is to be directed to sediment basins and storage dams prior to discharge from site. Water quality monitoring data (TSS) indicates that the water management system is effective in minimising erosion with all historical discharges (four) being in accordance with EPL1297 discharge water quality criteria. Erosion is assessed as a component of rehabilitation monitoring and inspection program and any significant erosion features are remediated as required. Since rehabilitation commenced in 21 there have been isolated instances of minor erosion which are remediated with conservation earthworks and recseeding as required Contaminated Land If decommissioning activities occur during the MOP period, contaminated land assessment and any required management will be undertaken. Once the site is to be permanently closed, the ROM coal handling and stockpiling facilities, workshops, fuel storage and chemical storage facilities will be assessed for potential contamination and remediated accordingly Flora and Fauna Sunnyside is located in an area which had previously (to operational commencement) been extensively cleared for agriculture and subsequently no major areas of native vegetation have, or will be, cleared within the footprint of the operation. Notwithstanding this, Whitehaven has incorporated flora and fauna management aspects into the Project. During the care and maintenance phase of these include: Ongoing implementation of the Koala Management Plan; Maintenance of fencing as necessary to exclude livestock from Koala habitat areas; Utilisation and maintenance of local tree species in revegetation maintenance with an emphasis on Koala feed trees; Control noxious weeds; Maintenance and improvement of habitat corridors on and adjacent to the Mine Site and protection of areas of native vegetation from agricultural activities on Whitehaven land external to the Mine Lease; and Maintenance of Koala habitat corridors to promote the linkage of remnant vegetation in the local area.

17 Report Number April 216 Revision Page Weeds and Pests Weed Management Under the NSW Noxious Weeds Act 1993, Whitehaven has a statutory responsibility to prevent the spread of noxious weeds on all Whitehaven lands at and surrounding Sunnyside. Weed species presence and abundance is assessed in the rehabilitation monitoring program on both rehabilitation areas and analogue sites. Pre mining assessments identified 34 weed species in the area of Sunnyside, including four declared noxious weeds, being: Prickly Pear C Opuntia stricta var. stricta; Johnson Grass C Sorghum halepense; Patterson s Curse C Echium plantagineum; and Galvanised Burr C Sclerolaena birchii. These declared species will be targeted for identification and treatment. Several environmental weeds of note are also present, including Paddy s Lucerne (Sida rhombifolia) and Horehound (Marrubium vulgare). These species have the potential to impact on areas of remnant vegetation and revegetation and will also be a key focus for control. Weed management practices to be adopted during the MOP term include: Ongoing visual assessments and weed monitoring as part of the rehabilitation monitoring program; Application of herbicides where required to control weed infestations; Recording and controlling any occurrences of Class 4 noxious weeds; Restriction of grazing and vehicular traffic to minimise spread of weeds; and Liaison with the North West Local Land Services (LLS) and adjacent landowners. Pest Animal Control Feral animals have not been a significant issue over the life of the mine and are not considered to present a significant risk to rehabilitation. Controls in place to minimise the impact and potential for feral animal infestation include: Ongoing visual observations of feral animal activity including inspections for all the nominated vertebrate pests will be conducted in conjunction with the biodiversity and postcmining rehabilitation monitoring program; and Liaison with adjoining landholders and the North West LLS, and participation with North West LLS vertebrate pest control programs. Pest control actions may include 18 poison baiting for the declared Rabbits and Wild Dogs as well as other nuisance species such as European Red Foxes and Feral Pigs Soil Resources and Management Soil Resources Soil resources at Sunnyside were assessed in the Soils and Land Capability Assessment by GCNRC in 28. GCNRC (28) identified and classified soils to be stripped ahead of disturbance for the Sunnyside operations.

18 Report Number April 216 Revision Page 12 Soil resources identified to be salvaged for rehabilitation were predominantly representative of three discrete soil mapping units (SMUs), being: SMU 1 C Soils of the Upper Slopes C to 14 cm deep over weathered rock; upper slope location; surface condition loose to firm; moderate to large amounts of surface stone present, rounded / angular to 1 cm; SMU 2 C Soils of the MidC and Lower Slopes C to 26 cm+ deep; midc and lower slope location; surface condition loose, firm or hardsetting; surface stone absent or some surface stone present, rounded or angular, 1C1 cm (usually 1 cm); and SMU 3 C Soils of the Drainage Depression Deep C to 26 cm+ deep; surface condition self mulching and cracking; surface stone absent. All available topsoil and subsoil has been recovered ahead of disturbance. Table 3 presents an inventory of the available topsoil and subsoil volumes for rehabilitation and closure of the mine. Table 3: Inventory of Soil Volumes (stockpiled and spread to date) At start of MOP Quantities At the end of the MOP Soil Stripped (m 3 ) 177, ,282 Soil used / spread (m 3 ),312,312 Stockpiled soil remaining (m 3 ) 121,97 121, Noise During the care and maintenance phase noise impacts are expected to be minimal and limited to care and maintenance activities undertaken at site (ie. inspections, limited equipment maintenance). No specific noise controls are proposed during the care and maintenance phase and implementation of a Noise Management Plan isn t required by PA 6_38 MOD1 until prior to ROM coal production recommencing Visual and Lighting The established northern bund wall screening the coal processing area remains in place and established rehabilitation of the site is progressing well, which assists with reducing visual impacts. Use of lighting is unlikely whilst the site is in care and maintenance Aboriginal and Cultural Heritage An Aboriginal Heritage Assessment was undertaken for the by Archaeological Surveys & Reports Pty Ltd (27). Four Aboriginal heritage sites were recorded during the field survey, including an axecgrinding groove, an artefact scatter and two isolated artefacts. All of these sites were assessed as being of low significance (Archaeological Surveys & Reports Pty Ltd, 27). All four of the Aboriginal heritage sites are located outside of the approved disturbance areas (three outside of the ML area) and accordingly there would be no direct impacts on these sites. The Aboriginal Cultural Heritage Management Plan remains in place while the site is in care and maintenance European Heritage There are no known features with European heritage value located within or immediately surrounding Sunnyside.

