Maximizing Uptime in Mission- Critical Facilities
|
|
|
- Simon Caldwell
- 9 years ago
- Views:
Transcription
1 Maximizing Uptime in Mission- Critical Facilities White Paper 7 Revision 0 by Joe Soroka > Executive summary As technology reaches into every corner of our world, the importance of, and reliance on, your mission critical facility reaches new heights. Uptime is no longer a lofty goal, it is an absolute necessity. However, uptime is not a product that you specify with the design of your facility, install, and then forget about. A facility designed to 99.99% of availability will not achieve / maintain that number, unless we fully understand the many factors that affect uptime. Maximum Uptime is a philosophy. It begins with the planning of your facility, and remains a continuous process through every step of design, construction, commissioning, operations, failure analysis, and recommissioning. Contents Click on a section to jump to it Lessons learned long ago help us achieve uptime today Planning 2 Construction 5 Commissioning 6 Operations 7 Conclusion 9 Resources 10 2 white papers are now part of the Schneider Electric white paper library produced by Schneider Electric s Data Center Science Center [email protected]
2 Lessons learned long ago help us achieve uptime today September 17, 1908: Orville Wright s flying machine crashes at Fort Meyer, Virginia, killing co-pilot T.E. Selfridge, and an aircraft accident investigation board is born. The Aeronautical Board of the U.S Army Signal Corps and the Aerial Experiment Association (AEA) headed by Alexander Graham Bell and his associates conducted a thorough accident investigation. Through their findings, Dr. Bell realized the importance of preventing failures in the future and wrote an article entitled "The Lessons to be learned from Orville Wright s Disaster". Lessons Learned have become an essential tool in the prevention of aircraft accidents. Today, based on their investigation into the cause of an accident, the National Transportation Safety Board (NTSB) develops and issues "lessons learned" to prevent similar failures in the future. Preventing failures in mission-critical facilities requires a similar approach to ensure maximum uptime. Four categories of failure NTSB investigations establish that accidents occur due to one or more types of failures: design failures, catastrophic failures, compounding failures or human-error failures. Downtime at mission-critical facilities can be attributed to these four types of failures, as well, and each requires a different approach on prevention. All four types of potential failures must be examined, and "lessons learned" programs established in order to realize Maximum Uptime for your Mission-Critical Facilities. Design failures can be eliminated by first engaging with competent vendors. Selecting the appropriate design firm, integration firm, construction companies and commissioning team along with the operations staff is crucial to acquiring the experience needed to reduce these types of failures. Catastrophic failures are usually unpredictable in nature. However, a comprehensive maintenance and operations programs can identify and eliminate as many potential problems as possible. This can also help eliminate the condition that contributed to the weakness and minimize the effects of truly unpredictable problems. Compounding failures are caused when multiple events occur to create a failure. The lack of attention to details is a leading cause in compounding failures. Little nuisance items in a large facility are sometimes left unnoticed and by themselves cause no ill effect to the facility, but along with other problems, can combine to create a system failure. Human-error failures are a leading cause of failures in mission-critical facilities. These failures can be reduced by having an experienced staff that receives continuous training. Even with a competent and trained staff, the requirement for switch-level, detailed Methodsof-Procedure (MOPs) are still required. These MOPs should be executed with a pilot/co-pilot approach. Planning Begin with the end in mind. Whether it s new construction, upgrading or operating an existing mission-critical facility, it is important to carefully plan the work and to work the plan. In the design phase, it is important to consult with design teams experienced in the design of the particular type of mission critical facilities that your organization requires. A crucial part of the design phase is the early development of the Design Intent. Unfortunately the Design Intent too often is not fully developed, or is vague. The Design Intent should clearly state the owner s requirements. A well-created Design Intent document Schneider Electric Data Center Science Center White Paper 7 Rev 0 2
3 will start with a narrative of the project background, and provide a detailed discussion of the required objectives and goals. Required functional uses and requirements of the missioncritical facility should be clearly explained. While often difficult to quantify, performance and maintenance criteria should also be addressed. Finally, the expected lifespan and overall quality of the project needs to be defined. A comprehensive Design Intent is crucial for all involved parties to succeed in achieving maximum uptime in a mission-critical facility. Without it, too much interpretation by the various parties involved, can lead to compromises and misunderstandings that weaken the integrity of everything which follows. Selecting a design concept Link to resource White Paper 122 Guidelines for Specification of Data Center Criticality / Tier Levels There is not a single ideal facility design configuration. Any of a number of design concepts will accomplish similar goals, each with its own advantages and disadvantages. The required system reliability and project budget will be a driving force. However, there are four basic categories of design concepts;tier I,Tier II,Tier III, and Tier IV. See White Paper 122, Guidelines for Specification of Data Center Criticality / Tier Levels, for more information on this topic. Tier 1 Single active delivery path Need (N) of capacity Site availability of % Annual downtime of 28.8 hours Tier II Single active delivery path Need + Redundancy (N+1) of capacity Site availability of % Annual downtime of 22.0 hours Tier III One active and one passive delivery path Need + Redundancy (N+1) of capacity Site availability of % Annual downtime of 1.6 hours Tier IV Two active delivery path Need + Need with Redundancy 2 (N+1) of capacity Site availability of % Annual downtime of 0.4 hours Equipment selection and integration Selecting the right equipment vendors for the project helps ensure its successful completion. It is crucial to ensure that the equipment vendor meets the engineering specifications. Beyond the equipment-side however, the vendor s ability to support the equipment is an Schneider Electric Data Center Science Center White Paper 7 Rev 0 3
