Outage Management System Implementation. Status Report
|
|
|
- Kathryn Stewart
- 9 years ago
- Views:
Transcription
1
2 OVERVIEW Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) is submitting this status report to the Massachusetts Department of Public Utilities ( DPU ) on its progress regarding the implementation of the last item to be completed as part of the December 2008 Ice Storm Self Assessment Report ( Report ), Item #8 OMS Acquisition, Development, and Staffing. This document outlines the overall status for the Outage Management System (OMS) Implementation. The OMS being implemented by Unitil is a 3 rd party product developed by ABB. As part of the ABB implementation, reporting is accomplished using Obvient Solutions. APPROACH Unitil has taken multiple steps to facilitate an accelerated, yet thorough implementation of the OMS. Single Vendor Point of Contact Multiple vendors are used for hardware purchases, software purchases, and reporting. As part of the agreement reached with ABB, all hardware purchases, software purchases, and reporting purchases are facilitated through ABB, with final cost and approval coming from Unitil. Single Vendor Licensing Multiple license agreements are required for the implementation of the OMS (i.e., Oracle, TIBCO, Obvient, etc). As part of the agreement reached with ABB, all software licensing related to the OMS are facilitated by ABB, with final cost and approval coming from Unitil. Two-Pronged testing approach Unitil has partnered with ABB to divide testing into two parts, Factory Acceptance Testing (FAT) - Completed on-site at the ABB Sugarland, TX site, and Site Acceptance Testing (SAT) completed once the system is installed in the Unitil offices. This allows for the best use of resources, time, and facilities, giving Unitil the opportunity to validate hardware/software, system configuration and integration among systems before introducing the OMS to the Unitil network environment. Centralized Project Management Unitil has assigned a Centralized Project Manager for the OMS implementation. ABB has also assigned a single project manager who works closely with Unitil s project manager. This ensures that all communication with the Vendor comes from a single point. This also gives Unitil s Executive Management a single point of contact for updates on project status and schedule. The Centralized Project Manager works with the OMS project steering committee to facilitate approval of project milestones, and any major project changes. HARDWARE/SOFTWARE Hardware The OMS system consists of 11 servers, 7 for the production environment, and 4 for the QA/Test environment, 3 switches, an external storage array, and redundant power for each of the 3 server racks. The system hardware is designed for full redundancy in the event of a component failure. Software 5 of the servers have Windows Server operating systems, and 6 servers have a Linux operating system. This is required to support the various software Unitil Page 2
3 programs. The ABB OMS system is installed, TIBCO middleware is used, and Obvient reporting solutions is installed. Status As previously reported, the Factory Acceptance Test has been completed. All OMS hardware/software was received at Unitil on 12/2/09, with the production hardware residing at one site and QA/Test hardware residing at an alternate site. Unitil decided to separate the location of these two environments for security in the event that one facility is compromised (i.e. fire). An initial delivery inventory and verification of the hardware was completed on 12/11/09. NETWORK UPGRADES As reported previously, Unitil contracted a network consulting firm to evaluate the Unitil network. The goal of this evaluation was to identify modifications that could be made to Unitil s computer network to: 1) improve reliability, 2) improve the customer experience with the IVR system, 3) ensure systems are current and on a regular refresh schedule, 4) ensure systems will support projected network growth, and 5) ensure adequate support is in place for all systems. As it relates to the OMS, this evaluation considered connectivity between the Interactive Voice Response (IVR) hardware and the OMS hardware. Additionally, OMS requirements for latency and bandwidth over the WAN were evaluated. Status The report containing recommended improvements for the network has been received by Executive Management and is being evaluated for costing and scheduling. After an initial review, the improvements required for the OMS implementation are targeted for completion in late January/early February INTEGRATION For the implementation of the OMS, there will be electric network data supplied from the Geographic Information System (GIS) and the Customer Information Systems (CIS). This information will be supplied in the form of an extract file from these source systems on a routine basis. The extract from the GIS will be loaded on a bi-monthly or monthly basis. The extract from the CIS will be loaded on a nightly basis. The OMS will