EDISON RFP Attachment 3 Existing Issues Management Plan.docx
|
|
|
- Erick French
- 9 years ago
- Views:
Transcription
1 !"!
2 1 INTRODUCTION Purpose and Objectives Background Scope Standards Approach ROLES AND RESPONSIBILITIES ISSUE RESOLUTION PROCESS Issue Identification Issue Documentation Issue Resolution Issue Priority Types Issue Status Categories Integrated Tracking and Control ATTACHMENT A: Decision/Information Request (DIR) ATTACHMENT B: Issue Log Template DATE OF ADOPTION BY THE PROJECT SPONSER Page 2 of 12
3 ISSUE MANAGEMENT PLAN 1 INTRODUCTION 1.1 Purpose and Objectives The Issue Management Process is used to manage issues and questions that have a significant impact on EDISON activities. The objectives of this Issue Management Plan are to: Ensure that critical issues are identified and resolved in a timely manner; Inform stakeholders of significant issues and facilitate their participation in issue resolution; Provide a systematic approach for: a. Identifying, assessing, and resolving issues b. Monitoring and reporting progress related to issue resolution; c. Creating an audit trail that documents the resolution of project issues. 1.2 Background The Integrated Planning and Budget (IBP) system was custom developed in the late 1980 s as a joint effort between the New Jersey Office of Information Technology (OIT) and the consulting firm, Ernst and Young. IBP runs on a VAX mainframe whose VMS operating system has not been upgraded in 10 years. Upgrades have not occurred because external vendor support is no longer available for software running on the VAX. State staff supports this software internally. In OIT, 5 data base administrators (DBA s) and three (3) programmer analysts support IBP; of these, four (4) of the five (5) DBA s are eligible for retirement. Two (2) support staff from the Office of Treasury Technology (OTT) provides system administrative services. Should any of the support staff leave State service, it would be next to impossible for the agency to replace the skill sets required to maintain this custom built, complex system that has been developed using now-obsolete technology. Page 3 of 12
4 Consequently, the Office of Management and Budget intends to develop a Request for Proposal (RFP), to be issued by the New Jersey Department of the Treasury, Division of Purchase and Property, on behalf of the Department of the Treasury s Office of Management and Budget (OMB). The RFP will solicit proposals from qualified bidders for the purpose of procuring and implementing a replacement of New Jersey s Planning and Budgeting automated systems. The targeted replacement systems include the Integrated Planning and Budgeting system and, as appropriate, ancillary systems that OMB currently uses to provide enhanced functionality to IPB. The new system will be known as EDISON. 1.3 Scope This Issue Management Plan is intended for EDISON internal and external stakeholders and all EDISON project participants. Its scope is limited to managing issues that affect the success of the project. It will be executed by the EDISON Project Control Office (PCO). 1.4 Standards This Issue Management Plan is developed according to generally accepted project management practices as set forth in the Project Management Book of Knowledge (PMBOK). That book identifies project management standards developed by the Project Management Institute. 1.5 Approach The EDISON Issue Management Plan includes the following elements: Issue Identification: Anyone affected by EDISON is expected to identify issues that, if not resolved, will result in project implementation delays or a system that may not meet OMB s business needs Issue Documentation: The EDISON Project Director will track all issues in an Issues Log and drive resolution of the issues. Issue Resolution: If OMB management cannot resolve an issue, the Program Director will escalate the issue to the EDISON Steering Committee for resolution. If the Steering Committee determines that the issue requires referral to a higher level for approval, the Program Director will escalate the issue to a more senior level for resolution. Issue Priorities: The Program Director will prioritize all issues. Issue Status Categories: Issues will be classified as new, revised, deferred, rejected, in analysis, being monitored or closed. Integrated Tracking and Control: All issues will be recorded on the Issues Tracking Log, which will be maintained by the EDISON Project Director. Page 4 of 12