4 equally important consideration. This includes delivery times, installation support, start-up services and the availability of spare parts and authorized maintenance personnel. For complex systems and fast-track projects, consider using an equipment integrator. Complex systems rely on the operation of multiple systems and platforms. Therefore, it is essential to have the support of an organization focused on the overall connectivity and interaction of multiple systems. A qualified integrator can help eliminate the confusion that multiple Request for Information (RFIs) from various installing contractors can cause. Integrators provide the owner with a single point- of-contact, reducing the project s completion time, and ensuring that all of the systems are properly installed and interconnected. When selecting equipment for your mission-critical facilities, work with an Integrator to verify that all of the equipment complies with the project specifications. Listed below are some equipment options to consider for a mission-critical facility. Generators When selecting the generator, review the technical specifications to ensure that your project needs are met. Review the generator s available options. For example, optional isolation valves on the jacket water heater hose are inexpensive at the time of purchase. Replacing the jacket water heater hose in the field however, will require taking the generator out of service for an extended period of time. Another generator option to consider is auxiliary breaker contacts. Generator outages caused by a tripped or open generator breaker are surprisingly common. In addition, monitor and/or alarm the auxiliary contacts. The generator is there to provide power in the case of an outage, make sure it is ready when needed. UPS Systems There are as many different types of UPS systems as there are topologies. Your requirements may be best suited for a double conversion, line interactive or delta conversion. Regardless of the type of system that fits the application, make sure the appropriate internal and external maintenance bypasses are installed. A maintenance bypass should be sized to support 100% load on external maintenance bypass while providing enough capacity to perform 100% load tests. UPS Batteries When using Valve Regulated Lead Acid (VRLA) batteries, specify multiple battery strings that can be independently isolated by opening a breaker. With an independently isolated VRLA battery string, maintenance can be performed while keeping the critical load on the UPS system. Monitoring Link to resource White Paper 104 Classification of Data Center Management Software Tools When selecting a monitoring system, understand the system s capabilities and establish the various alarms, trends and notification to provide not only alarm notification, but also important historical data that can be used to predict and prevent failures. It is, of course, essential that the monitoring system itself continues to operate when the systems that are being monitored fail. Proper setup of monitoring system alarm points is crucial to preventing failures and/or minimizing their impact. For more information on data center management software see White Paper 104, Classification of Data Center Management Software Tools. Setting the pace Developing a realistic project schedule and updating it throughout the project will help eliminate unwanted surprises and avoid delays. When developing the schedule, determine the required milestones and list the items that can impact them. Schneider Electric Data Center Science Center White Paper 7 Rev 0 4
5 Construction Well-planned and meticulously implemented construction is the key foundation to facility reliability and maintainability. The owner should take an active role in selecting and working with the team throughout the construction process. A team approach to building your missioncritical facility will help to ensure that your final product will meet your specifications. Safety first Insist on vendors providing safety plans before any work begins. Review the plans to ensure they re current and appropriate to your project. Injury and fatalities can affect the reputation of your organization, along with the potential for OSHA fines and other litigation costs. An unsafe project will add additional costs and delays to the project. Invest the upfront time to ensure the project site is safe from the beginning. It will save time, money and possibly lives. Construction Inspections The owner, or the owner s representative, should conduct regular inspections of the jobsite during the construction process to document and photograph the installation process. Any items of concern should be addressed immediately rather than waiting until after the installation is completed. Correcting construction issues at the time they occur will help to ensure that the project stays on schedule and within budget. Along with inspecting for proper installation, inspection for proper safety procedures, overall organization and cleanliness is a must. A dirty, disorganized and unsafe construction site can lead to accidents, delays and mistakes. Construction Meetings Conduct regular construction meetings that are professional and productive. Building a fasttrack project for a mission-critical facility requires a team approach and a team is most effective working in unison. Good facilitation and mediation skills can be tremendous assets. Professionalism, Team Work and Expertise will deliver a quality project on time. A keep sake moment Keeping a detail construction log along with digital pictures is very helpful to a project. After the site is operational, there will come a time when you will want to refer to the construction photos to see how a piece of equipment was installed. Well-organized construction photo albums will provide a wealth of information years after the project s completion when the operations staff must perform maintenance, upgrades or repairs. As-built drawings After the installation, be sure to secure the project s as-built drawings. Invest the time to verify the accuracy of the drawings. Then institute a practice that ensures that all applicable drawings are undated as upgrades occur at the facilities. If they do not exist, a set of as-built drawings should be developed. As-built drawings are valuable tools in quickly resolving problems and restoring service in the event of a failure. Additionally, they are valuable when initiating facility upgrades. Schneider Electric Data Center Science Center White Paper 7 Rev 0 5