be fully integrated with the IVR allowing two-way communication between these systems. This communication takes place via an Application Program Interface (API). The API being used for this integration is MultiSpeak compliant. (NRECA s MultiSpeak Specification is an industry-wide software standard that facilitates interoperability of diverse business and automation applications used in electric utilities. It has been developed and is maintained by the MultiSpeak Initiative.) Status Unitil has been regularly providing ABB with GIS information for development of the GIS extract process. As part of the FAT, Unitil was able to use, interact and test the electric network extract from GIS. The GIS extract process is complete. Unitil has been regularly providing ABB with CIS information that comes from the Unitil developed CIS extract process. The CIS extract process will be implemented into production at the same time the OMS is implemented. Additionally, as part of the FAT, a connectivity test was successfully completed with the IVR vendor (Milsoft). Communication was established between ABB and Milsoft. Unitil Page 3
4 Outage and restoration information was communicated back and forth between the systems and simulated customer callbacks were successfully initiated. REPORTING Reporting for the OMS is accomplished using the Obvient Solution. This solution provides for internal dashboard reporting of live outage information, user developed reporting via a GUI interface, ORP reporting, and customer facing web reporting via the Storm Central module of Obvient. Additionally, as part of the implementation all historical data will be converted and will be available via Obvient. Status As part of the FAT, Unitil was able to use dashboard reporting, and view live outage reporting. All historical data has been converted and is scheduled to be loaded the first week of January Configuration of the web reporting Storm Central module is currently underway and is targeted for completion by the end of January Unitil employees have received training on historical report development and are currently developing the required historical reports to replace Unitil s existing Trouble Interruption Reporting system. TESTING As outlined above, the testing is divided into two parts: Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT). As previously reported, FAT has been completed. This testing included interactive use of the OMS and a comprehensive test of the OMS functionality using Unitil data. The SAT will include functionality testing, comprehensive IVR testing, and a comprehensive report verification process. As part of the SAT, Unitil plans to conduct a stress test of the system using the IVR call data that was captured during the 2008 Ice Storm. Status Approval of the FAT test results was given on 11/20/09. Planning is underway for the SAT. Test plan, cases, and procedures are being finalized with SAT targeted for the end of February TRAINING Training for the use and administration of the OMS is being provided as part of the agreement with ABB. Training is divided into Overview training, Operator training, Report training, and System Administration. Unitil will ensure that individuals are properly trained whose storm assignment requires them to operate or interact with the OMS system. Status The Overview training was completed on 11/19/09. The Report training, including dashboards, report creation, and report system administration was completed the week of 12/14/09 (3 days of training). The initial operator training is targeted for late January OMS system administration training is targeted for early February IMPLEMENTATION The implementation of OMS is a parallel implementation. This means that all existing processes will be kept in place as a familiarization process takes place. As a comfort Unitil Page 4
5 level with new processes is achieved, old process will be decommissioned, with complete decommissioning of old processes to be completed by the end of The goal with this type of implementation is zero impact to the customer. Status OMS is targeted to go live in March Unitil Page 5
Milsoft Core E&O: An Overview. Stanley E. McHann, Jr. [email protected]. Your Mission Our Vision
he Milsoft Core E&O: An Overview Stanley E. McHann, Jr. [email protected] Your Mission Our Vision 1 Milsoft Core E&O White Paper Introduction to Milsoft A History of Outstanding Software and Support
Agenda Report. April 8, 2013. Honorable Mayor and City Council TO: THROUGH: Finance Committee (April 8, 2013) FROM: Water and Power Department
Agenda Report April 8, 2013 TO: Honorable Mayor and City Council THROUGH: Finance Committee (April 8, 2013) FROM: SUBJECT: Water and Power Department AUTHORIZATION TO ENTER INTO CONTRACTS WITH DESIGNATED
White Paper. Managed IT Services as a Business Solution
White Paper Managed IT Services as a Business Solution 1 TABLE OF CONTENTS 2 Introduction... 2 3 The Need for Expert IT Management... 3 4 Managed Services Explained... 4 5 Managed Services: Key Benefits...
