Electrical Method Statement. Guidance Note 8
|
|
|
- Dora Howard
- 9 years ago
- Views:
Transcription
1 Electrical Method Statement Guidance Note 8 1
2 Electrical Method Statement A Basic Guide to preparation Introduction This Guidance Note gives practical information about creating a method statement. A completed sample template has been included in Appendix 1 and a blank template in Appendix 2. If you wish to use the template in Appendix 2 to construct your own documents, you must ensure that all references to Santia Accreditation have been removed and the final documents are clearly incorporated into your existing safety management system. A method statement is an ideal way of recording the hazards involved in a specific work activity and communicating the risk and precautions required to all those involved in the work, including those undertaking the work and their immediate managers. A method statement should be developed in conjunction with a risk assessment and together these demonstrate a safe system of work. The method statement needs be clear, no longer than necessary, and not over complicated. The document should avoid ambiguities or generalisations, which could lead to confusion, and layout a step-by-step sequence of work to describe how the activity is to be carried out safely. Format The actual format is dependent on the work being undertaken and the organisational arrangements in place but generally the following headings should be present: Organisation/company in control of the operation Named individual responsible for the activity and its safety Name of method statement originator and authorisation date Arrangements for changing/deviating from method statement General description of activity Location of activity including access and restrictions General working environment considerations, e.g. temperature and wind speed Protection of others, e.g. members of the public Emergency procedures, including location of emergency equipment Identity of operatives (and any specific training or certification required) Requirements for Personal Protective Equipment Plant and equipment used, including safety precautions and restrictions Materials information e.g. hazard information and storage/transport requirements Work sequence, including associated risks and required control measures for each stage Safety checks/clearances at specific stages Final clearance that activity is completed to specification Any other additional information that may be relevant. 2
3 The list above is not exhaustive and a method statement may or may not include each and every item. However, as a minimum it must achieve the following objectives: It should be up to date, identifiable and its source accountable. It should contain the sequence of works. It should identify the associated risks and control measures. It should state actions/authorisation required to deviate from method statement. Appendix 1 is a sample method statement for electrical works. It can be as simple or as detailed as the job/risk requires, so long as it meets the four main objectives. 3
4 Appendix 1 Electrical Method Statement Contract Manager: Joe Bloggs Site Supervisor: David Jones Originator: Joe Bloggs Position: Contracts Manager Date: 01/11/2013 Strict adherence to this method statement is critical to the health and safety of all engaged in the work. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Modifying/Extending/Relocating Existing Lighting Circuits and Points (Single Core Cables in Trunking and Conduit). Location and Access: (attached plan as appropriate) Main Office Area. Working Environment & Restrictions: Open Plan Office. Only Electrical Contractors permitted to be present during operation. Existing sections of ceiling will be removed by others. Protection of others: Work undertaken out of hours. Only contractors and client representative present. Emergency Procedures: Normal site evacuation procedure to apply. Operatives/Competence: C&G Qualified Electricians. Personal Protective Equipment: Safety Footwear, Gloves, Goggles Plant & Equipment: Podium Steps, Cordless Drill. Materials Handling/Storage & Safety Information: All material in manageable individual lengths. 4
5 Critical Stages: (must be undertaken in correct sequence) 1. On arrival site contact made and site induction undertaken 2. Work area cleared for safe access 3. Final circuit arrangements will be determined as indicated on the installation drawings 4. Obtain Permit to work 5. Circuits to be modified will be identified, isolated from the electrical supply by the turning off the relevant circuit protective devices and fuses removed, danger label fitted and circuit verified dead. 6. Existing luminaries will be unplugged and removed to allow access to ceiling roses as required 7. Ceiling roses will be disconnected and removed 8. All wiring contained within the conduits will be pulled back to the nearest convenient point and left neatly coiled 9. The existing conduit/trunking installation will be amended to suit the new layout as indicated on the installation drawings 10. When the amended conduit installation is complete the cables will be drawn back in 11. Circuits will be rewired/amended as necessary to suit the new layout 12. The complete circuit will be tested in accordance with B.S TH Edition I.E.E. Wiring Regulations prior to connection. 13. Accessories/equipment will be second fixed. Luminaires will be replaced and repositioned/new luminaries will be installed. 14. When all accessories are fitted and it is safe to do so the circuits will be re-energised and danger label removed 15. Final live tests will be carried out 16. Site will be cleared and equipment replaced. 17. Site contact notified of work finished. 18. Cancel permit to work Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date: 5
6 Appendix 2 Blank Method Statement Template Contract Manager: Site Supervisor: Originator: Position: Date: Strict adherence to this method statement is critical to the health and safety of all engaged in the work. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Location and Access: (attached plan as appropriate) Working Environment & Restrictions: Protection of others: Emergency Procedures: Operatives/Competence: Personal Protective Equipment: Plant & Equipment: Materials Handling/Storage & Safety Information: Critical Stages: (must be undertaken in correct sequence) Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date: 6
7 Copyright Santia 2014 This publication may be freely reproduced, except for advertising, endorsement or commercial purposes. 7
Plumbing Method Statement
Plumbing Method Statement Guidance Note 23 Jan 14 1 Plumbing Method Statement A Basic Guide to preparation Introduction This Guidance Note gives practical information about creating a method statement.