6 Commissioning Commissioning is the systematic process of verifying and documenting the performance of the facility s equipment. This process has several distinct phases, including the Planning Phase, Design Phase, Construction Phase, Acceptance Phase and the Post-Acceptance Phase. Commissioning a facility has many benefits providing direct and indirect paybacks. Prior to starting the commissioning program, take the time to define the key purpose of the program. For example, systems can be setup to achieve higher energy efficiency, but this may affect the system reliability. Trade-offs between energy efficiency and system reliability must be carefully weighed. This is ultimately a priority-based decision for the owner. There are a number of benefits to Commissioning a facility, including: Improved system performance and reliability, Reduced energy consumption, Improved environmental controls and Indoor Air Quality (IAQ), Hands-on training for operations and maintenance personnel, Early identification of outstanding issues, Verification of operating parameters and procedures, Establishing an operating baseline, Extended equipment life, Reduced occupant IAQ complaints including hot and cold calls. Commissioning Procedures All operating procedures should be tested for functionality during the Commissioning process. This includes start-up and shutdown of equipment, equipment bypass and failure-recovery procedures. Equipment should be exercised through all of the modes of operation. To avoid future problems, it is essential to verify all operational modes and procedure methods before the facility is occupied. Recommissioning Recommissioning is the process of commissioning a previously-commissioned facility to which changes have been made. The original commissioning documents are used as a baseline for the facility s operating performance. When developing the recommissioning plan, it is important that all new equipment and upgrades are added to the new plan. Since the building is occupied during the recommissioning process, a detailed Method of Procedures must be developed to allow complete testing without affecting the facility operations. This may require temporarily placing equipment out of service, in bypass mode, after-hour work windows and the use of temporary equipment. In the case of a mission-critical facility, great care must be taken to evaluate the system and to develop the correct procedures to ensure the required uptime. How often a facility is recommissioned is dependent upon several factors, including the required system availability and reliability, the effects of improper performance on operations, energy consumption, energy costs, and the amount of changes and upgrades that have occurred since the facility was last commissioned. Typically, a mission-critical facility should be recommissioned every 3 to 6 years. Schneider Electric Data Center Science Center White Paper 7 Rev 0 6
7 Retro-commissioning Link to resource White Paper 148 Data Center Projects: Commissioning Retro-commissioning is the process of commissioning an existing building that has not previously been commissioned. The retro-commissioning process is the same as the commissioning process with the exception that the building is occupied. Since the building is occupied and needs to remain operational, proper planning and development of detailed Method of Procedures will need to occur in the same manner as a recommissioning effort. For more information on data center commissioning, see White Paper 148, Data Center Projects: Commissioning. Operations Operations and maintenance (O&M) staffing Once the site is operational you will need to decide how to staff your facility. Whether you use inside or outside staff it is important that the depth of knowledge meets the requirements of your mission-critical facilities. Operating Procedures The development and verification of site operation, maintenance and recovery procedures are vital to maximizing uptime. Methods of Procedure (MOPs) should be very thorough and specific, written to the switch level detail, and tested during the project s commissioning phase. Too often the rush to bring the facility online overshadows the need to develop, document and deploy MOPs. However, waiting to develop a procedure to transfer the UPS system, to maintenance bypass could prove much more costly than investing the time upfront to prepare for the inevitable. Procedures should be developed early and tested before the facility is fully operational. Maintenance Windows When designing or upgrading your facility, keep in mind the quantity and length of maintenance windows required to properly maintain the facility. The system will need the appropriate redundancy and bypasses in order to operate while maintenance is performed. An annual maintenance matrix should accompany the equipment list to ensure adequate redundancy allowances. Systems without the appropriate maintenance allowances may require the use of temporary equipment or the installation of additional systems if continuous uptime is a requirement. Predictive Maintenance Maintenance should go beyond remedial and preventative maintenance to include predictive maintenance. Using equipment trends and conducting a thorough failure analysis after each incident will help predict and in-turn proactively prevent future problems. All maintenance documentation should be detailed, and provide methods for predicting and anticipating potential trouble spots and weaknesses. Details are the building blocks of a comprehensive predictive maintenance program. Maintenance Planning Plan all maintenance in advance. Start with the basics. Develop a complete equipment list and use that as a basis for the planning matrix. Have specific procedures in place for each piece of equipment. The procedures should include start-up, shutdown, bypass, lock-out tag- Schneider Electric Data Center Science Center White Paper 7 Rev 0 7
