Verizon, 911 Service and the June 29, 2012, Derecho
|
|
|
- Aileen Newton
- 10 years ago
- Views:
Transcription
1 Verizon, 911 Service and the June 29, 2012, Derecho August 13, 2012
2 Verizon, 911 Service, and the June 29, 2012 Derecho Late in the evening of Friday June 29, 2012, a severe storm hit the Mid-Atlantic region with unusually intense straight-line winds. This Derecho caused widespread commercial power outages in the Washington D.C., Virginia and Maryland area, and widespread damage to Verizon s networks. Indeed, the Derecho downed more poles and generated more commercial trouble tickets for Verizon than Hurricane Irene. External power failures affected more than 100 Verizon locations. At each of these locations, batteries and nearly all the back-up generators worked as designed, allowing us to continue service. However, at two of these locations, generators failed to start, disabling hundreds of network transport systems, and causing Verizon to lose much of its visibility into its network in the impacted area. 1 Verizon designs its network to provide 911 services even during disasters. As explained further below, our 911 network designs include multiple levels of diversity and redundancy, as well as back-up power in critical facilities, to optimize resiliency during a crisis. Nevertheless, generator failures caused a temporary loss of 911 service to four of the more than two hundred 911 centers (referred to as Public Safety Answering Points, or PSAPs) that Verizon serves across the storm s path. As a result, three PSAPs (Fairfax County, Prince William County, and Manassas) did not receive 911 calls for several hours Saturday, June 30, and another (Manassas Park) did not receive 911 calls for much of that weekend. In addition, a number of area PSAPs (including those four) faced other 911-related problems, consisting primarily of a lack of delivery of location information on 911 calls and the loss of administrative and back-up phone 1 Across the impacted area, more than 1,900 network transport systems were damaged and failed. A very significant percentage of those systems were in Arlington and Fairfax, where the two generators failing to start caused the 911 issues. Across the impacted area, nine generators failed to operate properly out of 136 in total. 1
3 lines. 2 This document describes Verizon s final analysis of what happened and identifies important corrective actions to minimize the risk of future problems. * * * Two Generator Starting Failures Caused the 911 Outages Our investigation has determined that the failure of one of two back-up generators to start at each of our Arlington and Fairfax central offices following the loss of commercial power caused the Northern Virginia 911 disruptions. Multiple failures cascading from these specific generator problems and damage to the transport network combined to cause the outages for the four PSAPs. Included among those failures were systems that enable us to monitor the condition of our network facilities in Northern Virginia, and that loss of visibility over our network hindered our initial efforts to assess and repair damages. At critical facilities, Verizon deploys a combination of batteries and generators to support critical operations during a commercial power failure. The batteries provide an immediate source of power following the loss of commercial power until the generators go online (which is designed to occur automatically), and then the batteries act as the back-up power source should the generators fail. At more than 100 locations, Verizon s back-up batteries and generators worked as designed. However, one of two back-up generators did not start at each of the Fairfax and Arlington facilities, and these failures caused the four PSAPs 911 call completion problems. 2 Location information, referred to as Automatic Location Identifier ( ALI ) information, automatically provides the PSAP with the address of 911 callers using landlines. Callers can dial 911 and reach the PSAP even if the ALI systems are not operating, and the PSAP can dispatch the appropriate public safety response. In these cases, however, a 911 call-taker must obtain location information from the caller rather than the information appearing automatically. In addition, the Arlington County PSAP s regular business lines (which could also be used during emergencies) were not working because of the problems at the Arlington central office, explained in more detail below. 2
4 Arlington Facility The Arlington facility has two generators that must operate in tandem to support the site. At 10:55 PM on June 29, 2012, the Arlington facility lost commercial power. One of the two generators started, but the other did not. The single running generator could not support the entire site load, became overloaded and shut down as designed. Back-up batteries served the office s equipment into the morning of June 30. A power technician arrived at 12:28 AM on June 30, but despite best efforts throughout the night, could not get the second generator started. At approximately 5 AM on June 30, the batteries drained completely and network equipment failed. 3 We deployed additional resources, working in parallel both to start the second generator and prepare a replacement mobile generator. Commercial power was restored at 12:45 PM before those efforts were completed. Significantly, during the period while power was out in Arlington, we lost our telemetry systems and thus our ability to monitor parts of our network and facilities in Northern Virginia, including the Fairfax facility. Once Arlington was restored, our visibility into the network began to restore. Fairfax Facility The Fairfax facility has two generators that each support specific components of the network when commercial power is lost. At approximately 10:35 PM on June 29, the Fairfax facility lost commercial power. One of the generators started and supported its equipment as designed. The other generator did not start, so back-up batteries served the corresponding equipment into the morning of June 30. At approximately 6:15 AM, the batteries completely drained and the network equipment in the specific section of the facility served by the inoperable 3 Some network equipment is more sensitive to low voltage and failed before the batteries were completely exhausted. 3