Circuit Electrical Testing
Safe Isolation Procedure Circuit Electrical Testing Site Safety Management It is essential from the outset that effective management and control of the system, apparatus and equipment used on site is achieved
The Electrical Safety Regulation (pre and post 1 January 2014)
The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013
Electrical Contractors Association
Electrical Contractors Association Presents BS 7671 2008: Amendment No 1 BS 7671: 2008 Amendment No 1, 2011 IEE Wiring Regulations Now called IET Wiring Regulations History 1882 first edition of the Wiring
GUIDANCE ON ELECTRICAL INSPECTIONS
GUIDANCE ON ELECTRICAL INSPECTIONS Electricity Electricity is a versatile and convenient source of energy. However, it can be potentially dangerous if the system has not been properly designed, installed,
Level 2 NVQ in Installing Electrotechnical Systems
Level 2 NVQ in Installing Electrotechnical Systems 2356 Scheme information and assessment requirements Version 1 February 2003 Publications and enquiries The publications listed below are available free
TRAINING RESOURCE MANUAL NATIONAL SPECIALISED ELECTRICAL WORK RECORD OF WORK EXPERIENCE AND TRAINING UEENEEP024A UEENEEP017A. EE-Oz Training Standards
TRAINING RESOURCE MANUAL NATIONAL SPECIALISED ELECTRICAL WORK UEENEEP024A UEENEEP017A RECORD OF WORK EXPERIENCE AND TRAINING 1 CONTENTS Learner s Personal Details Page 3 Background Information Page 4 Definitions
MEM18084A Commission and decommission split air conditioning systems
MEM18084A Commission and decommission split air conditioning systems Release: 1 MEM18084A Commission and decommission split air conditioning systems Modification History Not Applicable Unit Descriptor
CONTRACTOR INDUCTION HANDBOOK
CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with
Level 3-4 NVQ in Lighting for Film and Television
Level 3-4 NVQ in Lighting for Film and Television Standards and assessment requirements Level 3 NVQ in Film and Television (Lighting Technician) QCA number 500/1169/8 Level 3 NVQ in Film and Television
Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147
Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Contents I. Introduction II. Scope and Application III. Definitions IV. Lockout/Tagout Manual V. Energy Control Procedures 1. Applying Energy
Health and Safety Policy
Health and Safety Policy October 2014 1 October 2014 Contents: Introduction 1. STATEMENT OF INTENT AND POLICY OBJECTIVES 2. RESPONSIBILITIES AND ACCOUNTABILITIES FOR HEALTH AND SAFETY 2.1 The Director
Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004
Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 [email protected] www.imperial.ac.uk
RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016
RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 3 Related Documents 3.1 Occupational Health and Safety Act, R.S.O. 1990 3.2 Regulations for Industrial Establishments, R.R.O.
THE ELECTRICAL CONTRACTOR SAFETY PROGRAM GUIDE
THE ELECTRICAL CONTRACTOR SAFETY PROGRAM GUIDE December 2013 Electrical Hazard Warning Sign Disclaimer Whilst this guide endeavours to provide general information on work health and safety issues relating
This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.
UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract
HEALTH & SAFETY POLICY
HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health
A guide to our training courses and premises. 01444 872 145 www.electriciancourses4u.co.uk
A guide to our training courses and premises Contents 3. About Us 4. Why Us? 5. Our Premises 6-16. Training Courses 6. Domestic Electrician Course 7. Domestic Electrician Package 8. 17th Edition Course
APPLICATION FOR RENEWAL OF LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION (Please read Explanatory Notes before completing the Forms)
2 FORM 1 APPLICATION FOR RENEWAL OF LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION (Please read Explanatory Notes before completing the Forms) PARTICULARS OF THE INSTALLATION Name of Electrical Installation/Company:
Pontyclun Electrotechnical Training Ltd. (P.E.T. Ltd.)
Pontyclun Electrotechnical Training Ltd. (P.E.T. Ltd.) Our highly-skilled and knowledgeable staff boast extensive industry experience as well relevant teaching qualifications. We are fully accredited by
Sakhalin Energy Investment Company LTD. Corporate Procedure For Lifting Operations Over Live Process Areas
Classification: Unclassified Issue Purpose Issue For Use March 2006 Sakhalin Energy Investment Company LTD. Corporate Procedure For Lifting Operations Over Live Process Areas Revision: 01 The copyright
DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)
DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation
The Electrical Contractor Safety Program Guide
The Electrical Contractor Safety Program Guide September 2013 Electrical Hazard Warning Sign Disclaimer Whilst this guide endeavors to provide general information on work health and safety issues relating
Technical Overview Add-on Sensors - Smoke Alarm. Get yours direct at: 01491 410913 www.theclimate.co.uk
Technical Overview Add-on Sensors - Smoke Alarm Get yours direct at: 01491 410913 www.theclimate.co.uk OVERVIEW This kit contains a standard smoke alarm and relay pattress. The Kidde Smoke Alarm supplied
Assessment Guidance for Mentors Expert Witness Advisors (EWA) Assessors and Internal Verifiers
UPSTREAM OIL & GAS INDUSTRY TECHNICIAN TRAINING PROGRAMME (UOGITTP) Assessment Guidance for Mentors Expert Witness Advisors (EWA) Assessors and Internal Verifiers A.G. Revision D October 2013 Page Page
OHS Training Guidelines
1. Introduction... 2 2. Legislative Requirements... 2 3. Definitions... 2 4. Responsibilities... 2 4.1. Senior Executive, Deans and Directors... 2 4.2. Management of Academic/Administrative Units... 3
Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool
Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool This WHS Auditing System Tool is to be used as a self-assessment of YOUR COMPANY compliance with AS 4801 and the Work Health and Safety Act
Contractor Connect Scheme Electrical Contractor and Worker Handbook
Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook
For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems
BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression
QUALIFICATION HANDBOOK
QUALIFICATION HANDBOOK Level 4 Award in the Design and Verification of Electrical Installations (2396-01) November 2011 Version 1.0 Qualification at a glance Subject area City & Guilds number 2396 Age
JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES
JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES Main Courses Duration: 26 weeks 1. NVQ Level 2 Performing Process Operation in Replicating Environment 2. NVQ Level 2 Performing
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons
SERVICE MANUAL 12VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOFTOP UNITS ONLY
SERVICE MANUAL 12VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOFTOP UNITS ONLY! WARNING - SHOCK HAZARD! TO PREVENT THE POSSIBILITY OF SEVERE PERSONAL INJURY, DEATH, OR EQUIPMENT DAMAGE DUE TO ELECTRICAL
REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER
REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER April 2010 HOW TO MAKE A SUBMISSION Written submissions are invited to this Issues Paper. Please send submissions by email to: [email protected]
Policy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
OH&S Management Systems Audit Checklist (NAT, E3)
3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the
Release 1. BSBWHS508A Manage WHS hazards associated with plant
Release 1 BSBWHS508A Manage WHS hazards associated with plant BSBWHS508A Manage WHS hazards associated with plant Modification History Release Release 1 Comments This Unit first released with BSB07 Business
WHS CONTRACTOR MANAGEMENT PROCEDURE
1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and
QUALIFICATION HANDBOOK
QUALIFICATION HANDBOOK Level 3 Award in Requirements for Electrical Installations BS7671: June 2008 (2011) (2382-12) October 2011 Version 1.1 (October 2011) Version 1.2 (March 2012) Qualification at a
National Occupational Standards for Health & Safety Stand Alone Units. Unit HSS8: Review health & safety procedures in workplaces
Unit HSS8: Review health & safety procedures in workplaces This unit is for a person required to review health and safety conditions in workplaces other than their own. This unit is about: Preparing to
Lifting Equipment - Work equipment for lifting or lowering loads and includes its attachments used for anchoring, fixing or supporting it.