8 out, maintenance and disaster recovery. Review maintenance windows and implement an automated equipment maintenance schedule that is strictly enforced. Disaster planning and recovery A comprehensive business continuity plan (BCP) is required for all mission-critical facilities. It is equally important to develop a comprehensive plan for all IT equipment and supporting infrastructure in your mission critical facility. The plan should be a joint effort between the IT and Facilities departments and should be tested and updated at least once a year and/or as facilities changes occur. Utilities The August 2003 blackout affected communities stretching from Detroit to New York. Seconds after the power outage, thousands of generators received a start signal and most of them started. However, dead batteries, low fuel, low coolant, and generally poor maintenance left the others in the dark. The time to prepare for the next outage is now. In addition to electrical utility outages, mission-critical facilities must also prepare for failures from other utilities, including telecommunications, water, sewer and gas. In the event of a water outage, sufficient water will be required to support the make-up water used in cooling towers as well as water for staff requirements. Redundant water sources, such as wells and storage tanks, are an important part of a disaster plan. In the event of a widespread outage, an adequate supply of diesel fuel is also important. During normal times, suppliers are able to provide more diesel fuel within hours, but a widespread outage will severely impact delivery schedules. Generator monitoring can help eliminate a fuel shortage. Training It is also important to have a comprehensive training program for the operation and maintenance staff. Training should start with the equipment manufacturer/installer. Start-ups and commissioning offer ideal opportunities for training operation and maintenance staff. Once the site is operational, schedule regular training to keep operational and maintenance staff current. Schneider Electric Data Center Science Center White Paper 7 Rev 0 8
9 Conclusion Ultimately, maximum uptime in the mission-critical facility runs on technology, trust, and teamwork. Your infrastructure integrator works to orchestrate and coordinate the efforts of this diverse team to ensure your mission-critical facility delivers the performance and availability you require. For an asset as crucial as your mission-critical facility's infrastructure, it pays to invest the time to select a company you can trust, with the experience and resources to maximize uptime and mitigate risk. Ideally, your mission critical infrastructure specialist will offer you all of the products, people, services and strategies needed to design, integrate, commission, staff, maintain, service and monitor your facility. Acquiring these crucial services from a single source can greatly reduce headaches and finger-pointing in the future. Technology has changed quite a bit in the nearly 100 years since Orville Wright s Disaster. However, learning from failure remains the key to ensuring that history doesn t repeat itself. An experienced mission-critical facilities infrastructure integrator can provide essential expertise in preventing failures and ensuring maximum uptime. Whether it s design failures, catastrophic failures, compounding failures or human-error failures, there are steps that can eliminate, minimize or mitigate their effects. And an ongoing site-specific "lessons learned" program will become a living document that continues to help maximize uptime for your mission-critical facilities. Uptime is not a product and it is never complete. Uptime is a philosophy. It is a never ending process that is practiced, lived, learned and refined every day. Acknowledgements Special thanks to Joe Soroka for authoring the original content of this white paper. Schneider Electric Data Center Science Center White Paper 7 Rev 0 9
10 Resources Click on icon to link to resource Classification of Data Center Management Software Tools White Paper 104 Data Center Projects: Commissioning White Paper 148 Guidelines for Specification of Data Center Criticality / Tier Levels White Paper 122 Browse all white papers whitepapers.apc.com Browse all TradeOff Tools tools.apc.com Contact us For feedback and comments about the content of this white paper: Data Center Science Center [email protected] If you are a customer and have questions specific to your data center project: Contact your Schneider Electric representative at Schneider Electric Data Center Science Center White Paper 7 Rev 0 10
Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers
Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data White Paper 2 Revision 0 by Bob Woolley > Executive summary How can you avoid making major mistakes when operating and
A Framework for Developing and Evaluating Data Center Maintenance Programs
A Framework for Developing and Evaluating Data Center Maintenance Programs White Paper 178 Revision 0 by Bob Woolley > Executive summary Inadequate maintenance and risk mitigation processes can quickly
Mastering Disaster A DATA CENTER CHECKLIST
Mastering Disaster A DATA CENTER CHECKLIST Disaster Doesn t Sleep It s not always a hurricane or a power grid failure that causes businesses to lose their data. More often than not, an isolated event like
Enterprise Remote Monitoring
Enterprise Remote Monitoring Alarm Management, Predictive Maintenance, Advanced Network Security Services For Business-Critical Continuity Can You Really Afford Not To Know? Loss of productivity and the
Data Center Commissioning: What you need to know
Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,
the limits of your infrastructure. How to get the most out of virtualization
the limits of your infrastructure. How to get the most out of virtualization Business white paper Table of contents Executive summary...4 The benefits of virtualization?...4 How people and processes add
Why Should Companies Take a Closer Look at Business Continuity Planning?