5 2 ROLES AND RESPONSIBILITIES All persons affected by EDISON have a role in issues management; they are responsible for identifying and helping to resolve issues. The EDISON Project Director and Program Director will manage the identification and tracking of issues, and conduct special issues resolution meetings, if warranted. At those meetings or during regularly scheduled project status meetings, decision makers will review newly identified issues, monitor progress on existing issues, and approve the recommended issue resolution. All regularly scheduled project meetings will include issues management as an agenda item. The table below identifies the roles and responsibilities of major participants in the issues management process. Title Issue Process Role Role Description and Actions EDISON Oversight Committee Issue Resolution Resolve issues that cannot be resolved at a lower level Project Control Office (PCO) Identification and Tracking of Issues Prepare agenda and facilitate appropriate meetings to discuss issues for management attention Confirm owner and date required for resolution for each issue Prepare decision request forms for issues that require a Steering Committee decision Communicate with team members so that they are aware of important issue updates Track and maintain issues in the Issue Log Include issues for management attention in the regular project status report Project Team Members Identification, Tracking and Resolution of Issues Participate in meetings to resolve project issues Page 5 of 12
6 3 ISSUE RESOLUTION PROCESS 3.1 Issue Identification Any person affected by EDISON can identify a potential issue. When a potential issue arises, the person identifying the issue needs to contact the PCO. The EDISON Project Director will work with the identifier to obtain all relevant information and to document the issue using the Decision/Information Request (DIR) form. Attachment A of this plan contains the DIR template. The DIR documents the issue, describes decision alternatives (including the pros and cons of decision alternatives), and provides a proposed recommendation. The level of detail and number of options will vary based on the specific issue. Use of the DIR facilitates discussion and resolution of the issue by providing complete analysis of the decision alternatives. 3.2 Issue Documentation The Project Director will maintain the file of DIRs and record and update each DIR on the Issues Log. It will be her responsibility to ensure that resolution due dates are assigned to each issue and that each issue is placed on the agenda for regularly scheduled project status meetings or that special issue resolution meetings are scheduled if necessary. She will also be responsible for tracking and recording the status of each issue through final resolution. 3.3 Issue Resolution If an issue cannot be resolved at the OMB management level, it will be escalated to the Steering Committee for resolution. In the event that the Steering Committee determines that the issue requires referral to a higher level for approval, the Program Director will escalate the issue to a more senior level for resolution. Page 6 of 12
7 The chart below graphically depicts the steps in the Issue Resolution Process. Page 7 of 12
8 ERROR: invalidaccess OFFENDING COMMAND: --filter-- STACK: /LZWDecode -filestream- [ ] true savelevel-
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
Governance Model: Issue Escalation and Resolution Framework
Governance Model: Issue Escalation and Resolution Framework Project Team Approved: 0/02/2007 Issue Escalation and Resolution Framework Q & A What is an Issue? An issue is a point of system function, feature,
Information Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Project Team Roles Adapted for PAAMCO
Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Decision Maker's Guide - Evaluation Checklist for ITSM Solutions High Level Requirements
Decision Maker's Guide - Evaluation Checklist for ITSM Solutions High Level Requirements Ability to support a 24x7 service desk operation Ability to provide workflow capabilities for efficient incident,
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
SUBJECT: Marcy-South Series Compensation Project Capital Expenditure Authorization Request and Contract Award
October 15, 2014 MEMORANDUM TO THE TRUSTEES FROM THE PRESIDENT and CHIEF EXECUTIVE OFFICER SUMMARY SUBJECT: Marcy-South Series Compensation Project Capital Expenditure Authorization Request and Contract
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan
DEPARTMENT OF CORRECTION SUPPORT Management Services DIRECTIVE NUMBER: SUBJECT: Correctional Integration Systems Change PAGE NUMBER: 1 of 10 Adopted: 12-15-03 01.00.00. POLICY OF THE DEPARTMENT It is the
Due Process for the GRI Reporting Framework