LIFTING EQUIPMENT POLICY Background and Legislation The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) apply in all premises and work situations subject to the Health and Safety at Work,
Good Research Practice
Page 1 of 8 The Royal Veterinary College Introduction Preface Good Research Practice Funding bodies need to be assured of the quality and validity of research they fund and ensure their contractors are
Event Management Guidelines. Month 2011. 1 Event Management Guidelines (Month, 2011)
Month 2011 1 (Month, 2011) Table of Contents Executive Summary... 2 More information... 2 Event Risk Assessment... 3 Event Checklist... 4 Event Details... 8 Event Contact List... 10 Event Task List...
WHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
USER S MANUAL HSC-24A
AIRREX AIR CONDITIONER USER S MANUAL HSC-24A Thank you for purchasing an AIRREX AIR CONDITIONER. BEFORE operation please read this user s manual carefully. Keep this manual readily available. It is ESSENTIAL
Building Services Engineering Technician
Building Services Engineering Technician A competent Building Services Engineering Technician is expected to be able to demonstrate the following skills and competences: Systems design in the building
WHS Contractor Management Procedure
Procedure Approved: 09/07/2013 Next Review: 09/07/2015 1. Overview The District council of Mount Remarkable Council is committed to engaging quality Contractors who have a sound understanding and commitment
This Guidance Notes is prepared by the Occupational Safety and Health Branch, Labour Department. This edition July 2004
This Guidance Notes is prepared by the Occupational Safety and Health Branch, Labour Department This edition July 2004 This Guidance Notes is issued free of charge and can be obtained from offices of the
WORKING IN CONFINED SPACES GUIDELINES
WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...
4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters
8 Appendix 4 of BS 7671 by Mark Coles Appendix 4, Current-carrying capacity and voltage drop for cables and flexible cords, has seen significant changes with the publishing of BS 7671:2008. This article
ASBESTOS POLICY MANAGEMENT PLAN
ASBESTOS POLICY & MANAGEMENT PLAN HS20 Version V2 Approved by: Health, Safety and Security Committee Date approved: March 2011 Ratified by: Hospital Executive Committee Date ratified 24 th April 2012 Document
ASBESTOS POLICY AND PROCEDURES
ASBESTOS POLICY AND PROCEDURES a CORPORATE RESOURCES DEPARTMENT PROPERTY SERVICES POLICY FOR THE MANAGEMENT OF ASBESTOS IN BUILDINGS OWNED AND/OR OPERATED BY LEICESTERSHIRE COUNTY COUNCIL LCC ASB/001 ISSUE
REPLACEMENT AIR CONDITIONING UNITS FOR BRITISH EMBASSY RESIDENCE
REPLACEMENT AIR CONDITIONING UNITS FOR BRITISH EMBASSY RESIDENCE FOREIGN & COMMENWEALTH OFFICE BE BAHRAIN TEL: MAY 2014 EMAIL: TENDER ISSUE: 002/2014 1. GENERAL REQUIREMENTS 1.01 LOCATION OF SITE The British
Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation
Page 1 of 11 Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation This work is copyright. It may be reproduced in whole or in part for study or training purposes
School of Engineering University of Glasgow
School of Engineering University of Glasgow Electronics Workshops Rankine Building 319A (2 Technicians) 510 (1 Technician) 712A (4 Technicians, 1 Modern Apprentice) James Watt South 619 (2 Technicians)
Corporate Standard. Contractor Management
Corporate Standard Contents Purpose... 2 Scope... 2 Definitions... 2 Background... 3 Specific Requirements... 4 Responsibilities... 11 Review Date... 11 References... 11 Date Issued July 2010 Management
LETTINGS POLICY. Claverham Community College. Adopted by the Governing Body on. Date. Signed
LETTINGS POLICY Claverham Community College Adopted by the Governing Body on Date Signed Claverham Community College Lettings Policy Contents Conditions governing the hiring of School Premises 1. General
ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
2301.1 Scope: Communications and Electronic Systems addressed in this section include:
Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and
R156. Commerce, Occupational and Professional Licensing. R156-55b. Electricians Licensing Act Rule. R156-55b-101. Title. R156-55b-102. Definitions.