whitepaper Why Should Companies Take a Closer Look at Business Continuity Planning? How Datalink s business continuity and disaster recovery solutions can help organizations lessen the impact of disasters
Availability and Disaster Recovery: Basic Principles
Availability and Disaster Recovery: Basic Principles by Chuck Petch, WVS Senior Technical Writer At first glance availability and recovery may seem like opposites. Availability involves designing computer
Creating Order from Chaos in Data Centers and Server Rooms
Creating from in Data Centers and Server Rooms White Paper 119 Revision 1 by Dennis Bouley > Executive summary Data center professionals can rid themselves of messy racks, sub-standard under floor air
Design Best Practices for Data Centers
Tuesday, 22 September 2009 Design Best Practices for Data Centers Written by Mark Welte Tuesday, 22 September 2009 The data center industry is going through revolutionary changes, due to changing market
Single Phase UPS Management, Maintenance, and Lifecycle
Single Phase UPS Management, Maintenance, and Lifecycle White Paper 210 Revision 0 by Justin Solis Executive summary How long will my battery last? and what is the best practice for maintaining my UPS?
ASSET Connect. The next level in Critical Environment Operational Efficiency
Connect The next level in Critical Environment Operational Efficiency 10-30% is the potential efficiency gain from optimized Data Centers and Critical Environments Operational Efficiency of Your Critical
Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches
Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your
NAVIGATING THROUGH A CATASTROPHIC DISASTER:
NAVIGATING THROUGH A CATASTROPHIC DISASTER: The five most common mistakes in business continuity planning As we continue to send our thoughts and prayers to the Japanese people, many of us are also reflecting
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure White Paper 37 Revision 7 by Neil Rasmussen > Executive summary The physical infrastructure of data centers and network rooms
Top 10 Mistakes in Data Center Operations. Eric Gallant Regional Director Lee Technologies
Top 10 Mistakes in Data Center Operations Eric Gallant Regional Director Lee Technologies Lee Technologies AGENDA Lee s Top 10 Working Group Breakouts Group 1 - Feedback of Top 10 Group 2 - What Can We
Common mistakes in datacentre planning
Common mistakes in datacentre planning White Paper Last edited: March 2013 Document Control Document Information Title Author Common mistakes in datacentre planning Nick Ewing This document is based upon
EMERGENCY PREPAREDNESS PLAN Business Continuity Plan
EMERGENCY PREPAREDNESS PLAN Business Continuity Plan GIS Bankers Insurance Group Powered by DISASTER PREPAREDNESS Implementation Small Business Guide to Business Continuity Planning Surviving a Catastrophic
Essential NCPI Management Requirements for Next Generation Data Centers
Essential NCPI Requirements for Next Generation Data Centers By Ted Ives White Paper #14 1 Executive Summary The management of physical infrastructure in data centers can no longer be considered independently
TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING
TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING A.K. Tang 1 1 President, L&T Engineering and Project Management Consultant, Mississauga. Canada Email: [email protected] ABSTRACT: Telecommunication
IT Service Management
IT Service Management Service Continuity Methods (Disaster Recovery Planning) White Paper Prepared by: Rick Leopoldi May 25, 2002 Copyright 2001. All rights reserved. Duplication of this document or extraction
SERVICES. Designing, deploying and supporting world class communications solutions.