5 generator failed. Throughout this period, the other generator supported its network equipment in the rest of the building. That morning, because we had lost visibility to the network at large, the decision was made to send technicians to various facilities, including Fairfax. A central office technician arrived at the site at 7:30 AM but did not immediately recognize that one section of the facility was not on generator. At approximately 9:45 AM, the central office technician realized there was an issue in one section of the building and called for a power technician. The power technician arrived at the Fairfax facility at approximately 11:30 AM, investigated the power plant, determined that the second generator had failed to start, initiated the starting procedures, and brought the generator back on manually by 12:15 PM. We immediately started restoring the equipment in the office and bringing services back on line. We have since conducted extensive testing using third-party experts to determine why the second generator in the Arlington facility did not start. We determined that air had entered the fuel system, resulting in a lack of fuel in the lines. We have since replaced the fuel lines for both of the back-up generators at the Arlington facility (even though no leaks were found in the generator that started). In Fairfax, Verizon s investigation has determined that the Fairfax generator did not start because the auto-start mechanisms failed. Those mechanisms are designed to automatically start the generator once commercial power is lost, but they did not operate correctly and have since been replaced. Proactive Improvements While the back-up power systems in place should have withstood the Derecho without the resulting 911 problems, our investigation has identified issues for which we are undertaking corrective action: 4
6 Issues Corrective Actions Generator system failures As described above, we suffered key generator system failures that were different in each location. The specific failures have been repaired but we are extending our review of critical locations to address potential issues. Emergency Practices and Procedures Our investigation determined we could have improved our restoration of service had we (i) recognized more quickly the partial power outage in Fairfax and (ii) been able to power some network equipment (e.g., telemetry systems) on the one generator in Arlington that was working. Communication and Mobilization We have a standard practice of internal mobilization based on actual or potential service impacts. These are triggered by alarms. The loss of visibility prevented us from receiving these alarms and delayed our response. Conduct backup power system audits in the mission-critical Verizon facilities supporting 911 in Virginia, Maryland and Washington, D.C. Institute any corrective measures identified in those power audits. For example, we have already completed the Arlington audit and are instituting automated controls to prioritize system loads (e.g., telemetry) in case one of the two generators fails. Develop and post site-specific backup power system assessment procedures that can be used by any employee to assess if there is a loss of power to an area of a building. Develop and post site-specific manual generator start and transfer procedures, including serving system loads on a prioritized basis. Enhance our critical facility Black Out testing. We test our back-up power systems regularly but will enhance this testing to include failed automated controls and prioritized system load transfer scenarios. Create two new event criteria for notification and mobilization purposes. We have enhanced our notification and mobilization procedures to trigger activity more quickly when batteries are activated or when telemetry is lost. Loss of visibility to multiple sites Redesign the telemetry network. We are redesigning the telemetry network to include more diverse connections and failover (alternative) locations. PSAP-Specific Routing Issues Compounded the Generator-Starting Problems Verizon s 911 design provides multiple diversities or redundancies inside the network. There are multiple tandem offices providing routing so that, if one fails, the calls to the failed 5
7 office are routed through the other(s). Verizon s ALI databases and links to each ALI database are redundant, as are Verizon s signaling systems, which route calls to their destinations. Verizon s analysis of the network impacts following the Derecho has identified areas for improvement, especially with ALI diversity, with specific PSAP configurations. Verizon will work directly with the specific PSAP partners to decide on improvements. 4 Communication Improvements Are Being Addressed PSAP Communications Over the past few years, Verizon has established robust processes to communicate with PSAPs during an emergency or system failure, particularly during high-volume (also known as mass calling or focused overload ) situations. In fact, we have a large team entirely dedicated to communicating with PSAPs. These new processes generally worked well during the Derecho, as Verizon stayed in constant communication with PSAPs during the 911 outages, including sending automatic notifications to PSAPs when certain alarms were triggered. But once Verizon lost its telemetry, we did not have the specific information needed by the PSAPs to understand the impact of the event and plan for alternatives. And certain automatic notifications that go to PSAPs stopped when the alarms stopped. As discussed above, Verizon is working to develop a better design to retain its visibility into the network, which will improve the utility of the communications in the face of catastrophic failures. As an example of how the lack of network visibility hindered communications, certain PSAPs, when they were no longer receiving 911 calls the morning after the storm, activated network controls to re-route calls through different paths or to a pre-designated alternate 4 Verizon is obliged to maintain the confidentiality of its specific PSAP customers network arrangements and is not free to share those details publicly; in addition, sharing such network design information would create security vulnerabilities. 6