PREMIER SERVICES MAXIMIZE PERFORMANCE AND REDUCE RISK
MAXIMIZE PERFORMANCE AND REDUCE RISK 1 BROCHURE COMPLEXITIES IN MISSION CRITICAL SYSTEMS CONTINUE TO INCREASE Mission critical communications systems have become increasingly complex as more features and
Domain Name Service Service Level Agreement (SLA) Vanderbilt Information Technology Services
Service Level Agreement Page 1 of 7 Domain Name Service Service Level Agreement (SLA) Vanderbilt Information Technology Services 1. Agreement This agreement is to define Domain Name Service (DNS) provided
Migration and Disaster Recovery Underground in the NEC / Iron Mountain National Data Center with the RackWare Management Module
Migration and Disaster Recovery Underground in the NEC / Iron Mountain National Data Center with the RackWare Management Module WHITE PAPER May 2015 Contents Advantages of NEC / Iron Mountain National
MultiSpeak Version 3.0 Interoperability Assertion Outage Analysis (OA) / Interactive Voice Response (IVR) (CH) (OD)
MultiSpeak Version 3.0 Interoperability Assertion Outage Analysis (OA) / Interactive Voice Response (IVR) (CH) (OD) Vendor: Milsoft Utility Solutions DisSPatch Outage Management System and Milsoft s Porche
Integrated Application and Data Protection. NEC ExpressCluster White Paper
Integrated Application and Data Protection NEC ExpressCluster White Paper Introduction Critical business processes and operations depend on real-time access to IT systems that consist of applications and
Cisco Disaster Recovery: Best Practices White Paper
Table of Contents Disaster Recovery: Best Practices White Paper...1 Introduction...1 Performance Indicators for Disaster Recovery...1 High Level Process Flow for Disaster Recovery...2 Management Awareness...2
Operational Continuity
Solution Brief Operational Continuity Achieve Maximum Uptime In a recent speech, Omar Sherin of the Qatar CERT, shared how they shifted their focus from protection and detection to response in the wake
Customer Support Policy
Customer Support Policy This Customer Support Policy ( Policy ) describes the Support that Invenias provides to Customers that have paid all applicable fees and that are using Licensed Software in a Supported
Migration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module
Migration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module June, 2015 WHITE PAPER Contents Advantages of IBM SoftLayer and RackWare Together... 4 Relationship between
Oracle Utilities Customer Care and Billing
Customer Care and Billing Utilities are faced with a rapidly changing industry and increasing expectations from their customers. Adapting to these factors with existing customer information systems likely
Advanced Server Virtualization: Vmware and Microsoft Platforms in the Virtual Data Center
Advanced Server Virtualization: Vmware and Microsoft Platforms in the Virtual Data Center Marshall, David ISBN-13: 9780849339318 Table of Contents BASIC CONCEPTS Introduction to Server Virtualization Overview
Highly Available Unified Communication Services with Microsoft Lync Server 2013 and Radware s Application Delivery Solution
Highly Available Unified Communication Services with Microsoft Lync Server 2013 and Radware s Application Delivery Solution The Challenge Businesses that rely on Microsoft Lync Server must guarantee uninterrupted
JOB DESCRIPTION Network Systems Technician I/II
CITY OF DEL MAR JOB DESCRIPTION Network Systems Technician I/II GENERAL PURPOSE Under supervision, provides liaison and technical assistance to system users for computer and network related problems; consults
DMS - Breakthrough Technology for the Smart Grid
DMS - Breakthrough Technology for the Smart Grid The emerging smart grid is expected to address many of the current challenges in the electrical power industry. It is expected to make the electric grid
Interfacing with Manufacturing Systems in Education and Small Industry Using Microcontrollers through the World Wide Web
Interfacing with Manufacturing Systems in Education and Small Industry Using Microcontrollers through the World Wide Web Samuel Cotton Ph.D. [email protected] Department of Industry and Technology Ball State
Oracle Data Guard OTN Case Study SWEDISH POST
Oracle Data Guard OTN Case Study SWEDISH POST Corporate Profile Annual revenue EUR 2.5 billion 40,000 employees Serving 3 million homes and 800.000 businesses daily url: http://www.posten.se Disaster Recovery
For Utility Operations
For Utility Operations Provided For: SCAMPS 2014 Annual Meeting Presented By: Michael E. Jenkins, PE What Are We Talking About? Simply, Preparing A Clear Picture Of Where And How The Utility Is Headed
Request for Proposal for Application Development and Maintenance Services for XML Store platforms
Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...