Designing, deploying and supporting world class communications solutions. DESIGN Expertise, technologies, tools and ideas Business environments, regulation, expansion and obsolescence are drivers that
MSP Service Matrix. Servers
Servers MSP Service Matrix Microsoft Windows O/S Patching - Patches automatically updated on a regular basis to the customer's servers and desktops. MS Baseline Analyzer and MS WSUS Server used Server
AUDIT REPORT 03-11 WEB PORTAL SECURITY REVIEW. 2004 FEBRUARY R. D. MacLEAN CITY AUDITOR
AUDIT REPORT 03-11 WEB PORTAL SECURITY REVIEW 2004 FEBRUARY R. D. MacLEAN CITY AUDITOR Web Portal Security Review Page 2 Audit Report 03-11 Web Portal Security Review INDEX SECTION I EXECUTIVE SUMMARY
Planned and Emergency Utility Outage Guidelines
Revised: April 4, 2014 GUIDELINES: PURPOSE: The purpose of these guidelines is to define roles and responsibilities in requesting, coordinating scheduling, and executing utility outages and restoration
10 How to Accomplish SaaS
10 How to Accomplish SaaS When a business migrates from a traditional on-premises software application model, to a Software as a Service, software delivery model, there are a few changes that a businesses
Classification of Data Center Infrastructure Management (DCIM) Tools
Classification of Infrastructure Management (DCIM) Tools White Paper 104 Revision 3 by Kevin Brown Dennis Bouley > Executive summary Data centers today lack a formal system for classifying infrastructure
Managing Cooling Capacity & Redundancy In Data Centers Today
Managing Cooling Capacity & Redundancy In Data Centers Today About AdaptivCOOL 15+ Years Thermal & Airflow Expertise Global Presence U.S., India, Japan, China Standards & Compliances: ISO 9001:2008 RoHS
Overcoming the Causes of Data Center Outages
Overcoming the Causes of Data Center Outages Executive Summary A data center s main function should be to provide constant uptime for the mission-critical applications it houses. However, unplanned outages
Security+ Guide to Network Security Fundamentals, Fourth Edition. Chapter 13 Business Continuity
Security+ Guide to Network Security Fundamentals, Fourth Edition Chapter 13 Business Continuity Objectives Define environmental controls Describe the components of redundancy planning List disaster recovery
Selecting Enterprise Software
Selecting Enterprise Software Introduction The path to selecting enterprise software is riddled with potential pitfalls and the decision can make or break project success, so it s worth the time and effort
Guidance for Calculation of Efficiency (PUE) in Data Centers
Guidance for Calculation of Efficiency (PUE) in Data Centers White Paper 158 Revision 1 by Victor Avelar > Executive summary Before data center infrastructure efficiency can be benchmarked using PUE or
FIREWALL CLEANUP WHITE PAPER
FIREWALL CLEANUP WHITE PAPER Firewall Cleanup Recommendations Considerations for Improved Firewall Efficiency, Better Security, and Reduced Policy Complexity Table of Contents Executive Summary... 3 The
Planned, Limited Notice and Emergency Outage Guidelines
Applies to: All Facilities Management Employees GUIDELINES: Issued: April 22, 2014 Revised: February 24, 2015 Author: Communications Coordinator PURPOSE: The purpose of these guidelines is to define roles
Community Anchor Institution Service Level Agreement
Community Anchor Institution Service Level Agreement Date: 3/13/2014 Version: 2.0 Prepared by: DC-Net Table of Contents 1 Service Level Agreement... 3 2 Definitions... 3 3 Service Delivery... 5 3.1 Network
The Role of Automation Systems in Management of Change
The Role of Automation Systems in Management of Change Similar to changing lanes in an automobile in a winter storm, with change enters risk. Everyone has most likely experienced that feeling of changing
Data Center Infrastructure & Managed Services Outline
Data Center Infrastructure & Managed Services Outline The 360 Technology Center Solutions Data Center is located in Lombard, IL, USA. We are 20 minutes outside of downtown Chicago. The 360TCS staff consists
The Data Center Tier Performance Standards and Their Importance to the Owner s Project Requirements
The Data Center Tier Performance Standards and Their Importance to the Owner s Project Requirements Edward P Rafter, P.E. CxAP Tier IV Consulting Group Synopsis The data center industry has experienced
Maintenance Plan. Many of the individual components of a comprehensive maintenance program are listed below, along with brief descriptions.
Maintenance Plan Introduction Maintenance is the cornerstone of asset sustainability. An effective preventive maintenance program, combined with good operational practices, will reduce the need for much
Top 10 Mistakes in Data Center operations:
Top 10 Mistakes in Data Center operations: Operating Efficient and Effective Data Centers By Lee Kirby Vice President, Business Development and Strategic Accounts Lee Technologies Top 10 Mistakes in Data
Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0
Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0 Unless otherwise stated, these Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies
11 Common Disaster Planning Mistakes
11 Common Disaster Planning Mistakes The world is full of risk. Floods, fires, hurricanes, thefts, IT system failures and blackouts are just a few of the incredibly damaging disasters that can and do strike
How To Write A Data Center Specification
Guidelines for Specifying Data Center Criticality / Tier Levels White Paper 122 Revision 2 by Victor Avelar > Executive summary A framework for benchmarking a future data center s operational performance
A cure for water damage in real estate
A cure for water damage in real estate Presented for BC Non-Profit Housing Association by Jeff Shearman, Zurich Services Corporation 2010 Zurich Canada Focused on our customer Reduce overall risk by reducing:
SCADA Business Continuity and Disaster Recovery. Presented By: William Biehl, P.E. 913-601-0104 (mobile) [email protected]
SCADA Business Continuity and Disaster Recovery Presented By: William Biehl, P.E. 913-601-0104 (mobile) [email protected] Business Continuity Planning, a Sound Process A Business Continuity Plan: "A
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
BEST PRACTICE GUIDE TO MAXIMIZE ROI OF ENERGY MANAGEMENT SYSTEMS. Bob Zak SVP, Facility Solutions Ecova
BEST PRACTICE GUIDE TO MAXIMIZE ROI OF ENERGY MANAGEMENT SYSTEMS Bob Zak SVP, Facility Solutions Ecova April 2013 BEST PRACTICE GUIDE TO MAXIMIZE ROI OF ENERGY MANAGEMENT SYSTEMS Once your organization
Elevator Malfunction Anyone Going Down?