8 location. Verizon has since determined that certain of these PSAPs would have been better off not doing so (i.e., they would have started receiving 911 calls earlier if they had not re-routed calls through different paths), but without the appropriate information, they were unable to make that determination at the time. We will discuss the network control process with the individual PSAPs to determine if improvements can be made (e.g., PSAPs may want to deactivate such controls if they do not improve call completion). The 911 Directors of the City of Alexandria, and the Counties of Arlington, Fairfax, Loudoun, Prince William and Stafford have recommended that Verizon adopt five steps in response to the storm, primarily focused on communications. The recommendations are constructive suggestions, and we look forward to working with the 911 Directors to most effectively implement these concepts. Specifically: Recommendation Verizon adopt, embrace, instruct, train and utilize the National Incident Management System (NIMS) model, to address and mitigate any and all significant events/incidents impacting providing service to the aforementioned jurisdictions. Assessment Positive. Verizon employs an "all hazards approach" to its Business Continuity, Disaster Recovery, Facility Preparedness and Emergency Management programs. These are essential to the protection of its employees, critical business processes and structural facilities located around the globe. Verizon today employs an Incident Management System (IMS) along with the concept of Crisis Management Centers to standardize control of certain emergency situations. When invoked, that process utilizes the National Incident Management System (NIMS) principles as published by the Department of Homeland Security. Verizon offers internal training and orientation courses on its National Emergency Command Center (NECC) Process, and an Introduction to the National Incident Management System. (In this event, Verizon did not activate its Emergency Command Center process; as noted above, thresholds for 7
9 invoking that process have been strengthened to more readily bring those procedures to bear in similar situations.) Verizon obtain and utilize a Reverse 911 type system to notify, via voice and text, those persons identified by the above jurisdictions, as soon it is known or suspected by Verizon that there is or may be an interruption of service to any or all of the above jurisdictions. The immediately transmitted voice and text message should contain, in plain language, the nature of the problem, current or potential impact of the problem, what Verizon is doing to address the problem, recommend actions the impacted center(s) should take and other appropriate information and include the name of the sender and the telephone number (business and mobile) at which the sender can be reached, and their address. Verizon work with the jurisdictions to develop, by no later than December 31, 2012, a method to semi-annually conduct a drill/exercise with each jurisdiction on actions to be taken by Verizon and the impacted jurisdiction(s) in the event of a potential or actual outage. Verizon provide the above jurisdictions, during the first week of each month, a current contact list; beginning with the name and contact information ( , business telephone number, business Positive. Since March 2011, Verizon has employed a broadcast process to provide specific ticket information to individual PSAPs, and also to provide general information and updates on issues that affect multiple PSAPs. Verizon will expand that process to include texting and will work with 911 Directors to establish the correct contact lists and process details. Based on experience with the process, it is evident that there is no one common standard vehicle that is universally desired by all PSAPs. Verizon will work with the 911 Directors to accommodate specific needs within a standard process. Verizon will make every effort to share actionable information with PSAPs as soon as we are aware of service interruptions. For events that may impact multiple PSAPs, we will recommend that conference bridges will be established to brief PSAPs on the situation and allow for questions and discussion. Recommended actions would be specific to each PSAP (based on their back-up configuration and event impact) and need to be developed jointly between Verizon and the PSAP. Positive. Verizon will engage the assistance of its Business Continuity Emergency Management (BCEM) team to work with Verizon s 911 Customer Care Center organization to develop and exercise procedures for drills that model potential or actual 911 outages with any of the jurisdictions that request such a joint exercise. Positive. A draft will be provided to PSAPs for comment and concurrence by August 17,