19 Report Number April 216 Revision Page Spontaneous Combustion The Hoskissons Coal Seam has potential for spontaneous combustion. Management of spontaneous combustion during the care and maintenance phase consists of as required earthworks to spread and/or smother hot spots as well as bulk earthworks for final capping of heated material Bushfire Fire prevention will continue to be undertaken in accordance with the Bushfire Management Plan which has been developed in consultation with the Rural Fire Service (RFS) local bushfire controller and the Gunnedah Shire Council Mine Subsidence The is located to the north of the now closed Gunnedah No. Coal Mine subsidence district. Subsequently, no specific management controls or monitoring programs are necessary. For the open pit area a barrier pillar of 4 m has been maintained as an offset from the old underground workings.

20 Report Number April 216 Revision Page 14 4 POST MINING LAND USE 4.1 Regulatory Requirements The regulatory and approval requirements relating to post mining land use and rehabilitation are summarised in Table 4. Table 4: Regulatory and Approval Requirements Relating to Post Mining Land Use and Rehabilitation Condition Requirement Status ML The proponent shall implement all practicable measures to prevent and / or minimise any harm to the environment that may result from the construction, operation or rehabilitation of the development. 7 Disturbed land must be rehabilitated to a sustainable/agreed end land use to the satisfaction of the DirectorCGeneral. 3 Mining Operations Plan (MOP) (a) Mining operations must not be carried out otherwise than in accordance with: a Mining Operations Plan (MOP) which has been approved by the DirectorCGeneral of the Department of Primary Industries. (b) The MOP must: i) identify areas that will be disturbed by mining operations; ii) detail the staging of specific mining operations; iii) identify how the mine will be managed to allow mine closure; iv) identify how mining operations will be carried out on site in order to prevent and or minimise harm to the environment; v) reflect the conditions of approval under: C the Environmental Planning and Assessment Act 1979 C the Protection of the Environment Operations Act 1997 C and any other approvals relevant to the development including the conditions of this lease; and vi) have regard to any relevant guidelines adopted by the DirectorCGeneral. (c) The titleholder may apply to the DirectorCGeneral to amend an approved MOP at any time. (d) It is not a breach of this condition if: i) the operations constituting the breach were necessary to comply with a lawful order or direction given under the Mining Act 1992, the Environmental Planning and Assessment Act 1979, Protection of the Environment Operations Act 1997 or the Occupational Health and Safety Act 2; and ii) the DirectorCGeneral had been notified in writing of the terms of the order or direction prior to the operations constituting the breach being carried out. (e) A MOP ceases to have affect 7 years after date of approval or other such period as identified by the DirectorCGeneral. An approved amendment to the MOP under condition does not constitute an approval for the purpose of this paragraph unless otherwise identified by the Director General. In progress. In progress. This MOP.

21 Report Number April 216 Revision Page 1 Condition Requirement Status 18 Operations must be carried out in a manner that does not cause or aggravate air pollution, water pollution (including sedimentation) or soil contamination or erosion, unless otherwise authorised by a relevant approval, and in accordance with an accepted Mining Operations Plan. For the purpose of this condition, water shall be taken to include any watercourse. waterbody or groundwaters. The lease holder must observe and perform any instructions given by the DirectorCGeneral in this regard. 22 Access tracks must be kept to a minimum and be positioned so that they do not cause any unnecessary damage to the land. Temporary access tracks must be ripped, topsoiled and revegetated as soon as possible after they are no longer required for mining operations. The design and construction of access tracks must be in accordance with specifications fixed by the Department of Environment and Climate Change. 31 The lease holder must make every reasonable attempt, and be able to demonstrate their attempts, to enter into a cooperation agreement with the holder(s) of any overlapping petroleum title(s). The cooperation agreement should address but not be limited to issues such as: access arrangements; operational interaction procedures; dispute resolution; information exchange; well location; timing of drilling; potential resource extraction conflicts; and EPL1297 rehabilitation issues. E1.1 The licensee must notify the EPA's Manager, Armidale Region in writing 1 month prior to mining or handling any coal on the premises. PA 6_38 Schedule 2 1 Schedule 2 Schedule 2 13 Schedule 3 28 Schedule 3 29 The Proponent shall implement all practicable measures to prevent and / or minimise any harm to the environment that may result from the construction, operation, or rehabilitation of the project. Mining operations may take place on the site until November 22. Note: Under this Approval, the Proponent is required to rehabilitate the site to the satisfaction of the Secretary and DRE. Consequently this approval will continue to apply in all other respects other than the right to conduct mining operations until the site has been rehabilitated to a satisfactory standard. The Proponent shall ensure that all demolition work is carried out in accordance with Australian Standard AS 261=21: The Demolition of Structures, or its latest version. The Proponent shall implement the Koala habitat management and enhancement actions described in the EA (shown conceptually in Figure 6 in Appendix 4) in consultation with the OEH and to the satisfaction of the Secretary. The Proponent shall rehabilitate the site to the satisfaction of the Secretary and DPI Water. In Progress This MOP. In Progress. N/A Pending recommencement of coal mining activities. See ML 1624 Condition 2. In progress. Also see ML 1624 Condition 7. To commence at decommissioning. In progress. In progress. Also see ML 1624 Condition 7.