Elevator Malfunction Anyone Going Down? Lessons Learned Volume 04 Issue 41 2004 USW Purpose Elevator Malfunction - Anyone Going Down? To conduct a small group lessons learned activity to share information
Ten Errors to Avoid When Commissioning a Data Center
Ten Errors to Avoid When Commissioning a Data Center By Paul Marcoux White Paper # 149 Executive Summary Data center commissioning can deliver an unbiased evaluation of whether a newly constructed data
Verizon, 911 Service and the June 29, 2012, Derecho
Verizon, 911 Service and the June 29, 2012, Derecho August 13, 2012 Verizon, 911 Service, and the June 29, 2012 Derecho Late in the evening of Friday June 29, 2012, a severe storm hit the Mid-Atlantic
Executive Summary WHAT IS DRIVING THE PUSH FOR HIGH AVAILABILITY?
MINIMIZE CUSTOMER SERVICE DISRUPTION IN YOUR CONTACT CENTER GENESYS SIP 99.999% AVAILABILITY PROVIDES QUALITY SERVICE DELIVERY AND A SUPERIOR RETURN ON INVESTMENT TABLE OF CONTENTS Executive Summary...1
A VERITAS PERSPECTIVE: Maximize Agility, Minimize Risk In The Multi-Vendor Hybrid Cloud
A VERITAS PERSPECTIVE: Maximize Agility, Minimize Risk In The Multi-Vendor Hybrid Cloud 1 THE HYBRID CLOUD DILEMMA Finding Agility without Adding Fragility Today, businesses have to move fast to stay competitive.
Dynamic Power Variations in Data Centers and Network Rooms
Dynamic Power Variations in Data Centers and Network Rooms White Paper 43 Revision 3 by James Spitaels > Executive summary The power requirement required by data centers and network rooms varies on a minute
Making the Business and IT Case for Dedicated Hosting
Making the Business and IT Case for Dedicated Hosting Overview Dedicated hosting is a popular way to operate servers and devices without owning the hardware and running a private data centre. Dedicated
Five steps to a successful material handling CMMS implementation
Five steps to a successful material handling CMMS implementation Upgrade maintenance operations with improved efficiency, quality and reduced overhead automation that delivers Five steps to a successful
Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans
Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans STATUTORY REFERENCE GUIDANCE CRITERIA The Henrico County Division of Fire s Office of Emergency Management provides this
Mixing Sodium and Lead Battery Technologies in Telecom Applications
Mixing Sodium and Lead Battery Technologies in Telecom Applications Paul Smith Shanon Kolasienski Technical Marketing Manager Application Engineer GE Critical Power GE Energy Storage Plano, TX 75074 Schenectady,
Maintaining Fire Protection Systems
Maintaining Fire Protection Systems Fire continues to be a major threat to your business and your personal safety. Each year several thousand people are injured or killed by fires and billions of dollars
Creating A Highly Available Database Solution
WHITE PAPER Creating A Highly Available Database Solution Advantage Database Server and High Availability TABLE OF CONTENTS 1 Introduction 1 High Availability 2 High Availability Hardware Requirements
White Paper. The Ten Features Your Web Application Monitoring Software Must Have. Executive Summary
White Paper The Ten Features Your Web Application Monitoring Software Must Have Executive Summary It s hard to find an important business application that doesn t have a web-based version available and
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
Monitoring the Computer Room s Physical Environment A white paper from Sensaphone, Inc.
Monitoring the Computer Room s Physical Environment A white paper from Sensaphone, Inc. Introduction Nearly all small- and medium-sized businesses rely on a computer network to maintain operations, communicate
DISTRIBUTED REDUNDANCY:
DISTRIBUTED REDUNDANCY: MAXIMUM AVAILABILITY AT MINIMAL COST A White Paper by: Liebert Corporation As the need for greater system availability intensifies across virtually every industry from global banking
Hydraulic Safety Program
Reduction of Risk and Elimination of Incident Associated with Hydraulics Hydraulic Safety Authority of Canada Preface The use of Hydraulic operated equipment has increased. Automation of many functions
Accounts Payable Invoice Processing. White Paper
www.allstarss.com ACCELERATING Business Processes Accounts Payable Invoice Processing Table of Contents Table of Contents TABLE OF CONTENTS... I THE BUSINESS CHALLENGE... 2 Invoice Processing Costs...