StorageX 7.5 Case Study
StorageX 7.5 Case Study This document will cover how StorageX 7.5 helps to transform a legacy Microsoft DFS environment into a modern, domain-based DFS environment The Challenge Microsoft has officially
Milsoft IVR SIP Upgrade (Virtual Server) Presented by George Buckner (Central Florida Electric Cooperative, Inc.)
Milsoft IVR SIP Upgrade (Virtual Server) Presented by George Buckner (Central Florida Electric Cooperative, Inc.) Central Florida Electric Cooperative, Inc. Headquarters: Chiefland, FL Active Services:
Migration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module
Migration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module June, 2015 WHITE PAPER Contents Advantages of IBM SoftLayer and RackWare Together... 4 Relationship between
Open Networking User Group SD-WAN Requirements Demonstration Talari Test Results
Open Networking User Group SD-WAN Requirements Demonstration Talari Test Results May 13, 2015 Talari 550 South Winchester Suite 550 San Jose, CA 95128 www.talari.com Defining the Software Defined WAN The
MultiSpeak Version 4.0 Interoperability Assertion. Milsoft Web Server 8.2 GV GV AVL 1.0 AVL GV AVL
MultiSpeak Version 4.0 Interoperability Assertion Statement of Interoperable Functionality Between: Vendors Products Product Version Role Web Client Interfaces Web Server Interfaces Milsoft Utility Solutions,
INFORMATION SYSTEMS SPECIALIST 4 1484
INFORMATION SYSTEMS SPECIALIST 4 1484 SERIES DESCRIPTION The INFORMATION SYSTEMS SPECIALIST (ISS) classification series has eight levels that describe technical and professional non-supervisory positions
Cloud Infrastructure Operational Excellence & Reliability
Cloud Infrastructure Operational Excellence & Reliability Page 1 Operational Excellence & Reliability Microsoft has invested over $15 billion in building one of the world s largest global cloud infrastructures.
CONDIS. IT Service Management and CMDB
CONDIS IT Service and CMDB 2/17 Table of contents 1. Executive Summary... 3 2. ITIL Overview... 4 2.1 How CONDIS supports ITIL processes... 5 2.1.1 Incident... 5 2.1.2 Problem... 5 2.1.3 Configuration...
SEP Support Definitions and Services
SEP Support Definitions and Services (For customers with valid Support Contracts signed before 01.03.2015 the conditions from this document are applicable.) Introduction SEP AG provides a variety of support
APPENDIX 8 TO SCHEDULE 3.3
EHIBIT Q to Amendment No. 60 - APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT EHIBIT Q to Amendment No.