10 mobile telephone number and any other appropriate information) for the Verizon account manager assigned to the jurisdiction and four immediately escalating Verizon personnel up to a Vice President level. Verizon, if/when requested by any of the above jurisdictions, have a Verizon representative with authority to act/react; respond to and to be present at the jurisdictions Emergency Operations Center (EOC), to provide current accurate information concerning service and outages, other telephone service, etc. and liaison with other parties staffing the EOC, when the EOC is activated. Positive. Verizon will work with the 911 Directors to explore ways in which we can accommodate this request. We have discussed options for virtual participation in any EOC via an "instant messaging - like" application with the Virginia Commonwealth emergency management leaders. We have discussed joint training with Fairfax Emergency Management personnel and would welcome the opportunity to participate in that activity. If PSAP discussions regarding a joint regional 911 EOC become the strategy, that would present an excellent vehicle for Verizon to be present with multiple jurisdictions in an emergency situation. Public Communications In the future, when we face significant network-related issues like those caused by the Derecho, Verizon will share additional information about our restoration efforts more quickly to provide greater insight regarding the extent of the impact to our subscribers and the expected duration of the restoral efforts. We are mobilizing a more robust emergency response communications process to ensure that media outlets and other channels are provided relevant information on a timely basis. 9
11 Conclusion Verizon understands the critical role of 911 services to the community, and is committed to making improvements to avoid the performance of the 911 system during the Derecho. We will work directly with the PSAPs, as well as the various governmental bodies considering these important matters, to implement the lessons learned. And we will look to apply improvements and lessons learned from the Washington metropolitan area to other areas in our service territory as well. 10
Appendix 3 Disaster Recovery Plan
Appendix 3 Disaster Recovery Plan December 13, 2006 Revision XXQwest Government Services, Inc. 4250 North Fairfax DriveArlington, VA 22203(Delete this page)revision history Revision Number Revision Date
ESF 12: Energy & Utilities
Table of Contents 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Scope... 1 1.3 ESF Activation & Plan Maintenance... 2 1.4 Policies... 2 2.0 Situation & Assumptions... 2 2.1 Situation... 2 2.2 Assumptions...
ANNEX B COMMUNICATIONS
ANNEX B COMMUNICATIONS APPROVAL & IMPLEMENTATION Annex B Communications This emergency management plan is hereby approved. This plan is effective immediately and supersedes all previous editions. Jeff
It also provides guidance for rapid alerting and warning to key officials and the general public of a potential or occurring emergency or disaster.
Emergency Support Function #2 Communications ESF Coordinator: Information Technology Department Support Agencies: Tucson Fire Department Parks and Recreation Department Tucson Police Department Tucson
EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS
EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS The following criteria are to be used when developing Comprehensive Emergency Management Plans (CEMP) for all ambulatory surgical
University of Victoria EMERGENCY RESPONSE PLAN
University of Victoria EMERGENCY RESPONSE PLAN 2013 Table of Contents PLAN FUNDAMENTALS... 2 PURPOSE... 2 PRIORITIES... 2 PLAN SCOPE... 2 AUTHORITY... 2 RESPONSE LEVELS... 2 BEFORE AN EMERGENCY... 3 DURING
IT Service Continuity Management PinkVERIFY
-11-G-001 General Criteria Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 Edition workflows and process integrations? -11-G-002 Does the tool have security controls in place to
National Capital Region: Urban Area Security Initiatives Grants Subgrants as of 01/31/14
National Capital Region: Urban Area Initiatives Grants Subgrants as of 01/31/14 Year Subgrantee Subgrant Name Award All Hazards Consortium HSEMA Performance and Professional Development Initiative (DC
MSRC Best Practices. Communications Infrastructure Security, Access & Restoration Working Group
MSRC Best Practices MEDIA SECURITY AND RELIABILITY COUNCIL Adopted Best Practices Recommendations Communications Infrastructure Security, Access & Restoration Working Group National Recommendations Prevention
Technology Infrastructure Services
LOB #303: DISASTER RECOVERY Technology Infrastructure Services Purpose Disaster Recovery (DR) for IT is a capability to restore enterprise-wide technology infrastructure, applications and data that are
BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged)
BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged) This document is a synopsis of the planning and preparation the College has undertaken to handle emergencies in a professional, efficient,
NAIT Guidelines. Implementation Date: February 15, 2011 Replaces: July 1, 2008. Table of Contents. Section Description Page
Recommended by Emergency Preparedness Committee: January 26, 2011 Recommended by President s Council: February 11, 2011 Approved by Executive Committee: February 14, 2011 NAIT Guidelines CS1.1 Emergency
White Paper AN INTRODUCTION TO BUSINESS CONTINUITY PLANNING AND SOLUTIONS FOR IT AND TELECOM DECISION MAKERS. Executive Summary
AN INTRODUCTION TO BUSINESS CONTINUITY PLANNING AND SOLUTIONS FOR IT AND TELECOM DECISION MAKERS Executive Summary Today s businesses rely heavily on voice communication systems and data networks to such
2015 CEO & Board University Taking Your Business Continuity Plan To The Next Level. Tracy L. Hall, MBCP
2015 CEO & Board University Taking Your Business Continuity Plan To The Next Level Tracy L. Hall, MBCP MEMBER OF PKF NORTH AMERICA, AN ASSOCIATION OF LEGALLY INDEPENDENT FIRMS 2015 Wolf & Company, P.C.