22 Report Number April 216 Revision Page 16 Condition Requirement Status Schedule 3 3 Schedule 3 31 Schedule 3 4 The Proponent shall prepare and implement a detailed Rehabilitation and Landscape Management Plan for the site to the satisfaction of the Secretary and DRE. This plan must: (a) be prepared in consultation with OEH, DPI Water and Council by suitably qualified expert(s) whose appointment(s) have been approved by the Secretary; and (b) be submitted to the Secretary and DRE for approval by 1 March 29; (c) include: the rehabilitation objectives for the site; description of how the rehabilitation of the site would be integrated with the landscape of the surrounding area; detailed performance and completion criteria for the rehabilitation of the site; a detailed description of the measures that would be implemented to achieve the performance and completion criteria for each site, including the procedures to be implemented for: C protection and enhancement of koala habitat; C progressively rehabilitating the areas disturbed by mining operations; C restoration of agricultural land suitability; C revegetating the site; C protecting and / or enhancing areas in the vicinity of the disturbance area; C conserving and recusing any topsoil; C controlling weeds and feral pests; C controlling access; and C bushfire management. a program to monitor the performance of the rehabilitation against the stated objectives, performance and completion criteria; a description of the potential risks to successful rehabilitation, and a description of the contingency measures that would be implemented to minimise these risks; and details of who is responsible for monitoring, reviewing and implementing the plan. At least two years prior to the cessation of mining operations on the site the Proponent shall prepare a Mine Closure Plan. This plan must: (a) define the objectives and criteria for mine closure; (b) investigate options for the future use of the site; (c) provide a detailed methodology for decommissioning the site s storage dams; (d) investigate ways to minimise the adverse socioceconomic effects associated with mine closure, including reduction in local and regional employment levels; (e) describe the measures that would be implemented to minimise or manage the oncgoing environmental effects of the project; and (f) describe how the performance of these measures would be monitored over time. The Proponent shall minimise the visual impacts of the project to the satisfaction of the Secretary. Complete. Pending Modification Application and final mining cessation. An existing Closure Plan is in place (GSSE 21) as part of the Rehabilitation and Landscape Management Plan developed in accordance with Schedule 3, 3. In progress.

23 Report Number April 216 Revision Page Post Mining Land Use Goals The overall closure goal for Sunnyside is to establish a stable and safe landform that is sympathetic with the surrounding topography and which maximises the return to an appropriate agricultural land use comparable to the prec mining level, but considerate of the fact that the land form is a backfilled mining area. The rehabilitation strategy also includes the enhancement of habitat value and ecosystem connectivity Biodiversity Enhancement The post mining landform will include approximately 3. ha of land rehabilitated with woodland species to enhance biodiversity values of the area. The rehabilitation of disturbed areas with woodland species targets the enhancement of Koala habitat and movement corridors and includes the batters of the regraded outcofcpit waste emplacement. The elevated areas (undisturbed by mining activities) on the southern end of the property will remain as Koala habitat. Additionally, approximately 18 hectares of additional tree planting on areas undisturbed by mining activities along the eastern, northern and western boundaries of the property will enhance wildlife corridors. The development of Sunnyside mine site has not involved the clearing of native vegetation and as such no biodiversity offsets were required. Native vegetation rehabilitation areas and enrichment zones are shown on Plan Pasture The post mining landform will include approximately 44 ha of land rehabilitated with a mix of native and exotic pasture species. Pasture rehabilitation areas will be created with a mix of land capability classes that is generally in accordance with the precmining environment to restore the potential for some productive grazing areas with characteristics similar to pasture areas in the general locality, Plan Final Void In accordance with the Project Approval, one final void will remain in the south of the mining area adjacent to limits of the open cut extraction area. The final void area will be constructed to function as a minor clean water storage for local catchments following rainfall and is expected to remain dry during drier periods with no groundwater seepage expected above the final floor level. The highwall has been developed in competent rock and will have a slope in the order of 41 degrees between the backfill floor (minimum RL 33 m) and the crest (approximate RL of 372 m) (Plan ). The backfilling of the void to a minimum of 33 m at the highwall is intended to buttress the highwall and enhance long term stability. The slope of the ramp batters and lowwalls will be constructed to a slope in the order of 1 to 18 degrees Retained Infrastructure Following closure it is intended to retain only the Turkeys Nest Dam in the southeast, clean water dams, some tracks and the bore into the underground workings. Plan 4 is conceptual only, with additional detail to be developed in the Closure MOP. 4.3 Rehabilitation Objectives Key rehabilitation objectives to achieve the desired post mining land use goals include:

24 Report Number April 216 Revision Page Short@term rehabilitation objectives: a) To minimise clearing / vegetation disturbance consistent with operational requirements; b) To schedule operations including overburden / interburden emplacement and shaping and revegetation to minimise visual exposure; c) To rehabilitate areas of disturbance no longer required for mining related operations; d) To apply soil (topsoil / subsoil) to the final landform based on material availability and postc mining land use; e) To stabilise all earthworks, drainage lines and disturbed areas in order to minimise erosion and sedimentation; and f) To control vermin, feral animals and noxious weeds Long@term rehabilitation objectives: a) Continuation and / or restoration of biodiversity and ecological integrity of areas affected by mining or agriculture within the mining lease; b) To establish a low maintenance, geoctechnically stable landform commensurate with agricultural and nature conservation land uses; c) To blend the created landforms to appear as a natural extension with the surrounding landforms; d) To provide habitat for fauna and corridors for fauna movement within the final landform; e) To enhance Koala habitat in accordance with the Koala Management Plan; and f) To monitor rehabilitation success in terms of physical and biological parameters.

25 Report Number April 216 Revision Page 19 REHABILITATION PLANNING.1 Domain Selection The primary domains discussed in Section 2.2 and Section 2.3 and depicted on Plan 2 have been defined in accordance with the requirements of ESG3 and represent the set of discrete areas that have a particular operational or functional purpose. All areas previously disturbed by mining, or proposed to be subject to the activities described in the sections below, have been assigned to an appropriate primary domain. The relevant primary domains at Sunnyside are defined in Table. The footprint of each primary domain at the commencement of the MOP term is depicted on Plan 2. Table : Primary Domains Primary Domains Code Description Infrastructure 1 Footprint of areas disturbed for existing and decommissioned infrastructure including; amenity facilities, sealed and unsealed roads and carparks, workshop and wash down bay Maintenance Facility and associated laydown area, gravel production area and explosives magazine. Water management area 3 The network of clean water and dirty water dams and associated infrastructure used for operational and rehabilitation water management. Overburden emplacement area 4 Footprint of outcofcpit overburden waste and incpit overburden waste dumps. Stockpiled material Material stockpiled for future management, (e.g. soil resources). Void (Open cut void) 6 Footprint of the open cut pit area that is below natural (precmining) ground level. Rehabilitation area 7 Footprint of existing rehabilitation areas. Secondary domains are land management units with similar post mining land use objectives, such as pasture and native vegetation rehabilitation areas. Secondary domains reflect the proposed post mining land use described throughout Section 4 and have been selected in accordance with all relevant regulatory requirements for rehabilitation. Secondary domains are depicted on Plans 2 to 4, and are described in Table 6.

26 Report Number April 216 Revision Page 2 Table 6: Secondary Domains Secondary Domains Code Description Infrastructure A Infrastructure proposed to be retained following relinquishment including some access tracks and the bore into the underground workings. Water management areas B The network of dams and water management structures retained in the final landform. Dams will provide water resources for grazing areas and native fauna. These include the Turkeys Nest Dam in the southeast and other clean water dams. Rehabilitation areas C Pasture D Footprint of areas rehabilitated with native pasture species and a rural land capability of (at least) Class VI, sufficient to sustain a grazing land use. Approximately 44 hectares is targeted for establishment. Rehabilitation areas C Woodland E The footprint of areas rehabilitated with native vegetation species analogous to adjacent remnant vegetation communities in the areas surrounding Sunnyside. Native vegetation areas will have characteristics similar to existing analogue sites to provide suitable habitat and movement corridors for native fauna. Approximately 3. hectares is targeted for establishment. Final Void I The footprint of the open cut extraction area not backfilled to the prec mining RL. The final void will be designed and constructed to capture limited localised run off from areas surrounding the void and due to evaporation levels is expected to otherwise generally remain dry. Lowwall slopes will generally be less than 18 degrees and the final buttressed highwall will be in the order of 41 degrees. Conservation and Biodiversity Offset area J Enrichment zones / New Vegetation C The footprint of areas undisturbed by mining activities (including remnant vegetation and pasture areas), preserved and enhanced with supplementary plantings to enhance biodiversity values such as movement corridors. Approximately 17.7 hectares are targeted for enhancement or new vegetation planting.

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Mine Rehab Conference 2014 Best Practice Ecological Rehabilitation

More information

This Chapter was compiled by GCS (2014) as part of the EMP Consolidation for MP 30/5/1/2/2/133MR and remains pertinent.

This Chapter was compiled by GCS (2014) as part of the EMP Consolidation for MP 30/5/1/2/2/133MR and remains pertinent. 11 ENVIRONMENTAL REHABILITATION PLAN The overall land use vision for the MR133 area is to ensure that the operations are safe, stable and non-polluting over the long-term in order to be integrated into

More information

MAC-ENC-MTP-041 ENVIRONMENTAL MANAGEMENT STRATEGY

MAC-ENC-MTP-041 ENVIRONMENTAL MANAGEMENT STRATEGY ENVIRONMENTAL MANAGEMENT STRATEGY Document Owner Mike Gale, Environmental Superintendent Document Approver Rob Hayes, Environment Manager Revision History Version No Date Published Details 1.1 30 June

More information

MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15

MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15 MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15 Page 2 of 165 Table of Contents 1 Introduction... 6 1.1 Approvals, Leases and Licences... 9 1.2 Mine Contacts... 12 1.3 Actions Required at Previous

More information

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY TABLE OF CONTENTS 1. INTRODUCTION... 3 2. DESCRIPTION OF ACTIVITY... 4 3. DESCRIPTION OF THE ENVIRONMENT... 4 4. DESCRIPTION OF THE ACTIVITY IN RELATION TO THE ENVIRONMENT...