SPRINT SIP TRUNKING SERVICE PRODUCT ANNEX
SPRINT SIP TRUNKING SERVICE PRODUCT ANNEX The following terms and conditions in this Sprint SIP Trunking Service Product Annex ( Annex ), together with the applicable Sprint service agreement ( Agreement
Oracle RAC Services Appendix
1 Overview Oracle RAC Services Appendix As usage of the Blackboard Academic Suite grows and the system reaches a mission critical level, customers must evaluate the overall effectiveness, stability and
Nortel - 922-104. Communication Server 1000 Rls.6.0 Upgrades for Engineers
1 Nortel - 922-104 Communication Server 1000 Rls.6.0 Upgrades for Engineers Question: 1 A customer is upgrading an existing Communication Server (CS) 1000M with a CPPM Signaling Server at Rls. 5.0 to a
FUNCTIONAL AREA 12. Network Administration (NET)
FUNCTIONAL AREA 12 Network Administration (NET) Incumbents in this functional area address interoperability issues related to hardware, software, and connectivity of communications such as cable, fiber
HA / DR Jargon Buster High Availability / Disaster Recovery
HA / DR Jargon Buster High Availability / Disaster Recovery Welcome to Maxava s Jargon Buster. Your quick reference guide to Maxava HA and industry technical terms related to High Availability and Disaster
OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:
Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission
Ohio Supercomputer Center
Ohio Supercomputer Center IT Business Continuity Planning No: Effective: OSC-13 06/02/2009 Issued By: Kevin Wohlever Director of Supercomputer Operations Published By: Ohio Supercomputer Center Original
GE Oil & Gas. Cyber Security for NERC CIP Versions 5 & 6 Compliance
GE Oil & Gas Cyber Security for NERC CIP Versions 5 & 6 Compliance Cyber Security for NERC CIP Versions 5 & 6 Compliance 2 Contents Cyber Security for NERC CIP Compliance... 5 Sabotage Reporting... 6 Security
Cloud Services Guide. (Managed Services Guide) JDA Cloud Services. Version 3.3. Date: 29th October 2012
Cloud Services Guide (Managed Services Guide) JDA Cloud Services Version 3.3 Date: 29th October 2012 Legal notice Copyright 2012, JDA Software Group, Inc. All rights reserved. JDA is a Registered Trademark
How To Help Your Hotel With A Guest Room Service
ORACLE HOSPITALITY CLOUD CONSULTING SERVICE DESCRIPTIONS September 10, 2015 TABLE OF CONTENTS Service Offerings CONSULTING SERVICE OFFERINGS ORACLE HOSPITALITY FOOD AND BEVERAGE POINT OF SALE IMPLEMENTATION
City of Houston HITS Cloud Strategy and Body Worn Camera Project. Tina Carkhuff CIO/Interim Director
City of Houston HITS Cloud Strategy and Body Worn Camera Project 1 Tina Carkhuff CIO/Interim Director Agenda 2 Overall HITS Goals Definitions On-Premise Storage Cloud-based Storage Advantages and Disadvantages
Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation. July 2015
Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation July 2015 Background Energy Management System EMS - Used by System Controllers to monitor, control and optimize the performance
Abhi Rathinavelu Foster School of Business
Abhi Rathinavelu Foster School of Business What is Disaster? A disaster is considered any incident or event that results in a major interruption of business operations Major: Earthquake >5.0, Volcanic
DCIM Software and IT Service Management - Perfect Together
DCIM Software and IT Service Management - Perfect Together A White Paper from Raritan 2014 Raritan Inc Overview Information Technology is so fundamental to every business today that every organization
Texas State Library and Archives Commission. Information Technology Detail. August 26, 2010
Texas State Library and Archives Commission Information Technology Detail 82 th Regular Session, Agency Submission, Version 1 August 26, 2010 PAGE: 1 of 6 5005 ACQUISITN INFO RES TECH 4 Computer Resources/Network
Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission
Program Summary DoIT provides support for 1,200 virtual and 150 physical servers. Housed in DoIT data centers to take advantage of climate control, power conditioning and redundancy, fire suppression systems,
Optimizing and Securing an Industrial DCS with VMware
Optimizing and Securing an Industrial DCS with VMware Global Process Automation deploys a new DCS using VMware to create a secure and robust operating environment for operators and engineers. by Doug Clarkin
CHANGE MANAGEMENT POLICY
DEPARTMENT OF TECHNOLOGY (DTECH) CHANGE MANAGEMENT POLICY Revised: 10/20/14 799 G Street, Sacramento, CA 95814 Table of Contents Introduction... 3 Definition of Change... 3 Definition of Change... 3 Objectives...