2010 MWCOG Electricity Consumption by Jurisdiction
2010 MWCOG Electricity Consumption by Jurisdiction Jurisdiction DC TOTAL 254,257 11,538,622,434 Pepco Residential 226,272 1,891,782,070 Commercial 24,946 6,529,129,128 Government 3,039 3,117,711,236 Jurisdiction
Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans
Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans STATUTORY REFERENCE GUIDANCE CRITERIA The Henrico County Division of Fire s Office of Emergency Management provides this
STATE SUPPORT FUNCTION ANNEX 2 COMMUNICATIONS
STATE SUPPORT FUNCTION ANNEX 2 COMMUNICATIONS PRIMARY AGENCIES: Department of Information and Innovation Department of Public Safety, Radio Technology Services SUPPORT AGENCIES: Agency of Transportation
The Emergency Operations Plan provides guidance for managing emergency communications resources.
Emergency Support Function #2 - Communication ESF # 2 Primary Agency Office of Emergency Preparedness Information Technology University Relations 911 Centers Secondary/Support Agencies Law Enforcement
Unit 5: NIMS Resource Management
Unit 5: NIMS Resource Management This page intentionally left blank. Objectives At the end of this unit, the participants should be able to: Describe the importance of resource management. Define the concepts
Community Anchor Institution Service Level Agreement
Community Anchor Institution Service Level Agreement Date: 3/13/2014 Version: 2.0 Prepared by: DC-Net Table of Contents 1 Service Level Agreement... 3 2 Definitions... 3 3 Service Delivery... 5 3.1 Network
Table of Contents ESF-12-1 034-00-13
Table of Contents Primary Coordinating Agency... 2 Local Supporting Agencies... 2 State, Regional, and Federal Agencies and Organizations... 2 Purpose... 3 Situations and Assumptions... 4 Direction and
BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 1/2016 (abridged)
BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 1/2016 (abridged) This document is a synopsis of the planning and preparation the College has undertaken to handle emergencies in a professional, efficient,
HELP DESK MANAGEMENT PLAN
AT&T Help Desk Overview: DIR Platinum Customer Status AT&T is committed to continuous process improvement to meet DIR requirements and expectations, and to improve the end user experience. Today s process
DIR CONTRACT NO. DIR-TEX-AN-NG-CTSA-010 ATTACHMENT F-3 TO EXHIBIT F BUSINESS CONTINUITY AND DISASTER RECOVERY PLAN FINAL VERSION
This document describes the Business Continuity and Disaster Recovery processes and activities for DIR or customer initiated and Verizon-initiated Business Continuity and Disaster Recovery Requests in
Workforce Solutions Business Continuity Plan May 2014
Workforce Solutions Business Continuity Plan May 2014 Contents 1. Purpose... 3 2. Declaration of Emergency... 4 3. Critical Operations... 4 3.1 Communication... 4 3.1.1 Internal Communication During Emergencies...
Mastering Disaster A DATA CENTER CHECKLIST
Mastering Disaster A DATA CENTER CHECKLIST Disaster Doesn t Sleep It s not always a hurricane or a power grid failure that causes businesses to lose their data. More often than not, an isolated event like
Western Washington University Basic Plan 2013. A part of Western s Comprehensive Emergency Management Plan
2013 A part of Western s Record of Changes Change # Date Entered Description and Location of Change(s) Person making changes 2 1. PURPOSE, SCOPE, SITUATION OVERVIEW, ASSUMPTIONS AND LIMITATIONS A. PURPOSE
Emergency Restoration Plan (ERP) Components
Note: Each electric utility is different. The differences may include: System Configuration Designs and Construction Standards Construction and Line Materials Operating procedures and practices Work methods
SCADA Business Continuity and Disaster Recovery. Presented By: William Biehl, P.E. 913-601-0104 (mobile) [email protected]
SCADA Business Continuity and Disaster Recovery Presented By: William Biehl, P.E. 913-601-0104 (mobile) [email protected] Business Continuity Planning, a Sound Process A Business Continuity Plan: "A
Comparison of Joint Commission and Healthcare Facilities Accreditation Program (HFAP) Emergency-Related Standards for Hospitals.