Introduction 1. All documents in the GRI Framework must be developed in accordance with the due process principles approved by the GRI Board of Directors and outlined in this document. The Technical Advisory
Change Management Control Procedure
Change Management Control Procedure Procedure Name: Procedure Number: Prepared By: Approved By: Change Management Control ESS100 Nancy Severance Director, Administrative Computing Services Paul Foley Director,
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Roadmap Steering Committee Meeting. Results of the 9/26/2008 Meeting
Roadmap Steering Committee Meeting Results of the 9/26/2008 Meeting 1 Agenda The plan to modernize the state s core financial systems o Are we in agreement on what is included in the scope of core financial
REQUEST FOR PROPOSALS: PAYROLL SERVICES
REQUEST FOR PROPOSALS: PAYROLL SERVICES Brookhaven Innovation Academy ( BIA ) is a public charter school located in Gwinnett County, Georgia and authorized by the Georgia State Charter Schools Commission
Request for Proposal Valley Health Team, INC FCC Healthcare Connect Fund
Request for Proposal Valley Health Team, INC FCC Healthcare Connect Fund The Valley Health Team, INC, on behalf of several clinic members of the consortium, is seeking bids for telecom services under the
SENTINEL AUDIT V: STATUS OF
SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted
Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997
Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then
COMMUNITY CARE FOR THE ELDERLY (CCE) PROGRAM REQUEST FOR PROPOSAL (RFP) GUIDELINES
COMMUNITY CARE FOR THE ELDERLY (CCE) PROGRAM REQUEST FOR PROPOSAL (RFP) GUIDELINES This document is intended for use as guidance by area agencies on aging in the development of an area-specific request
RFP-00118 ADDENDUM NO. 1
INTERNAL SERVICES DEPARTMENT PROCUREMENT MANAGEMENT SERVICES 111 NW 1 ST Street Suite 1300 Miami, Florida 33128-1974 Telephone: 305-375-4725 Fax: (305) 375-5688 RFP-00118 ADDENDUM NO. 1 DATE: March 26,
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Title: DISASTER RECOVERY/ MAJOR OUTAGE COMMUNICATION PLAN
POLICY: This policy is intended to address organizational wide communication executed during a or major IS service outage. When a disaster occurs or when any critical system/infrastructure component is
California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
Guidelines for the Procurement of Information Technology Hardware, Hardware Maintenance, Software, Software Maintenance and Support Services
Guidelines for the Procurement of Information Technology Hardware, Hardware Maintenance, Software, Software Maintenance and Support Services Rule Category Threshold Procurement Method Additional Additional
Operational Change Control Best Practices
The PROJECT PERFECT White Paper Collection The Project Perfect White Paper Collection Operational Change Control Best Practices Byron Love, MBA, PMP, CEC, IT Project+, MCDBA Internosis, Inc Executive Summary
REQUEST FOR PROPOSALS. 403(b) Retirement Plan Investment Analysis and Consulting. July 2012
REQUEST FOR PROPOSALS 403(b) Retirement Plan Investment Analysis and Consulting July 2012 I. Investment Analysis and Consulting The Corporation for Public Broadcasting ( CPB ) is seeking proposals for
SALEM STATE UNIVERSITY
SALEM STATE UNIVERSITY INVITATION TO BID THIS IS NOT AN ORDER 1. The university is an agency of the Commonwealth of Massachusetts and is exempt from any State tax or Federal excise tax 2. Unless otherwise
153rd SESSION OF THE EXECUTIVE COMMITTEE
PAN AMERICAN HEALTH ORGANIZATION WORLD HEALTH ORGANIZATION 153rd SESSION OF THE EXECUTIVE COMMITTEE Washington, D.C., USA, 4 October 2013 Provisional Agenda Item 5.2 CE153/5 (Eng.) 30 September 2013 ORIGINAL:
Data Governance Center Positioning
Data Governance Center Positioning Collibra Capabilities & Positioning Data Governance Council: Governance Operating Model Data Governance Organization Roles & Responsibilities Processes & Workflow Asset
Why are PMO s are Needed on Large Projects?
Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects
Contracting for Services
Contracting for Services A National State Auditors Association Best Practices Document Published by the National State Auditors Association Copyright 2003 by the National State Auditors Association. All
Netstar Strategic Solutions Practice Development Methodology
Netstar Strategic Solutions Practice Development Methodology Netstar Corporation Abstract This document contains a high level description of the development methodology used by the Netstar Strategic Solutions
REQUEST FOR PROPOSAL: PAYROLL SERVICES
REQUEST FOR PROPOSAL: PAYROLL SERVICES RFP Information Bid Title: Send Proposals To: Due Date & Time: Contact Information: Professional Payroll Services City of Southaven Department of Finance & Administration