PART 10 COMPUTER SYSTEMS
PART 10 COMPUTER SYSTEMS 10-1 PART 10 COMPUTER SYSTEMS The following is a general outline of steps to follow when contemplating the purchase of data processing hardware and/or software. The State Board
COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY
Updated: 0-0-0 EB-0-0 Tab Page of COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY.0 OVERVIEW 0 Information Technology ( IT ) refers to computer systems (hardware, software and applications) that
OUTAGE MANAGEMENT SYSTEMS What, How, Why. Steven E Collier Director, Smart Grid Strategies MILSOFT Utility Solutions
OUTAGE MANAGEMENT SYSTEMS What, How, Why Steven E Collier Director, Smart Grid Strategies MILSOFT Utility Solutions DETECT LOCATE assess analyze INFORM RESTORE INVESTIGATE IMPROVE WHAT IS OMS? Outage
SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist
SCADA The Heart of an Energy Management System Presented by: Doug Van Slyke SCADA Specialist What is SCADA/EMS? SCADA: Supervisory Control and Data Acquisition Retrieves data and alarms from remote sites
Junifer Utility CIS. Flexibility. Scalability. Cost Effectiveness
Junifer Utility CIS The volumes associated with Smart Meter rollout can be overwhelming. For instance in just the first two hours of operation, a Smart Meter implementation will generate the same amount
Total Cost of Ownership Analysis
Total Cost of Ownership Analysis Abstract A total cost of ownership (TCO) analysis can measure the cost of acquiring and operating a new technology solution against a current installation. In the late
Functional Area 1. Skill Level 101 : Information Systems Administration and Planning Manager (Mercer 1998 Job 006)
Functional Area 1 Skill Level 101 : Information Systems Administration and Planning Manager (Mercer 1998 Job 006) Description: Directs the preparation, review and consolidation of corporate, regional,
Analytics Reporting Service
1. Rate per month $19.00 per user 2. General Overview: The provides the technologies for transforming large quantities of raw data into useable information serving the agency s functions. includes interactive
ACHIEVING 100% UPTIME WITH A CLOUD-BASED CONTACT CENTER
ACHIEVING 100% UPTIME WITH A CLOUD-BASED CONTACT CENTER Content: Introduction What is Redundancy? Defining a Hosted Contact Center V-TAG Distribution Levels of Redundancy Conclusion Fault Tolerance Scalability
YubiCloud Validation Service. Version 1.1
YubiCloud Service Version 1.1 5/29/2012 Introduction Disclaimer Yubico is the leading provider of simple, open online identity protection. The company s flagship product, the YubiKey, uniquely combines
Cisco Change Management: Best Practices White Paper
Table of Contents Change Management: Best Practices White Paper...1 Introduction...1 Critical Steps for Creating a Change Management Process...1 Planning for Change...1 Managing Change...1 High Level Process
EPA Classification No.: CIO 2123.0-P-01.1 CIO Approval Date: 06/10/2013 CIO Transmittal No.: 13-003 Review Date: 06/10/2016
Issued by the EPA Chief Information Officer, Pursuant to Delegation 1-84, dated June 7, 2005 CONFIGURATION MANAGEMENT PROCEDURE 1 PURPOSE The purpose of this procedure is to describe the process EPA Program
The calm after the storm
The calm after the storm Human decision support in storm outage recovery Rafael Ochoa, Amitava Sen It s a fact of life that interruptions in an electrical distribution utility happen. Although they can
data center - why choose a data center facility
data center - why choose a data center facility Do you have the highest levels of security, redundancy, reliability, infrastructure and technical expertise necessary to operate your Internet operations?
Real-time Data Replication
Real-time Data Replication from Oracle to other databases using DataCurrents WHITEPAPER Contents Data Replication Concepts... 2 Real time Data Replication... 3 Heterogeneous Data Replication... 4 Different
QUICK FACTS. Managing a Service Operations Team for a Leading Software Developer. TEKsystems Global Services Customer Success Stories.