Comparison of Joint Commission and Healthcare Facilities Accreditation Program (HFAP) Emergency-Related Standards for Hospitals Planning Activities Emergency Plan Joint Commission The hospital must engage
OREGON STATE UNIVERSITY MASTER EMERGENCY MANAGEMENT PLAN
OREGON STATE UNIVERSITY MASTER EMERGENCY MANAGEMENT PLAN Last Edit 2/8/2011 OVERVIEW This document provides a management framework for responding to incidents that may threaten the health and safety of
DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES
APPENDIX 1 DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES March 2008 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto TABLE OF CONTENTS EXECUTIVE SUMMARY...1
AMBULATORY SURGICAL CENTERS
AMBULATORY SURGICAL CENTERS STATUTE RULE CRITERIA Current until changed by State Legislature or AHCA Hospitals and Ambulatory Surgical Centers Statutory Reference 3 395.1055 (1)(c), Florida Statutes Rules
HELP DESK MANAGEMENT PLAN
AT&T Help Desk Overview: DIR Platinum Customer Status AT&T is committed to continuous process improvement to meet DIR requirements and expectations, and to improve the end user experience. Today s process
UCF Office of Emergency Management. 2013-2018 Strategic Plan
UCF Office of Emergency Management 2013-2018 Strategic Plan Table of Contents I. Introduction... 2 Purpose... 2 Overview... 3 Mission... 5 Vision... 5 II. Mandates... 6 III. Accomplishments and Challenges...
University of California Santa Cruz EMERGENCY RESPONSE PLAN
University of California Santa Cruz EMERGENCY RESPONSE PLAN September 2007 University of California, Santa Cruz Page 2 of 11 I. INTRODUCTION... 3 A. Purpose... 3 B. Scope... 3 C. Authority... 3 D. Mission...
Ensuring your DR plan does not Lead to a Disaster
Common Disaster Recovery Plan Misconceptions Ensuring your DR plan does not Lead to a Disaster Outages do not discriminate. Not having had an outage for a year (or even ten years) does not mean you are
National Capital Region: Urban Area Security Initiatives Subgrants as of 02/01/12
National Capital Region: Urban Area Initiatives Subgrants as of 02/01/12 Year Subgrantee Subgrant Name Award American Red Cross of the National Capital Area Mass Care (Maintenance) 146,258 American Red
Hurricane Irene Response Before, During and After the Storm. John D. Rea Director of Operations Support, Penelec. October 12, 2011
Pennsylvania Public Utility Commission Special Electric Reliability Forum Hurricane Irene Response Before, During and After the Storm John D. Rea Director of Operations Support, Penelec October 12, 2011
Ongoing Help Desk Management Plan
Ongoing Help Desk Management Plan HELP DESK IMPLEMENTATION /MANAGEMENT The Vendor shall provide in its Response to DIR a Help Desk Implementation Plan which shall include, but not be limited to: a. Customer
Business Continuity Planning and Disaster Recovery Planning
4 Business Continuity Planning and Disaster Recovery Planning Basic Concepts 1. Business Continuity Management: Business Continuity means maintaining the uninterrupted availability of all key business
Table of Contents ESF-3-1 034-00-13
Table of Contents Primary Coordinating Agency... 2 Local Supporting Agencies... 2 State, Regional, and Federal Agencies and Organizations... 3 Purpose... 3 Situations and Assumptions... 4 Direction and
Understanding the Electric Power Industry s Response and Restoration Process
Understanding the Electric Power Industry s Response and Restoration Process Electricity is a crucial product many of us take for granted. We scarcely think about it, unless we don t have it. Because electricity
Security in Space: Intelsat Information Assurance
Security in Space: Intelsat Information Assurance 14/03/6997 Intelsat Information Assurance Intelsat maintains the highest standards of Information Assurance by assessing and building the Intelsat infrastructure,
Voyageur Internet Inc. 323 Edwin Street Winnipeg MB R3B 0Y7 Main: (204) 233-5555 Fax: (204) 975-0554 [email protected]
1. Scope of Service Level Agreement (Effective June 1, 2013) 1.1. This Service Level Agreement (SLA) documents the commitment for "Voyageur Internet Corporation." (herein referred to as "Voyageur") to
BUSINESS CONTINUITY PLAN OVERVIEW
BUSINESS CONTINUITY PLAN OVERVIEW INTRODUCTION The purpose of this document is to provide Loomis customers with an overview of the company s Business Continuity Plan (BCP). Because of the specific and
MONTGOMERY COUNTY, KANSAS EMERGENCY OPERATIONS PLAN. ESF14-Long Term Community Recovery
MONTGOMERY COUNTY, KANSAS EMERGENCY OPERATIONS PLAN ESF14-Long Term Community Recovery Planning Team Support Agency Coffeyville Public Works Independence Public Works Montgomery County Public Works 1/15/2009
Regulatory Notice 13-25
Regulatory Notice 13-25 FINRA, the SEC and CFTC Issue Joint Advisory on Executive Summary Following Hurricane Sandy, which caused widespread damage on the northeast coast of the United States in October
Why Should Companies Take a Closer Look at Business Continuity Planning?