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

Ontario Mining Act Fact Sheet Mine Closure Plans Your Right to Know!

Ontario Mining Act Fact Sheet Mine Closure Plans Your Right to Know! Ontario Mining Act Fact Sheet Mine Closure Plans Your Right to Know! Part VII Rehabilitation of Mining Lands In Ontario, a mining company cannot (re)commence mining operations until a certified Closure

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia Minerals Regulatory Guidelines MG5 Guidelines for miners: tailings and tailings storage facilities in South Australia Mineral Resources Group Division of Minerals and Energy Resources Primary Industries

More information

Rural dwellings including bed and breakfast accommodation

Rural dwellings including bed and breakfast accommodation MORNINGTON PENINSULA SHIRE COUNCIL - INTERIM POLICY - JUNE 2011 Rural dwellings including bed and breakfast accommodation This policy applies to the use and development of land for a dwelling, including

More information

1. Purpose and scope. 2. SEPA's role in hydropower and planning

1. Purpose and scope. 2. SEPA's role in hydropower and planning Page no: 1 of 10 1. Purpose and scope 1.1 The purpose of this note is to provide guidance on the approach that we will take when dealing with hydropower development management consultations. We welcome

More information

Exploration rehabilitation and relinquishment report

Exploration rehabilitation and relinquishment report Form EDG13 Exploration rehabilitation and relinquishment report Mining Act 1992 and Petroleum (Onshore) Act 1991 April 2016 v2.1 More information For help with lodging this application, or for more information,

More information

Dysart Road and Associated Services Infrastructure Project Compliance Report Environment Protection and Biodiversity Conservation Act 1999

Dysart Road and Associated Services Infrastructure Project Compliance Report Environment Protection and Biodiversity Conservation Act 1999 Dysart Road and Associated Services Infrastructure Project Compliance Report Environment Protection and Biodiversity Conservation Act 1999 March 2015 About this report In accordance with condition 6 of

More information

Development proposals will require to demonstrate, according to scale, type and location, that they:-

Development proposals will require to demonstrate, according to scale, type and location, that they:- Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on

More information

HUNTER WATER CORPORATION Review of Environmental Factors Guidance Notes EG0041

HUNTER WATER CORPORATION Review of Environmental Factors Guidance Notes EG0041 HUNTER WATER CORPORATION Review of Environmental Factors Guidance Notes EG0041 January 2014 Document control Document controller: Manager Environment & Sustainability Document number: EG0041 Rev Date Description

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

2.1 Environmental Responsibility & Land Capability

2.1 Environmental Responsibility & Land Capability 2.1 Environmental Responsibility & Land Capability Introduction The Land use permissibility of a development in a particular under the zone, as indicated by the Lake Macquarie LEP 2004 does not mean indication

More information

LAND ACCESS ARRANGEMENT FOR MINERAL EXPLORATION Template published in accordance with Section 141(1A) of the Mining Act 1992

LAND ACCESS ARRANGEMENT FOR MINERAL EXPLORATION Template published in accordance with Section 141(1A) of the Mining Act 1992 LAND ACCESS ARRANGEMENT FOR MINERAL EXPLORATION Template published in accordance with Section 141(1A) of the Mining Act 1992 This arrangement ( Agreement ), which is an access arrangement for the purposes

More information

Recommendations for future developments

Recommendations for future developments C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

Tiger Brennan Drive Extension Stage 2. Project Environmental Management Plan

Tiger Brennan Drive Extension Stage 2. Project Environmental Management Plan Tiger Brennan Drive Extension Stage 2 Project Environmental Management Plan Volume 2 of 2 Macmahon Ref No: N016 Controlled Copy # Copyright 2009. All rights reserved. No unauthorised reproduction or use

More information

Department of Natural Resources and Mines. Offset Area Management Plan Template December 2012. Offset Area Management Plan - Inderi

Department of Natural Resources and Mines. Offset Area Management Plan Template December 2012. Offset Area Management Plan - Inderi Department of Natural Resources and Mines Offset Area Management Plan Template December 2012 Offset Area Management Plan - Inderi State of Queensland, Department of Natural Resources and Mines, 2012. The

More information

UPDATE ON MANAGEMENT OF LEGACY ENVIRONMENTAL ISSUES IN GHANA

UPDATE ON MANAGEMENT OF LEGACY ENVIRONMENTAL ISSUES IN GHANA UPDATE ON MANAGEMENT OF LEGACY ENVIRONMENTAL ISSUES IN GHANA UPDATE ON MANAGEMENT OF LEGACY ENVIRONMENTAL ISSUES IN GHANA AUGUST 2015 AngloGold Ashanti acknowledges that there are some legacy environmental

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

Works Approval Conditions 1 General

Works Approval Conditions 1 General Works Approval Conditions 1 General 1.1 Interpretation 1.1.1 In the Works Approval, definitions from the Environmental Protection Act 1986 apply unless the contrary intention appears. 1.1.2 In the Works