Providing an IT Education Business Processing [ Information Technology, Applications Management ] TEKsystems Global Services Customer Success Stories Client Profile Industry: Software Revenue: $74.3 billion
Information Systems. Background
Background The goal of the Information Systems is to provide an integrated set of information systems to efficiency and effectively support the administration and operational needs of the District. Functional
Commercial Software Licensing
Commercial Software Licensing CHAPTER 10: (ITAM) Software Asset Management (SAM) Prepared by DoD ESI January 2013 Chapter Overview (ITAM) and Software Asset Management (SAM) allow for a complete and accurate
ORACLE CONFIGURATION SERVICES EXHIBIT
ORACLE CONFIGURATION SERVICES EXHIBIT This exhibit incorporates by reference the terms of the order for Exadata Database Machine, Exadata Storage Expansion Rack, SuperCluster, Exalogic on SuperCluster,
Running Successful Disaster Recovery Tests
Running Successful Disaster Recovery Tests Understanding the DR Process Running Successful Disaster Recovery Tests Understanding the DR Process Presented by Ray Lucchesi President Silverton Consulting,
Fax and Oracle Collaboration Suite. An Oracle White Paper August 2005
Fax and Oracle Collaboration Suite An Oracle White Paper August 2005 Fax and Oracle Collaboration Suite Introduction... 3 Fax Support in Oracle Collaboration Suite... 4 Outbound Fax Configuration... 7
Five Reasons Why Companies Move from JDEdwards to Microsoft Dynamics AX
Five Reasons Why Companies Move from JDEdwards to Microsoft Dynamics AX Production Solutions, May 2009 Introduction A company s ERP system is the repository for and custodian of a mass of information that
INFORMATION TECHNOLOGY PROGRAMMER/ANALYST
JOB DESCRIPTION MICHIGAN CIVIL SERVICE COMMISSION JOB SPECIFICATION INFORMATION TECHNOLOGY PROGRAMMER/ANALYST Employees in this job function as information technology professionals, participating in or
OnCommand Insight 6.4
OnCommand Insight 6.4 OnCommand Insight Planning User Guide NetApp, Inc. 495 East Java Drive Sunnyvale, CA 94089 U.S. Telephone: +1(408) 822-6000 Fax: +1(408) 822-4501 Support telephone: +1(888) 4-NETAPP
The LCO Group. Backup & Disaster Recovery. Protect your data. Protect your business.
The LCO Group Backup & Disaster Recovery Protect your data. Protect your business. SMB Disaster Preparedness Survey By Applied Research 50% 36% 50% of SMB s Have No Backup and Disaster Recovery Plan Out
Pennsylvania Summer Reliability
A. Reliability Enhancement Programs In 2015, Pennsylvania Power Company s ( Penn Power or Company ) reliability plan incorporates projects and programs to enhance overall reliability. The plan is structured
IFS-8000 V2.0 INFORMATION FUSION SYSTEM
IFS-8000 V2.0 INFORMATION FUSION SYSTEM IFS-8000 V2.0 Overview IFS-8000 v2.0 is a flexible, scalable and modular IT system to support the processes of aggregation of information from intercepts to intelligence
APPENDIX 8 TO SCHEDULE 3.3
APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE
Orangeburg Implements Best in Class AMI/ MDM Solution
Orangeburg Department of Public Utilities Prepared by: UtiliWorks Consulting, LLC. Orangeburg Implements Best in Class AMI/ MDM Solution Version 1.0: March 4, 2014 Authors: Carter Boling and Nicole Pennington,
COMP5426 Parallel and Distributed Computing. Distributed Systems: Client/Server and Clusters
COMP5426 Parallel and Distributed Computing Distributed Systems: Client/Server and Clusters Client/Server Computing Client Client machines are generally single-user workstations providing a user-friendly
COMMUNICATIONS SERVICES SPECIALISTS SERIES
COMMUNICATIONS SERVICES SPECIALISTS SERIES Occ. Work Prob. Effective Code No. Class Title Area Area Period Date 4778(3296) Communications Services Specialist I 02 730 6 mo. 11/15/00 4779(3296) Communications
Hosting Services VITA Contract VA-120416-AISN (Statewide contract available to any public entity in the Commonwealth)
Hosting Services VITA Contract VA-120416-AISN (Statewide contract available to any public entity in the Commonwealth) March 2014 Premier Provider of egov Services to the Commonwealth of Virginia Virginia
Section 2, Chapter 7 TESTING & DOCUMENTATION
Section 2, Chapter 7 7.0 General TESTING & DOCUMENTATION This section describes the specific requirements for testing and documentation of the SCADA/DMS system. The general requirements of testing and
MECOMS Customer Care & Billing As A Service
MECOMS Customer Care & Billing As A Service MECOMS As A Service. Your pay as you grow meter-to-cash solution. Introducing MECOMS As A Service, an innovative customer management and billing solution for