Submitted by: Christopher Mead, Director, Department of Information Technology
Office of the City Manager INFORMATION CALENDAR March 21, 2006 To: From: Honorable Mayor and Members of the City Council Phil Kamlarz, City Manager Submitted by: Christopher Mead, Director, Department
New Jersey Educational Facilities Authority Request For Proposal Arbitrage Compliance Services
New Jersey Educational Facilities Authority Request For Proposal Arbitrage Compliance Services General Information: The New Jersey Educational Facilities Authority (the "Authority") requests your proposal
BUSINESS SYSTEMS ANALYST I BUSINESS SYSTEMS ANALYST II
CITY OF ROSEVILLE BUSINESS SYSTEMS ANALYST I BUSINESS SYSTEMS ANALYST II DEFINITION To perform professional level work in the analysis, design, programming, testing, installation and maintenance of business
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
ITS Project Management
ITS Project Management Policy Contents I. POLICY STATEMENT II. REASON FOR POLICY III. SCOPE IV. AUDIENCE V. POLICY TEXT VI. PROCEDURES VII. RELATED INFORMATION VIII. DEFINITIONS IX. FREQUENTLY ASKED QUESTIONS
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
ABB s Supplier Qualification System Registration in Achilles Power & Tech Frequently Asked Questions (FAQs) June 2013
ABB s Supplier Qualification System Registration in Achilles Power & Tech Frequently Asked Questions (FAQs) June 2013 ABB Supplier FAQ Version 2.0 03042014 Page 1 of 16 Contents Overview... 4 Why has ABB
Audit of NSERC Award Management Information System
Internal Audit Audit Report Audit of NSERC Award Management Information System TABLE OF CONTENTS 1. EXECUTIVE SUMMARY... 2 2. INTRODUCTION... 3 3. AUDIT FINDINGS- BUSINESS PROCESS CONTROLS... 5 4. AUDIT
SACWIS PLANNING FOR DEPARTMENT OF HUMAN SERVICES DRAFT - STRATEGIC IMPLEMENTATION PLAN: MILESTONES & TIMELINES FOR A FULL IMPLEMENTATION
STATE OF MICHIGAN SACWIS PLANNING FOR DEPARTMENT OF HUMAN SERVICES DRAFT - STRATEGIC IMPLEMENTATION PLAN: MILESTONES & TIMELINES FOR A FULL IMPLEMENTATION September 13, 2010 DRAFT -Strategic Plan: Key
Blanket Purchase Agreement Attachment C Ordering Guide. DLT Solutions/Autodesk. Blanket Purchase Agreement (BPA): N00104-12-A-ZF30
DLT Solutions/Autodesk Blanket Purchase Agreement (BPA): N00104-12-A-ZF30 1 Version Dated: January 23, 2015 DOD ESI BPA ORDERING GUIDE This Ordering Guide has been developed by the DoD ESI team to assist
LGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
Subject Area 1 Project Initiation and Management
DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This
Role and Skill Descriptions. For An ITIL Implementation Project
Role and Skill Descriptions For An ITIL Implementation Project The following skill traits were identified as fairly typical of those needed to execute many of the key activities identified: Customer Relationship
TechExcel. ITIL Process Guide. Sample Project for Incident Management, Change Management, and Problem Management. Certified
TechExcel ITIL Process Guide Sample Project for Incident Management, Management, and Problem Management. Certified Incident Management Red Arrows indicate that the transition is done automatically using
Systems Programmer/Analyst (12203) (31002632)
GENERAL DESCRIPTION OF WORK Positions in this banded class perform specialized work in supporting information technology equipment and systems for the business, research, and instructional functions of
Data Center Assistance Group, Inc. DCAG Contact: Tom Bronack Phone: (718) 591-5553 Email: [email protected] Fax: (718) 380-7322
Business Continuity and Disaster Recovery Job Descriptions Table of Contents Business Continuity Services Organization Chart... 2 Director Business Continuity Services Group... 3 Manager of Business Recovery
The Corporation of the City of London Quarterly Report on Internal Audit Results
www.pwc.com/ca The Corporation of the City of London Quarterly Report on Internal Audit Results - Corporate Services - IT: Project Management and System Prioritization February 13, 2014 Agenda Rating Scale
PROCUREMENT MANAGEMENT PLAN <PROJECT NAME>
PROCUREMENT MANAGEMENT PLAN TEMPLATE This Project Procurement Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template
Application Support Solution
Application Support Solution White Paper This document provides background and administration information on CAI s Legacy Application Support solution. PRO00001-MNGMAINT 080904 Table of Contents 01 INTRODUCTION
The consultant found that the original contract s objective of modernizing the state s IT infrastructure has been largely achieved.