Clinic Business Continuity Plan Guidelines
Clinic Business Continuity Plan Guidelines Emergency notification contacts: Primary Role Name Address Home phone Mobile/Cell phone Business Continuity Plan Coordinator QSP Business Continuity Plan Coordinator
GREEN HOUSE DATA. Managing IT in Uncertain Economic Times: Is a An External Private Cloud the Way to Go? Built right. Just for you.
Built right. Just for you. Managing IT in Uncertain Economic Times: Is a An External Private Cloud the Way to Go? Presented by: Shawn Mills, Founder and CEO of Green House Data Green House Data 340 Progress
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure White Paper 37 Revision 6 by Neil Rasmussen > Executive summary The physical and power infrastructure of data centers and network
HP Technical Phone Support service agreement ( Agreement ) terms and conditions
HP Technical Phone Support service agreement ( Agreement ) terms and conditions Thank you for purchasing this HP Technical Phone Support Service Agreement. Service descriptions with more detailed information
A Quick Primer on Data Center Tier Classifications
A Quick Primer on Data Center Tier Classifications What You Should Know Before Starting a Data Center Project White Paper Abstract Data center facility projects are often driven by the Uptime Institute
Mellanox Value Added Services & Support
Mellanox Value Added Services & Support Mellanox Services Mission Support our customers and partners unlock the potential of Mellanox products 2 3 Mellanox Value Added Services & Support Value Added Services
IBM Virtualization Engine TS7700 GRID Solutions for Business Continuity
Simplifying storage processes and ensuring business continuity and high availability IBM Virtualization Engine TS7700 GRID Solutions for Business Continuity The risks are even greater for companies that
Matthias Machowinski, Directing Analyst for Enterprise Networks and Video, Infonetics Research, 20152
The Cold, Hard Facts About Uptime Executive Summary By the year 2020, when the Internet of Things is in full swing and Internet-connected devices and data are as important as electricity, data center uptime
Section 3 -- Framework Design: Hardware and Software
IT Disaster Recovery Plan Template CONTENTS: Section 1: Determine Scope and Size of DR Plan Section 2: Definitions of Disaster Section 3: Framework Design/Hardware and Software Section 4: Framework Design/Environmental
CRM Inspection Experience & Lessons Learned
CRM Inspection Experience & Lessons Learned Ken Yoss, Control Center Manager Chevron Pipe Line Company (CPL) CPL s Opportunity Align with Control Center Vision Enhance pipeline safety by strengthening
Ensuring your DR plan does not Lead to a Disaster
Common Disaster Recovery Plan Misconceptions Ensuring your DR plan does not Lead to a Disaster Outages do not discriminate. Not having had an outage for a year (or even ten years) does not mean you are
Power plant safety: a wise business move
Power plant safety: a wise business move Power plant safety: a wise business move Going to work in a controlled and safe environment is not an unreasonable expectation for any worker. In many occupations,
Colocation Hosting Primer Making the Business and IT Case for Colocation
Where every interation matters. Colocation Hosting Primer Making the Business and IT Case for Colocation White Paper February 2012 By: Peer 1 Hosting Product Team www.peer1.com Contents Overview 3 Why
Disaster Recovery Hosting Provider Selection Criteria
Disaster Recovery Hosting Provider Selection Criteria By, Solution Director 6/18/07 As more and more companies choose to use Disaster Recovery (DR), services the questions that keep coming up are What
High Availability with Postgres Plus Advanced Server. An EnterpriseDB White Paper
High Availability with Postgres Plus Advanced Server An EnterpriseDB White Paper For DBAs, Database Architects & IT Directors December 2013 Table of Contents Introduction 3 Active/Passive Clustering 4
Improving. Summary. gathered from. research, and. Burnout of. Whitepaper
Whitepaper Improving Productivity and Uptime with a Tier 1 NOC Summary This paper s in depth analysis of IT support activities shows the value of segmenting and delegatingg activities based on skill level
Staffing Your Test Automation Team
Staffing Your Test Automation Team 2002-2009, Mosaic, Inc. www.mosaicinc.com 205 N. Michigan Ave. Suite 2211 Chicago, IL 60601 312-819-2220 Automation_Staffing.PDF Page 1 2002-2009, Mosaic, Inc. INTRODUCTION
Unit Guide to Business Continuity/Resumption Planning
Unit Guide to Business Continuity/Resumption Planning (February 2009) Revised June 2011 Executive Summary... 3 Purpose and Scope for a Unit Business Continuity Plan(BCP)... 3 Resumption Planning... 4 Assumptions