whitepaper Why Should Companies Take a Closer Look at Business Continuity Planning? How Datalink s business continuity and disaster recovery solutions can help organizations lessen the impact of disasters
Chatham County Disaster Recovery Plan Recovery Planning Update. Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015
Chatham County Disaster Recovery Plan Recovery Planning Update Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015 Welcome Introduction to Recovery Planning Recovery Planning Process
Module 7: System Component Failure Contingencies
Module 7: System Component Failure Contingencies Introduction The purpose of this module is to describe procedures and standards for recovery plans to be implemented in the event of system component failures.
Emergency Support Function 14 Long-Term Community Recovery and Mitigation
ESF Coordinator: Grant County Emergency Management Primary Agencies: Grant County Emergency Management Grant County Assessor s Office Grant County Public Works Grant County Building Department Support
EMERGENCY PREPAREDNESS PLAN Business Continuity Plan
EMERGENCY PREPAREDNESS PLAN Business Continuity Plan GIS Bankers Insurance Group Powered by DISASTER PREPAREDNESS Implementation Small Business Guide to Business Continuity Planning Surviving a Catastrophic
CISM Certified Information Security Manager
CISM Certified Information Security Manager Firebrand Custom Designed Courseware Chapter 4 Information Security Incident Management Exam Relevance Ensure that the CISM candidate Establish an effective
Emergency Support Function (ESF) #3 Public Works and Engineering
Emergency Support Function (ESF) #3 Public Works and Engineering Lead Coordinating Agency: Primary Agency: Support Agencies: State Agencies: Private Agencies: Green County Highway Department Municipal
Office of Emergency Management
Emergency Management Mission In cooperation with internal and external partners, enhance public protective actions and promote domestic preparedness through a comprehensive and effective emergency management
CEMP Criteria for Residential Treatment Facilities
CEMP Criteria for Residential Treatment Facilities Lee County Emergency Management The following minimum criteria are to be used when Comprehensive Emergency Management Plans (CEMP) for all Residential
George Mason University Accident and Incident Plan
George Mason University Prepared by: Environmental Health and Safety Office May 2015 Foreword The is intended for use by all parties working at, attending, or visiting George Mason University. This Plan
Hospital Emergency Operations Plan
Hospital Emergency Operations Plan I-1 Emergency Management Plan I PURPOSE The mission of University Hospital of Brooklyn (UHB) is to improve the health of the people of Kings County by providing cost-effective,
University of San Francisco EMERGENCY OPERATIONS PLAN
University of San Francisco EMERGENCY OPERATIONS PLAN University of San Francisco Emergency Operations Plan Plan Contact Eric Giardini Director of Campus Resilience 415-422-4222 This plan complies with
11 Common Disaster Planning Mistakes
11 Common Disaster Planning Mistakes The world is full of risk. Floods, fires, hurricanes, thefts, IT system failures and blackouts are just a few of the incredibly damaging disasters that can and do strike
EMERGENCY MANAGEMENT PLANNING CRITERIA FOR HOSPITALS
EMERGENCY MANAGEMENT PLANNING CRITERIA FOR HOSPITALS The following minimum criteria are to be used when developing Comprehensive Emergency Management Plans (CEMP) for all hospitals. These criteria will
Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0
Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0 Unless otherwise stated, these Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies
Page Administrative Summary...3 Introduction Comprehensive Approach Conclusion
TABLE OF CONTENTS Page Administrative Summary...3 Introduction Comprehensive Approach Conclusion PART 1: PLANNING General Considerations and Planning Guidelines... 4 Policy Group Oversight Committee Extended
Texas Universities Recover from Hurricane Ike University of Texas Medical Branch Galveston and Texas A&M University Galveston
Texas Universities Recover from Hurricane Ike University of Texas Medical Branch Galveston and Texas A&M University Galveston Business Continuity and Disaster Recovery State of Texas Executive Summary
Federal Financial Institutions Examination Council FFIEC BCP. Business Continuity Planning FEBRUARY 2015 IT EXAMINATION H ANDBOOK
Federal Financial Institutions Examination Council FFIEC Business Continuity Planning BCP FEBRUARY 2015 IT EXAMINATION H ANDBOOK Table of Contents Introduction 1 Board and Senior Management Responsibilities
Fairfax County Government. Emergency Planning Guidance for Medical and Patient Care Facilities
This guidance is designed to provide facilities with information that stimulates emergency preparation assessment planning discussions with key personnel in medical and patient care facilities. These facilities
TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING
TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING A.K. Tang 1 1 President, L&T Engineering and Project Management Consultant, Mississauga. Canada Email: [email protected] ABSTRACT: Telecommunication
Regulatory Framework for Disaster Recovery Planning for the ICT Industry
Regulatory Framework for Disaster Recovery Planning for the ICT Industry Kingdom of Saudi Arabia Regulatory Framework for Disaster Recovery Planning for the ICT Industry Page 1 of 6 1. INTRODUCTION 1.1
University of Prince Edward Island. Emergency Management Plan
Emergency Management Plan March 2012 ON CAMPUS Emergency Dial Security Assistance Dial 566-0384 OFF CAMPUS SUPPORT AGENCIES Fire & Ambulance... 9-1-1 Charlottetown Fire Department... 566-5548 Fire Marshal...