MEMORANDUM TO: FROM: SUBJECT: Members of the Joint Legislative Audit and Review Commission Mark Gribbin; Principal Analyst for Ongoing Oversight and Fiscal Analysis Consultant s review of the state s central
COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
SOUTH FLORIDA INTERNATIONAL CHARTER SCHOOL
SOUTH FLORIDA INTERNATIONAL CHARTER SCHOOL 1225 SE 2nd Avenue, Ft. Lauderdale, FL sfics.org South Florida International Charter School is a Florida not for profit corporation, which will be operating Public
Streamline your staffing process with a vendor management system that fits your business
Peopleclick VMS Streamline your staffing process with a vendor management system that fits your business Peopleclick VMS is web-based, enterprise-wide vendor management software that automates, tracks
BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects b) The path to Service Delivery and Service Support for efficient and effective
SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005
SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005 ROLE RESPONSIBILITY REVIEW SIGN- OFF CTO Manage IT assets to meet corporate goals Establish and chair the Information Technology
Risk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
Prosecutorial Case Management System Maintenance/Enhancement Support Services. Request for Proposal: RFP # 7549208
RFP # 7549208 Solicitation Information December 12, 2014 TITLE: Prosecutorial Case Management System Maintenance/Enhancement Support Services Submission Deadline: Wednesday, January 14, 2015 at 2:00 PM
Contract and Vendor Management Guide
Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier
4.4 Customer Relations Management Tools
Section 4 Bidder's Products, Methodology, and Approach to the Project 4.1 FACTS II Requirements Summary 4.11 Interfaces 4.2 Functional Requirements 4.12 System Development 4.3 Technical Requirements 4.13
IT Service Provider and Consumer Support Engineer Position Description
Engineer Position Description February 9, 2015 Engineer Position Description February 9, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...
Enterprise Business Systems Project Director
Announcing an Outstanding Career Opportunity Enterprise Business Systems Project Director Application Deadline: August 25, 2013 A national search is underway for highly qualified candidates for Enterprise
Blank Project Management Templates. Saving Time! Saving Money! Saving Stress!
www.projectagency.co.uk Blank Project Management Templates Saving Time! Saving Money! Saving Stress! Please feel free to copy any of the attached documents. You can alter any of them to suit the needs
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
Enterprise Test Management Standards
Enterprise Test Management Standards Version 4.0 09/28/2012 Document Number: FSA_TOADG_STDS_TEST.TMS_001 Document Version Control This section summarizes this document revision history. Each entry includes
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Small Business Process
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Small Business Process Contracts Directorate DCMA-INST 119 OPR: DCMA-AQS 1. PURPOSE. This Instruction: a. Reissues and updates DCMA
Key USP s. Multiple PCI level GRC tool
PCI GRC tool Introduction GP history Visa level 1 approved hosting facility Niche product for a specific problem Reduce BAU cost and cost of PCI compliance Reduce cost in managing 3rd parties PCI stakeholder
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES Appointment to the New Jersey Building Authority Capital Budget Modeling and Advisory Services State Fiscal Years 2016, 2017 and 2018 Issued by the
PeopleSoft Strategic Sourcing
PeopleSoft Strategic Sourcing Oracle s PeopleSoft Strategic Sourcing enables your organization to streamline its RFx processes, conduct real-time auctions, and strategically award contracts or purchase
Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
Judiciary Judicial Information Systems
Audit Report Judiciary Judicial Information Systems November 2008 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related follow-up correspondence
HP Service Manager. Software Version: 9.40 For the supported Windows and Linux operating systems. Processes and Best Practices Guide (Codeless Mode)
HP Service Manager Software Version: 9.40 For the supported Windows and Linux operating systems Processes and Best Practices Guide (Codeless Mode) Document Release Date: December, 2014 Software Release
Building a Data Quality Scorecard for Operational Data Governance
Building a Data Quality Scorecard for Operational Data Governance A White Paper by David Loshin WHITE PAPER Table of Contents Introduction.... 1 Establishing Business Objectives.... 1 Business Drivers...
Title: Contract Management Software Solutions (CMS) and Procurement Front-End System
Page 1 Universal Service Administrative Company (USAC) Request for Information (RFI) for Contract Management Software Solutions and Procurement Front-End System RFI Number: USAC-FI-2016-02-005-RFI Title:
SOLICITATION INFORMATION JANUARY 13, 2015 TITLE: INTEGRATED CIVIL DIVISION CASE MANAGEMENT SYSTEM
SOLICITATION INFORMATION JANUARY 13, 2015 RFP# 7549264 TITLE: INTEGRATED CIVIL DIVISION CASE MANAGEMENT SYSTEM SUBMISSION DEADLINE: FEBRUARY 11, 2015 AT 2:30 PM (ET) QUESTIONS CONCERNING THIS SOLICITATION
PHASE 1: INITIATION PHASE
PHASE 1: INITIATION PHASE The Initiation Phase begins when agency management determines that a business function requires enhancement through an agency information technology (IT) project and investment