More information

CORPORATE POLICY STATEMENT NO. 12 MANAGEMENT OF PEST ANIMALS

CORPORATE POLICY STATEMENT NO. 12 MANAGEMENT OF PEST ANIMALS 1. OBJECTIVE CORPORATE POLICY STATEMENT NO. 12 MANAGEMENT OF PEST ANIMALS August 2015 To provide direction and guidance for the management of pest animals on lands and waters managed by the Department

More information

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project

More information

Appendix A1. Register of legal and other requirements

Appendix A1. Register of legal and other requirements Appendix A1 Register of legal and other requirements 1 Table 1 Legal register Act Activity / General Environmental Planning and Assessment Act 1979 All Comply with the terms Minister for Planning and Infrastructure

More information

Appendix C. Municipal Planning and Site Restoration Considerations

Appendix C. Municipal Planning and Site Restoration Considerations Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning

More information

Daryl Henehan, Consent Planner Natural Resources. JOHN AND RIA WILMS - REPORT REP10-05-05- Report prepared for hearing of 3 May 2010

Daryl Henehan, Consent Planner Natural Resources. JOHN AND RIA WILMS - REPORT REP10-05-05- Report prepared for hearing of 3 May 2010 STAFF REPORT TO: FROM: REFERENCES: SUBJECT: Environment & Planning Subcommittee Daryl Henehan, Consent Planner Natural Resources RM090804 - Land Use Earthworks JOHN AND RIA WILMS - REPORT REP10-05-05-

More information

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein

More information

February 4, 2011. hoffman.stephen@epa.gov. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth

February 4, 2011. hoffman.stephen@epa.gov. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth February 4, 2011 VIA E-MAIL AND CERTIFIED MAIL #7010 0290 0002 0577 6226 Mr. Stephen Hoffman US Environmental Protection Agency (5304P) 1200 Pennsylvania Avenue, NW Washington, DC 20460 hoffman.stephen@epa.gov

More information

CONSERVING OUR RURAL ENVIRONMENT

CONSERVING OUR RURAL ENVIRONMENT HUME CITY COUNCIL CONSERVING OUR RURAL ENVIRONMENT Grant Guidelines 2015 2016 hume.vic.gov.au CONTENTS 1. GRANT OVERVIEW 1 1.1 Program introduction 1 1.2 Who can apply? 1 1.3 Grant types 1 2. GRANT SELECTION

More information

Environmental compliance and performance report. Management of dust from coal mines

Environmental compliance and performance report. Management of dust from coal mines Environmental compliance and performance report Management of dust from coal mines Environmental compliance and performance report Management of dust from coal mines The Environmental compliance and performance

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes

More information

ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS

ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County,

More information

Note on Draft Progress Report Template

Note on Draft Progress Report Template Note on Draft Progress Report Template The Draft Progress Report template is provided as a guide to applicants on possible reporting requirements for the Biodiversity Fund. This actual report will be provided

More information

MANAGEMENT STANDARD CLOSURE PLANNING

MANAGEMENT STANDARD CLOSURE PLANNING AngloGold Ashanti Limited \ Reg. No.1944/017354/06 76 Jeppe Street \ Newtown \ 2001 \ PO Box 62117 \ Marshalltown \ 2107 \ South Africa Tel +27 (0)11 637 6000 \ Fax +27 (0)11 637 6624 \ Website: www.anglogoldashanti.com

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

HYDROCARBON SPILLS PROCEDURE SIG-ENV-PR003

HYDROCARBON SPILLS PROCEDURE SIG-ENV-PR003 Page: 1 of 6 PROCEDURE SIG-ENV-PR003 Revision Approved Date Description 1 AV 01/04/99 New EP 2 AV 07/06/00 Revision of EP 3 AV 04/04/03 Revision of EP 4 Stuart Roseby DRAFT 5 Stuart Roseby 25/07/2005 Approved

More information

EDG17 GUIDELINE FOR APPLICATIONS FOR SUBSIDENCE MANAGEMENT APPROVALS. December 2003

EDG17 GUIDELINE FOR APPLICATIONS FOR SUBSIDENCE MANAGEMENT APPROVALS. December 2003 GUIDELINE FOR APPLICATIONS FOR SUBSIDENCE MANAGEMENT APPROVALS December 2003 From 1 July 2014, the Division of Resources & Energy's former Subsidence Management Plan process was replaced by a consolidated

More information

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk 1 Introduction 1.1 Key objective The aim of this study is to identify and assess possible options for improving the quality of the river channel and habitats in the River South Esk catchment whilst helping

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

edms 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions

edms 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions In Australia, an Intergovernmental Agreement for a National Water Initiative (NWI) was signed by the Australian Government, all state and

More information

Section 25.2 provides an overview of the area of influence and reviews legal and other requirements relevant to closure (1).

Section 25.2 provides an overview of the area of influence and reviews legal and other requirements relevant to closure (1). 25 Mine Closure 25.1 Introduction This chapter of the Simandou Mine SEIA addresses the closure of the Simandou Mine, including the cessation of operations, decommissioning of plant and equipment, rehabilitation

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

approval of matters specified in conditions; and The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013

approval of matters specified in conditions; and The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 Application for: planning permission; planning permission in principle; further applications; approval of matters specified in conditions; and mineral workings (if the planning authority do not have a

More information

Pollution Incident Response Management

Pollution Incident Response Management For Notification Procedure, please turn to Section 5 for Pollution Incident Response Management Document Table of Contents 1 Introduction... 3 1.1 Background and Scope... 3 1.2 Regulatory Requirements...