Business Continuity & Recovery Plan Summary
Introduction An organization s ability to survive a significant business interruption is determined by the company s ability to develop, implement, and maintain viable recovery and business continuity
Data Center Colocation - SLA
1 General Overview This is a Service Level Agreement ( SLA ) between and Data Center Colocation to document: The technology services Data Center Colocation provides to the customer The targets for response
Flood Events Preparedness, Remediation and Restoration. Rev 3 Dec 2014
Flood Events Preparedness, Remediation and Restoration Rev 3 Dec 2014 Impacts PART 1 - IMPACTS 2013 Brookfield Johnson Controls January 30, 2015 2 Impacts 2013 Brookfield Johnson Controls January 30, 2015
PART 2 LOCAL, STATE, AND FEDERAL EMERGENCY RESPONSE SYSTEMS, LAWS, AND AUTHORITIES. Table of Contents
PART 2 LOCAL, STATE, AND FEDERAL EMERGENCY RESPONSE SYSTEMS, LAWS, AND AUTHORITIES (Updates in Yellow Highlight) Table of Contents Authorities: Federal, State, Local... 2-1 UCSF s Emergency ManagemenT
Continuity of Business
White Paper Continuity of Business SAS Continuity of Business initiative reflects our commitment to our employees, to our customers, and to all of the stakeholders in our global business community to be
Meeting the FCC Backup Power Mandate From Site Audit to Total Site Solutions. DC Power, Outside Plant & Services for Business-Critical Continuity
Meeting the FCC Backup Power Mandate From Site Audit to Total Site Solutions DC Power, Outside Plant & Services for Business-Critical Continuity Integrated Backup Power Solutions to increase your network
1.0 Introduction. 1.1 Purpose of the Client s Guide. 1.1.1 Access to the Client s Guide. 1.1.2 Verizon WITS 3 Web Site
1.0 Introduction 1.1 Purpose of the The Verizon WITS 3 has been developed as an informational resource for WITS 3 contract stakeholders. It is a resource to assist WITS 3 stakeholders with: Guidance and
Business Continuity Plan
Business Continuity Plan October 2007 Agenda Business continuity plan definition Evolution of the business continuity plan Business continuity plan life cycle FFIEC & Business continuity plan Questions
Franklin County Emergency Management Department (FCEMD) All County Emergency Response Team (CERT) Agencies. Table of Contents
Concept of Operations Lead Agency Support Agency Standard Operating Procedures Emergency Operations Center (EOC) Franklin County Emergency Management Department (FCEMD) All County Emergency Response Team
Intel Business Continuity Practices
Intel Business Continuity Practices As a global corporation with locations and suppliers all over the world, Intel requires every designated Intel organization to embed business continuity as a core business
Emergency Support Function #1 Transportation Annex
Emergency Support Function #1 Transportation Annex Primary Agency: Support Agencies: Department of Transportation Department of Agriculture, Forest Service Department of Defense Department of Homeland
Success or Failure? Your Keys to Business Continuity Planning. An Ingenuity Whitepaper
Success or Failure? Your Keys to Business Continuity Planning An Ingenuity Whitepaper May 2006 Overview With the level of uncertainty in our world regarding events that can disrupt the operation of an