R156. Commerce, Occupational and Professional Licensing. R156-55b. Electricians Licensing Act Rule. R156-55b-101. Title. This rule is known as the "Electricians Licensing Act Rule". R156-55b-102. Definitions.
CoolWave r 2 Phase Control Board and Cable Replacement Kits
Instruction Sheet P/N 1102452A CoolWave r 2 Phase Control Board and Cable Replacement Kits Two kits are available to replace the CoolWave 2 phase control board: S S Phase Control Board and Cable Kit (required
1.1. EMERGENCY PROCEDURE On discovering a fire or being informed of an emergency;
Fire Action Plan FIRE ACTION PLAN SEStran aims to provide and maintain safe & healthy working conditions, equipment and systems of work for all our employees, and to provide such information, training
FPICOT2221A Trim and cross cut felled trees
FPICOT2221A Trim and cross cut felled trees Release: 1 FPICOT2221A Trim and cross cut felled trees Modification History Not applicable. Unit Descriptor This unit specifies the outcomes required to trim
SERVICE MANUAL FOR 12 VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOF TOP UNITS ONLY
RV Products Division SERVICE MANUAL FOR 12 VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOF TOP UNITS ONLY Airxcel, Inc. RV Products Division P.O. Box 4020 Wichita, KS 67204 1976A376 (1-11) TABLE OF CONTENTS
Training Management Guidelines
Training Management Guidelines February 2009 Training Management Guidelines - February 2009 These guidelines provide a strategic approach to training and skills development in the construction industry
Contents. Company Name: XTP Recruitment Ltd ( the Company ) Policy No. XTP002. Policy Name: Model Health and Safety Policy. Date: January 2014
Company Name: Policy No. Policy Name: XTP Recruitment Ltd ( the Company ) XTP002 Model Health and Safety Policy Date: January 2014 Version: 1 Contents Contents Section 1 - General statement of policy Section
Blast management plan template
Guidance note Blast management plan template Information for shotfirers on what a blast management plan may look like. April 2012 Background A blast management plan (BMP) is a risk control plan used in
Level 3 Certificate in the Certification of Electrical Installations (Design, Erection and Verification of Electrical Installations) (2391-20)
Level 3 Certificate in the Certification of Electrical Installations (Design, Erection and Verification of Electrical Installations) (2391-20) www.cityandguilds.com March 2007 Version 1.0 Qualification
Employee Health and Safety Induction Training Record
COMPANY NAME Employee Health and Safety Induction Training Record Employee name Job Title Department Start Date - PBS 2010/2 Employee Health & Safety Induction Training Record Page 1 of 6 INDUCTION TRAINING
Asbestos Management Policy (Version 3)
Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos
Guide to Assessment and Rating for Regulatory Authorities
Guide to Assessment and Rating for Regulatory Authorities January 2013 Copyright The details of the relevant licence conditions are available on the Creative Commons website (accessible using the links
Air Conditioning Equipment
1. PURPOSE OF THIS DOCUMENT This document has been written to assist DCC Premises Managers in obtaining quotations for the ongoing servicing and maintenance of where fitted to their premises. Specialist
Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)
Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)
Greenhouse Assembly Instructions
Greenhouse Assembly Instructions 6 x 1.93m) 6 x 8 GREENHOUSE 01 ASSEMBLY INSTRUCTIONS 6 x 6 GREENHOUSE 02 ASSEMBLY INSTRUCTIONS 6 x 4 GREENHOUSE 03 ASSEMBLY INSTRUCTIONS 6ft (1.93m x 1.9 Introduction Safety
Asbestos Policy & Procedure
Asbestos Policy & Procedure 1. Purpose & Introduction This policy and procedure sets out Octavia s commitment and approach to ensuring, so far as reasonably practicable, that residents, contractors and
Cooktop Low-Profile Ventilation Hoods
INSTALLATION GUIDE Cooktop Low-Profile Ventilation Hoods Contents Wolf Cooktop Low-Profile Ventilation Hoods........ 3 Cooktop Low-Profile Hood Specifications.......... 4 Cooktop Low-Profile Hood Installation............