More information

Designed and produced by geo-graphicsdesign.com DP 300 3/02

Designed and produced by geo-graphicsdesign.com DP 300 3/02 Designed and produced by geo-graphicsdesign.com DP 300 3/02 Guidance for Developers and Regulators Purpose This booklet is produced on behalf of the North East Scotland Flooding Advisory Group and is intended

More information

Section 75J of the Environmental Planning & Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979 Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 As delegate of the Minister for Planning and Infrastructure under delegation executed on 14 September 2011, the Planning

More information

SUPPLEMENTARY EVIDENCE OF SHONA CLAIRE MYERS ON BEHALF OF THE KAPITI COAST DISTRICT COUNCIL. Terrestrial ecology. DATE: 3 February 2012

SUPPLEMENTARY EVIDENCE OF SHONA CLAIRE MYERS ON BEHALF OF THE KAPITI COAST DISTRICT COUNCIL. Terrestrial ecology. DATE: 3 February 2012 BEFORE A BOARD OF INQUIRY TRANSMISSION GULLY PROPOSAL UNDER the Resource Management Act 1991 IN THE MATTER OF applications for resource consents and notices of requirement in relation to the Transmission

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Section 2 Description of the Existing Mt Arthur Coal Mine

Section 2 Description of the Existing Mt Arthur Coal Mine Section 2 Description of the Existing Mt Arthur Coal Mine TABLE OF CONTENTS 2 DESCRIPTION OF THE EXISTING MT ARTHUR COAL MINE 2-1 2.1 MINING 2-1 2.2 COAL PREPARATION PLANT AND RAIL LOADING FACILITIES 2-3

More information

PLANNING POLICY 3.3.5

PLANNING POLICY 3.3.5 PLANNING POLICY 3.3.5 CHILD CARE PREMISES 1. Introduction A Child Care Premises is used to provide a child care service within the meaning of the Child Care Services Act 2007, but does not include a Family

More information

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:

More information

OSU Extension FACT SHEET

OSU Extension FACT SHEET OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding

More information

Guidelines. for a Native Vegetation Significant Environmental Benefit Policy for the clearance of scattered trees. Approved August 2007

Guidelines. for a Native Vegetation Significant Environmental Benefit Policy for the clearance of scattered trees. Approved August 2007 Guidelines for a Native Vegetation Significant Environmental Benefit Policy for the clearance of scattered trees Approved August 2007 WEB LINKS Native Vegetation in South Australia http://www.environment.sa.gov.au/nativevegetation

More information

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 JBA Prepared by : John Barnett and Associates / SLR Consulting 7 Dundrum Business Park

More information

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.)

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER, 1994 (Made under section 11A(1)) (Incorporating

More information

As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing

As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing N A T U R A L R E S O U R C E C O N S E R V A T I O N As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing conservation

More information

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)

More information

Storm Water Management Requirements for Construction Projects Less than One Acre

Storm Water Management Requirements for Construction Projects Less than One Acre Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to

More information

Environmental Impact Assessment of Forestry Projects

Environmental Impact Assessment of Forestry Projects Environmental Impact Assessment of Forestry Projects Flow chart of EIA process Developer submits grant application FC screens when sufficient info received, normally at "Proposal Submit stage Developer

More information

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta

More information

Exploration for natural gas

Exploration for natural gas FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with

More information

AUGUST 2013. Habitat compensation under the Biodiversity Conservation Strategy

AUGUST 2013. Habitat compensation under the Biodiversity Conservation Strategy AUGUST 2013 Habitat compensation under the Biodiversity Conservation Strategy Published by the Victorian Government Department of Environment and Primary Industries Melbourne, August 2013 The State of

More information

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !"l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=?

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=? ./01&2/M./T34 1MP36T ST3T.M./T 1a$t3l$4 536e-al4 13$7363 83%3te9 Sol9ara 1 Pro;ect!"l$%e ( Mai$ &e(ort Te-t )e*te%,e- 2//0 :; =?@ ENVIRONMENTAL IMPACT STATEMENT VOLUME A: MAIN REPORT TEXT CR 7008_09_v4

More information

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history:

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history: ANNUAL COMPLIANCE ASSESSMENT REPORT Brockman Railway Infrastructure Project (Ministerial Statement 923) 2014 2015 Revision history: Revision Prepared Reviewed Approved Dated Issued Description A G. Firth

More information

The State of Queensland, Department of Agriculture, Fisheries and Forestry, 2012.

The State of Queensland, Department of Agriculture, Fisheries and Forestry, 2012. PR09 4476 The State of Queensland, Department of Agriculture, Fisheries and Forestry, 2012. The Queensland Government supports and encourages the dissemination and exchange of its information. The copyright

More information

A Developer s Guide: Watershed-Wise Development

A Developer s Guide: Watershed-Wise Development A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another

More information

GENERAL SPECIFICATION

GENERAL SPECIFICATION R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

Living & Working Managing Natural Resources and Waste

Living & Working Managing Natural Resources and Waste Living & Working Managing Natural Resources and Waste 5.13 Managing Natural Resources and Waste Background 5.13.1 This chapter focuses on how we manage resources within the AONB. It includes renewable

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012

DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012 DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY August 2012 SECTION 2 The storage requirements in Directive 055 apply to upstream petroleum facilities, well sites, and pipelines

More information

Management of Environmental Risks and Emergencies. Compliance Audit Program

Management of Environmental Risks and Emergencies. Compliance Audit Program Management of Environmental Risks and Emergencies Compliance Audit Program 2012 State of NSW and Environment Protection Authority The State of NSW and the Environment Protection Authority (EPA) are pleased

More information

Attended Noise Monitoring - Quarter Ending December 2013

Attended Noise Monitoring - Quarter Ending December 2013 Big Island Mining Pty Ltd Majors Creek Road Majors Creek Version: Page 2 PREPARED BY: ABN 29 001 584 612 Units 7-8, 26-28 Napier Close Deakin ACT 2600 Australia (PO Box 9344 Deakin ACT 2600 Australia)

More information

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 Division(s): Sutton Courtenay & Harwell Contact Officer: John Duncalfe (john.duncalfe@oxfordshire.gov.uk) Tel: 01865 815356 PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 TO CRUSH, SCREEN, BLEND AND STOCK

More information

Pest Toolkit. Pest proofing your land for a sustainable community. Help is at hand. Main topics: Pest Animal control. pest plant control

Pest Toolkit. Pest proofing your land for a sustainable community. Help is at hand. Main topics: Pest Animal control. pest plant control Pest Toolkit Pg1 Main topics: RPMP Pest proofing your land for a sustainable community Pg2 Pg3 Pg4 Pest Animal control pest plant control weed control in retirement areas Pests are unwanted plants (invasive

More information

www.epa.nsw.gov.au August 2014

www.epa.nsw.gov.au August 2014 Report on the Findings of the NSW Environment Protection Authority s Review of Snowy Hydro Limited Cloud Seeding Program: 2013 Annual Compliance Report August 2014 www.epa.nsw.gov.au State of NSW, Environment

More information

HERITAGE MANAGEMENT PLAN

HERITAGE MANAGEMENT PLAN HERITAGE MANAGEMENT PLAN Edition Rev. Comments Author Authorised By Date 1 0 Initial document R.W. Corkery & Co. Pty Ltd Keith Ross Dec 2005 2 0 2010 Modification review Jill Scealy Danny Young March 2011

More information

BB CONSTRAINTS MAPPING

BB CONSTRAINTS MAPPING BB CONSTRAINTS MAPPING ENTER HERE BACK TO CONTENTS The Bowen Gas Project (the Project) constraints analysis has been developed to support the environmental framework approach as detailed in the Environmental

More information

Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations with Companies Seeking Easements

Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations with Companies Seeking Easements Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations As a property owner, you should make a decision about granting an easement based on the same level of information available

More information

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents AMENDMENTS TO THE REGIONAL PLANS RELATING TO LAND REPAIR ON EARTHQUAKE DAMAGED RESIDENTIAL LAND UNDER s27 OF THE CANTERBURY EARTHQUAKE RECOVERY ACT 2011 1. This memorandum outlines the specific changes

More information

Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited

Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited Report and recommendations of the Environmental Protection Authority Environmental Protection Authority Perth,

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra

More information

WHITEHAVEN COAL LIMITED QUARTERLY REPORT TO 31 DECEMBER 2009 (Q2 FY 2010)

WHITEHAVEN COAL LIMITED QUARTERLY REPORT TO 31 DECEMBER 2009 (Q2 FY 2010) Highlights WHITEHAVEN COAL LIMITED WHITEHAVEN COAL LIMITED ABN 68 124 425 396 Level 9 1 York Street Sydney, NSW 2000 PO Box R1113 Royal Exchange NSW 1225 Ph: 02 8507 9700 Fax: 02 8507 9701 QUARTERLY REPORT

More information

Agricultural & Farm Development - The Planning Issues

Agricultural & Farm Development - The Planning Issues Agricultural & Farm Development - The Planning Issues Generally, smaller developments of an agricultural or forestry nature are exempt, however, larger developments do require planning permission. In addition,

More information

Carlton Fields Memorandum

Carlton Fields Memorandum Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed

More information

AS 4708:2013. Interpretation of Requirements relating to the Recovery of Forest Products from a Water Body

AS 4708:2013. Interpretation of Requirements relating to the Recovery of Forest Products from a Water Body AS 4708:2013 Interpretation of Requirements relating to the Recovery of Forest Products from a Water Body BACKGROUND Australian Forestry Standard Limited has been asked for an interpretation of the Australian

More information

Stormwater harvesting

Stormwater harvesting Stormwater harvesting How to collect and re-use stormwater from Sydney Water s stormwater system Most of the stormwater pipes and channels in the Sydney metropolitan area are the responsibility of local

More information

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW SURFACE REMEDIATION AND MANAGEMENT OVERVIEW Giant Mine Remediation Project Environmental Assessment Public Hearings September 10-14, 2012 Adrian Paradis (AANDC) Mike Nahir (AANDC) Bruce Halbert (Technical

More information

5.2 Condition of our Biodiversity

5.2 Condition of our Biodiversity Biodiversity is the variety of all life forms - the different plants, animals and micro-organisms, the genes they contain and the ecosystems in which they live. Biodiversity underpins the ecological processes

More information