High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance
Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety
WHS CONTRACTOR MANAGEMENT PROCEDURE
WHS CONTRACTOR MANAGEMENT PROCEDURE Version No: Issued 3.0 18/11/2013 15/11/2018 1. Overview The District Council of Peterborough as part of its commitment under its WHS Contractor Management policy, recognises
Confined Spaces Safe Working Practices
Confined Spaces Safe Working Practices INTRODUCTION Any person planning, authorising, directing or supervising work in CONFINED SPACES must comply with the Confined Spaces Regulations 1997. These notes
DOCUMENTED PROCEDURE MANUAL
NAPIT REGISTERED INSTALLERS DOCUMENTED PROCEDURE MANUAL CONTENTS 1. INTRODUCTION 2. DEFINITIONS 3. RESPONSIBILITY FOR QUALITY 4. DOCUMENT AND DATA CONTROL 5. CUSTOMER ENQUIRIES AND QUOTATIONS 6. CONTRACTS
NATIONAL DIPLOMA IN ARCHITECTURAL TECHNOLOGY
PROGRAMME: COURSE NAME: NATIONAL DIPLOMA IN ARCHITECTURAL TECHNOLOGY SITE MANAGEMENT COURSE CODE: BLD 206 DURATION: 0 3 3 UNITS: 3 UNITS GOAL: GENERAL OBJECTIVES: On completion of this module the trainee
Unit ID: 482 Domain AUTOMOTIVE ELECTRICAL AND ELECTRONICS Title: Install and repair electrical lighting system of vehicles Level: 2 Credits: 6
Unit ID: 482 Domain AUTOMOTIVE ELECTRICAL AND ELECTRONICS Title: Install and repair electrical lighting system of vehicles Level: 2 Credits: 6 Purpose This unit standard specifies the competencies required
Document Title: Supply of Clinical Trials Investigational Material: Dispensing, Returns and Accountability
Document Title: Supply of Clinical Trials Investigational Material: Document Number: SOP072 Staff involved in development: Job titles only Document author/owner: Directorate: Department: For use by: RM&G
CPC40912 Certificate IV in Plumbing and Services
CPC40912 Certificate IV in Plumbing and Services Release: 1 CPC40912 Certificate IV in Plumbing and Services Modification History Revised qualification deemed not equivalent to CPC40911 Core and elective
Safe Work in Confined Spaces
Safe Work in Confined Spaces This publication is prepared by the Occupational Safety and Health Branch Labour Department Edition November 2010 This publication is issued free of charge and can be obtained
Loss Prevention Standard
Loss Prevention Standard : ISSUE 3.0 Requirements for the LPCB Approval and Listing of Companies Undertaking the Maintenance and Repair of Doorsets, Shutters, and Active Smoke/Fire Barriers This standard
Health and safety regulation... a short guide
...... a short guide...... a short guide Why this guide? The Health and Safety Commission (HSC) conducted a review of health and safety regulation in 1994. It found that people were confused about the
Fire Safety Log Book
Fire Safety Log Book Company... Address........ Responsible Person. Competent Person. Date Started For Additional Information: Safety Management (UK) Ltd Holme Suite, Clawthorpe Hall Business Centre, Burton
Preventative Maintenance & Statutory Testing
Preventative Maintenance & Statutory Testing Emergency Evacuation Lighting - Inspection and Maintenance It is an Occupational Health and Safety Act requirement that employers have a legal duty of care
OHSMS Implementation Guide
OHSMS Implementation Guide Developed by the Employee Health Unit, Department of Education and Early Childhood Development and Marsh Pty Ltd. Published by the Employee Health Unit, Department of Education
WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES
WHS UNIT WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES Contents 1 Purpose... 1 2 Scope... 1 3 Definitions... 1 4 Responsibilities... 1 4.1 WHS Unit... 1 4.2 Auditor(s)... 1 4.3 Managers of Faculties
Six steps to Occupational Health and Safety
Six steps to Occupational Health and Safety This booklet gives basic guidelines for workplace health and safety systems to help industry in NSW comply with the "duty of care" principle outlined in the
SYSTEMS SILVER APPROVAL CRITERIA
SYSTEMS SILVER APPROVAL CRITERIA These Criteria are to be read in conjunction with the Regulations relating to Systems Silver Approval. No Company shall hold out or claim that it meets Systems Silver Approval